# INTERIOR GAS UTILITY — Notice of Amendment

- **operation:** document
- **citation:** CPF 52022016NOA
- **title:** INTERIOR GAS UTILITY — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2022-11-03
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 192.605(b)(1), 192.605(b)(2), 192.605(b)(3), 192.605(b)(4), 192.614(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-52022016noa.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-52022016noa.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-52022016noa
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/52022016NOA
**body:**

Notice of Amendment involving INTERIOR GAS UTILITY. PHMSA's enforcement data identifies the cited regulations as 192.605(b)(1),  192.605(b)(2),  192.605(b)(3),  192.605(b)(4),  192.614(a). The case was opened on 2022-11-03 and is reported as closed as of 2023-01-31. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

52022016NOA_Closure Letter_01312023_(21-217219).pdf: https://primis.phmsa.dot.gov/enforcement-documents/52022016NOA/52022016NOA_Closure%20Letter_01312023_(21-217219).pdf

52022016NOA_Closure Letter_01312023_(21-217219)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/52022016NOA/52022016NOA_Closure%20Letter_01312023_(21-217219)_text.pdf

52022016NOA_Notice of Amendment_11032022_(21-217219).pdf: https://primis.phmsa.dot.gov/enforcement-documents/52022016NOA/52022016NOA_Notice%20of%20Amendment_11032022_(21-217219).pdf

52022016NOA_Notice of Amendment_11032022_(21-217219)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/52022016NOA/52022016NOA_Notice%20of%20Amendment_11032022_(21-217219)_text.pdf

52022016NOA_Operator Response to Notice_12012022_(21-217219).pdf: https://primis.phmsa.dot.gov/enforcement-documents/52022016NOA/52022016NOA_Operator%20Response%20to%20Notice_12012022_(21-217219).pdf

52022016NOA_Notice of Amendment_11032022_(21-217219)_text.pdf

NOTICE OF AMENDMENT
VIA E-MAIL TO MR. DANIEL BRITTON
November 3, 2022
Mr. Daniel Britton
General Manager
Interior Gas Utility
2525 Phillips Field Road
Fairbanks, AK 99709
CPF 5-2022-016-NOA
Dear Mr. Britton:
From August 2 through 6, 2021, representatives of the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code, inspected Interior
Gas Utility’s (IGU) procedures for Maintenance & Operations, Emergency Operations,
Reporting, Design & Construction and Distribution Integrity Management in Fairbanks, Alaska.
On the basis of the inspection, PHMSA has identified apparent inadequacies found within IGU’s
plans or procedures, as described below:
1. § 192.605 Procedural manual for operations, maintenance, and emergencies.
(a) . . .
(b) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following, if applicable, to provide
safety during maintenance and operations.
(1) Operating, maintaining, and repairing the pipeline in accordance with each of
the requirements of this subpart and subpart M of this part.



