# Failure Report- Sunoco Pipeline L.P. 8/2/11

- **operation:** document
- **citation:** PHMSA FIR, Sunoco Pipeline L.P., 2011-08-02
- **title:** Failure Report- Sunoco Pipeline L.P. 8/2/11
- **source type:** incident
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2016-03-22
- **effective on:** 2011-08-02
- **summary:** Sunoco Pipeline L.P.; Hazardous Liquid; PA; failure 2011-08-02; apparent cause: Corrosion Internal.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-sunoco-pipeline-lp-8211.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-sunoco-pipeline-lp-8211.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-fir-failure-report-sunoco-pipeline-lp-8211
- **source url:** https://www.phmsa.dot.gov/safety-reports/failure-report-sunoco-pipeline-lp-8211
**body:**

<<<PAGE 1>>>

Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank Leak
DOT US Department of Transportation
PHMSA Pipeline and Hazardous Materials Safety Administration
OPS Office of Pipeline Safety
Eastern Region
Principal Investigator Christian Sellu
Senior Accident Investigator Michael Yazemboski
Region Director Byron Coy
Date of Report 7/12/2013
Subject Failure Investigation Report – Sunoco Pipeline L.P.,
Darby Creek Tank Leak
Operator, Location, & Consequences
Date of Failure 2/8/2011
Commodity Released Crude Oil
City/County & State Folcroft, Delaware County, Pennsylvania
OpID & Operator Name 18718 - Sunoco Pipeline L.P.
Unit # & Unit Name 20041 - Fort Mifflin-PA/NJ
SMART Activity # 133500
Milepost / Location Latitude: 39.89810181, Longitude: 75.26255272
Type of Failure Corrosion Leak in Tank DC9 tank bottom
Fatalities None
Injuries None
Description of Area
Impacted
Leak contained to tank dike area. Facility located in a High Consequence
Area (HCA).
Total Costs $257,250

<<<PAGE 2>>>

Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank DC9 Leak
Failure Date 02/08/2011
Executive Summary
At 12:13 p.m. on February 8, 2011, crude oil was
discovered in the dike area of Tank DC9 in the Sunoco
Logistics (Sunoco) Darby Creek Tank Farm (DCTF). Tank
DC9 is designated as a break-out tank and is regulated
under Part 195 of the Code of Federal Regulations (CFR).
The leak originated from a hole in the bottom of the
tank resulting in a spill of approximately 38 barrels of
crude oil within the tank dike area. The cause of the
leak was due to corrosion located on the internal topside and underside of the tank floor. The Tank is
located in a designated high consequence area (HCA) and an Unusually Sensitive Area (USA) per
Sunoco’s Integrity Management program (IMP). The tank area is approximately 500 feet from a local
highway and 600 feet from a residential community. There were no injuries or fatalities, evacuations, or
supply disruptions as a result of the incident. The tank will remain out-of-service until remediation
efforts can be completed.
An inspector from PHMSA’s Eastern Region was dispatched to the location on February 14, 2011, to
conduct an investigation into the cause of the release.
System Details
Sunoco Pipeline L.P. operates more than 7,500 miles of hazardous liquid pipelines. The Darby Creek
Tank Farm (DCTF) is a crude oil storage terminal for Sunoco’s Philadelphia refinery. This facility has a
total storage capacity of approximately three million barrels. Darby Creek receives crude oil from the
Fort Mifflin Terminal and Hog Island Wharf through its pipelines. The tank farm stores the crude oil and
pumps it to the Philadelphia refinery.
The DCTF comprises 30 above-ground atmospheric breakout tanks that are utilized for transit, storing,
and blending crude oils. The crude oils are sent to the tank farm from the 3-mile-long, 24-inch-diameter
North and South Ship lines. These lines are supplied with products from barges and ships at Fort Mifflin
Dock and Hog Island Wharf near the Philadelphia International Airport. The products are blended at the
DCTF and are pumped to the Sunoco Girard Point refinery through a 4-mile, 16-inch-diameter crude line.
The 24-inch-diameter ship lines and the 16-inch-diameter crude line are under PHMSA’s jurisdiction
(Appendix A).
Tank DC9 is a 96,000-barrel break-out tank, measures 48 feet high by 120 feet in diameter, and was
constructed in 1948 (Appendix A,
-4).
Events Leading up to the Failure
Prior to the leak that was discovered on February 8, 2011, Tank DC9 was in normal service. There were
no leaks or operational issues reported since the tank bottom was replaced following the 1992 out-of-
service inspection.
Page 2 of 4

