# Failure Report- Kiantone Pipeline Company 8/25/15

- **operation:** document
- **citation:** PHMSA FIR, Kiantone Pipeline Company, 2015-08-25
- **title:** Failure Report- Kiantone Pipeline Company 8/25/15
- **source type:** incident
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2016-06-09
- **effective on:** 2015-08-25
- **summary:** Kiantone Pipeline Company; Hazardous Liquid; PA; failure 2015-08-25; apparent cause: Natural Force Damage.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-kiantone-pipeline-company-82515.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-kiantone-pipeline-company-82515.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-kiantone-pipeline-company-82515
- **source url:** https://www.phmsa.dot.gov/safety-reports/failure-report-kiantone-pipeline-company-82515
**body:**

<<<PAGE 1>>>

Failure Investigation Report – Kiantone Tank Line Leak, West Seneca New York
DOT US Department of Transportation
PHMSA Pipeline and Hazardous Materials Safety Administration
OPS Office of Pipeline Safety Eastern Region
Principal Investigator Terry Wasielewski, NYSDPS
Senior Accident Investigator Michael Yazemboski, PHMSA
Region Director Byron Coy
Date of Report 3/28/2016
Subject Failure Investigation Report – Kiantone Pipeline Company – Cracked 2
inch NPS Drain - Crude Oil Leak, West Seneca Terminal, NY
Operator, Location, & Consequences
Date of Failure 08/25/2015
Commodity Released Heavy Crude Oil
City/County & State West Seneca, New York
OpID & Operator Name 10250, Kiantone Pipeline Company
Unit # & Unit Name #761, West Seneca Terminal
SMART Activity # 151195
Milepost / Location 550 Meyers Road, West Seneca, NY 14224
Type of Failure Leak
Fatalities 0
Injuries 0
Description of area
impacted
Leak at base of Tank 703 inside a diked area which is inside the fenced in
West Seneca Pipeline terminal
Total Costs $42,430
Page 1 of 4

<<<PAGE 2>>>

Failure Investigation Report – Kiantone Tank Line Leak, West Seneca New York
Executive Summary
On August 25, 2015, the New York State Department
of Public Service (NYSDPS) received notification of a
product release at the Kiantone Pipeline Tank Facility
located in West Seneca, NY. The leak was identified
by a Kiantone employee at approximately 10:00
during a routine patrol. The leak was located near the
base of Tank 703 within a diked area. Approximately
5 gallons of heavy crude oil was released. The cause
of the incident was a cracked Weldolet branch
connection fitting on a 2-inch NPS pump line. A bolted
repair sleeve was installed, and the line was
pressurized and monitored for 24 hours before being
backfilled and returned to service. There were no
evacuations, injuries, deaths, or property damage
associated with this incident.
System Details
Kiantone Pipeline Corporation is owned and operated
by the United Refining Company (URC) of Warren, PA. Its purpose is to receive, store, blend and
transport crude oil for the URC refinery located in Warren.
The Kiantone pipeline is 78 miles long, connecting West Seneca Terminal, near Buffalo NY, to the
refinery at Warren, PA, through a tank farm 3.4 miles from the refinery.
West Seneca Terminal is the custody transfer point for ownership of the crude entering Kiantone. This
terminal contains crude oil meters, pumps and tanks, and serves as the originating station for Kiantone
Pipeline. Terminal operations are coordinated by Kiantone Pipeline staff, along with personnel from the
Warren Lab Control Center.
Oil enters the terminal and flows into the incoming meter manifold, where the oil volume is measured
by positive displacement meters. Two of the four meters are in use during normal operations.
Oil flows to one of the three aboveground storage tanks (701, 702, or 703). Tank 701 contains sweet
crude, 702 contains asphaltic crude, and 703 contains sour crude.
Each tank has an incoming and outgoing line, with a motor-operated valve on each. The tanks have
hardware and software level alarms, and a Varec automatic tank gauge. The tanks are surrounded by
dikes, which are designed to contain oil in the event of a spill. Each dike has a drain valve to release any
accumulated water.
The failure was on a 2-inch drain line on the bottom of a 12-inch NPS line which travels from the sample
building to Tank 703.
Events Leading up to the Failure
Tank 703 was out of service for an internal inspection. The input line to the tank had a blind flange on it,
and was closed in with crude in it at a pressure of approximately 15 psig. The leak located at the ground
interface was discovered by an inspector.
Page 2 of 4

