# MIDWAY SUNSET COGENERATION CO — Notice of Amendment

- **operation:** document
- **citation:** CPF 520171010M
- **title:** MIDWAY SUNSET COGENERATION CO — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2017-06-22
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 192.605(b)(1), 192.605(e).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-520171010m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-520171010m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-520171010m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/520171010M
**body:**

Notice of Amendment involving MIDWAY SUNSET COGENERATION CO. PHMSA's enforcement data identifies the cited regulations as 192.605(b)(1),  192.605(e). The case was opened on 2017-06-22 and is reported as closed as of 2017-08-03. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520171010M_Closure Letter_08032017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520171010M/520171010M_Closure%20Letter_08032017.pdf

520171010M_Closure Letter_08032017_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520171010M/520171010M_Closure%20Letter_08032017_text.pdf

520171010M_Notice of Amendment_06222017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520171010M/520171010M_Notice%20of%20Amendment_06222017.pdf

520171010M_Notice of Amendment_06222017_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520171010M/520171010M_Notice%20of%20Amendment_06222017_text.pdf

520171010M_Operator Response to Notice_07182017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520171010M/520171010M_Operator%20Response%20to%20Notice_07182017.pdf

520171010M_Notice of Amendment_06222017_text.pdf

NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
June 22, 2017
Mr. Dave Faiella
Executive Director
Midway Sunset Cogeneration Company
3466 W. Crocker Springs Road
Fellows, CA 93224-0457
CPF 5-2017-1010M
Dear Mr. Faiella:
On February 6 through 8, 2017, a representative of the Pipeline and Hazardous Materials
Safety Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code,
inspected Midway Sunset Cogeneration Company’s (MSCC) gas transmission pipeline
procedural manual for operations and maintenance in Fellows, California.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within
MSCC’s plans or procedures, as described below:
1. §192.605 Procedural manual for operations, maintenance, and emergencies.
(b) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following, if applicable, to provide
safety during maintenance and operations.
(1) Operating, maintaining, and repairing the pipeline in accordance with each of
the requirements of this subpart and subpart M of this part.
MSCC’s operations and maintenance manual did not establish adequate written procedures to
address prompt remedial action in correcting any valve found inoperable, unless it designates
an alternative valve, in accordance with §192.745(b). MSCC failed to define the meaning of
"immediately" or "in a prompt manner" the repair or replacement of emergency shutdown



(ESD) valve or critical valve found to be inoperable, unless the operator uses an alternative
valve.
2. §192.605 Procedural manual for operations, maintenance, and emergencies.
(e) Surveillance, emergency response, and accident investigation. The procedures
required by §§192.613(a), 192.615, and 192.617 must be included in the manual
required by paragraph (a) of this section.
MSCC did not establish adequate written procedures to train the appropriate operating
personnel to assure that they are knowledgeable of emergency procedures and verify that the
training is effective in accordance with §192.615(b)(2). MSCC lacked written procedures to
undertake regular and periodic training and review of the emergency procedures with
appropriate operating personnel.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed
as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. 552(b), along with the complete original document
you must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under §190.211. If you do not respond within 30 days
of receipt of this Notice, this constitutes a waiver of your right to contest the allegations in
this Notice and authorizes the Associate Administrator for Pipeline Safety to find facts as
alleged in this Notice without further notice to you and to issue an Order Directing
Amendment. If your plans or procedures are found inadequate as alleged in this Notice, you
may be ordered to amend your plans or procedures to correct the inadequacies (49 C.F.R. §
190.206). If you are not contesting this Notice, we propose that you submit your amended
procedures to my office within 60 days of receipt of this Notice. This period may be extended
by written request for good cause. Once the inadequacies identified herein have been
addressed in your amended procedures, this enforcement action will be closed.



It is requested (not mandated) that Midway Sunset Cogeneration Company maintains
documentation of the safety improvement costs associated with fulfilling this Notice of
Amendment (preparation/revision of plans, procedures) and submit the total to Huy Nguyen,
Acting Director, Western Region, Pipeline and Hazardous Materials Safety Administration. In
correspondence concerning this matter, please refer to CPF 5-2017-1010M and, for each
document you submit, please provide a copy in electronic format whenever possible.
Sincerely,
Huy Nguyen
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings
cc: PHP-60 Compliance Registry
PHP-500 N. Cruz (#154969)

520171010M_Closure Letter_08032017_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
August 3, 2017
Mr. Dave Faiella
Executive Director
Midway Sunset Cogeneration Company
3466 W. Crocker Springs Road
Fellows, CA 93224
CPF 5-2017-1010M
Closure Letter
Dear Mr. Faiella:
On February 6 to 8, 2017, a representative from the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to chapter 601 of 49 United States Code, conducted an
on-site pipeline safety inspection of Midway Sunset Cogeneration Company’s (MSCC)
procedures in Fellows, CA. As a result of the inspection, MSCC was issued a Notice of
Amendment on June 22, 2017, which proposed amendment of your procedures.
MSCC submitted its amended procedures on July 18, 2017. My staff reviewed the amended
procedures, and it appears that the inadequacies outlined in this Notice of Amendment have
been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank
you for your cooperation.
Sincerely,
Dustin Hubbard
Acting Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 N. Cruz (#154969)
- **truncated:** false