<<<PAGE 3>>>

Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank DC9 Leak
Failure Date 02/08/2011
Emergency Response
On February 8, 2011, at approximately 12:13 p.m., a company utility operator discovered product in the
dike area around Tank DC9 at the DCTF. Upon confirming the leak, Sunoco began immediately
transferring product from Tank DC9 to Tank 35. At approximately 12:49 p.m., a vacuum truck was
dispatched to the location to begin removing spilled product from the dike area. On February 11, 2011,
fresh product was found in a runoff trench near the outer wall of Tank DC9. Arrangements were made
by Sunoco to have the DC9 tank bottom inspected using a Magnetic Flux Leakage Examination Scanner
(MFE). An American Petroleum Institute (API) 653 out-of-service inspection was conducted by DJA
Inspection Services Inc., and a report was issued on April 20, 2011 (Appendix E).
Remediation of the area in which the product was spilled continued through February 14, 2011
(Appendix A-6 / Appendix A-7 / Appendix A-8). Sunoco notified the National Response Center (NRC) of
the incident on February 11, 2011 (Appendix B), at approximately 4:20 p.m. Sunoco successfully
implemented their Emergency Plan and Oil Pollution Act Plan in response to the tank leakage and
resulting spill.
Summary of Return-to-Service
Tank DC9 will remain out of service until Sunoco can complete the repairs as outlined in the out of
service inspection report, dated April 20, 2011, and provided by DJA Inspection Services.
Investigation Details
Tank DC9 is located in a designated High Consequence Area (HCA) and an Unusually Sensitive Area (USA)
as described in Sunoco’s Integrity Management Plan (IMP). The tank dike area is within approximately
500 feet from a local highway and 600 feet from a residential community. The investigation conducted
by PHMSA’s Eastern Region consisted of a review of the operating and maintenance history, tank
inspection procedures, and records. Tank DC 9 was constructed in 1948 and was originally owned and
operated by Chevron. Sunoco assumed ownership in 2003. The bottom of the tank consists of 3/8-inch
annual ring plates and ¼-inch-thick inner bottom plates. The tank is insulated with no heating coils and
stores crude at approximately 90 degrees Fahrenheit. The tank is currently sitting on soil over a High
Density Polyethylene Liner (HDPE) with a 4-inch concrete base, and the original steel bottom. The HDPE
liner was reported to be in good condition. The tank was under cathodic protection prior to 1992, but
due to the installation of a double bottom in 1992, the cathodic protection was rendered ineffective.
The inspection history for tank DC9 consists of the following API Standard 653 Inspections:
Type Appendix
Certification Date May 11, 1992 Out-of-Service D4
Sept 28, 1993 D5
August 5, 1997 In-Service D1
Page 3 of 4

<<<PAGE 4>>>

Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank DC9 Leak
Failure Date 02/08/2011
August 1, 2002 In-Service D2
June 5, 2007 In-Service D3
The most recent API Standard 653 out-of-service inspection was performed on December 9, 1992
(Appendix D-4). This report identified a total of five deficiencies that required remediation. As a result
of this out-of-service Inspection, the entire tank bottom was replaced and a new protective fiberglass
reinforcement plastics (FRP) coating was added.
The most recent API Standard 653 in-service inspection was performed on June 5, 2007. This inspection
was conducted to collect data to evaluate the structural integrity of the tank and fitness for continued
service. The results of the 2007 in-service inspection identified a total of six deficiencies. These
deficiencies were external in nature and did not affect the overall integrity of the tank. The report
identified the remaining life of the tank shell and nozzles to be greater than 20 years based on
calculations using ultra-sonic thickness measurements.
A post-accident inspection conducted by DJA Inspection Services, dated April 20, 2011, identified
significant topside corrosion on the floor plates in tank DC9 due to a failure of the FRP coating that was
applied in 1992 (Appendix E). The report also indicated that approximately 60 percent of the floor could
not be accurately MFE scanned during the post-accident inspection due to the severity of the topside
corrosion and the FRP disbondment. The report also indicated that minor soil-side corrosion was found
around the outside of the inner bottom plates against the annular ring. The report recommended
replacing the entire bottom of the tank or repairing the tank by replacing approximately 60% of the
bottom and performing various other procedures. The report also recommended that all of the annual
rings be re-welded due to the amount of corrosion that was identified in these locations.
Findings and Contributing Factors
The primary immediate cause of this release was due to a hole in the tank bottom caused by a
combination of internal topside corrosion and external underside soil-side corrosion. The topside
corrosion was due to the failure of the FRP protective coating material that was applied when the tank
bottom was replaced in 1992.
As a result of the investigation, PHMSA’s Eastern Region findings are consistent with those identified in
the post-accident inspection that was performed by DJA Inspection Services and the recommendations
outlined in the subsequent report dated April 20, 2011.
Appendices
Appendix Description
A 133500 Appendix A Maps and Photos
B 133500 Appendix B NRC Report 967232
C 133500 Appendix C Operator Liquid Accident Report ID 20110080
D 133500 Appendix D (D-1 to D-5) Operator Inspection Records
E 133500 Appendix E Post incident tank inspection
Page 4 of 4

<<<PAGE 5>>>

Appendix A
Map Removed
File Available at PHMSA

<<<PAGE 6>>>

130058 Appendix A Map and Photographs
Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank Leak (Activity #133500)
Accident Date 02/08/2011
Photo 1 – Oil Water Box
Page 4 of 10

