# Failure Report- Southern Star Central Gas Pipeline 3/2/10

- **operation:** document
- **citation:** PHMSA FIR, Southern Star Central Gas Pipeline, 2010-03-02
- **title:** Failure Report- Southern Star Central Gas Pipeline 3/2/10
- **source type:** incident
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2012-02-15
- **effective on:** 2010-03-02
- **summary:** Southern Star Central Gas Pipeline; Gas Transmission; KS; failure 2010-03-02; apparent cause: Material Failure Weld.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-southern-star-central-gas-pipeline-3210-0.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-southern-star-central-gas-pipeline-3210-0.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-southern-star-central-gas-pipeline-3210-0
- **source url:** https://www.phmsa.dot.gov/safety-reports/failure-report-southern-star-central-gas-pipeline-3210-0
**body:**

<<<PAGE 1>>>

DOT US Department of Transportation
PHMSA Pipeline and Hazardous Materials Safety Administration
OPS Office of Pipeline Safety
Central Region
Principal Investigator Roger Sneegas
Region Director David Barrett
Date of Report 1/11/2012
Subject Failure Investigation Report – Southern Star Butt Weld Failure in KS
Operator, Location, & Consequences
Date of Failure 3/2/2010
Commodity Released Natural Gas
City/County & State Abbyville/Reno, Kansas
OpID & Operator Name 31711 Southern Star Central Gas Pipeline Co. Inc.
Unit # & Unit Name 853 Lyons
SMART Activity # 129328
Milepost / Location Station 140 – 260+06, milepost 161, About 10 miles downstream of
Stafford Station.
Butt weld separated due to crack in weld and external forces
Type of Failure Fatalities 0
Injuries 0
Description of area
impacted
Property Damage $953,905
Class 1 rural pasture land – wetland near a river

<<<PAGE 2>>>

Failure Investigation Report – Southern Star Butt Weld Failure in KS
Failure Date 3/2/2010
Executive Summary
At approximately 4:20 am on March 2, 2010, a pipeline rupture resulted in an unintentional release of
natural gas from a Southern Star gas pipeline located in Reno County, KS. An estimated 91,089
thousand cubic feet (Mcf) of natural gas was released from the pipeline. The incident occurred on the
pipeline right-of-way near milepost 161 in a wetland in a Class 1 Location. No fatalities or injuries
occurred as a result of the incident and the gas did not ignite. The total cost of the incident is estimated
at $953,905. Gas service was temporarily interrupted to the town of Partridge, Kansas until Southern
Star could provide a temporary connection from another line. The 26-inch butt weld failure was caused
by tensile overload in the presence of a large crack in the girth weld.
System Details
Southern Star’s RA line is a 26-inch diameter natural gas loop pipeline that parallels the R Line for about
26 miles southwest of Hesston, Kansas. The R Line moves natural gas from the Hugoton, Kansas gas
production fields to Hesston, Kansas and eventually to the Kansas City area.
At the incident location, the pipeline is constructed of material having the characteristics of API 5L line
pipe. The specified minimum yield strength (SMYS), 60,000 psig, has been established by supplier
receipts. The pipeline was installed in 1968 and consists of new pipe manufactured by National Tube.
The pipe is 0.281-inch wall thickness, coated with coal tar enamel and glass felt and the longitudinal
seam is double submerged arc welded (DSAW).
The pipeline maximum allowable operating pressure (MAOP) was established by hydrostatic test in
conformance with 49CFR 192.619(a) (1) and (2) in 1968. The test pressure was 1,260 psig and Southern
Star established an MAOP of 900 psig after considering the weakest component of the pipeline. A
review of Southern Star leak records identified no pipeline leaks on the RA Line in the last 5 years.
Events Leading up to the Failure
On the day of the failure, Southern Star was operating the pipeline at 833 psig, which corresponds to a
hoop stress of 64.2% of SMYS.
Emergency Response
On March 2, 2010 at 4:20 am, Southern Star gas control received a low pressure indication (100 psig
drop) on the R and RA line system. At 4:30 am the controller contacted field operations and asked them
to check for any problems in the vicinity of Hesston Station. Although the failure was closer to the
Stafford Station, Southern Star has a field office at the Station in Hesston, so personnel were available to
respond. At 5:08 am a third party reported a pipeline leak to Reno County Kansas Emergency Services.
Southern Star employees were dispatched to the Incident site starting at 5:08 am. Reno County fire,
police and emergency services were already on site and starting evacuations. The Southern Star field
office immediately dispatched the District Manager who arrived on site at 6:06 am and confirmed the
leak.
The affected section of pipeline was isolated by manually closing the upstream mainline valve (Langdon
MLV) and the downstream mainline valve (RA Arkansas River MLV). Both valves were operated at about
7:45 am. The 24 mile long pipeline segment was blown down to 0 psig by about 8:30 am.
Sothern Star notified the National Response Center (NRC) at 9:02 am (Appendix B).
Page 2 of 4

