# gh Package & Product Testing and Consulting, Inc. — Hazardous Materials Safety Interpretation

- **operation:** document
- **citation:** 07-0009
- **title:** gh Package & Product Testing and Consulting, Inc. — Hazardous Materials Safety Interpretation
- **source type:** guidance
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** guidance
- **official:** true
- **published on:** 2007-03-20
- **effective on:** Not available
- **summary:** 07-0009 response to gh Package & Product Testing and Consulting, Inc. concerning 178.601.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-interpretation-07-0009.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-interpretation-07-0009.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-interpretation-07-0009
- **source url:** https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/2007/070009.pdf
**body:**

<<<PAGE 1>>>

s. Depanmel
Transportatic
Washington, D.C. 20590
400 Seventh Street, S.W.
ipeline and Hazardou
laterials Safety Administratio
MAR
Mr. H. Perry Hock
Technical Director
Ref. No.: 07-0009
gh Package & Product Testing
and Consulting, Inc.
4090 Thunderbird Lane
Fairfield, OH 45014-2234
Dear Mr. Hock:
This is in response to your January 16, 2007 letter regarding selective testing of packagings
under the Hazardous Materials Regulations (HMR; 49 CFR Parts 171-180). Specifically, you
§ 178.601(g) (2).
ask if partition dividers may be added to a packaging tested in accordance with Variation 2 under
The answer is yes, provided the dividers do not replace any integral cushioning material present
type in an outer packaging without retesting if the specific conditions of the variation are met.
in the original testing of the packaging design type. Variation 2 allows inner packagings of any
Therefore, as long as the conditions in § 178.601(g)(2) are met, the addition of dividers does not
require further testing.
I hope this information is helpful. If you have further questions, please do not hes tate to contact
Sincerely
Hattie L. Mitchell
Office of Hazardous Materials Standards
Chief, Regulatory Review and Reinvention
178.601g) (2)
070009

<<<PAGE 2>>>

Pollack
$178.601(g)z)
gh Package
gh
& Product
Testing
Testing and
07-0009
Consulting, Inc.
Mr. H. Perry Hock
Technical Director
gh Package & Product Testing
1090 Thunderbird Lane
and Consulting, Inc
Fairfield, OH 45014-2234
Don,
Question regarding a 4GV from a customer:
o cushioning between the bottles, and there was 3 inches of cushioning between th
he ship a 18 x 18 inch box - the pack passed with 9 bottles in the center. There is wa
bottles and the exterior.
Top view
look like this from the top: It would actually increase the filling between the bottles an
Can they use a 4 x 4 divider, filling the void spaces with the same cushioning, that woul
the exterior wall from 3" to just under 4 ½½"
Partition not present
during testing
Thanks,
H. Perry Hock
gh Package & Product, Testing and Consulting, Inc.
513.870.0080 ext 103