<<<PAGE 7>>>

130058 Appendix A Map and Photographs
Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank Leak (Activity #133500)
Accident Date 02/08/2011
Photo 2 ‐ Apparent Leakage from tank bottom
Page 5 of 10

<<<PAGE 8>>>

130058 Appendix A Map and Photographs
Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank Leak (Activity #133500)
Accident Date 02/08/2011
Photo 3 – Tank Piping
Page 6 of 10

<<<PAGE 9>>>

130058 Appendix A Map and Photographs
Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank Leak (Activity #133500)
Accident Date 02/08/2011
Photo 4 – Tank Dike
Page 7 of 10

<<<PAGE 10>>>

130058 Appendix A Map and Photographs
Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank Leak (Activity #133500)
Accident Date 02/08/2011
Photo 5 – Traces of Crude – Tank Dike
Page 8 of 10

<<<PAGE 11>>>

130058 Appendix A Map and Photographs
Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank Leak (Activity #133500)
Accident Date 02/08/2011
Photo 6 – Tank Dike
Page 9 of 10

<<<PAGE 12>>>

130058 Appendix A Map and Photographs
Failure Investigation Report – Sunoco Pipeline L.P., Darby Creek Tank Leak (Activity #133500)
Accident Date 02/08/2011
Photo 7 – Hole on bottom of tank DC9. Floor Plate #35.
Page 10 of 10

<<<PAGE 13>>>

TeleDetail
Page 1 of 2
133500 Appendix B NRC Report 967232
HMIS->INCIDENTS->TELEPHONICS
(Version 3.4.06 PROD ) Rules of Behavior Home Logout Menu
[Return to Search]
NRC Number: 967232
Call Date: 02/11/2011 Call Time: 16:20:08
Caller Information
First Name: CLAUDIA Last Name: PANKOWSKI
Company Name: SUNOCO LOGISTICS
Address: 1824 HORSESHOE PIKE
City: HONEY BROOK State: PA
Country: USA Zip: 19344
Phone 1: 6109992879 Phone 2:
Organization Type: PRIVAT Is caller the spiller? Yes Yes No No No Response No Response
Confidential: Yes Yes No No No Response No Response
Discharger Information
First Name: CLAUDIA Last Name: PANKOWSKI
Company Name: SUNOCO LOGISTICS
Address: 1824 HORSESHOE PIKE
City: HONEY BROOK State: PA
Country: USA Zip: 19344
Phone 1: 6109992879 Phone 2:
Organization Type: PRIVAT
Spill Information
State: PA County: DELAWARE
Nearest City: SHARON HILL Zip Code: 19079
Location
1207 CALCON HOOK ROAD
Spill Date: (mm/dd/yyyy)
12:13:00
02/08/2011 Spill Time: (24hh:mm:ss)
DTG Type: DISCOVERED
Incident Type PIPELINE Reported Incident Type PIPELINE
Description
COMPANY PERSONNEL DISCOVERED A SPILL OF CRUDE OIL INTO TANK DIKE. PRODUCT
CONTAINED INSIDE THE FACILITY. NO FIRE, NO EXPLOSION, NO INJURIES, NO
FATALITIES, NO WATERWAYS AFFECTED. SOURCE OF SPILL STILL UNDETERMINED AND COULD
BE A NON-PHMSA JURISDICTIONAL LINE. NO ADDITIONAL PRODUCT WAS BEING SPILLED AT
DISCOVERY.
Materials Involved
Material / Chris Name Chris Code Total Qty. Water Qty.
OIL: CRUDE OIL 1600 GALLON(S)
Page 1 of 2
https://phmhqnwas003/hmis/telephonics/Teledetail.aspx?showresult=Y&ReceivedDate=02...
8/8/2011

<<<PAGE 14>>>

TeleDetail
Page 2 of 2
133500 Appendix B NRC Report 967232
Medium Type: LAND
Additional Medium Information:
TANK DIKE
Injuries: Fatalites:
Evacuations: Yes Yes No No Unknown Unknown No. of Evacuations:
Damages: Yes Yes No No Unknown Unknown Damage Amount:
Federal Agency Notified: Yes Yes No No Unknown Unknown State Agency Notified: Yes Yes No No Unknown Unknown
Other Agency Notified: Yes Yes No No Unknown Unknown
Remedial Actions
REMOVAL OF PRODUCT. TANK BEING EMPTIED. EXPLORATORY DIGS INTO WATER LINES.
Additional Info
WEB REPORT.
Latitude
Degrees: 39 Minutes: 53 Seconds: 42 Quadrant: N
Longitude
Degrees: 75 Minutes: 15 Seconds: 38 Quadrant: W
Distance from City: Direction:
Section: Township: DARBY
Range: Milepost:
Rescinded Rescinded Comments (max 250 characters)
<< Previous << Previous 1..1 of 1 << Save >>
Page 2 of 2
https://phmhqnwas003/hmis/telephonics/Teledetail.aspx?showresult=Y&ReceivedDate=02...
8/8/2011

