# County of Harris — Pipeline Safety Interpretation

- **operation:** document
- **citation:** PI-78-014
- **title:** County of Harris — Pipeline Safety Interpretation
- **source type:** guidance
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** guidance
- **official:** true
- **published on:** 1978-05-24
- **effective on:** Not available
- **summary:** PI-78-014 response to County of Harris concerning 192.707.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-78-014.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-78-014.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-78-014
- **source url:** https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/1978/PI78014.pdf
**body:**

<<<PAGE 1>>>

Mr. Richard P. Doss
County Engineer
County of Harris
1115 Congress Street
Houston, Texas 77002
Dear Mr. Doss:
This is in further response to your letter of February 27, 1978, to Mr. Robert F. Aubry, Chief,
Southwest Region, concerning the crossing of county highways by gas pipelines.
Your letter states that placement of line markers in accordance with 49 CFR 192.707 at highway
crossings at locations other than highway right-of-way lines creates difficulties in mowing and in
maintaining roadway shoulders. In this regard, you ask whether a County Order which, among
other things, requires markers at right-of-way lines, qualifies under Section 192.707(b) as a
"program for preventing interference with underground pipelines" that would exempt pipelines in
Class 3 and Class 4 locations from the Section 192.707 line marking requirement.
We have reviewed the County Order and find that it does not establish a "program" that would
entitle gas pipelines to an exemption under Section 192.707(b). The "program" contemplated by
Section 192.707(b) is one, such as the commonly referred to "one-call system," which serves as
an alternative to line marking. A qualified program compels both pipeline operators and
construction contractors to cooperate in carefully identifying the location of underground
pipelines before construction activities may begin. In contrast, the County Order does not contain
these features. It is written more to protect the highway against the possible hazards of a pipeline
crossing than to protect the pipeline from damage by further construction activities at the
crossing. Although the requirement for placement of line markers at right-of-way boundaries
does offer protection against unintended interference, it is not a "program" which serves as an
alternative to line marking within the meaning of Section 192.707(b).
For most normal rights-of-way, it seems that placement of markers at each right-of-way should
meet the requirements of Section 192.707. In some cases, however, markers at right-of-way lines
may not meet the intent of Section 192.707 if they do not definitively identify the location of the
DB
C:\WP51\INTERPRT\192\707\78-05-24
1

<<<PAGE 2>>>

pipeline, or are too far removed from the actual road crossing or potential sites for excavation, to
serve any useful purpose in warning an excavator of the presence of an underground pipeline.
In such cases, we believe that your problem could be resolved if the County were to discuss it
with pipeline operators and suggest ways to install markers which do not interfere with mowing
and shoulder maintenance but still meet the line marking requirements of Section 192.707.
Sincerely,
Cesar De Leon
Associate Safety Regulation
Materials Transportation Bureau
DB
C:\WP51\INTERPRT\192\707\78-05-24
2

<<<PAGE 3>>>

Mr. Richard P. Doss, County Engineer
Room 650 Family Law Center Building
1115 Congress Street
Houston, Texas 77002
Dear Mr. Doss:
Reference is made to your letter of February 27, 1978, regarding Section 192.707, Line
Markers for Mains and Transmission Lines.
In order to expedite this matter, your letter and the attachment has been forwarded to our
Washington office with the request that a reply be forwarded directly to you.
If this office can be of further assistance, please let me know.
Sincerely,
Robert F. Auby
Chief, Southwest Region
Office of Pipeline Safety Operations
DB
C:\WP51\INTERPRT\192\707\78-05-24
3

<<<PAGE 4>>>

Mr. Robert F. Aubry
Chief
Department of Transportation
Southwest Region OPSO
6622 Hornwood
Houston, Texas 77074
Dear Mr. Aubry:
Recent review of D.O.T. Regulations for the Transportation of Natural and Other Gas by
Pipeline, Parts 191 and 192, has made it necessary to request an opinion from your office.
Certain problem areas exist between Section 192.707, Line Markers for Mains and Transmission
Lines, and the pursuance of normal maintenance procedures by Harris County forces in the field.
To be specific, the presence of line markers at locations other than right-of-way lines creates
severe difficulties in mowing and in the maintenance of roadway shoulders.
In the opinion of this office, the limitation of markers to right-of-way lines is both advantageous
to Harris County and well within the realm of safe practice. This opinion is supported in the
Utility Accommodation Policy of the Texas Department of Highways and Public Transportation,
Sections 402 and 403, concerning markers for both high and low pressure pipelines, which has
been incorporated into the Harris County Pipeline Regulations, a copy of which is enclosed.
Both sets of regulations state that "the utility company shall place a readily identifiable and
suitable marker at each right-of-way line where it is crossed by any high (low) pressure gas or
liquid petroleum line except where marked by a vent.
DB
C:\WP51\INTERPRT\192\707\78-05-24
4