IGU Standard Operating Procedures (SOP) were inadequate because they did not include
processes to operate, maintain and repair the pipeline as required by § 192.605. The following
inadequacies were discovered:
1. SOP S1-7125 Relief, ESD, Regulator and Control Systems Maintenance stated under
Pressure Safety Relief Valve Test Procedure section 2 that, “[d]istribution header
pressure relief valve will be tested annually to have enough capacity, be operable and
pressure to not exceed MAOP of 60 psi." The procedure listed under number three
directed testing the relief valve on a testing bench, disconnected from the system. The
procedure failed to require testing the capacity of the Pressure Safety Relief Valve in-
place or by review and calculations as required by § 192.743(a).
2. The SOPs for Sites 3 and 4 (SOP S3-7125 LNG Site #3 Relief, ESD, Regulator and
Control System Maintenance and SOP S4-7125 Relief, ESD, Regulator and Control
System Maintenance) required annual testing of the distribution header pressure relief
valve. The SOPs were inadequate because Sites 3 and 4 did not have pressure relief
valves at the distribution headers. It is notable that the procedures requiring the
distribution header pressure relief valve to “be tested annually to have enough capacity,
be operable and pressure to not exceed MAOP of 60 psi” was identical to the SOP for
Site 1, though Site 1 had a Pressure Safety Relief Valve and Sites 3 and 4 did not.
3. SOP S3-7125 LNG Site #3 Relief, ESD, Regulator and Control System Maintenance
stated on page 3 as follows: "Regulators that must be inspected and tested are: a.
Distribution/Meter Run regulator." Site 3 has four regulators connected to the distribution
header: PCV 400a, PCV 400b, PCV 401a, and PCV 401b. The procedure did not specify
that each of these regulators must be included in the inspection.
4. The procedures did not require equipment used in joining plastic pipe to be maintained in
accordance with the manufacturer's recommended practices or with written procedures
that had been proven by test and experience to produce acceptable joints, as required by §
192.756.
5. The procedures did not state MAOP limits as described in § 192.619. SOP D-2115
Maximum Allowable Operating Pressure did not require that the MAOP be the lowest of
the Design Pressure determined by the HDPE material characteristics and division of 1.5
of the test pressure. The procedures also failed to state that the amount of allowable
build-up is limited to 10% above MAOP.
IGU must amend its procedures to (1) require testing the capacity of the Pressure Safety Relief
Valve in-place or by review and calculations as required by § 192.743(a); (2) appropriately
account for differing equipment in site specific documents; (3) specify that all regulators must be
included in the inspection; (4) require equipment used in joining plastic pipe to be maintained in
accordance with the manufacturer's recommended practices or with written procedures that had
been proven by test and experience to produce acceptable joints as required by § 192.756; (5)
include requirements for telemetering readings; and (6) require that the MAOP be the lowest of
the Design Pressure determined by the HDPE material characteristics and division of 1.5 of the
test pressure, and state that the amount of allowable build-up is limited to 10% above MAOP.
2. § 192.605 Procedural manual for operations, maintenance, and emergencies.



(a) . . .
(b) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following, if applicable, to provide
safety during maintenance and operations.
(1) . . .
(2) Controlling corrosion in accordance with the operations and maintenance
requirements of subpart I of this part.
IGU SOPs were inadequate to meet the requirements of § 192.605 (b)(2). S1-7205 Corrosion
Control, S3-7205 LNG Site #3 Corrosion Control, and S4-7205 Corrosion Control included
procedures to inspect distribution headers at the LNG storage Sites 1, 3, and 4, respectively.
However, IGU did not have a procedure that outlined atmospheric corrosion inspections of
aboveground distribution piping outside of the LNG storage sites, such as at customer meter
sets. Nor did the operator have a tracking process that ensured each meter set was inspected at
the required intervals. IGU must amend its procedures to include a procedure outlining
atmospheric corrosion inspections of aboveground distribution piping outside of the LNG
storage sites, as well as a tracking process to ensure that each meter set is inspected at required
intervals.
3. § 192.605 Procedural manual for operations, maintenance, and emergencies.
(a) . . .
(b) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following, if applicable, to provide safety
during maintenance and operations.
(1) . . .
(3) Making construction records, maps, and operating history available to
appropriate operating personnel.
IGU SOPs failed to meet the requirements of § 192.605 (b)(3). IGU's procedures did not include
a requirement to make construction records, maps, and operating history available to appropriate
operating personnel. IGU must amend its SOPs to include a procedure for making construction
records, maps, and operating history available to appropriate operating personnel.
4. § 192.605 Procedural manual for operations, maintenance, and emergencies.
(a) . . . .
(b) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following, if applicable, to provide
safety during maintenance and operations.
(1) . . . .
(4) Gathering of data needed for reporting incidents under Part 191 of this chapter
in a timely and effective manner.
IGU SOPs were inadequate to meet the requirements of § 192.605(b)(4) and § 191.9(a). SOP G-
1005 Reporting did not require preparation and filing of an incident report as soon as practicable,



