# BARROW UTILITIES & ELECTRIC CORP — Notice of Amendment

- **operation:** document
- **citation:** CPF 520110019M
- **title:** BARROW UTILITIES & ELECTRIC CORP — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2011-10-25
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 192.616.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-520110019m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-520110019m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-520110019m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/520110019M
**body:**

Notice of Amendment involving BARROW UTILITIES & ELECTRIC CORP. PHMSA's enforcement data identifies the cited regulation as 192.616. The case was opened on 2011-10-25 and is reported as closed as of 2012-02-16. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520110019M_closure letter_02162012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520110019M/520110019M_closure%20letter_02162012.pdf

520110019M_closure letter_02162012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520110019M/520110019M_closure%20letter_02162012_text.pdf

520110019M_notice of amendment_10252011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520110019M/520110019M_notice%20of%20amendment_10252011.pdf

520110019M_notice of amendment_10252011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520110019M/520110019M_notice%20of%20amendment_10252011_text.pdf

520110019M_notice of amendment_10252011_text.pdf

NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
October 25, 2011
Mr. Allen Nesteby
Operations Superintendent
Barrow Utilities & Electric Cooperative, Inc.
1295 Agvik St.
P.O. Box 449
Barrow Alaska 99723
CPF 5-2011-0019M
Dear Mr. Nesteby:
On October 1, 2011, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code inspected
Barrow Utilities & Electric Cooperative’s (BUECI) procedures for Public Awareness
Program in Anchorage, Alaska.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within
BUECI’s plans or procedures, as described below:
1. §192.616 Public Awareness
(a) Except for an operator of a master meter or petroleum gas system covered
under paragraph (j) of this section, each pipeline operator must develop and
implement a written continuing public education program that follows the
guidance provided in the American Petroleum Institute's (API) Recommended
Practice (RP) 1162 (incorporated by reference,
BUECI’s Public Awareness Program does not list where a statement of management support
can be found. BUECI’s Public Awareness Program section 1.5, “Commitment from
Management” lists table 13. Table 13 lists Chapter 2, Section U of BUECI’s O&M manual.
The O&M manual did not contain a section U, in Chapter 2. BUECI’s Public Awareness
Program must list where a statement of management support can be found.



2. §192.616 Public Awareness
(a) Except for an operator of a master meter or petroleum gas system covered
under paragraph (j) of this section, each pipeline operator must develop and
implement a written continuing public education program that follows the
guidance provided in the American Petroleum Institute's (API) Recommended
Practice (RP) 1162 (incorporated by reference,
BUECI’s Public Awareness Program indicates that no incidents or near-misses have
occurred on their system in the past 10 years (Section 1.1). The 2010 Annual Report
indicates that third party damage has occurred in 2010. BUECI must amend the Public
Awareness Program to indicate that damage has occurred.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.237. Enclosed
as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. 552(b), along with the complete original document
you must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not respond
within 30 days of receipt of this Notice, this constitutes a waiver of your right to contest the
allegations in this Notice and authorizes the Associate Administrator for Pipeline Safety to
find facts as alleged in this Notice without further notice to you and to issue a Final Order.
If, after opportunity for a hearing, your plans or procedures are found inadequate as alleged
in this Notice, you may be ordered to amend your plans or procedures to correct the
inadequacies (49 C.F.R. § 190.237). If you are not contesting this Notice, we propose that
you submit your amended procedures to my office within 90 days of receipt of this Notice.
This period may be extended by written request for good cause. Once the inadequacies
identified herein have been addressed in your amended procedures, this enforcement action
will be closed.
It is requested (not mandated) that Barrow Utilities & Electric Cooperative, Inc. maintain
documentation of the safety improvement costs associated with fulfilling this Notice of
Amendment (preparation/revision of plans, procedures) and submit the total to Dennis
Hinnah, Deputy Director, Western Region, Pipeline and Hazardous Materials Safety
Administration. In correspondence concerning this matter, please refer to CPF 5-2011-
0019M and, for each document you submit, please provide a copy in electronic format
whenever possible.
2



Sincerely,
Dennis Hinnah
Deputy Director, Western Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings
cc: PHP-60 Compliance Registry
PHP-500 B. Flanders (#135551)
3

520110019M_closure letter_02162012_text.pdf

February 16, 2012
Mr. Allen Nesteby
Operations Superintendent
Barrow Utilities & Electric Cooperative, Inc.
1295 Agvik St.
P.O. Box 449
Barrow Alaska 99723
CPF 5-2011-0019M
Dear Mr. Nesteby:
On October 1, 2011, a representative from the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to chapter 601 of 49 United States Code, conducted an
on-site pipeline safety inspection of Barrow Utilities & Electric Cooperative’s (BUECI)
Public Awareness Program procedures in Borrow, Alaska. As a result of the inspection,
BUECI was issued a Notice of Amendment on October 25, 2011, which proposed
amendment of your procedures.
BUECI submitted its amended procedures on January 31, 2011. My staff reviewed the
amended procedures, and it appears that the inadequacies outlined in this Notice of
Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank
you for your cooperation.
Sincerely,
Dennis Hinnah
Deputy Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 B. Flanders (#135551)