# FAIRBANKS NATURAL GAS — Notice of Amendment

- **operation:** document
- **citation:** CPF 520083001M
- **title:** FAIRBANKS NATURAL GAS — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2008-05-02
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 193.2915.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-520083001m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-520083001m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-520083001m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/520083001M
**body:**

Notice of Amendment involving FAIRBANKS NATURAL GAS. PHMSA's enforcement data identifies the cited regulation as 193.2915. The case was opened on 2008-05-02 and is reported as closed as of 2008-11-14. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520083001M_notice of amendment_05022008.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520083001M/520083001M_notice%20of%20amendment_05022008.pdf

520083001m_notice of amendment_05022008_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520083001M/520083001m_notice%20of%20amendment_05022008_text.pdf

520083001M_operator response_05162008.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520083001M/520083001M_operator%20response_05162008.pdf

520083001M_operator response_10012008.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520083001M/520083001M_operator%20response_10012008.pdf

520083001m_notice of amendment_05022008_text.pdf

O
U. S. Department
of Transportation
Pipeline and
Hazardous Materials Safety
Administration
12300 W Dakota Ave, Suite 110
Lakewood, CO 80228
NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT RE UESTED
May 2, 2008
Mr. Dan Britton
President
Fairbanks Natural Gas
3408 International Way
Fairbanks, AK 99701-9701
CPF 5-2008-3001M
Dear Mr. Britton:
On November 16-18, 2007, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code, inspected the
Fairbanks Natural Gas procedures for Operations and Maintenance (08cM) in Fairbanks,
Alaska.
On the basis of the inspection, PHMSA has identified the apparent inadequacy found within
your plans or procedures, as described below:
$193. 2017 Plans and procedures.
(a) Each operator shall maintain at each LNG plant the plans and procedures
required for that plant by this part. The plans and procedures must be available
upon request for review and inspection by the Administrator or any State Agency
that has submitted a current certification or agreement with respect to the plant
under the pipeline safety laws (49 U. S. C. 60101 et seq. ). In addition, each change to
the plans or procedures must be available at the LNG plant for review and
inspection within 20 days after the change is made.
$193. 2915 Alternative power sources.
An alternative source of power that meets the requirements of $193. 2445 must be
provided for security lighting and security monitoring and warning systems
required under $/193. 2911 and 193. 2913.



At the time of the inspection, Fairbanks Natural Gas's O&M Manual did not have an adequate
procedure to demonstrate that they have an alternate power source for security lighting.
Res onse to this Notice
This Notice is provided pursuant to 49 U. S, C. ) 60108(a) and 49 C. F. R. ) 190. 237. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U. S. C. 552(b), along with the complete original document
you must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted information
qualifies for confidential treatment under 5 U. S. C, 552(b). If you do not respond within 30 days
of receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this
Notice and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in
this Notice without further notice to you and to issue a Final Order.
If, after opportunity for a hearing, your plans or procedures are found inadequate as alleged in
this Notice, you may be ordered to amend your plans or procedures to correct the inadequacies
(49 C. F. R. $ 190. 237). If you are not contesting this Notice, we propose that you submit your
amended procedures to my office within 30 days of receipt of this Notice. This period may be
extended by written request for good cause. Once the inadequacies identified herein have been
addressed in your amended procedures, this enforcement action will be closed.
In correspondence concerning this matter, please refer to CPF 5-2008-3001M and, for each
document you submit, please provide a copy in electronic format whenever possible.
Y)
ol
Chris da
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 B. Brown (¹120709)
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings
- **truncated:** false
- **body characters:** 4812