# GAS TRANSMISSION NORTHWEST LLC — Warning Letter

- **operation:** document
- **citation:** CPF 520191006W
- **title:** GAS TRANSMISSION NORTHWEST LLC — Warning Letter
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2019-01-23
- **effective on:** Not available
- **summary:** CLOSED warning letter citing 192.147(b), 192.481(b), 192.481(c), 192.745, 192.947(d).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-520191006w.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-520191006w.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-520191006w
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/520191006W
**body:**

Warning Letter involving GAS TRANSMISSION NORTHWEST LLC. PHMSA's enforcement data identifies the cited regulations as 192.147(b),  192.481(b),  192.481(c),  192.745,  192.947(d). The case was opened on 2019-01-23 and is reported as closed as of 2019-01-23. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520191006W_Warning Letter_01232019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520191006W/520191006W_Warning%20Letter_01232019.pdf

520191006W_Warning Letter_01232019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520191006W/520191006W_Warning%20Letter_01232019_text.pdf

520191006W_Warning Letter_01232019_text.pdf

WARNING LETTER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
February 11, 2019
Ms. Sonya Kirby
Vice President, Safety, Quality & Compliance
TransCanada
P.O. Box 1000
Station M
Calgary AB, Canada
T2P 4K5
CPF 5-2019-1006W
Dear Ms. Kirby:
From November 27, 2017 through September 7, 2018, representatives of the Pipeline &
Hazardous Materials Safety Administration (PHMSA) and the Washington Utilities and
Transportation Commission, pursuant to Chapter 601 of 49 United States Code, inspected the
TransCanada Gas Transmission Northwest Pipeline System (GTN) in the states of
Washington, Oregon, and Idaho.
During the inspection, the following probable violations of the Pipeline Safety Regulations,
Title 49, Code of Federal Regulations (CFR) were noted. The potential regulatory
deficiencies observed and probable violation(s) are:
1. §192.147 Flanges and flange accessories.
(b) Each flange assembly must be able to withstand the maximum pressure at
which the pipeline is to be operated and to maintain its physical and chemical
properties at any temperature to which it is anticipated that it might be subjected
in service.
A flange at the Schweitzer Meter station, in Idaho was improperly installed to
withstand anticipated service conditions. All of the studs on one side of the flange



were too short to go all the way through some of the nuts. Without the studs going all
the way through the nut, maximum strength is not achieved and the applicable flange
fitting may not provide the design strength for the flanges or the strength needed for
the applicable Maximum Allowable Operating Pressure.
2. §192.947 What records must an operator keep?
(d) Documents to support any decision, analysis and process developed and used
to implement and evaluate each element of the baseline assessment plan and
integrity management program. Documents include those developed and used in
support of any identification, calculation, amendment, modification, justification,
deviation and determination made, and any action taken to implement and
evaluate any of the program elements.
Documents to support GTN’s analysis and decision making process used to conduct
their risk analysis of its pipeline to identify additional measures to protect their high
consequences areas per §192.935 were not provided to our inspectors. The list of
Preventative and Mitigative Measures (P&M Measures) implemented on the pipeline
system and presented to the inspection team did not include any documents that GTN
used to support the decisions, analysis, processes, or developed to support the
identification, applicable calculations, amendments, modifications, justifications,
deviations and determinations made by GTN to justify any action taken regarding the
program elements on the P&M Measures list. The operator is required to keep records
used to implement and evaluate each element to their Integrity Management program
including their P&M Measures per §192.935.
3. §192.745 Valve maintenance: Transmission lines.
(a) Each transmission line valve that might be required during any emergency
must be inspected and partially operated at intervals not exceeding 15 months,
but at least once each calendar year.
(b) Each operator must take prompt remedial action to correct any valve found
inoperable, unless the operator designates an alternative valve.
Valve 20-A, line bypass at Starbuck Compressor #7, (Wallula District, WA), leaked or
sprayed oil over the all of the external surfaces of the valve assembly. GTN personnel
stated that the valve was still operational but believed it needs a new poppet valve.
During the last valve inspection, the GTN inspection noted that between 5 and 10
gallons of hydraulic oil had to be added to the valve’s oil reservoir.
4
§192.481(b) Atmospheric corrosion control: Monitoring.
(b) During inspections the operator must give particular attention to pipe at soil-
to-air interfaces, under thermal insulation, under disbonded coatings, at pipe
supports, in splash zones, at deck penetrations, and in spans over water.
1) The A-Line pig bypass line at the Starbuck Compressor station #7, (Wallula
2



District, WA) had areas of disbonded tape wrap at the soil to air interface. The tape
wrap appeared to be sagging off the bottom of the pipeline where it entered the
soil. It could not be determined whether this visible tape wrap is a secondary
protective coating over, for example a Fusion Bound Epoxy (FBE) coating, or it is
the primary coating at the soil/air interface. If the tape wrap is the primary coating,
there is the possibility that water and soil could be in direct contact with the pipe
and cause corrosion issues.
2) The A-Line pig receiver piping at the Rosalia Compressor station (Rosalia District,
WA) showed signs of surface rust through the coating at the soil to air interface. It
appears that there is only a paint coating where the pipe is partially resting on soil
and is a wrap coating. It could not be determined whether this visible tape wrap is
a secondary protective coating over, for example a Fusion Bound Epoxy (FBE)
coating, or it is the primary coating at the soil/air interface. If the tape wrap is the
primary coating, there is the possibility that water and soil could be in direct
contact with the pipe and cause corrosion issues. It could not be determined
during the inspection whether the rust is bleeding through paint or through an FBE
coating.
3) The crossover blowdown at the top of an in-line tee fitting at the soil to air
interface at the Rosalia Compressor station (Rosalia District, WA) had visible rust
and possible corrosion. The tape wrap was peeled away and was disbonded from
the pipe leaving the potential for moisture under the wrap and potential corrosion.
Some type of sealant or filler was previously applied around the pipe at the top of
the tape wrap. The sealant has cracked away from the pipe and wrap leaving a
portion of the pipe above the wrap exposed to what appears to be bare pipe.
5. §192.481(b) Atmospheric corrosion control: Monitoring.
(c) If atmospheric corrosion is found during an inspection, the operator must
provide protection against the corrosion as required by §192.479.
The A-Line pig bypass line at the Starbuck Compressor station #7, (Wallula District,
WA) had an area above the soil/air interface where the coating appears to have been
knocked off the pipeline. Surface rust was visible as are signs of possible early
corrosion where the coating was missing and appeared to be chipped off of the pipe.
There were areas of cracking in the remaining coating where moisture could wick
under the coating and be trapped causing corrosion issues.
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to
exceed $209,002 per violation per day the violation persists, up to a maximum of $2,090,022
for a related series of violations. For violations occurring prior to November 2, 2015, the
maximum penalty may not exceed $200,000 per violation per day, with a maximum penalty
not to exceed $2,000,000 for a related series of violations. We have reviewed the
3



circumstances and supporting documents involved in this case, and have decided not to
conduct additional enforcement action or penalty assessment proceedings at this time.
We advise you to correct the item(s) identified in this letter during future construction
activities. Failure to do so will result in Gas Transmission Northwest Pipeline System being
subject to additional enforcement action. No reply to this letter is required. If you choose to
reply, in your correspondence please refer to CPF 5-2019-1006W. Be advised that all
material you submit in response to this enforcement action is subject to being made publicly
available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b).
Sincerely,
Chris Hoidal
Acting Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP 60 Compliance Registry
PHP-500 B. Brown (#157147, 160064, 160666, 160063, 160062, 164173)
4
- **truncated:** false
- **body characters:** 9056