<<<PAGE 15>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
NOTICE: This report is required by 49 CFR Part 195. Failure to report can result in a civil penalty not to
exceed $100,000 for each violation for each day that such violation persists except that the maximum civil
penalty shall not exceed $1,000,000 as provided in 49 USC 60122.
OMB NO: 2137-0047
EXPIRATION DATE: 01/31/2013
Report Date: 03/07/2011
U.S Department of Transportation
Pipeline and Hazardous Materials Safety Administration
No. 20110080 - 16865
--------------------------
(DOT Use Only)
ACCIDENT REPORT - HAZARDOUS LIQUID
PIPELINE SYSTEMS
A federal agency may not conduct or sponsor, and a person is not required to respond to, nor shall a person be subject to a penalty for failure to comply
with a collection of information subject to the requirements of the Paperwork Reduction Act unless that collection of information displays a current valid
OMB Control Number. The OMB Control Number for this information collection is 2137-0047. Public reporting for this collection of information is estimated
to be approximately 10 hours per response (5 hours for a small release), including the time for reviewing instructions, gathering the data needed, and
completing and reviewing the collection of information. All responses to this collection of information are mandatory. Send comments regarding this
burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to: Information Collection Clearance
Officer, PHMSA, Office of Pipeline Safety (PHP-30) 1200 New Jersey Avenue, SE, Washington, D.C. 20590.
INSTRUCTIONS
Important: Please read the separate instructions for completing this form before you begin. They clarify the information requested and provide specific
examples. If you do not have a copy of the instructions, you can obtain one from the PHMSA Pipeline Safety Community Web Page at
http://www.phmsa.dot.gov/pipeline.
PART A - KEY REPORT INFORMATION
Report Type: (select all that apply) Original: Supplemental: Final:
Yes Yes
Last Revision Date: 08/28/2012
1. Operator's OPS-issued Operator Identification Number (OPID): 18718
2. Name of Operator SUNOCO PIPELINE L.P.
3. Address of Operator:
3a. Street Address 525 FRITZTOWN ROAD
3b. City SINKING SPRING
3c. State Pennsylvania
3d. Zip Code 19608
4. Local time (24-hr clock) and date of the Accident: 02/08/2011 12:13
5. Location of Accident:
Latitude: 39.897834
Longitude: -75.262507
6. National Response Center Report Number (if applicable): 967232
7. Local time (24-hr clock) and date of initial telephonic report to the
National Response Center (if applicable): 02/11/2011 16:20
8. Commodity released: (select only one, based on predominant
volume released) Crude Oil
- Specify Commodity Subtype:
- If "Other" Subtype, Describe:
- If Biofuel/Alternative Fuel and Commodity Subtype is
Ethanol Blend, then % Ethanol Blend:
%:
- If Biofuel/Alternative Fuel and Commodity Subtype is
Biodiesel, then Biodiesel Blend (e.g. B2, B20, B100):
B
9. Estimated volume of commodity released unintentionally (Barrels): 38.00
10. Estimated volume of intentional and/or controlled release/blowdown
(Barrels):
11. Estimated volume of commodity recovered (Barrels): 38.00
12. Were there fatalities? No
- If Yes, specify the number in each category:
12a. Operator employees
12b. Contractor employees working for the Operator
12c. Non-Operator emergency responders
12d. Workers working on the right-of-way, but NOT
associated with this Operator
12e. General public
12f. Total fatalities (sum of above)
13. Were there injuries requiring inpatient hospitalization? No
- If Yes, specify the number in each category:
13a. Operator employees
13b. Contractor employees working for the Operator
13c. Non-Operator emergency responders
13d. Workers working on the right-of-way, but NOT
Page 1 of 14
Reproduction of this form is permitted
Page 1 of 14