<<<PAGE 3>>>

Failure Investigation Report – Kiantone Tank Line Leak, West Seneca New York
Emergency Response
Approximately 5 gallons of heavy crude oil was spilled on the ground. Kiantone implemented their OPA
plan for a liquid spill. Kiantone shut down the West Seneca facility, and immediately notified PHMSA
through NRC 1126637. They also contacted the New York State Department of Public Service (NYSDPS),
along with all other State and Federal agencies outlined in their emergency plan.
Summary of Return-to-Service
Kiantone conducted an investigation to determine the root cause of the crude oil release. Kiantone
contracted a local excavation company and an environmental contractor to assist in the cleanup of the
area. A 20 foot by 10 foot area around the 12-inch pipeline was excavated to a depth of approximately 7
feet.
Kiantone removed the surrounding soil, applied absorbents and removed any excess oil with a vacuum
truck. The soil was stored in a plastic lined container and removed per New York Department of
Environmental Conversation (NYSDEC) regulations.
The leak was identified on a 2-inch Weldolet on the bottom of the 12-inch NPS pumpout line. The
Weldolet was cracked and the crude oil was leaking from the crack. Kiantone installed a modified 12-
inch Plidco clamp over the cracked section that included the 2 inch weldolet. Kiantone pressurized the
line to 20 psig and then monitored the repair for 24 hours. The clamp was coated per Kiantone’s
cathodic protection procedures. The area was then backfilled with fly ash to within 18 inches of grade
and left to settle for 24 hours. Once settled, the line was covered with fill.
Investigation Details
Kiantone conducted an internal investigation of this event,
as documented in their Form 2.2.1 (Appendix F). This form
documents their review of a number of different factors
involved including:
Control Room Factors – Kiantone reviewed controller
actions and activities and found no evidence of them being
a causative factor to this event. This review included CR procedures, fatigue issues and CR equipment.
HCA Impacts – Kiantone’s Integrity Management plan (IMP) identifies this pipeline facility as a “could
affect” segment for both high population and drinking water HCAs. The release was contained within
the diked area around the tank and no impacts were noted.
Physical Analysis – Kiantone’s in-house subject matter experts conducted a physical examination of the
cracked piping before the repair clamp was installed. They attributed the pipe failure to natural force
damage resulting from years of freeze/thaw cycles. The cracked piping was not removed from the
system or sent out for metallurgical analysis.
Findings and Contributing Factors
Page 3 of 4

<<<PAGE 4>>>

Failure Investigation Report – Kiantone Tank Line Leak, West Seneca New York
The apparent cause of this failure was natural force damage. The distorted shape of the piping is
consistent with long term force actions. There were no indications of a pressure exceedance, corrosion
or mechanical damage. Control room records and procedures were reviewed and ruled out as a
causative factor. No metallurgical analysis was conducted.
Appendices
A Maps
B Photos
C Incident Report Form 7000.1
D NRC Report 1126637
E Kiantone Failure Investigation Report
Page 4 of 4

<<<PAGE 5>>>

151195 Appendix A - Maps
Wehrle Dr
(78
Wehrle Dr
Wehrle Dr
Niagara Pkwy
190
Hertel Ave
Wehrle Di
Buffalo Crushed
Stone Quarry
•New YorkS
Cleveland Hill
(33
The Buffalo Zoo a
International Airport *
Buffalo Niagara
BLACK ROG
33
[155
21
198
Forest Ave
5
Pleasant View Dr
Walden Ave
(124
122)
19
ELMWOOD
(240)
VILLAGE
Pine Hill
Walden Ave
Fillmore Ave
George Urban Blvd
Sunset Di
Inited State
Jefferson Ave
Walden Ave
Dellwood
Doat St
Walden Ave
Walden Ave
Fort Erie
266
Best St
ALLENTOWN
33
Cheektowaga
Depew
20
139
Sycamore St
Broadway
Sloan
277
1
Bellevue
•Broadway
Town Line
Buffalo
354
William St
Union
Losson Rd
William St
William St
90
354
French Rd
South Park Ave
(16
277)
Abbott Rd
354
354)
Hopkins St
Kiantone Pipeline
Corporation
Seneca Creek Rdi
(20
Elma
Potters Ro
West Seneca
Bullis Rd
Bullis Rd
90
East Seneca
Lackawanna
(219
(400)
Elma Center
Fisher Rd
(240
78
E and West Rd
Rice Rd
Rice Rd
Martin Rd
Spring Brook
277) Reserve Rd
(20
Girdle
PY SIRON
Michael Rd
187)
-Jamison Rd
Woodlawn
(62)
Lake Ave
Windom.
Milestrip Rd
Websters
Billington
(20)
Corners
Heights
Bariew Re
Willardshire Rd
Ralph Wilson Stadium wi
Athol Springs
Orchard Park
Knox Farm East Aurora
20A
State Park
(20A
P10g9V
Mt Vernon
Jewett Holmwood
400
Wanakah
Google
(62)
Map data ©2016 Google
2 mi
Page 1 of 3

<<<PAGE 6>>>

151195 Appendix A - Maps
MineraliSprings Rdi
Indian Church
Indian Church Rd
Buffalo Cree
Indian Church Rd
BOCES©
HarlemS
Kiantone Pipeline
Corporation
Buffalo Niagara O
Court Center
Aurora Expy
Harlem Ra
Google
Imagery ©2016 Google, Map data ©2016 Google
500 ft
Page 2 of 3