<<<PAGE 3>>>

Failure Investigation Report – Southern Star Butt Weld Failure in KS
Failure Date 3/2/2010
Summary of Return-to-Service
After the field investigation at the failure site was complete, replacement pipe was installed in the area
where the Incident occurred. Gas service to the town of Partridge was provided through a crossover
valve from the R Line. This temporary system did not include a pressure regulating device, so Southern
Star personnel manually operated the crossover valve to regulate the pressure to Partridge. Southern
Star also hydrotested an isolated one-mile segment of the pipeline that included the failure location.
Southern Star presented a return to service plan for the RA line on April 20, 2010. As a part of the plan,
they engaged Kiefner and Associates to analyze 2008 magnetic flux leakage (MFL) in-line inspection (ILI)
results for the RA line. The analysis was intended to find correlations between crack features in the ILI
results and actual cracks in girth welds. After reviewing the ILI results, Southern Star excavated girth
welds to physically inspect for cracks. After several iterations Southern Star and Kiefner developed a
process that accurately identified girth weld cracks about 50% of the time. The metallurgical analysis of
the failed weld determined that external forces were required, in addition to a crack, to cause failure of
the weld. The locations of ILI crack indications were prioritized based on the presence external stresses
such as buoyant forces or soil subsidence. The indications in the higher priority areas were then
excavated and repaired. A geotechnical consultant was also engaged to identify the high risk areas.
Based on the analysis and repairs on the RA line, PHMSA Central Region approved the return to service
plan and the RA line was re-started on December 12, 2011. After re-start Southern Star also agreed to
do an instrumented leak survey and another ILI run with geospatial capability. The ILI run will then be
compared with a previous run to determine areas where the pipeline has moved enough to cause
additional stress on the welds.
Investigation Details
On March 3, 2010, PHMSA Central Region inspectors conducted an on-site investigation of the incident.
In situ visual inspection of the damaged pipe joint revealed a circumferential separation of a girth weld.
The pipe ends were horizontally separated by about 2 inches and vertically offset about 6 inches. The
pipeline longitudinal seams were located between 12:00 and 3:00. See pictures in Appendix A.
At the failure location, the pipeline lies in a wetland near the Ninnescaw River. Preceding the incident,
the weather had begun to warm and the snow at the site was starting to melt. However, subsequent
excavations showed that the ground was still frozen over the pipeline. At the time of the incident the
wetland was dry at the surface. However the water table in the area was high enough that Southern
Star needed to continually pump water out of the excavation. Pipeline anchors were noted in the area
of the failure during the field investigation. Southern Star reported that screw anchors were at 30 foot
centers in the area of the failure; indicating that buoyant forces were considered during the pipeline
construction. The soil in the area was sandy so stress from clay soil expansion was not a factor in the
failure. The Ninnescaw River is about 300 feet northeast of the failure site so soil subsidence on the
river bank is another possible contributing factor.
Southern Star removed a section of pipe containing the failed weld (#17330) near milepost 161. This
section of pipe was transported to Kiefner and Associates for metallurgical analysis (Appendix D). The
analysis concluded the failure originated in a hydrogen-assisted crack in the girth weld. The crack was
circumferentially oriented, 16.5 inches long, and centered at approximately the 9:00 position, and had a
maximum depth of about 71% of the pipe wall.
Southern Star also excavated and x-rayed 10 welds adjacent to the failure; 4 upstream and 6
downstream. Circumferential cracks were found in 8 of the 10 additional welds x-rayed. These cracks
were almost evenly distributed at every clock position except 9:00. In addition to the 10 welds in the
Page 3 of 4

<<<PAGE 4>>>

Failure Investigation Report – Southern Star Butt Weld Failure in KS
Failure Date 3/2/2010
vicinity of the failure, Southern Star has excavated and x-rayed 22 other welds in the area. Of the 32
welds x-rayed, all were either cut out and replaced or repaired with a weld wrap.
A high-resolution MFL tool was run on the pipeline in 2008. The tool indicated an 11% metal loss
anomaly at the failed girth weld. The circumferential feature length was 1.5 inches. This indication did
not meet Southern Star’s repair criteria at the time.
Southern Star updated its incident report to PHMSA after the completion of the metallurgical analysis
(Appendix C).
Investigation Findings & Contributing Factors
The Southern Star 26-inch diameter RA Line Incident was caused by tensile overload in the presence of a
large crack in a girth weld. The crack initiated during construction in 1968. The metallurgical analysis
calculated that the longitudinal stress on the pipeline from temperature variations and line pressure was
not enough to cause the weld failure. The calculated failure stress on the weld indicated an additional
10 ksi was required to cause the failure. The most likely source is additional bending stress from pipe
buoyancy in a rising water table. The screw anchors used in the area of the failure were apparently not
effective in the wetland soil surrounding the pipeline.
Appendices
A Map and Photographs
B NRC Report No. 932729
C Incident Report 20100006
D Kiefner Laboratory Analysis
Page 4 of 4

