# Eastern Shore Natural Gas Company — Pipeline Safety Interpretation

- **operation:** document
- **citation:** PI-75-023
- **title:** Eastern Shore Natural Gas Company — Pipeline Safety Interpretation
- **source type:** guidance
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** guidance
- **official:** true
- **published on:** 1975-05-29
- **effective on:** Not available
- **summary:** PI-75-023 response to Eastern Shore Natural Gas Company concerning 192.703.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-75-023.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-75-023.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-75-023
- **source url:** https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/1975/PI75023.pdf
**body:**

<<<PAGE 1>>>

May 29, 1975
Mr. Howard E. Boller
General Superintendent
Eastern Shore Natural Gas Company
P.O. Box 615
Dover, Delaware 19901
Dear Mr. Boller:
This responds to your letter of April 18, 1975, regarding construction of a public road over an
existing gas pipeline. You ask what criteria should be used in determining whether the pipeline
should remain in place or be relocated.
Under the circumstances of a pending road construction, the Federal gas pipeline safety standards
in 49 CFR 192.613 and 192.703(b) require that the pipeline be evaluated for safety and
appropriate remedial or protective measures taken, if necessary, in accord with those sections. In
determining what measures may be necessary, you should consider the types and magnitudes of all
anticipated external forces which may be applied to the pipeline during and after the road
construction. Various causes of external forces which you should consider include: unstable
soils, floods, traffic, movement by heavy construction or maintenance equipment, and direct
damage by construction equipment.
If it is decided that a portion of the pipeline should be replaced, relocated or otherwise changed to
protect it against likely external forces, that replacement, relocation, or change must comply with
the requirements in 49 CFR Part 192 applicable to design, installation, and testing of pipelines.
We trust this satisfactorily answers your inquiry.
Sincerely,
Joseph C. Caldwell
Director
Office of Pipeline Safety
dal\192\703\75-05-29
1

<<<PAGE 2>>>

April 18, 1975
Mr. Joseph C. Caldwell, Director
Office of Pipeline Safety
Department of Transportation
Washington, D.C. 20590
Dear Mr. Caldwell:
We have a section of pipeline which lies in a Class 3 Location and operates at between 30
and 39% SMYS. This pipeline is within the confines of the state highway right of way. We have
received plans from the State Highway Department indicating they are going to widen and change
the location of this road with the result that our pipeline will be under the new roadbed.
What criteria must we use in determining whether the pipeline can remain under the new
roadbed or it must be relocated?
Sincerely yours,
EASTERN SHORE NATURAL GAS COMPANY
Howard E. Boller
General Superintendent
dal\192\703\75-05-29
2
- **truncated:** false
- **body characters:** 2280