<<<PAGE 7>>>

151195 Appendix A - Maps
@
Kiantone Pipeline
Corporation
(b) (7)(F)
Google
Imagery ©2016 Google, Map data ©2016 Google
100 ft
Page 3 of 3

<<<PAGE 8>>>

151195 Appendix B - Photos
PHOTO #1: Crack on the 2” pumpout line, connected to the 12” tank line at the 6 o’clock position
Photo by Terry Wasielewski, NYSDPS, 08/25/2015
Page 1 of 3

<<<PAGE 9>>>

151195 Appendix B - Photos
Photo #2 – Installed repair clamp
Photo by Terry Wasielewski, NYSDPS, 08/25/2015
Page 2 of 3

<<<PAGE 10>>>

151195 Appendix B - Photos
Photo #3 – Incident location in reference to Tank 703
Photo by Terry Wasielewski, NYSDPS, 08/25/2015
Page 3 of 3

<<<PAGE 11>>>

151195 Appendix C - Incident Report 7000.1
NOTICE: This report is required by 49 CFR Part 195. Failure to report can result in a civil penalty not to
exceed $100,000 for each violation for each day that such violation persists except that the maximum civil
penalty shall not exceed $1,000,000 as provided in 49 USC 60122.
OMB NO: 2137-0047
EXPIRATION DATE: 07/31/2015
Original Report
Date: 09/17/2015
U.S Department of Transportation
Pipeline and Hazardous Materials Safety Administration
No. 20150331 - 20746
--------------------------
(DOT Use Only)
ACCIDENT REPORT - HAZARDOUS LIQUID
PIPELINE SYSTEMS
A federal agency may not conduct or sponsor, and a person is not required to respond to, nor shall a person be subject to a penalty for failure to comply
with a collection of information subject to the requirements of the Paperwork Reduction Act unless that collection of information displays a current valid
OMB Control Number. The OMB Control Number for this information collection is 2137-0047. All responses to the collection of information are mandatory.
Send comments regarding this burden or any other aspect of this collection of information, including suggestions for reducing the burden to: Information
Collection Clearance Officer, PHMSA, Office of Pipeline Safety (PHP-30) 1200 New Jersey Avenue, SE, Washington, D.C. 20590.
INSTRUCTIONS
Important: Please read the separate instructions for completing this form before you begin. They clarify the information requested and provide specific
examples. If you do not have a copy of the instructions, you can obtain one from the PHMSA Pipeline Safety Community Web Page at
http://www.phmsa.dot.gov/pipeline/library/forms.
PART A - KEY REPORT INFORMATION
Report Type: (select all that apply) Original: Supplemental: Final:
Yes
Last Revision Date:
1. Operator's OPS-issued Operator Identification Number (OPID): 10250
2. Name of Operator KIANTONE PIPELINE CORP
3. Address of Operator:
3a. Street Address PO BOX 780
3b. City WARREN
3c. State Pennsylvania
3d. Zip Code 16365
4. Local time (24-hr clock) and date of the Accident: 08/25/2015 10:15
5. Location of Accident:
Latitude:
Longitude:
(b) (7)(F)
6. National Response Center Report Number (if applicable): 1126637
7. Local time (24-hr clock) and date of initial telephonic report to the
National Response Center (if applicable): 08/25/2015 11:57
8. Commodity released: (select only one, based on predominant
volume released) Crude Oil
- Specify Commodity Subtype:
- If "Other" Subtype, Descr be:
- If Biofuel/Alternative Fuel and Commodity Subtype is
Ethanol Blend, then % Ethanol Blend:
- If Biofuel/Alternative Fuel and Commodity Subtype is
Biodiesel, then Biodiesel Blend e.g. B2, B20, B100
9. Estimated volume of commodity released unintentionally (Barrels): .70
10. Estimated volume of intentional and/or controlled release/blowdown
(Barrels):
11. Estimated volume of commodity recovered (Barrels): .70
12. Were there fatalities? No
- If Yes, specify the number in each category:
12a. Operator employees
12b. Contractor employees working for the Operator
12c. Non-Operator emergency responders
12d. Workers working on the right-of-way, but NOT
associated with this Operator
12e. General public
12f. Total fatalities (sum of above)
13. Were there injuries requiring inpatient hospitalization? No
- If Yes, specify the number in each category:
13a. Operator employees
13b. Contractor employees working for the Operator
13c. Non-Operator emergency responders
13d. Workers working on the right-of-way, but NOT
associated with this Operator
13e. General public
Form PHMSA F 7000.1
Page 1 of 13

