# Mr. John P. McGavis — Hazardous Materials Safety Interpretation

- **operation:** document
- **citation:** 00-0157
- **title:** Mr. John P. McGavis — Hazardous Materials Safety Interpretation
- **source type:** guidance
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** guidance
- **official:** true
- **published on:** 2000-06-21
- **effective on:** Not available
- **summary:** 00-0157 response to Mr. John P. McGavis concerning 180.407.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-interpretation-00-0157.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-interpretation-00-0157.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-interpretation-00-0157
- **source url:** https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/2000/000157.pdf
**body:**

<<<PAGE 1>>>

of Transportation
U.S. Department
400 Seventh Street, S.W.
Washington, D.C.
20590
Research and
Special Programs
Administration
JUN 2 1 2000
Mr. John P. McGavis
Ref. No. 00-0157
Specialized Transport Repair, Inc.
100 Commerce Drive
Buffalo, New York 14218
Dear Mr. McGavis:
This is in further response to your letter, dated May 25, 2000, concerning cargo tank retest
requirements under the Hazardous Materials Regulations (HMR; 49 CFR Parts 171-180). You asked
whether an MC 307 cargo tank on which the manway cover has been altered by the addition of a 3"
nozzle must complete a pressure test before it can be returned to service:
After further discussion with technical staff of the Research and Special Programs Administration's
Office of Hazardous Materials Technology and the Federal Motor Carrier Safety Administration's
Hazardous Materials Division, we have determined that our previous response to your question, in our
letter dated June 7, 2000, was in error. The addition of a 3" nozzle to a manway cover is, in fact, a
"modification" to the cargo tank because it involves a change to the design and construction of the
cargo tank that affects its lading retention capability (see § 180.403 of the HMR). Thus, a Design
Certifying Engineer must certify that the modified design for the manhole assembly meets the structural
integrity requirements of the DOT 407 specification, and a Registered Inspector must certify that the
modified manhole assembly conforms to the DOT 407 specification by issuing a supplemental
manufacturer's certificate (see § 180.413(d)(5)). The modified manhole assembly must conform to the
requirements for the DOT 407 cargo tank specification in § 178.345-5.
In addition, the suitability of a modification that affects the structural integrity of a cargo tank with
respect to pressure must be determined by a pressure test (see § 180.413(d)(10)). For the
modification of the manway cover that you have described, this requirement may be met by the
performance of a bench test of the modified cover, provided that your bench test fixture is
representative of the manhole assembly on the cargo tank. You need not complete a pressure test of
the entire cargo tank.
180.407
000157

<<<PAGE 2>>>

Page 2
I hope this information is helpful. Please accept my apology for any confusion that may have resulted
from our previous response. If you have further questions, please do not hesitate to contact this office.
Sincerely,
Thomas t. allan
Thomas G. Allan
Senior Transportation Regulations Specialist
Office of Hazardous Materials Standards
....
cordoned
0:0*7
53****:
Hit:
6s..
4220570%

<<<PAGE 3>>>

STE
1530020
100 Commerce Drive
SPECIALIZED TRANSPORT
Buffalo, NY 14218
REPAIR Inc.
Phone (716) 827-8265
Fax (716) 827-7231
May 25, 2000
Federal Motor Carrier Safety Administration
Gorsky
Hazardous Materials Division
400 Tin St. SW
Research and Special Programs Administration
5180.407
Washington, DC 20590
00-0157
Mr. Daniel Shelton,
a customer. The alteration involves the addition of one 3'" nozzle into the manway cover.
Per our conversation today, we are being asked to alter a group of MC307SS cargo tanks for
This is to enable connection of these trailers to vapor recovery systems at loading areas.
The manway covers are Betts 6-lug Model 8310 and 8355 and possibly other similar
models) and are removed from the trailers for the alteration. No welding or other repairs or
alterations of the tank shell itself are involved. Alterations are done to ASME and National
Board standards under our R-stamp authorization.
Our question is, can these covers be bench tested and then reinstalled onto the trailers rather
than completing a pressure test of the complete tank trailer? Please advise.
Thank you,
John P. McGavis