<<<PAGE 5>>>

A method of solving the maintenance problems of Harris County and full compliance with D.O.T.
Regulations presents itself in Section 192.707 of Part 192, Title 49 of the Code of Federal
Regulations. It is this method upon which our request for an opinion is based.
It is clearly stated in Section 192.707(b) that "line markers are not required for buried mains and
transmission lines (2) in Class 3 or Class 4 locations (i. i.) where a program for preventing
interference with underground pipelines is established by la.
Population density and land development indicated that at present almost all of Harris County
qualifies as either a Class 3 or Class 4 location, as outlined in Section 192,5 of your regulations,
and that this will certainly be the case in the near future.
If this blanket qualification of Harris County as falling into Class 3 or Class 4 locations is coupled
with "a program for preventing interference...established by law" in the form of the attached
Harris County Pipeline Regulations, then a viable Solution to our problem exists.
Please review this situation and render an opinion as to the validity of our interpretation of the
intent of your regulations.
Your assistance in this matter will be greatly appreciated.
Very truly yours,
Richard P. Doss
County Engineer
DB
C:\WP51\INTERPRT\192\707\78-05-24
5

<<<PAGE 6>>>

A REVISED ORDER REGULATING THE LAYING, CONSTRUCTION, MAINTAINING
AND REPAIRING OF PUBLIC UTILITY PIPELINES, AND/OR MAINS, IN, UNDER,
ACROSS OR ALONG ROADS, STREETS, AND HIGHWAYS IN HARRIS COUNTY,
TEXAS, UNDER THE JURISDICTION OF THE COMMISSIONERS' COURT OF HARRIS
COUNTY, THAT QUALIFY AS AUTHORIZED PUBLIC UTILITY PIPELINES AND/OR
MAINS
ADOPTED BY
COMMISSIONERS' COURT
MAY 12, 1977
VOLUME 95 PAGE 328
DB
C:\WP51\INTERPRT\192\707\78-05-24
6

<<<PAGE 7>>>

It is the intent of Harris County to amend our current rules and regulations for installing,
adjusting and maintaining pipelines to adapt these specifications to those of the State of Texas and
the Federal specifications and guidelines as set forth by the Department of Transportation. Any
omission or deletion from these specifications that is contained in the State and Federal
specification shall be construed as being contained herein.
These revised specifications cover all public utility pipelines and/or mains, in, under,
across or along all County roads, streets and/or highways in Harris county, Texas, under the
jurisdiction of the Commissioners' Court of Harris County, Texas. owned and operated by any
person, firm, limited partnership, joint stock association, or corporation having the right to lay his
or its pipeline or pipelines and/or mains, under, along, across and/or over County roads, streets,
and/or highways by virtue of his, its or their qualifications as authorized public utility pipelines
and/or mains, under and/or by virtue of the Revised Civil Statutes of Texas, (1925), as amended,
hereinafter called pipeline and/or pipelines, shall henceforth be laid, and/or constructed and/or
maintained and/or repaired under the following regulations and provisions:
I. That said pipeline and/or pipelines shall not be laid or constructed in, under, across
or along such County roads, streets, and/or highways prior to furnishing to the
County Engineer of Harris County, Texas, the following information: surveys,
description and other data:
a. Notice of pipeline activity, upon the notice form herein adopted by
Commissioners' Court, an example of which is attached hereto, which when
completed shall show the name of the person or entity desiring to initiate
any pipeline activity; the pipe size, wall thickness of the pipe; grade of the
pipe; type of material or substance being or to be carried in the pipe' and
the anticipated working pressure. If the pipeline crosses or is to cross any
County road, the following additional information shall be given in the
blanks provided for same on such form, road name, survey and abstract,
length of crossing, and the type of construction, whether bored, jacked,
driven, tunneled or open cut under the road. If the pipeline runs or is to
run parallel to any County road within such roads, right-of-way, then in
addition to naming such road, there will be added a description of the point
at which such pipeline begins as well as a description of the point at
b. To such notice form shall be attached a map or plat reflecting the distance
and direction of such pipeline or pipelines, through Harris County, Texas,
as it affects the County roads, streets and highways of Harris County,
Texas.
DB
C:\WP51\INTERPRT\192\707\78-05-24
7