<<<PAGE 12>>>

151195 Appendix C - Incident Report 7000.1
13f. Total injuries (sum of above)
14. Was the pipeline/facility shut down due to the Accident? Yes
- If No, Explain:
- If Yes, complete Questions 14a and 14b: (use local time, 24-hr clock)
14a. Local time and date of shutdown: 08/25/2015 12:23
14b. Local time pipeline/facility restarted: 08/26/2015 20:50
- Still shut down? (* Supplemental Report Required)
15. Did the commodity ignite? No
16. Did the commodity explode? No
17. Number of general public evacuated: 0
18. Time sequence (use local time, 24-hour clock):
18a. Local time Operator identified Accident - effective 7- 2014
changed to "Local time Operator identified failure": 08/25/2015 10:15
18b. Local time Operator resources arrived on site: 08/25/2015 10:15
PART B - ADDITIONAL LOCATION INFORMATION
1. Was the origin of the Accident onshore? Yes
If Yes, Complete Questions (2-12)
If No, Complete Questions (13-15)
- If Onshore:
2. State: New York
3. Zip Code: 14224
4. City West Seneca
5. County or Parish Erie
6. Operator-designated location: Survey Station No.
Specify: Facility
7. Pipeline/Facility name: West Seneca Terminal
8. Segment name/ID: West Seneca Terminal
9. Was Accident on Federal land, other than the Outer Continental Shelf
(OCS)? No
10. Location of Accident: Totally contained on Operator-controlled property
11. Area of Accident (as found): Underground
Specify: Under soil
- If Other, Descr be:
Depth-of-Cover (in): 36
12. Did Accident occur in a crossing? No
- If Yes, specify type below:
- If Bridge crossing –
Cased/ Uncased:
- If Railroad crossing –
Cased/ Uncased/ Bored/drilled
- If Road crossing –
Cased/ Uncased/ Bored/drilled
- If Water crossing –
Cased/ Uncased
- Name of body of water, if commonly known:
- Approx. water depth (ft) at the point of the Accident:
- Select:
- If Offshore:
13. Approximate water depth (ft) at the point of the Accident:
14. Origin of Accident:
- In State waters - Specify:
- State:
- Area:
- Block/Tract #:
- Nearest County/Parish:
- On the Outer Continental Shelf (OCS) - Specify:
- Area:
- Block #:
15. Area of Accident:
PART C - ADDITIONAL FACILITY INFORMATION
1. Is the pipeline or facility: Interstate
2. Part of system involved in Accident: Onshore Terminal/Tank Farm Equipment and Piping
- If Onshore Breakout Tank or Storage Vessel, Including Attached
Appurtenances, specify:
3. Item involved in Accident: Auxiliary Piping (e.g. drain lines)
- If Pipe, specify:
3a. Nominal diameter of pipe (in):
Form PHMSA F 7000.1
Page 2 of 13

<<<PAGE 13>>>

151195 Appendix C - Incident Report 7000.1
3b. Wall thickness (in):
3c. SMYS (Specified Minimum Yield Strength) of pipe (psi):
3d. Pipe specification:
3e. Pipe Seam , specify:
- If Other, Descr be:
3f. Pipe manufacturer:
3g. Year of manufacture:
3h. Pipeline coating type at point of Accident, specify:
- If Other, Descr be:
- If Weld, including heat-affected zone, specify. If Pipe Girth Weld,
3a through 3h above are required:
- If Other, Descr be:
- If Valve, specify:
- If Mainline, specify:
- If Other, Descr be:
3i. Manufactured by:
3j. Year of manufacture:
- If Tank/Vessel, specify:
- If Other - Descr be:
- If Other, descr be:
4. Year item involved in Accident was installed: 1976
5. Material involved in Accident: Carbon Steel
- If Material other than Carbon Steel, specify:
6. Type of Accident Involved: Leak
- If Mechanical Puncture – Specify Approx. size:
in. (axial) by
in. (circumferential)
- If Leak - Select Type: Other
- If Other, Descr be: mechanical damage
- If Rupture - Select Orientation:
- If Other, Describe:
Approx. size: in. (widest opening) by
in. (length circumferentially or axially)
- If Other – Describe:
PART D - ADDITIONAL CONSEQUENCE INFORMATION
1. Wildlife impact: No
1a. If Yes, specify all that apply:
- Fish/aquatic
- Birds
- Terrestrial
2. Soil contamination: Yes
3. Long term impact assessment performed or planned: No
4. Anticipated remediation: No
4a. If Yes, specify all that apply:
- Surface water
- Groundwater
- Soil
- Vegetation
- Wildlife
5. Water contamination: No
5a. If Yes, specify all that apply:
- Ocean/Seawater
- Surface
- Groundwater
- Drinking water: (Select one or both)
- Private Well
- Public Water Intake
5b. Estimated amount released in or reaching water (Barrels):
5c. Name of body of water, if commonly known:
6. At the location of this Accident, had the pipeline segment or facility
been identified as one that "could affect" a High Consequence Area
(HCA) as determined in the Operator's Integrity Management Program?
Yes
7. Did the released commodity reach or occur in one or more High
Consequence Area (HCA)? Yes
7a. If Yes, specify HCA type(s): (Select all that apply)
- Commercially Navigable Waterway:
Was this HCA identified in the "could affect"
determination for this Accident site in the Operator's
Form PHMSA F 7000.1
Page 3 of 13