<<<PAGE 5>>>

6” Vertical Offset
APPENDIX A Maps and Photographs
Photo number 1 of failure and site map March 4, 2010
Crater
26” “RA” Loop Line
Girth Weld Failure,
Looking North
2” Longitudinal
Separation
26” “R” Line
26” “RA” Loop Line
“RA” Loop Line Girth Weld Failure
Location

<<<PAGE 6>>>

Appendix B NRC Report
HMIS->INCiDENTs->TELEPhONiCs
(Version 3.4.05 PROD ) Rules of Behavior Home Logout Menu
[Return to Search]
1..1 of 1
Rescinded Comments (max 250 characters)
NRC Number: 932729
Call Date: 03/02/2010Call Time: 09:02:29
Caller Information
First Name: Last Name:
Company Name:
Address:
City: State:
Country: Zip:
Phone 1: Phone 2:
Organization Type: Is caller the spiller? Yes No No Response
Confidential: Yes No No Response
Discharger Information
First Name: Last Name:
Company Name:
Address:
City: State:
Country: Zip:
Phone 1: Phone 2:
Organization Type:
Spill Information
State: County:
Nearest City: Zip Code:
Location
Spill Date: (mm/dd/yyyy) Spill Time: (24hh:mm:ss)
DTG Type: DISCOVERED
Incident Type PIPELINE Reported Incident Type
Description
Page 1 of 2

<<<PAGE 7>>>

Materials Involved
Appendix B NRC Report
Material / Chris Name Chris Code Total Qty. Water Qty.
NATURAL GAS ONG 0 UNKNOWN AMOUNT
Medium Type: AIR
Additional Medium Information:
Injuries: Fatalites:
Evacuations: Yes No Unknown No. of Evacuations:
Damages: Yes No Unknown Damage Amount:
Federal Agency Notified: Yes No Unknown State Agency Notified: Yes No Unknown
Other Agency Notified: Yes No Unknown
Remedial Actions
Additional Info
Latitude
Degrees: Minutes: Seconds: Quadrant:
Longitude
Degrees: Minutes: Seconds: Quadrant:
Distance from City: Direction:
Section: Township:
Range: Milepost:
Page 2 of 2

<<<PAGE 8>>>

Appendix C Incident Report 20100006
NOTICE: This report is required by 49 CFR Part 191. Failure to report can result in a civil penalty not to
exceed 100,000 for each violation for each day that such violation persists except that the maximum civil
penalty shall not exceed $1,000,000 as provided in 49 USC 60122.
OMB NO: 2137-0522
EXPIRATION DATE: 01/31/2013
Report Date: 03/26/2010
No. 20100006 - 15418
U.S Department of Transportation
Pipeline and Hazardous Materials Safety Administration
--------------------------------------------------
(DOT Use Only)
INCIDENT REPORT - GAS TRANSMISSION AND
GATHERING PIPELINE SYSTEMS
A federal agency may not conduct or sponsor, and a person is not required to respond to, nor shall a person be subject to a penalty for failure to comply
with a collection of information subject to the requirements of the Paperwork Reduction Act unless that collection of information displays a current valid
OMB Control Number. The OMB Control Number for this information collection is 2137-0522. Public reporting for this collection of information is estimated
to be approximately 10 hours per response, including the time for reviewing instructions, gathering the data needed, and completing and reviewing the
collection of information. All responses to this collection of information are mandatory. Send comments regarding this burden estimate or any other aspect
of this collection of information, including suggestions for reducing this burden to: Information Collection Clearance Officer, PHMSA, Office of Pipeline
Safety (PHP-30) 1200 New Jersey Avenue, SE, Washington, D.C. 20590.
INSTRUCTIONS
Important: Please read the separate instructions for completing this form before you begin. They clarify the information requested and provide specific
examples. If you do not have a copy of the instructions, you can obtain one from the PHMSA Pipeline Safety Community Web Page at
http://www.phmsa.dot.gov/pipeline.
PART A - KEY REPORT INFORMATION
Report Type: (select all that apply) Original: Supplemental: Yes Final:
Yes
Last Revision Date: 01/10/2012
1. Operator's OPS-issued Operator Identification Number (OPID): 31711
2. Name of Operator SOUTHERN STAR CENTRAL GAS PIPELINE, INC
3. Address of Operator:
3a. Street Address 4700 HIGHWAY 56; BOX 20010
3b. City OWENSBORO
3c. State Kentucky
3d. Zip Code: 42301
4. Local time (24-hr clock) and date of the Incident: 03/02/2010 04:20
5. Location of Incident:
Latitude: 37.94216
Longitude: -98.25881
6. National Response Center Report Number (if applicable): 932729
7. Local time (24-hr clock) and date of initial telephonic report to the
National Response Center (if applicable): 03/02/2010 08:00
8. Incident resulted from: Unintentional release of gas
9. Gas released: (select only one, based on predominant volume
released) Natural Gas
- Other Gas Released Name:
10. Estimated volume of commodity released unintentionally - Thousand
Cubic Feet (MCF): 91,089.00
11. Estimated volume of intentional and controlled release/blowdown -
Thousand Cubic Feet (MCF)
12. Estimated volume of accompanying liquid release (Barrels):
13. Were there fatalities? No
- If Yes, specify the number in each category:
13a. Operator employees
13b. Contractor employees working for the Operator
13c. Non-Operator emergency responders
13d. Workers working on the right-of-way, but NOT
associated with this Operator
13e. General public
13f. Total fatalities (sum of above)
14. Were there injuries requiring inpatient hospitalization? No
- If Yes, specify the number in each category:
14a. Operator employees
14b. Contractor employees working for the Operator
14c. Non-Operator emergency responders
14d. Workers working on the right-of-way, but NOT
associated with this Operator
14e. General public
14f. Total injuries (sum of above)
15. Was the pipeline/facility shut down due to the incident? Yes
- If No, Explain:
Page 1 of 13