<<<PAGE 16>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
associated with this Operator
13e. General public
13f. Total injuries (sum of above)
14. Was the pipeline/facility shut down due to the Accident? No
- If No, Explain: Facility was on scheduled shut down. Facility resumed
operations on 2/23/11
- If Yes, complete Questions 14a and 14b: (use local time, 24-hr clock)
14a. Local time and date of shutdown:
14b. Local time pipeline/facility restarted:
- Still shut down? (* Supplemental Report Required)
15. Did the commodity ignite? No
16. Did the commodity explode? No
17. Number of general public evacuated: 0
18. Time sequence (use local time, 24-hour clock):
18a. Local time Operator identified Accident: 02/08/2011 12:13
18b. Local time Operator resources arrived on site: 02/08/2011 12:49
PART B - ADDITIONAL LOCATION INFORMATION
1. Was the origin of Accident onshore? Yes
If Yes, Complete Questions (2-12)
If No, Complete Questions (13-15)
- If Onshore:
2. State: Pennsylvania
3. Zip Code: 19079
4. City Sharon Hill
5. County or Parish Delaware
6. Operator-designated location:
Specify:
7. Pipeline/Facility name: Darby Creek Tank Farm
8. Segment name/ID:
9. Was Accident on Federal land, other than the Outer Continental Shelf
(OCS)? No
10. Location of Accident: Totally contained on Operator-controlled property
11. Area of Accident (as found): Tank, including attached appurtenances
Specify:
- If Other, Describe:
Depth-of-Cover (in):
12. Did Accident occur in a crossing? No
- If Yes, specify below:
- If Bridge crossing –
Cased/ Uncased:
- If Railroad crossing –
Cased/ Uncased/ Bored/drilled
- If Road crossing –
Cased/ Uncased/ Bored/drilled
- If Water crossing –
Cased/ Uncased
- Name of body of water, if commonly known:
- Approx. water depth (ft) at the point of the Accident:
- Select:
- If Offshore:
13. Approximate water depth (ft) at the point of the Accident:
14. Origin of Accident:
- In State waters - Specify:
- State:
- Area:
- Block/Tract #:
- Nearest County/Parish:
- On the Outer Continental Shelf (OCS) - Specify:
- Area:
- Block #:
15. Area of Accident:
PART C - ADDITIONAL FACILITY INFORMATION
1. Is the pipeline or facility: Interstate
2. Part of system involved in Accident: Onshore Breakout Tank or Storage Vessel, including
Attached Appurtenances
- If Onshore Breakout Tank or Storage Vessel, Including Attached
Appurtenances, specify: Atmospheric or Low Pressure
Page 2 of 14
Reproduction of this form is permitted
Page 2 of 14

<<<PAGE 17>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
3. Item involved in Accident: Tank/Vessel
- If Pipe, specify:
3a. Nominal diameter of pipe (in):
3b. Wall thickness (in):
3c. SMYS (Specified Minimum Yield Strength) of pipe (psi):
3d. Pipe specification:
3e. Pipe Seam , specify:
- If Other, Describe:
3f. Pipe manufacturer:
3g. Year of manufacture:
3h. Pipeline coating type at point of Accident, specify:
- If Other, Describe:
- If Weld, including heat-affected zone, specify:
- If Other, Describe:
- If Valve, specify:
- If Mainline, specify:
- If Other, Describe:
3i. Manufactured by:
3j. Year of manufacture:
- If Tank/Vessel, specify: Double Bottom System
- If Other - Describe:
- If Other, describe:
4. Year item involved in Accident was installed: 1948
5. Material involved in Accident: Material other than Carbon Steel
- If Material other than Carbon Steel, specify: Steel
6. Type of Accident Involved: Leak
- If Mechanical Puncture – Specify Approx. size:
in. (axial) by
in. (circumferential)
- If Leak - Select Type: Other
- If Other, Describe: Hole in tank floor
- If Rupture - Select Orientation:
- If Other, Describe:
Approx. size: in. (widest opening) by
in. (length circumferentially or axially)
- If Other – Describe:
PART D - ADDITIONAL CONSEQUENCE INFORMATION
1. Wildlife impact: No
1a. If Yes, specify all that apply:
- Fish/aquatic
- Birds
- Terrestrial
2. Soil contamination: Yes
3. Long term impact assessment performed or planned: No
4. Anticipated remediation: No
4a. If Yes, specify all that apply:
- Surface water
- Groundwater
- Soil
- Vegetation
- Wildlife
5. Water contamination: No
5a. If Yes, specify all that apply:
- Ocean/Seawater
- Surface
- Groundwater
- Drinking water: (Select one or both)
- Private Well
- Public Water Intake
5b. Estimated amount released in or reaching water (Barrels):
5c. Name of body of water, if commonly known:
6. At the location of this Accident, had the pipeline segment or facility
been identified as one that "could affect" a High Consequence Area
(HCA) as determined in the Operator's Integrity Management Program?
Yes
7. Did the released commodity reach or occur in one or more High
Consequence Area (HCA)? Yes
7a. If Yes, specify HCA type(s): (Select all that apply)
- Commercially Navigable Waterway: Yes
Page 3 of 14
Reproduction of this form is permitted
Page 3 of 14