but no later than 30 days after discovery of a reportable incident for their distribution system.
IGU must amend its procedures to comply with the requirements of § 191.9(a).
5. § 192.614 Damage prevention program.
(a) Except as provided in paragraphs (d) and (e) of this section, each operator of a
buried pipeline must carry out, in accordance with this section, a written program
to prevent damage to that pipeline from excavation activities. For the purposes of
this section, the term “excavation activities” includes excavation, blasting, boring,
tunneling, backfilling, the removal of aboveground structures by either explosive or
mechanical means, and other earthmoving operations.
IGU SOPs were inadequate to meet the requirements of § 192.614. Specifically, SOP D-1405
Line Locating Policy and Procedures did not include detail describing how the Excavator
Mailing List, which is required by § 192.614(c)(1), is compiled. Further, there was no clause in
the procedure requiring IGU to conduct an inspection of its system if personnel suspected that
excavation activities had damaged a line, which is required by § 192.614(c)(6). IGU must
amend its procedures to describe how the Excavator Mailing List is compiled and require IGU to
conduct an inspection of its system if damage to a line is suspected.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings.
Please refer to this document and note the response options. Be advised that all material you
submit in response to this enforcement action is subject to being made publicly available. If you
believe that any portion of your responsive material qualifies for confidential treatment under 5
U.S.C. 552(b), along with the complete original document you must provide a second copy of
the document with the portions you believe qualify for confidential treatment redacted and an
explanation of why you believe the redacted information qualifies for confidential treatment
under 5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under §190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this
Notice and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in
this Notice without further notice to you and to issue an Order Directing Amendment. If your
plans or procedures are found inadequate as alleged in this Notice, you may be ordered to amend
your plans or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not
contesting this Notice, we propose that you submit your amended procedures to my office within
90 days of receipt of this Notice. This period may be extended by written request for good
cause. Once the inadequacies identified herein have been addressed in your amended
procedures, this enforcement action will be closed.



It is requested (not mandated) that Interior Gas Utility maintain documentation of the safety
improvement costs associated with fulfilling this Notice of Amendment (preparation/revision of
plans, procedures) and submit the total to Dustin Hubbard, Director, Western Region, Pipeline
and Hazardous Materials Safety Administration. In correspondence concerning this matter,
please refer to CPF 5-2022-016-NOA and, for each document you submit, please provide a copy
in electronic format whenever possible.
Sincerely,
Dustin Hubbard
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings
cc: PHP-60 Compliance Registry
PHP-500 G. St. Pierre (#21-217219)
Mark Rockwell, Interior Gas Utility (via email)
Brendan Kern, Engineer, Interior Gas Utility (via email)

52022016NOA_Closure Letter_01312023_(21-217219)_text.pdf

VIA E-MAIL TO MR. DANIEL BRITTON
January 31, 2023
Mr. Daniel Britton
General Manager
Interior Gas Utility
2525 Phillips Field Road
Fairbanks, AK 99709
CPF 5-2022-016-NOA
Closure Letter
Dear Mr. Britton:
From August 2 through 6, 2021, representatives from the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to chapter 601 of 49 United States Code, conducted an on-site
pipeline safety inspection of Interior Gas Utility’s (IGU) procedures in Fairbanks, Alaska. As a result of
the inspection, IGU was issued a Notice of Amendment on November 3, 2022, which proposed
amendment of your procedures.
IGU submitted its amended procedures on December 1, 2022 and subsequent information on January 16,
2023. My staff reviewed the amended procedures, and it appears that the inadequacies outlined in this
Notice of Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you for your
cooperation.
Sincerely,
Dustin Hubbard
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 G. St. Pierre (#21-217219)
Mark Rockwell, Interior Gas Utility (via email)
Brendan Kern, Interior Gas Utility (via email)