<<<PAGE 9>>>

Appendix C Incident Report 20100006
- If Yes, complete Questions 15a and 15b: (use local time, 24-hr clock)
15a. Local time and date of shutdown 03/02/2010 08:00
15b. Local time pipeline/facility restarted
- Still shut down? (* Supplemental Report Required) Yes
16. Did the gas ignite? No
17. Did the gas explode? No
18. Number of general public evacuated: 20
19. Time sequence (use local time, 24-hour clock):
19a. Local time operator identified Incident 03/02/2010 04:20
19b. Local time operator resources arrived on site 03/02/2010 06:03
PART B - ADDITIONAL LOCATION INFORMATION
1. Was the origin of the Incident onshore? Yes
- Yes (Complete Questions 2-12)
- No (Complete Questions 13-15)
If Onshore:
2. State: Kansas
3. Zip Code: 67510
4. City Abbyville
5. County or Parish Reno
6. Operator designated location Survey Station No.
Specify: 140/26053
7. Pipeline/Facility name: Hugoton 26" Loop
8. Segment name/ID: RA
9. Was Incident on Federal land, other than the Outer Continental Shelf
(OCS)? No
10. Location of Incident : Pipeline Right-of-way
11. Area of Incident (as found) : Underground
Specify: Under soil
Other – Describe:
Depth-of-Cover (in): 40
12. Did Incident occur in a crossing? No
- If Yes, specify type below:
- If Bridge crossing –
Cased/ Uncased:
- If Railroad crossing –
Cased/ Uncased/ Bored/drilled
- If Road crossing –
Cased/ Uncased/ Bored/drilled
- If Water crossing –
Cased/ Uncased
Name of body of water (If commonly known):
Approx. water depth (ft) at the point of the Incident:
Select:
If Offshore:
13. Approx. water depth (ft) at the point of the Incident:
14. Origin of Incident:
- If "In State waters":
- State:
- Area:
- Block/Tract #:
- Nearest County/Parish:
- If "On the Outer Continental Shelf (OCS)":
- Area:
- Block #:
15. Area of Incident:
PART C - ADDITIONAL FACILITY INFORMATION
1. Is the pipeline or facility: - Interstate - Intrastate Interstate
2. Part of system involved in Incident: Onshore Pipeline, Including Valve Sites
3. Item involved in Incident: Weld, including heat-affected zone
- If Pipe – Specify:
3a. Nominal diameter of pipe (in):
3b. Wall thickness (in):
3c. SMYS (Specified Minimum Yield Strength) of pipe (psi):
3d. Pipe specification:
3e. Pipe Seam – Specify:
Page 2 of 13