<<<PAGE 14>>>

151195 Appendix C - Incident Report 7000.1
Integrity Management Program?
- High Population Area: Yes
Was this HCA identified in the "could affect"
determination for this Accident site in the Operator's
Integrity Management Program?
Yes
- Other Populated Area
Was this HCA identified in the "could affect" determination
for this Accident site in the Operator's Integrity
Management Program?
- Unusually Sensitive Area (USA) - Drinking Water Yes
Was this HCA identified in the "could affect" determination
for this Accident site in the Operator's Integrity
Management Program?
Yes
- Unusually Sensitive Area (USA) - Ecological
Was this HCA identified in the "could affect" determination
for this Accident site in the Operator's Integrity
Management Program?
8. Estimated cost to Operator – effective 12-2012, changed to "Estimated Property Damage":
8a. Estimated cost of public and non-Operator private property
damage paid/reimbursed by the Operator – effective 12-2012,
"paid/reimbursed by the Operator" removed
$ 0
8b. Estimated cost of commodity lost $ 30
8c. Estimated cost of Operator's property damage & repairs $ 10,000
8d. Estimated cost of Operator's emergency response $ 16,400
8e. Estimated cost of Operator's environmental remediation $ 16,000
8f. Estimated other costs $ 0
Descr be:
8g. Estimated total costs (sum of above) – effective 12-2012,
changed to "Total estimated property damage (sum of above)" $ 42,430
PART E - ADDITIONAL OPERATING INFORMATION
1. Estimated pressure at the point and time of the Accident (psig): 15.00
2. Maximum Operating Pressure (MOP) at the point and time of the
Accident (psig): 150.00
3. Describe the pressure on the system or facility relating to the
Accident (psig): Pressure did not exceed MOP
4. Not including pressure reductions required by PHMSA regulations
(such as for repairs and pipe movement), was the system or facility
relating to the Accident operating under an established pressure
restriction with pressure limits below those normally allowed by the
MOP?
No
- If Yes, Complete 4.a and 4.b below:
4a. Did the pressure exceed this established pressure
restriction?
4b. Was this pressure restriction mandated by PHMSA or the
State?
5. Was "Onshore Pipeline, Including Valve Sites" OR "Offshore
Pipeline, Including Riser and Riser Bend" selected in PART C, Question
2?
No
- If Yes - (Complete 5a. – 5f below) effective 12-2012, changed to "(Complete 5.a – 5.e below)"
5a. Type of upstream valve used to initially isolate release
source:
5b. Type of downstream valve used to initially isolate release
source:
5c. Length of segment isolated between valves (ft):
5d. Is the pipeline configured to accommodate internal
inspection tools?
- If No, Which physical features limit tool accommodation? (select all that apply)
- Changes in line pipe diameter
- Presence of unsuitable mainline valves
- Tight or mitered pipe bends
- Other passage restrictions (i.e. unbarred tee's,
projecting instrumentation, etc.)
- Extra thick pipe wall (applicable only for magnetic
flux leakage internal inspection tools)
- Other -
- If Other, Descr be:
5e. For this pipeline, are there operational factors which
significantly complicate the execution of an internal inspection tool
run?
- If Yes, Which operational factors complicate execution? (select all that apply)
Form PHMSA F 7000.1
Page 4 of 13