<<<PAGE 18>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
Was this HCA identified in the "could affect"
determination for this Accident site in the Operator's
Integrity Management Program?
Yes
- High Population Area: Yes
Was this HCA identified in the "could affect"
determination for this Accident site in the Operator's
Integrity Management Program?
Yes
- Other Populated Area
Was this HCA identified in the "could affect" determination
for this Accident site in the Operator's Integrity
Management Program?
- Unusually Sensitive Area (USA) - Drinking Water
Was this HCA identified in the "could affect" determination
for this Accident site in the Operator's Integrity
Management Program?
- Unusually Sensitive Area (USA) - Ecological Yes
Was this HCA identified in the "could affect" determination
for this Accident site in the Operator's Integrity
Management Program?
Yes
8. Estimated Property Damage:
8a. Estimated cost of public and non-Operator private property
damage $ 0
8b. Estimated cost of commodity lost $ 0
8c. Estimated cost of Operator's property damage & repairs $ 0
8d. Estimated cost of Operator's emergency response $ 257,250
8e. Estimated cost of Operator's environmental remediation $ 0
8f. Estimated other costs $ 0
Describe: This includes emergency response and cleaning of the tank
to investigate cause.
8g. Total estimated property damage (sum of above) $ 257,250
PART E - ADDITIONAL OPERATING INFORMATION
1. Estimated pressure at the point and time of the Accident (psig): .00
2. Maximum Operating Pressure (MOP) at the point and time of the
Accident (psig): .00
3. Describe the pressure on the system or facility relating to the
Accident (psig): Pressure did not exceed MOP
4. Not including pressure reductions required by PHMSA regulations
(such as for repairs and pipe movement), was the system or facility
relating to the Accident operating under an established pressure
restriction with pressure limits below those normally allowed by the
MOP?
No
- If Yes, Complete 4.a and 4.b below:
4a. Did the pressure exceed this established pressure
restriction?
4b. Was this pressure restriction mandated by PHMSA or the
State?
5. Was "Onshore Pipeline, Including Valve Sites" OR "Offshore
Pipeline, Including Riser and Riser Bend" selected in PART C, Question
2?
No
- If Yes - (Complete 5a. – 5f. below)
5a. Type of upstream valve used to initially isolate release
source:
5b. Type of downstream valve used to initially isolate release
source:
5c. Length of segment isolated between valves (ft):
5d. Is the pipeline configured to accommodate internal
inspection tools?
- If No, Which physical features limit tool accommodation? (select all that apply)
- Changes in line pipe diameter
- Presence of unsuitable mainline valves
- Tight or mitered pipe bends
- Other passage restrictions (i.e. unbarred tee's,
projecting instrumentation, etc.)
- Extra thick pipe wall (applicable only for magnetic
flux leakage internal inspection tools)
- Other -
- If Other, Describe:
5e. For this pipeline, are there operational factors which
significantly complicate the execution of an internal inspection tool
run?
Page 4 of 14
Reproduction of this form is permitted
Page 4 of 14

<<<PAGE 19>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
- If Yes, Which operational factors complicate execution? (select all that apply)
- Excessive debris or scale, wax, or other wall buildup
- Low operating pressure(s)
- Low flow or absence of flow
- Incompatible commodity
- Other -
- If Other, Describe:
5f. Function of pipeline system:
6. Was a Supervisory Control and Data Acquisition (SCADA)-based
system in place on the pipeline or facility involved in the Accident? Yes
If Yes -
6a. Was it operating at the time of the Accident? Yes
6b. Was it fully functional at the time of the Accident? Yes
6c. Did SCADA-based information (such as alarm(s),
alert(s), event(s), and/or volume calculations) assist with
the detection of the Accident?
No
6d. Did SCADA-based information (such as alarm(s),
alert(s), event(s), and/or volume calculations) assist with
the confirmation of the Accident?
No
7. Was a CPM leak detection system in place on the pipeline or facility
involved in the Accident? Yes
- If Yes:
7a. Was it operating at the time of the Accident? Yes
7b. Was it fully functional at the time of the Accident? Yes
7c. Did CPM leak detection system information (such as
alarm(s), alert(s), event(s), and/or volume calculations) assist
with the detection of the Accident?
No
7d. Did CPM leak detection system information (such as
alarm(s), alert(s), event(s), and/or volume calculations) assist
with the confirmation of the Accident?
No
8. How was the Accident initially identified for the Operator? Local Operating Personnel, including contractors
- If Other, Specify:
8a. If "Controller", "Local Operating Personnel", including
contractors", "Air Patrol", or "Guard Patrol by Operator or its
contractor" is selected in Question 8, specify the following:
Operator employee
9. Was an investigation initiated into whether or not the controller(s) or
control room issues were the cause of or a contributing factor to the
Accident?
- If No, the Operator did not find that an investigation of the
controller(s) actions or control room issues was necessary due to:
(provide an explanation for why the operator did not investigate)
No, the Operator did not find that an investigation of the
controller(s) actions or control room issues was necessary
due to: (provide an explanation for why the Operator did not
investigate)
The facility was down for maintenance at the time of the
accident
- If Yes, specify investigation result(s): (select all that apply)
- Investigation reviewed work schedule rotations,
continuous hours of service (while working for the
Operator), and other factors associated with fatigue
- Investigation did NOT review work schedule rotations,
continuous hours of service (while working for the
Operator), and other factors associated with fatigue
Provide an explanation for why not:
- Investigation identified no control room issues
- Investigation identified no controller issues
- Investigation identified incorrect controller action or
controller error
- Investigation identified that fatigue may have affected the
controller(s) involved or impacted the involved controller(s)
response
- Investigation identified incorrect procedures
- Investigation identified incorrect control room equipment
operation
- Investigation identified maintenance activities that affected
control room operations, procedures, and/or controller
response
- Investigation identified areas other than those above:
Describe:
PART F - DRUG & ALCOHOL TESTING INFORMATION
Page 5 of 14
Reproduction of this form is permitted
Page 5 of 14