<<<PAGE 10>>>

Appendix C Incident Report 20100006
- If Other, Describe:
3f. Pipe manufacturer:
3g. Year of manufacture:
3h. Pipeline coating type at point of Incident – Specify:
- If Other, Describe:
- If Weld, including heat-affected zone – Specify: Pipe Girth Weld
- If Other, Describe:
- If Valve – Specify:
- If Mainline – Specify:
- If Other, Describe:
3i. Mainline valve manufacturer:
3j. Year of manufacture:
- If Other, Describe:
4. Year item involved in Incident was installed: 1968
5. Material involved in Incident: Carbon Steel
- If Material other than Steel or Plastic – Specify:
6. Type of Incident involved: Rupture
- If Mechanical Puncture – Specify Approx. size:
Approx. size: in. (in axial) by
in. (circumferential)
- If Leak - Select Type:
- If Other – Describe:
- If Rupture - Select Orientation: Circumferential
- If Other – Describe:
Approx. size: in. (widest opening):
by in. (length circumferentially or axially): 81.6
- If Other – Describe:
PART D - ADDITIONAL CONSEQUENCE INFORMATION
1. Class Location of Incident: Class 1 Location
2. Did this Incident occur in a High Consequence Area (HCA)? No
- If Yes:
2a. Specify the Method used to identify the HCA:
3. What is the PIR (Potential Impact Radius) for the location of this
Incident? Feet: 538
4. Were any structures outside the PIR impacted or otherwise damaged
due to heat/fire resulting from the Incident? No
5. Were any structures outside the PIR impacted or otherwise damaged
NOT by heat/fire resulting from the Incident? No
6. Were any of the fatalities or injuries reported for persons located
outside the PIR? No
7. Estimated cost to Operator :
7a. Estimated cost of public and non-Operator private
property damage paid/reimbursed by the Operator $ 0
7b. Estimated cost of gas released unintentionally $ 313,880
7c. Estimated cost of gas released during intentional and
controlled blowdown $ 0
7d. Estimated cost of Operator's property damage & repairs $ 638,025
7e. Estimated cost of Operator's emergency response $ 2,000
7f. Estimated other costs $ 0
Describe:
7g. Estimated total costs (sum of above) $ 953,905
PART E - ADDITIONAL OPERATING INFORMATION
1. Estimated pressure at the point and time of the Incident (psig): 833.00
2. Maximum Allowable Operating Pressure (MAOP) at the point and
time of the Incident (psig): 900.00
3. Describe the pressure on the system or facility relating to the
Incident: Pressure did not exceed MAOP
4. Not including pressure reductions required by PHMSA regulations
(such as for repairs and pipe movement), was the system or facility
relating to the Incident operating under an established pressure
restriction with pressure limits below those normally allowed by the
MAOP?
No
- If Yes - (Complete 4a and 4b below)
4a. Did the pressure exceed this established pressure
restriction?
Page 3 of 13

<<<PAGE 11>>>

Appendix C Incident Report 20100006
4b. Was this pressure restriction mandated by PHMSA or the
State?
5. Was "Onshore Pipeline, Including Valve Sites" OR "Offshore Pipeline,
Including Riser and Riser Bend" selected in PART C, Question 2? Yes
- If Yes - (Complete 5a. - 5f. below):
5a. Type of upstream valve used to initially isolate release source: Manual
5b. Type of downstream valve used to initially isolate release
source:
Manual
5c. Length of segment isolated between valves (ft): 128,139
5d. Is the pipeline configured to accommodate internal inspection
tools? Yes
- If No – Which physical features limit tool accommodation? (select all that apply)
- Changes in line pipe diameter
- Presence of unsuitable mainline valves
- Tight or mitered pipe bends
- Other passage restrictions (i.e. unbarred tee's, projecting
instrumentation, etc.)
- Extra thick pipe wall (applicable only for magnetic flux
leakage internal inspection tools)
- Other
- If Other, Describe:
5e. For this pipeline, are there operational factors which
significantly complicate the execution of an internal inspection tool
run?
No
- If Yes, which operational factors complicate execution? (select all that apply)
- Excessive debris or scale, wax, or other wall build-up
- Low operating pressure(s)
- Low flow or absence of flow
- Incompatible commodity
- Other
- If Other, Describe:
5f. Function of pipeline system: Transmission System
6. Was a Supervisory Control and Data Acquisition (SCADA)-based
system in place on the pipeline or facility involved in the Incident? Yes
- If Yes:
6a. Was it operating at the time of the Incident? Yes
6b. Was it fully functional at the time of the Incident? Yes
6c. Did SCADA-based information (such as alarm(s), alert(s),
event(s), and/or volume or pack calculations) assist with the
detection of the Incident?
Yes
6d. Did SCADA-based information (such as alarm(s), alert(s),
event(s), and/or volume calculations) assist with the confirmation of
the Incident?
Yes
7. How was the Incident initially identified for the Operator? Controller
- If Other – Describe:
7a. If "Controller", "Local Operating Personnel, including
contractors", "Air Patrol", or "Ground Patrol by Operator or its
contractor" is selected in Question 7, specify the following:
Operator employee
8. Was an investigation initiated into whether or not the controller(s) or
control room issues were the cause of or a contributing factor to the
Incident?
No, the Operator did not find that an investigation of the
controller(s) actions or control room issues was necessary
due to: (provide an explanation for why the Operator did not
investigate)
- If No, the operator did not find that an investigation of the
controller(s) actions or control room issues was necessary due to:
(provide an explanation for why the operator did not investigate)
The incident was not identified as a controller failure
possibility.
- If Yes, Describe investigation result(s) (select all that apply):
- Investigation reviewed work schedule rotations, continuous
hours of service (while working for the operator), and other
factors associated with fatigue
- Investigation did NOT review work schedule rotations,
continuous hours of service (while working for the Operator)
and other factors associated with fatigue
- Provide an explanation for why not:
- Investigation identified no control room issues
- Investigation identified no controller issues
- Investigation identified incorrect controller action or
controller error
- Investigation identified that fatigue may have affected the
controller(s) involved or impacted the involved controller(s)
response
- Investigation identified incorrect procedures
Page 4 of 13

