# MERIT ENERGY COMPANY — Notice of Amendment

- **operation:** document
- **citation:** CPF 520105029M
- **title:** MERIT ENERGY COMPANY — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2010-10-21
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 195.214(a), 195.402(c)(8), 195.402(c)(9), 195.402(e)(3), 195.402(e)(8), 195.404(a)(1), 195.404(c)(3), 195.420(a), 195.557(a), 195.563(a), 195.573(c), 195.589(c).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-520105029m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-520105029m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-520105029m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/520105029M
**body:**

Notice of Amendment involving MERIT ENERGY COMPANY. PHMSA's enforcement data identifies the cited regulations as 195.214(a),  195.402(c)(8),  195.402(c)(9),  195.402(e)(3),  195.402(e)(8),  195.404(a)(1),  195.404(c)(3),  195.420(a),  195.557(a),  195.563(a),  195.573(c),  195.589(c). The case was opened on 2010-10-21 and is reported as closed as of 2011-06-20. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520105029M_closure letter_06202011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520105029M/520105029M_closure%20letter_06202011.pdf

520105029M_closure letter_06202011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520105029M/520105029M_closure%20letter_06202011_text.pdf

520105029M_notice of amendment_10212010.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520105029M/520105029M_notice%20of%20amendment_10212010.pdf

520105029M_notice of amendment_10212010_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520105029M/520105029M_notice%20of%20amendment_10212010_text.pdf

520105029M_operator_response_12092010.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520105029M/520105029M_operator_response_12092010.pdf

520105029M_notice of amendment_10212010_text.pdf

NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
October 21, 2010
Mr. Jay Prudhomme
Vice President
Merit Energy Company
1327 Noel Road, Suite 500
Dallas, TX 75240
CPF 5-2010-5029M
Dear Mr. Prudhomme:
Between May 3 and May 6, 2010, a representative of the Pipeline and Hazardous Materials
Safety Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code, inspected
Merit Energy’s procedures for Operations and Maintenance of the Sage Creek NGL pipeline and
the Bairoil CO2 pipeline in Casper, Wyoming.
On the basis of the inspection, PHMSA has identified apparent inadequacies within Merit’s plans
or procedures, as described below:
1. §195.214 Welding procedures.
(a) Welding must be performed by a qualified welder in accordance with welding
procedures qualified under Section 5 of API 1104 or Section IX of the ASME Boiler
and Pressure Vessel Code (ibr, see § 195.3) . The quality of the test welds used to
qualify the welding procedure shall be determined by destructive testing.
Merit’s Operations and Maintenance (O&M) Procedural Manual pertaining to the welding
procedures is inadequate because Merit’s procedure 6.6 for welding, NDT and repair procedures
refers to the “latest approved” edition of API 1104; however, the “latest approved” edition
number of API 1104 is not listed within their manual. That is not consistent with the
requirement of Part 195.214(a). An operator cannot simply refer to the “latest approved” edition



of a standard that is referenced by Part 195. The welding procedure referenced the specific API
1104 edition that will be used.
2. §195.402 Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(8) In the case of pipeline that is not equipped to fail safe, monitoring from an
attended location pipeline pressure during startup until steady state pressure and
flow conditions are reached and during shut-in to assure operation within limits
prescribed by §195.406.
Merit’s O&M Procedural Manual pertaining to shut-in operation is inadequate because Merit’s
emergency shutdown procedure for the Sage Creek NGL pipeline did not require the pipeline
pressures to be monitored. Per 195.402(c)(8), a pipeline that is not equipped with fail safe
mechanism must have a written procedure to require monitoring during shut-in and to assure
operations within the Maximum Operating Pressure (MOP) of the pipeline.
3. §195.402 Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(9) In the case of facilities not equipped to fail safe that are identified under
§195.402(c)(4) or that control receipt and delivery of the hazardous liquid or carbon
dioxide, detecting abnormal operating conditions by monitoring pressure,
temperature, flow or other appropriate operational data and transmitting this data
to an attended location.
Merit’s O&M Procedural Manual pertaining to pipeline operations is inadequate because Merit’s
normal and abnormal operations procedures did not provide clear guidance for detecting
abnormal operations. Merit is monitoring pressure, temperature, flow, and other operational data
from the following sites and transmitting data to attended location: the Sage Creek NGL
pipeline at the Highway 59 crossing identified per 195.402(c)(4), the receipt of NGL at the Sage
Creek Gas Processing Plant, the delivery of NGL at the Sage Creek Meter Station, the Bairoil
CO2 pipeline at the receipt of CO2 at Chute Creek, and the delivery of CO2 at the Bairoil Recycle
Plant. Regardless, Merit does not have procedures that allow those personnel at the Attwood
facilities to detect when an abnormal operation is or has occurred. An operator must have
written procedures for detecting abnormal operations by monitoring pressures, temperatures,
flow rates or other appropriate operational data at facilities that are identified under
§194.402(c)(4), and the control receipt and delivery of hazardous liquid or carbon dioxide are
monitored from an attended location.
4. §195.402 Procedural manual for operations, maintenance, and emergencies.
(e) Emergencies. The manual required by paragraph (a) of this section must
include procedures for the following to provide safety when an emergency condition
occurs;
2