<<<PAGE 15>>>

151195 Appendix C - Incident Report 7000.1
- Excessive debris or scale, wax, or other wall buildup
- Low operating pressure(s)
- Low flow or absence of flow
- Incompatible commodity
- Other -
- If Other, Descr be:
5f. Function of pipeline system: > 20% SMYS Regulated Trunkline/Transmission
6. Was a Supervisory Control and Data Acquisition (SCADA)-based
system in place on the pipeline or facility involved in the Accident? Yes
If Yes -
6a. Was it operating at the time of the Accident? Yes
6b. Was it fully functional at the time of the Accident? Yes
6c. Did SCADA-based information (such as alarm(s),
alert(s), event(s), and/or volume calculations) assist with
the detection of the Accident?
No
6d. Did SCADA-based information (such as alarm(s),
alert(s), event(s), and/or volume calculations) assist with
the confirmation of the Accident?
No
7. Was a CPM leak detection system in place on the pipeline or facility
involved in the Accident? No
- If Yes:
7a. Was it operating at the time of the Accident?
7b. Was it fully functional at the time of the Accident?
7c. Did CPM leak detection system information (such as
alarm(s), alert(s), event(s), and/or volume calculations) assist
with the detection of the Accident?
7d. Did CPM leak detection system information (such as
alarm(s), alert(s), event(s), and/or volume calculations) assist
with the confirmation of the Accident?
8. How was the Accident initially identified for the Operator? Local Operating Personnel, including contractors
- If Other, Specify:
8a. If "Controller", "Local Operating Personnel", including
contractors", "Air Patrol", or "Ground Patrol by Operator or its
contractor" is selected in Question 8, specify:
Contractor working for the Operator
9. Was an investigation initiated into whether or not the controller(s) or
control room issues were the cause of or a contributing factor to the
Accident?
- If No, the Operator did not find that an investigation of the
controller(s) actions or control room issues was necessary due to:
(provide an explanation for why the operator did not investigate)
No, the Operator did not find that an investigation of the
controller(s) actions or control room issues was necessary
due to: (provide an explanation for why the Operator did not
investigate)
Cause of leak was unrelated to pipeline operations or
controller actions
- If Yes, specify investigation result(s): (select all that apply)
- Investigation reviewed work schedule rotations,
continuous hours of service (while working for the
Operator), and other factors associated with fatigue
- Investigation did NOT review work schedule rotations,
continuous hours of service (while working for the
Operator), and other factors associated with fatigue
Provide an explanation for why not:
- Investigation identified no control room issues
- Investigation identified no controller issues
- Investigation identified incorrect controller action or
controller error
- Investigation identified that fatigue may have affected the
controller(s) involved or impacted the involved controller(s)
response
- Investigation identified incorrect procedures
- Investigation identified incorrect control room equipment
operation
- Investigation identified maintenance activities that affected
control room operations, procedures, and/or controller
response
- Investigation identified areas other than those above:
Descr be:
PART F - DRUG & ALCOHOL TESTING INFORMATION
1. As a result of this Accident, were any Operator employees tested
under the post-accident drug and alcohol testing requirements of DOT's
Drug & Alcohol Testing regulations?
No
- If Yes:
1a. Specify how many were tested:
Form PHMSA F 7000.1
Page 5 of 13

<<<PAGE 16>>>

151195 Appendix C - Incident Report 7000.1
1b. Specify how many failed:
2. As a result of this Accident, were any Operator contractor employees
tested under the post-accident drug and alcohol testing requirements of
DOT's Drug & Alcohol Testing regulations?
No
- If Yes:
2a. Specify how many were tested:
2b. Specify how many failed:
PART G – APPARENT CAUSE
Select only one box from PART G in shaded column on left representing the APPARENT Cause of the Accident, and answer
the questions on the right. Describe secondary, contributing or root causes of the Accident in the narrative (PART H).
Apparent Cause: G2 - Natural Force Damage
G1 - Corrosion Failure - only one sub-cause can be picked from shaded left-hand column
Corrosion Failure – Sub-Cause:
- If External Corrosion:
1. Results of visual examination:
- If Other, Descr be:
2. Type of corrosion: (select all that apply)
- Galvanic
- Atmospheric
- Stray Current
- Microbiological
- Selective Seam
- Other:
- If Other, Descr be:
3. The type(s) of corrosion selected in Question 2 is based on the following: (select all that apply)
- Field examination
- Determined by metallurgical analysis
- Other:
- If Other, Descr be:
4. Was the failed item buried under the ground?
- If Yes :
4a. Was failed item considered to be under cathodic
protection at the time of the Accident?
If Yes - Year protection started:
4b. Was shielding, tenting, or disbonding of coating evident at
the point of the Accident?
4c. Has one or more Cathodic Protection Survey been
conducted at the point of the Accident?
If "Yes, CP Annual Survey" – Most recent year conducted:
If "Yes, Close Interval Survey" – Most recent year conducted:
If "Yes, Other CP Survey" – Most recent year conducted:
- If No:
4d. Was the failed item externally coated or painted?
5. Was there observable damage to the coating or paint in the vicinity of
the corrosion?
- If Internal Corrosion:
6. Results of visual examination:
- Other:
7. Type of corrosion (select all that apply): -
- Corrosive Commodity
- Water drop-out/Acid
- Microbiological
- Erosion
- Other:
- If Other, Descr be:
8. The cause(s) of corrosion selected in Question 7 is based on the following (select all that apply): -
- Field examination
- Determined by metallurgical analysis
- Other:
- If Other, Descr be:
9. Location of corrosion (select all that apply): -
- Low point in pipe
- Elbow
- Other:
Form PHMSA F 7000.1
Page 6 of 13