<<<PAGE 12>>>

Appendix C Incident Report 20100006
- Investigation identified incorrect control room equipment
operation
- Investigation identified maintenance activities that affected
control room operations, procedures, and/or controller
response
- Investigation identified areas other than those above –
Describe:
PART F - DRUG & ALCOHOL TESTING INFORMATION
1. As a result of this Incident, were any Operator employees tested
under the post-accident drug and alcohol testing requirements of DOT's
Drug & Alcohol Testing regulations?
No
- If Yes:
1a. Describe how many were tested:
1b. Describe how many failed:
2. As a result of this Incident, were any Operator contractor employees
tested under the post-accident drug and alcohol testing requirements of
DOT's Drug & Alcohol Testing regulations?
No
- If Yes:
2a. Describe how many were tested:
2b. Describe how many failed:
PART G - APPARENT CAUSE
Select only one box from PART G in the shaded column on the left representing the APPARENT Cause of the Incident, and answer the
questions on the right. Describe secondary, contributing, or root causes of the Incident in the narrative (PART H).
Apparent Cause: G5 - Material Failure of Pipe or Weld
G1 - Corrosion Failure - only one sub-cause can be picked from shaded left-hand column
Corrosion Failure – Sub-cause:
- If External Corrosion:
1. Results of visual examination:
- If Other, Describe:
2. Type of corrosion: (select all that apply)
- Galvanic
- Atmospheric
- Stray Current
- Microbiological
- Selective Seam
- Other
- If Other – Describe:
3. The type(s) of corrosion selected in Question 2 is based on the following: (select all that apply)
- Field examination
- Determined by metallurgical analysis
- Other
- If Other – Describe:
4. Was the failed item buried under the ground?
- If Yes:
4a. Was failed item considered to be under cathodic protection at
the time of the incident?
- If Yes, Year protection started:
4b. Was shielding, tenting, or disbonding of coating evident at the
point of the incident?
4c. Has one or more Cathodic Protection Survey been conducted
at the point of the incident?
If "Yes, CP Annual Survey" – Most recent year conducted:
If "Yes, Close Interval Survey" – Most recent year conducted:
If "Yes, Other CP Survey" – Most recent year conducted:
- If No:
4d. Was the failed item externally coated or painted?
5. Was there observable damage to the coating or paint in the vicinity of
the corrosion?
- If Internal Corrosion:
6. Results of visual examination:
- If Other, Describe:
7. Cause of corrosion (select all that apply):
Page 5 of 13

<<<PAGE 13>>>

Appendix C Incident Report 20100006
- Corrosive Commodity
- Water drop-out/Acid
- Microbiological
- Erosion
- Other
- If Other, Describe:
8. The cause(s) of corrosion selected in Question 7 is based on the following (select all that apply):
- Field examination
- Determined by metallurgical analysis
- Other
- If Other, Describe:
9. Location of corrosion (select all that apply):
- Low point in pipe
- Elbow
- Drop-out
- Other
- If Other, Describe:
10. Was the gas/fluid treated with corrosion inhibitors or biocides?
11. Was the interior coated or lined with protective coating?
12. Were cleaning/dewatering pigs (or other operations) routinely
utilized?
13. Were corrosion coupons routinely utilized?
Complete the following if any Corrosion Failure sub-cause is selected AND the "Item Involved in Incident" (from PART C,
Question 3) is Pipe or Weld.
14. Has one or more internal inspection tool collected data at the point
of the Incident?
14a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run:
- Magnetic Flux Leakage Tool
Most recent year run:
- Ultrasonic
Most recent year run:
- Geometry
Most recent year run:
- Caliper
Most recent year run:
- Crack
Most recent year run:
- Hard Spot
Most recent year run:
- Combination Tool
Most recent year run:
- Transverse Field/Triaxial
Most recent year run:
- Other
Most recent year run:
If Other, Describe:
15. Has one or more hydrotest or other pressure test been conducted
since original construction at the point of the Incident?
- If Yes,
Most recent year tested:
Test pressure (psig):
16. Has one or more Direct Assessment been conducted on this
segment?
- If Yes, and an investigative dig was conducted at the point of the Incident:
Most recent year conducted:
- If Yes, but the point of the Incident was not identified as a dig site:
Most recent year conducted:
17. Has one or more non-destructive examination been conducted at
the point of the Incident since January 1, 2002?
17a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year examined:
- Guided Wave Ultrasonic
Most recent year examined:
- Handheld Ultrasonic Tool
Most recent year examined:
- Wet Magnetic Particle Test
Most recent year examined:
Page 6 of 13