(3) Having personnel, equipment, instruments, tools, and material available as
needed at the scene of an emergency.
Merit’s Emergency Procedural Manual pertaining to response equipment is inadequate because
Merit’s procedure 4A.15 did not include a list of available emergency response equipment for
either the Sage Creek NFL pipeline or Bairoil CO2 pipeline. Emergency response procedures
must include information for response personnel that directs them to available equipment,
instruments, tools, and materials that may be needed in the case of an emergency.
5. §195.402 Procedural manual for operations, maintenance, and emergencies.
(e) Emergencies. The manual required by paragraph (a) of this section must
include procedures for the following to provide safety when an emergency condition
occurs;
(8) In the case of failure of a pipeline transporting a highly volatile liquid, use of
appropriate instruments to assess the extent and coverage of the vapor cloud and
determine the hazardous areas.
Merit’s Procedural Manual pertaining to emergency response is inadequate because Merit’s
procedures for the Sage Creek NGL pipeline did not describe all of the necessary steps to be
taken in an event of a release of HVL to assess the extent and coverage of a vapor cloud, and
determine the hazardous areas by using appropriate instruments. An operator of HVL pipelines
must have a written emergency procedure for responding to a release and for determining the
extent and coverage of the vapor cloud, and determine the hazardous areas by using appropriate
instruments.
6. §195.404 Maps and Records.
(a) Each operator shall maintain current maps and records of its pipeline systems
that include at least the following information;
(1) Location and identification of the following pipeline facilities;
(v) Facilities to which §195.402(c) (9) applies;
(vii) Safety devices to which §195.428 applies.
Merit’s O&M Procedural Manual pertaining to maps and records is inadequate because Merit’s
maps and records procedure 2.3, paragraph 2.a. refers to Part 195.402(c) (9) and Part 195.428 as
items that will be maintained on their maps. That is not consistent with the requirement of Part
195.404(a) (1). An operator’s procedures for maintaining current maps and records cannot
simply refer to Part 195 for guidance. A procedure must be described in detail on how each type
of pipeline facilities to be included.
7. §195.404 Maps and Records.
(c) Each operator shall maintain the following records for the periods specified;
(3) A record of each inspection and test required by this subpart shall be
maintained for at least 2 years or until the next inspection or test is performed,
whichever is longer.
3



Merit’s O&M Procedural Manual pertaining to maps and records is inadequate because Merit’s
procedure 2.16 for complying with §195.402(c) (13) did not include all the documentation
requirements. An operator’s O&M procedures must include a record of each inspection and test
that is covered by their procedures. In addition, Merit’s emergency response training review
procedure 2.2.4 for complying with §195.403(b) (1) did not include all the documentation
requirements.
8. §195.420 Valve maintenance.
(a) Each operator shall maintain each valve that is necessary for the safe operation
of its pipeline systems in good working order at all times.
Merit’s O&M Procedural Manual pertaining to valve maintenance is inadequate because Merit’s
valve procedure 2.11.5 did not describe in detail how to maintain each valve that is necessary for
the safe operation of its pipeline system so it will be in good working order at all times.
Furthermore, Merit’s procedure 2.11.5 did not identify what valves are necessary for the safe
operation of its pipeline system. Furthermore, the operator must maintain a listing of those
valves required to be in good working order to ensure the safe operation of its pipeline system
and so pipeline personnel know which valves must be maintained per §195.420(a).
9. §195.557 Which pipelines must have coating for external corrosion control?
Except bottoms of aboveground breakout tanks, each buried or submerged pipeline
must have an external coating for external corrosion control if the pipeline is--
(a) Constructed, relocated, replaced, or otherwise changed after the applicable date
in Sec. 195.401(c), not including the movement of pipe covered by Sec. 195.424; or
Merit’s O&M Procedural Manual pertaining to external corrosion control program is inadequate
because Merit’s procedure 2.12.1.5 only reference Part 195.401(c). An operator’s external
corrosion control procedures must specify the date when external coatings are required and on
which pipeline facilities.
10. §195.563 Which pipelines must have cathodic protection?
(a) Each buried or submerged pipeline that is constructed, relocated, replaced, or
otherwise changed after the applicable date in Sec. 195.401(c) must have cathodic
protection. The cathodic protection must be in operation not later than 1 year after
the pipeline is constructed, relocated, replaced, or otherwise changed, as applicable.
Merit’s O&M Procedural Manual pertaining to external corrosion control program is inadequate
because Merit’s procedure 2.12.1.5 only referenced 195.401(c) for the applicable date of which
pipelines constructed, relocated, replaced, or otherwise changed must have cathodic protection
program. An operator’s procedure cannot only reference Part 195. The procedure must define
the actual dates of when a cathodic protection program must be implemented and on which
pipelines.
4