<<<PAGE 17>>>

151195 Appendix C - Incident Report 7000.1
- If Other, Descr be:
10. Was the commodity treated with corrosion inhibitors or biocides?
11. Was the interior coated or lined with protective coating?
12. Were cleaning/dewatering pigs (or other operations) routinely
utilized?
13. Were corrosion coupons routinely utilized?
Complete the following if any Corrosion Failure sub-cause is selected AND the "Item Involved in Accident" (from PART C,
Question 3) is Tank/Vessel.
14. List the year of the most recent inspections:
14a. API Std 653 Out-of-Service Inspection
- No Out-of-Service Inspection completed
14b. API Std 653 In-Service Inspection
- No In-Service Inspection completed
Complete the following if any Corrosion Failure sub-cause is selected AND the "Item Involved in Accident" (from PART C,
Question 3) is Pipe or Weld.
15. Has one or more internal inspection tool collected data at the point of the
Accident?
15a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run: -
- Magnetic Flux Leakage Tool
Most recent year:
- Ultrasonic
Most recent year:
- Geometry
Most recent year:
- Caliper
Most recent year:
- Crack
Most recent year:
- Hard Spot
Most recent year:
- Combination Tool
Most recent year:
- Transverse Field/Triaxial
Most recent year:
- Other
Most recent year:
Descr be:
16. Has one or more hydrotest or other pressure test been conducted since
original construction at the point of the Accident?
If Yes -
Most recent year tested:
Test pressure:
17. Has one or more Direct Assessment been conducted on this segment?
- If Yes, and an investigative dig was conducted at the point of the Accident::
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site:
Most recent year conducted:
18. Has one or more non-destructive examination been conducted at the
point of the Accident since January 1, 2002?
18a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Descr be:
G2 - Natural Force Damage - only one sub-cause can be picked from shaded left-handed column
Natural Force Damage – Sub-Cause: Temperature
- If Earth Movement, NOT due to Heavy Rains/Floods:
1. Specify:
Form PHMSA F 7000.1
Page 7 of 13

<<<PAGE 18>>>

151195 Appendix C - Incident Report 7000.1
- If Other, Descr be:
- If Heavy Rains/Floods:
2. Specify:
- If Other, Descr be:
- If Lightning:
3. Specify:
- If Temperature:
4. Specify: Frost Heave
- If Other, Descr be: ,,
- If Other Natural Force Damage:
5. Describe:
Complete the following if any Natural Force Damage sub-cause is selected.
6. Were the natural forces causing the Accident generated in
conjunction with an extreme weather event? No
6a. If Yes, specify: (select all that apply)
- Hurricane
- Tropical Storm
- Tornado
- Other
- If Other, Descr be:
G3 - Excavation Damage - only one sub-cause can be picked from shaded left-hand column
Excavation Damage – Sub-Cause:
- If Previous Damage due to Excavation Activity: Complete Questions 1-5 ONLY IF the "Item Involved in Accident" (from PART
C, Question 3) is Pipe or Weld.
1. Has one or more internal inspection tool collected data at the point of
the Accident?
1a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run: -
- Magnetic Flux Leakage
Most recent year conducted:
- Ultrasonic
Most recent year conducted:
- Geometry
Most recent year conducted:
- Caliper
Most recent year conducted:
- Crack
Most recent year conducted:
- Hard Spot
Most recent year conducted:
- Combination Tool
Most recent year conducted:
- Transverse Field/Triaxial
Most recent year conducted:
- Other
Most recent year conducted:
Descr be:
2. Do you have reason to believe that the internal inspection was
completed BEFORE the damage was sustained?
3. Has one or more hydrotest or other pressure test been conducted since
original construction at the point of the Accident?
- If Yes:
Most recent year tested:
Test pressure (psig):
4. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Accident:
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site:
Most recent year conducted:
5. Has one or more non-destructive examination been conducted at the
point of the Accident since January 1, 2002?
5a. If Yes, for each examination, conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
Form PHMSA F 7000.1
Page 8 of 13

<<<PAGE 19>>>

151195 Appendix C - Incident Report 7000.1
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Descr be:
Complete the following if Excavation Damage by Third Party is selected as the sub-cause.
6. Did the operator get prior notification of the excavation activity?
6a. If Yes, Notification received from: (select all that apply) -
- One-Call System
- Excavator
- Contractor
- Landowner
Complete the following mandatory CGA-DIRT Program questions if any Excavation Damage sub-cause is selected.
7. Do you want PHMSA to upload the following information to CGA-
DIRT (www.cga-dirt.com)?
8. Right-of-Way where event occurred: (select all that apply) -
- Public
- If "Public", Specify:
- Private
- If "Private", Specify:
- Pipeline Property/Easement
- Power/Transmission Line
- Railroad
- Dedicated Public Utility Easement
- Federal Land
- Data not collected
- Unknown/Other
9. Type of excavator:
10. Type of excavation equipment:
11. Type of work performed:
12. Was the One-Call Center notified?
12a. If Yes, specify ticket number:
12b. If this is a State where more than a single One-Call Center
exists, list the name of the One-Call Center notified:
13. Type of Locator:
14. Were facility locate marks vis ble in the area of excavation?
15. Were facilities marked correctly?
16. Did the damage cause an interruption in service?
16a. If Yes, specify duration of the interruption (hours)
17. Description of the CGA-DIRT Root Cause (select only the one predominant first level CGA-DIRT Root Cause and then, where
available as a choice, the one predominant second level CGA-DIRT Root Cause as well):
Root Cause:
- If One-Call Notification Practices Not Sufficient, specify:
- If Locating Practices Not Sufficient, specify:
- If Excavation Practices Not Sufficient, specify:
- If Other/None of the Above, explain:
G4 - Other Outside Force Damage - only one sub-cause can be selected from the shaded left-hand column
Other Outside Force Damage – Sub-Cause:
- If Damage by Car, Truck, or Other Motorized Vehicle/Equipment NOT Engaged in Excavation:
1. Vehicle/Equipment operated by:
- If Damage by Boats, Barges, Drilling Rigs, or Other Maritime Equipment or Vessels Set Adrift or Which Have Otherwise Lost
Their Mooring:
2. Select one or more of the following IF an extreme weather event was a factor:
- Hurricane
- Tropical Storm
- Tornado
- Heavy Rains/Flood
- Other
- If Other, Descr be:
- If Previous Mechanical Damage NOT Related to Excavation: Complete Questions 3-7 ONLY IF the "Item Involved in
Accident" (from PART C, Question 3) is Pipe or Weld.
3. Has one or more internal inspection tool collected data at the point of
Form PHMSA F 7000.1
Page 9 of 13