<<<PAGE 20>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
1. As a result of this Accident, were any Operator employees tested
under the post-accident drug and alcohol testing requirements of DOT's
Drug & Alcohol Testing regulations?
No
- If Yes:
1a. Specify how many were tested:
1b. Specify how many failed:
2. As a result of this Accident, were any Operator contractor employees
tested under the post-accident drug and alcohol testing requirements of
DOT's Drug & Alcohol Testing regulations?
No
- If Yes:
2a. Specify how many were tested:
2b. Specify how many failed:
PART G – APPARENT CAUSE
Select only one box from PART G in shaded column on left representing the APPARENT Cause of the Accident, and answer
the questions on the right. Describe secondary, contributing or root causes of the Accident in the narrative (PART H).
Apparent Cause: G1 - Corrosion Failure
G1 - Corrosion Failure - only one sub-cause can be picked from shaded left-hand column
External Corrosion:
Internal Corrosion: Yes
- If External Corrosion:
1. Results of visual examination:
- If Other, Describe:
2. Type of corrosion: (select all that apply)
- Galvanic
- Atmospheric
- Stray Current
- Microbiological
- Selective Seam
- Other:
- If Other, Describe:
3. The type(s) of corrosion selected in Question 2 is based on the following: (select all that apply)
- Field examination
- Determined by metallurgical analysis
- Other:
- If Other, Describe:
4. Was the failed item buried under the ground?
- If Yes :
4a. Was failed item considered to be under cathodic
protection at the time of the Accident?
If Yes - Year protection started:
4b. Was shielding, tenting, or disbonding of coating evident at
the point of the Accident?
4c. Has one or more Cathodic Protection Survey been
conducted at the point of the Accident?
If "Yes, CP Annual Survey" – Most recent year conducted:
If "Yes, Close Interval Survey" – Most recent year conducted:
If "Yes, Other CP Survey" – Most recent year conducted:
- If No:
4d. Was the failed item externally coated or painted?
5. Was there observable damage to the coating or paint in the vicinity of
the corrosion?
- If Internal Corrosion:
6. Results of visual examination: Localized Pitting
- Other:
7. Type of corrosion (select all that apply): -
- Corrosive Commodity
- Water drop-out/Acid
- Microbiological
- Erosion Yes
- Other:
- If Other, Describe:
8. The cause(s) of corrosion selected in Question 7 is based on the following (select all that apply): -
- Field examination
Page 6 of 14
Reproduction of this form is permitted
Page 6 of 14

<<<PAGE 21>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
- Determined by metallurgical analysis Yes
- Other:
- If Other, Describe:
9. Location of corrosion (select all that apply): -
- Low point in pipe
- Elbow
- Other: Yes
- If Other, Describe: Tank Floor
10. Was the commodity treated with corrosion inhibitors or biocides? No
11. Was the interior coated or lined with protective coating? Yes
12. Were cleaning/dewatering pigs (or other operations) routinely
utilized? Not applicable - Not mainline pipe
13. Were corrosion coupons routinely utilized? Not applicable - Not mainline pipe
Complete the following if any Corrosion Failure sub-cause is selected AND the "Item Involved in Accident" (from PART C,
Question 3) is Tank/Vessel.
14. List the year of the most recent inspections:
14a. API Std 653 Out-of-Service Inspection Yes
- No Out-of-Service Inspection completed 2011
14b. API Std 653 In-Service Inspection Yes
- No In-Service Inspection completed 2011
Complete the following if any Corrosion Failure sub-cause is selected AND the "Item Involved in Accident" (from PART C,
Question 3) is Pipe or Weld.
15. Has one or more internal inspection tool collected data at the point of the
Accident?
15a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run: -
- Magnetic Flux Leakage Tool
Most recent year:
- Ultrasonic
Most recent year:
- Geometry
Most recent year:
- Caliper
Most recent year:
- Crack
Most recent year:
- Hard Spot
Most recent year:
- Combination Tool
Most recent year:
- Transverse Field/Triaxial
Most recent year:
- Other
Most recent year:
Describe:
16. Has one or more hydrotest or other pressure test been conducted since
original construction at the point of the Accident?
If Yes -
Most recent year tested:
Test pressure:
17. Has one or more Direct Assessment been conducted on this segment?
- If Yes, and an investigative dig was conducted at the point of the Accident::
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site:
Most recent year conducted:
18. Has one or more non-destructive examination been conducted at the
point of the Accident since January 1, 2002?
18a. If Yes, for each examination conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Page 7 of 14
Reproduction of this form is permitted
Page 7 of 14