<<<PAGE 14>>>

Appendix C Incident Report 20100006
- Dry Magnetic Particle Test
Most recent year examined:
- Other
Most recent year examined:
If Other, Describe:
G2 - Natural Force Damage - only one sub-cause can be picked from shaded left-handed column
Natural Force Damage – Sub-Cause:
- If Earth Movement, NOT due to Heavy Rains/Floods:
1. Specify:
- If Other, Describe:
- If Heavy Rains/Floods:
2. Specify:
- If Other, Describe:
- If Lightning:
3. Specify:
- If Temperature:
4. Specify:
- If Other, Describe:
- If High Winds:
- If Other Natural Force Damage:
5. Describe:
Complete the following if any Natural Force Damage sub-cause is selected.
6. Were the natural forces causing the Incident generated in conjunction
with an extreme weather event?
6a. If yes, specify: (select all that apply):
- Hurricane
- Tropical Storm
- Tornado
- Other
- If Other, Describe:
G3 - Excavation Damage only one sub-cause can be picked from shaded left-hand column
Excavation Damage – Sub-Cause:
- If Excavation Damage by Operator (First Party):
- If Excavation Damage by Operator's Contractor (Second Party):
- If Excavation Damage by Third Party:
- If Previous Damage Due to Excavation Activity:
Complete Questions 1-5 ONLY IF the "Item Involved in Incident" (From Part C, Question 3) is Pipe or Weld.
1. Has one or more internal inspection tool collected data at the point of
the Incident?
1a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run:
- Magnetic Flux Leakage
Year:
- Ultrasonic
Year:
- Geometry
Year:
- Caliper
Year:
- Crack
Year:
- Hard Spot
Year:
- Combination Tool
Year:
- Transverse Field/Triaxial
Year:
- Other:
Year:
Describe:
2. Do you have reason to believe that the internal inspection was
Page 7 of 13

<<<PAGE 15>>>

Appendix C Incident Report 20100006
completed BEFORE the damage was sustained?
3. Has one or more hydrotest or other pressure test been conducted
since original construction at the point of the Incident?
- If Yes:
Most recent year tested:
Test pressure (psig):
4. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Incident:
Most recent year conducted:
- If Yes, but the point of the Incident was not identified as a dig site:
Most recent year conducted:
5. Has one or more non-destructive examination been conducted at the
point of the Incident since January 1, 2002?
5a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Year:
- Guided Wave Ultrasonic
Year:
- Handheld Ultrasonic Tool
Year:
- Wet Magnetic Particle Test
Year:
- Dry Magnetic Particle Test
Year:
- Other
Year:
Describe:
Complete the following if Excavation Damage by Third Party is selected as the sub-cause.
6. Did the operator get prior notification of the excavation activity?
6a. If Yes, Notification received from (select all that apply):
- One-Call System
- Excavator
- Contractor
- Landowner
Complete the following mandatory CGA-DIRT Program questions if any Excavation Damage sub-cause is selected.
7. Do you want PHMSA to upload the following information to CGA-
DIRT (www.cga-dirt.com)?
8. Right-of-Way where event occurred (select all that apply):
- Public
- If Public, Specify:
- Private
- If Private, Specify:
- Pipeline Property/Easement
- Power/Transmission Line
- Railroad
- Dedicated Public Utility Easement
- Federal Land
- Data not collected
- Unknown/Other
9. Type of excavator :
10. Type of excavation equipment :
11. Type of work performed :
12. Was the One-Call Center notified? - Yes - No
12a. If Yes, specify ticket number:
12b. If this is a State where more than a single One-Call Center
exists, list the name of the One-Call Center notified:
13. Type of Locator:
14. Were facility locate marks visible in the area of excavation?
15. Were facilities marked correctly?
16. Did the damage cause an interruption in service?
16a. If Yes, specify duration of the interruption: (hours)
17. Description of the CGA-DIRT Root Cause (select only the one predominant first level CGA-DIRT Root Cause and then, where
available as a choice, then one predominant second level CGA-DIRT Root Cause as well):
- Predominant first level CGA-DIRT Root Cause:
- If One-Call Notification Practices Not Sufficient, Specify:
- If Locating Practices Not Sufficient, Specify:
Page 8 of 13