<<<PAGE 20>>>

151195 Appendix C - Incident Report 7000.1
the Accident?
3a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run:
- Magnetic Flux Leakage
Most recent year conducted:
- Ultrasonic
Most recent year conducted:
- Geometry
Most recent year conducted:
- Caliper
Most recent year conducted:
- Crack
Most recent year conducted:
- Hard Spot
Most recent year conducted:
- Combination Tool
Most recent year conducted:
- Transverse Field/Triaxial
Most recent year conducted:
- Other
Most recent year conducted:
Descr be:
4. Do you have reason to believe that the internal inspection was
completed BEFORE the damage was sustained?
5. Has one or more hydrotest or other pressure test been conducted
since original construction at the point of the Accident?
- If Yes:
Most recent year tested:
Test pressure (psig):
6. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Accident:
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site:
Most recent year conducted:
7. Has one or more non-destructive examination been conducted at the
point of the Accident since January 1, 2002?
7a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Descr be:
- If Intentional Damage:
8. Specify:
- If Other, Descr be:
- If Other Outside Force Damage:
9. Describe:
G5 - Material Failure of Pipe or Weld - only one sub-cause can be selected from the shaded left-hand column
Use this section to report material failures ONLY IF the "Item Involved in Accident" (from PART C, Question 3) is "Pipe" or
"Weld."
Material Failure of Pipe or Weld – Sub-Cause:
1. The sub-cause shown above is based on the following: (select all that apply)
- Field Examination
- Determined by Metallurgical Analysis
- Other Analysis
- If "Other Analysis", Descr be:
- Sub-cause is Tentative or Suspected; Still Under Investigation
(Supplemental Report required)
Form PHMSA F 7000.1
Page 10 of 13

<<<PAGE 21>>>

151195 Appendix C - Incident Report 7000.1
- If Construction, Installation, or Fabrication-related:
2. List contr buting factors: (select all that apply)
- Fatigue or Vibration-related
Specify:
- If Other, Descr be:
- Mechanical Stress:
- Other
- If Other, Descr be:
- If Environmental Cracking-related:
3. Specify:
- If Other - Describe:
Complete the following if any Material Failure of Pipe or Weld sub-cause is selected.
4. Additional factors: (select all that apply):
- Dent
- Gouge
- Pipe Bend
- Arc Burn
- Crack
- Lack of Fusion
- Lamination
- Buckle
- Wrinkle
- Misalignment
- Burnt Steel
- Other:
- If Other, Descr be:
5. Has one or more internal inspection tool collected data at the point of
the Accident?
5a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run:
- Magnetic Flux Leakage
Most recent year run:
- Ultrasonic
Most recent year run:
- Geometry
Most recent year run:
- Caliper
Most recent year run:
- Crack
Most recent year run:
- Hard Spot
Most recent year run:
- Combination Tool
Most recent year run:
- Transverse Field/Triaxial
Most recent year run:
- Other
Most recent year run:
Descr be:
6. Has one or more hydrotest or other pressure test been conducted since
original construction at the point of the Accident?
- If Yes:
Most recent year tested:
Test pressure (psig):
7. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Accident -
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site -
Most recent year conducted:
8. Has one or more non-destructive examination(s) been conducted at the
point of the Accident since January 1, 2002?
8a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted: -
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
Form PHMSA F 7000.1
Page 11 of 13

<<<PAGE 22>>>

151195 Appendix C - Incident Report 7000.1
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Descr be:
G6 – Equipment Failure - only one sub-cause can be selected 
- **truncated:** true
- **body characters:** 48684