<<<PAGE 22>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
Describe:
G2 - Natural Force Damage - only one sub-cause can be picked from shaded left-handed column
Natural Force Damage – Sub-Cause:
- If Earth Movement, NOT due to Heavy Rains/Floods:
1. Specify:
- If Other, Describe:
- If Heavy Rains/Floods:
2. Specify:
- If Other, Describe:
- If Lightning:
3. Specify:
- If Temperature:
4. Specify:
- If Other, Describe:
- If High Winds:
- If Other Natural Force Damage:
5. Describe:
Complete the following if any Natural Force Damage sub-cause is selected.
6. Were the natural forces causing the Accident generated in
conjunction with an extreme weather event?
6a. If Yes, specify: (select all that apply)
- Hurricane
- Tropical Storm
- Tornado
- Other
- If Other, Describe:
G3 - Excavation Damage - only one sub-cause can be picked from shaded left-hand column
Excavation Damage – Sub-Cause:
- If Excavation Damage by Operator (First Party):
- If Excavation Damage by Operator's Contractor (Second Party):
- If Excavation Damage by Third Party:
- If Previous Damage due to Excavation Activity:
Complete Questions 1-5 ONLY IF the "Item Involved in Accident" (from PART C, Question 3) is Pipe or Weld.
1. Has one or more internal inspection tool collected data at the point of
the Accident?
1a. If Yes, for each tool used, select type of internal inspection tool and indicate most recent year run: -
- Magnetic Flux Leakage
Most recent year conducted:
- Ultrasonic
Most recent year conducted:
- Geometry
Most recent year conducted:
- Caliper
Most recent year conducted:
- Crack
Most recent year conducted:
- Hard Spot
Most recent year conducted:
- Combination Tool
Most recent year conducted:
- Transverse Field/Triaxial
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
2. Do you have reason to believe that the internal inspection was
completed BEFORE the damage was sustained?
3. Has one or more hydrotest or other pressure test been conducted since
original construction at the point of the Accident?
- If Yes:
Page 8 of 14
Reproduction of this form is permitted
Page 8 of 14

<<<PAGE 23>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
Most recent year tested:
Test pressure (psig):
4. Has one or more Direct Assessment been conducted on the pipeline
segment?
- If Yes, and an investigative dig was conducted at the point of the Accident:
Most recent year conducted:
- If Yes, but the point of the Accident was not identified as a dig site:
Most recent year conducted:
5. Has one or more non-destructive examination been conducted at the
point of the Accident since January 1, 2002?
5a. If Yes, for each examination, conducted since January 1, 2002, select type of non-destructive examination and indicate most
recent year the examination was conducted:
- Radiography
Most recent year conducted:
- Guided Wave Ultrasonic
Most recent year conducted:
- Handheld Ultrasonic Tool
Most recent year conducted:
- Wet Magnetic Particle Test
Most recent year conducted:
- Dry Magnetic Particle Test
Most recent year conducted:
- Other
Most recent year conducted:
Describe:
Complete the following if Excavation Damage by Third Party is selected as the sub-cause.
6. Did the operator get prior notification of the excavation activity?
6a. If Yes, Notification received from: (select all that apply) -
- One-Call System
- Excavator
- Contractor
- Landowner
Complete the following mandatory CGA-DIRT Program questions if any Excavation Damage sub-cause is selected.
7. Do you want PHMSA to upload the following information to CGA-
DIRT (www.cga-dirt.com)?
8. Right-of-Way where event occurred: (select all that apply) -
- Public
- If "Public", Specify:
- Private
- If "Private", Specify:
- Pipeline Property/Easement
- Power/Transmission Line
- Railroad
- Dedicated Public Utility Easement
- Federal Land
- Data not collected
- Unknown/Other
9. Type of excavator:
10. Type of excavation equipment:
11. Type of work performed:
12. Was the One-Call Center notified?
12a. If Yes, specify ticket number:
12b. If this is a State where more than a single One-Call Center
exists, list the name of the One-Call Center notified:
13. Type of Locator:
14. Were facility locate marks visible in the area of excavation?
15. Were facilities marked correctly?
16. Did the damage cause an interruption in service?
16a. If Yes, specify duration of the interruption (hours)
17. Description of the CGA-DIRT Root Cause (select only the one predominant first level CGA-DIRT Root Cause and then, where
available as a choice, the one predominant second level CGA-DIRT Root Cause as well):
Root Cause:
- If One-Call Notification Practices Not Sufficient, specify:
- If Locating Practices Not Sufficient, specify:
- If Excavation Practices Not Sufficient, specify:
- If Other/None of the Above, explain:
G4 - Other Outside Force Damage - only one sub-cause can be selected from the shaded left-hand column
Page 9 of 14
Reproduction of this form is permitted
Page 9 of 14

<<<PAGE 24>>>

133500 Appendix C Sunoco 7000-1 DC9 - Final Report
Other Outside Force Damage – Sub-Cause:
- If Nearby Industrial, Man-made, or Other Fire/Explosion as Primary Cause of Incident:
- If Damage by Car, Truck, or Other Motorized Vehicle/Equipment NOT Engaged in Excavation:
1. Vehicle/Equipment operated by:
- If Damage by Boats, Barges, Drilling Rigs, or Other Maritime Equipment or Vessels Set Adrift or Which Have Otherwise Lost
Their Mooring:
2. Select one or more of the following IF an extreme weather event was a factor:
- Hurrican
- **truncated:** true
- **body characters:** 49574