11. §195.573 What must I do to monitor external corrosion control?
(c) Rectifiers and other devices. You must electrically check for proper
performance each device in the first column at the frequency stated in the second
column.
Device Check frequency
Rectifier.................................
At least six times each calendar year, but
Reverse current switch
with intervals not exceeding 2 ½ months
Diode
Interference bond whose failure
would jeopardize structural
protection
Other interference bond.................. At least once each calendar year, but with
intervals not exceeding 15 months.
Merit’s O&M Procedural Manual pertaining to external corrosion control monitoring program is
inadequate because Merit’s Sage Creek external corrosion control procedure 2.12.1.7 states that
each critical bond, reverse current switch and diode must be inspected once each calendar year
not to exceed 15 months. An operator’s procedure for critical bond, reverse current switch, and
diode must inspect these devices at least six (6) times each calendar year with intervals not
exceeding 2-½ months.
12. §195.589 What corrosion control information do I have to maintain?
(c) You must maintain a record of each analysis, check, demonstration,
examination, inspection, investigation, review, survey, and test required by this
subpart in sufficient detail to demonstrate the adequacy of corrosion control
measures or that corrosion requiring control measures does not exist. You must
retain these records for at least 5 years, except that records related to Secs. 195.569,
195.573(a) and (b), and 195.579(b)(3) and (c) must be retained for as long as the
pipeline remains in service.
Merit’s O&M Procedural Manual pertaining to corrosion control records is inadequate because
Merit’s corrosion control procedure 2.12 only referenced Part §195.589 for retention
requirements of their corrosion control records. An operator’s corrosion control procedures
cannot only reference Part 195 for records retention requirements. A procedure must explicitly
define which corrosion control records must be retained and for how long per Part 195.589.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.237. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), along with the complete original document you
5



must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted information
qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not respond within 30 days
of receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this
Notice and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in
this Notice without further notice to you and to issue a Final Order.
If, after opportunity for a hearing, your plans or procedures are found inadequate as alleged in
this Notice, you may be ordered to amend your plans or procedures to correct the inadequacies
(49 C.F.R. § 190.237). If you are not contesting this Notice, we propose that you submit your
amended procedures to my office within 30 days of receipt of this Notice. This period may be
extended by written request for good cause. Once the inadequacies identified herein have been
addressed in your amended procedures, this enforcement action will be closed.
In correspondence concerning this matter, please refer to CPF 5-2010-5029M and, for each
document you submit, please provide a copy in electronic format whenever possible.
Sincerely,
Chris Hoidal
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings
cc: PHP-60 Compliance Registry
PHP-500 G. Davis (#128461 and #128464)
6

520105029M_closure letter_06202011_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
June 20, 2011
Mr. Jay Prudhomme
Vice President
Merit Energy Company
1327 Noel Road, Suite 500
Dallas, TX 75240
CPF 5-2010-5029M
Dear Mr. Prudhomme:
On May 3 through May 6, 2010, a representative from the Pipeline and Hazardous Materials
Safety Administration (PHMSA), pursuant to chapter 601 of 49 United States Code, conducted
an on-site pipeline safety inspection of Merit Energy Company‘s (Merit) operation and
maintenance procedures in Casper, Wyoming. As a result of the inspection, Merit was issued
a Notice of Amendment on October 21, 2010, which proposed amendment of your operations
and maintenance procedures.
Merit responded with amended procedures on December 9, 2010, May 4, 2011, and June 17,
2011. My staff reviewed the amended procedures, and it appears that the inadequacies
outlined in this Notice of Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank
you for your cooperation.
Sincerely,
Chris Hoidal
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 G. Davis (#128461 and #128464)