<<<PAGE 16>>>

Appendix C Incident Report 20100006
- If Excavation Practices Not Sufficient, Specify:
- If Other/None of the Above, Explain:
G4 - Other Outside Force Damage - only one sub-cause can be selected from the shaded left-hand column
Other Outside Force Damage – Sub-Cause:
- If Nearby Industrial, Man-made, or Other Fire/Explosion as Primary Cause of Incident:
- If Damage by Car, Truck, or Other Motorized Vehicle/Equipment NOT Engaged in Excavation:
1. Vehicle/Equipment operated by:
- If Damage by Boats, Barges, Drilling Rigs, or Other Maritime Equipment or Vessels Set Adrift or Which Have Otherwise Lost
Their Mooring:
2. Select one or more of the following IF an extreme weather event was a factor:
- Hurricane
- Tropical Storm
- Tornado
- Heavy Rains/Flood
- Other
- If Other, Describe:
- If Routine or Normal Fishing or Other Maritime Activity NOT Engaged in Excavation:
- If Electrical Arcing from Other Equipment or Facility:
- If Previous Mechanical Damage NOT Related to Excavation:
Complete Questions 3-7 ONLY IF the "Item Involved in Incident" (from PART C, Question 3) is Pipe or Weld.
3. Has one or more internal inspection tool collected data at the point of
the Incident?
3a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run:
- Magnetic Flux Leakage
Most recent year run:
- Ultrasonic
Most recent year run:
- Geometry
Most recent year run:
- Caliper
Most recent year run:
- Crack
Most recent year run:
- Hard Spot
Most recent year run:
- Combination Tool
Most recent year run:
- Transverse Field/Triaxial
Most recent year run:
- Other:
Most recent year run:
Describe:
4. Do you have reason to believe that the internal inspection was
completed BEFORE the damage was sustained?
5. Has one or more hydrotest or other pressure test been conducted
since original construction at the point of the Incident?
- If Yes:
Most recent year tested:
Test pressure (psig):
6. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Incident :
Most recent year conducted:
- If Yes, but the point of the Incident was not identified as a dig site:
Most recent year conducted:
7. Has one or more non-destructive examination been conducted at the
point of the Incident since January 1, 2002?
7a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Page 9 of 13

<<<PAGE 17>>>

Appendix C Incident Report 20100006
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
If - If Intentional Damage:
8. Specify:
- If Other, Describe:
- If Other Outside Force Damage:
9. Describe:
Use this section to report material failures ONLY IF the "Item Involved in
Incident" (from PART C, Question 3) is "Pipe" or "Weld."
G5 - Pipe, Weld, or Joint Failure
Only one sub-cause can be selected from the shaded left-hand column
Pipe, Weld or Join Failure – Sub-Cause: Construction-, Installation-, or Fabrication-related
1. The sub-case selected below is based on the following (select all that apply):
- Field Examination Yes
- Determined by Metallurgical Analysis Yes
- Other Analysis
- If "Other Analysis", Describe
- Sub-cause is Tentative or Suspected; Still Under Investigation
(Supplemental Report required)
- If Construction-, Installation- or Fabrication- related:
2. List contributing factors: (select all that apply)
- If Fatigue or Vibration related:
Specify:
- If Other, Describe:
- Mechanical Stress Yes
- Other
- If Other, Describe:
- If Original Manufacturing-related (NOT girth weld or other welds formed in the field):
2. List contributing factors: (select all that apply)
- If Fatigue or Vibration related:
Specify:
- If Other, Describe:
- Mechanical Stress
- Other
- If Other, Describe:
- If Environmental Cracking-related:
3. Specify:
- If Other, Describe:
Complete the following if any Material Failure of Pipe or Weld sub-cause is selected.
4. Additional Factors (select all that apply):
- Dent
- Gouge
- Pipe Bend
- Arc Burn
- Crack Yes
- Lack of Fusion
- Lamination
- Buckle
- Wrinkle
- Misalignment
- Burnt Steel
- Other
- If Other, Describe:
5. Has one or more internal inspection tool collected data at the point of
the Incident? Yes
Page 10 of 13

<<<PAGE 18>>>

Appendix C Incident Report 20100006
5a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run:
- Magnetic Flux Leakage Yes
Most recent year run: 2008
- Ultrasonic
Most recent year run:
- Geometry Yes
Most recent year run: 2008
- Caliper Yes
Most recent year run: 2008
- Crack
Most recent year run:
- Hard Spot
Most recent year run:
- Combination Tool
Most recent year run:
- Transverse Field/Triaxial
Most recent year run:
- Other
Most recent year run:
Describe:
6. Has one or more hydrotest or other pressure test been conducted
since original construction at the point of the Incident? No
- If Yes:
Most recent year tested:
Test pressure (psig):
7. Has one or more Direct Assessment been conducted on the pipeline
segment? No
- If Yes, and an investigative dig was conducted at the point of the Incident:
Most recent year conducted:
- If Yes, but the point of the Incident was not identified as a dig site:
Most recent year conducted:
8. Has one or more non-destructive examination(s) been conducted at
the point of the Incident since January 1,2002? No
8a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conduc
- **truncated:** true
- **body characters:** 44733