<<<PAGE 8>>>

II. III. IV. V. c. To such notice form shall attached detailed plans and specifications for the
construction under, across or along any County road right-of-way, such
plans and specifications to reflect the depth at which such pipeline or
pipelines are to be constructed along and/or across such County road right-
of-way, size and other information necessary to reflect accurately the
manner in which such pipeline will be constructed, in under, across or
along such County road right-of-way.
No pipeline shall be laid, maintained or repaired in such a manner as to interfere
with the construction, maintenance or repair of the County road, roadbed, ditches
or right-of-way in, over, across or along which such pipeline is constructed, and in
the event it shall develop that such pipeline interferes in any manner with the
construction, maintenance or repair of any County road, in, under, across or along
which it is constructed because of the depth at which such pipeline has been laid,
because of the widening, improving, maintaining or for reasons of public safety and
welfare, upon request of the County Engineer such pipeline shall be changed to
altered promptly under the existing right-of-way by the owner and/or operator of
such pipeline in such a manner as to interfere no longer with such construction,
maintenance, repair or the safety of the traveling public, and the owner and/or
operator of such pipeline shall, if demand therefore is made by the Commissioners'
Court of Harris County, bear all or a reasonable part of the cost and expense of
such change or alteration.
No pipeline shall be laid in such a manner as to interfere with the use of or obstruct
unreasonably a County road for the purpose of vehicular and pedestrian traffic, or
so as to interfere with or unreasonably obstruct any drainage on or along such
road, and no such pipeline shall be laid, maintained or repaired in such a manner as
to constitute a danger or hazard of any kind to persons or vehicles using such road,
nor shall any pipeline be laid, maintained or repaired so as to constitute a danger or
hazard to the public property within the boundaries of the right-of-way of said
County road, or to maintenance thereof by County employees.
That all pipelines that cross improved County roads shall be either jacked,
tunneled, bored or driven under the road for the full width of the improved portion
of the road. Improved County Roads as herein used are defined as any road
surfaced with a material other than dirt and the improved portion as that portion of
the road and shoulder lying between the backslope of each ditch.
Depth of Cover for High Pressure Pipe Lines
DB
C:\WP51\INTERPRT\192\707\78-05-24
8

<<<PAGE 9>>>

A. B. C. D. All pipelines that cross unimproved County roads shall be laid at a depth of
6 feet below natural ground.
All pipelines that cross County roads with open-ditch drainage shall be laid
a minimum of 36" below the bottom of ditch.
On curb and gutter sections all high pressure pipelines that cross County
roads shall be installed at least 24" below the bottom of the slab at the
gutter; provided however, in particular instances where it is determined by
the County Engineer that a greater depth is required, such pipeline shall be
installed as directed by the County Engineer.
In particular instances where it is determined by the County Engineer that a
greater depth for a particular pipeline should be required due to the
location or size of same, the type of product carried or other reason of
public safety or necessity, such pipeline shall be laid at such greater depth
as may be required by the County Engineer, but not to exceed the greater
of the following depths: At least eight (8) feet below the crown of the road
or four (4) feet below the bottom of the ditches on each side of such
County road, unless by reason of proposed or anticipated changes in the
grade of such County road or road ditches, the County Engineer should
determine a greater depth is advisable.
V.
1. Depth of Cover for Low Pressure Pipe Lines
For low pressure gas lines the minimum depth of cover within the right-of-
way and under roadway ditches, but outside the pavement structure, shall
be twenty-four inches for either encased or u--encased installations.
Exceptions may be authorized to permit existing lines to remain in place
with a reduction of six inches in the above specified depth. Low pressure
gas lines shall be a minimum of eighteen inches or one-half the diameter of
the pipe, whichever is greater, beneath the bottom of the pavement
structure. Where materials and other conditions justify, such as on existing
lines to remain in place, a minimum depth under the pavement structure of
twelve inches or one-half the diameter of the pipe, whichever is greater,
may be permitted.
As used herein, depth of lines is the depth to the tope of carrier pipe or
casing as applicable.
DB
C:\WP51\INTERPRT\192\707\78-05-24
9

<<<PAGE 10>>>

IV. VII. VIII. Any damage whatsoever to any County road, roadbed, ditches, or the
structure on or in the County road right-of-way caused by reason of the
laying, constructing, maintaining and repairing of a pipeline, in, under,
across or along such County road right-of-way shall be repaired
immediately and restored to the condition that such County road, roadbed,
ditches or other structures on or in such right-of-way was in before the
damage took place, such repairing and restoration to be at the sole cost and
expense of the owner or operator of such pipeline.
Where a pipeline or pipelines are constructed parallel with a County road
and where dirt is piled along the side of the trench cut for such pipeline,
weep holes shall be dug through such pile of dirt in order that water may
drain from roadbed and shoulders to the road ditches. Such weep holes
shall be dug through such piles of dirt at intervals not to exceed two
hundred (200) feet along such parallel pipeline construction, and at all
swags or low places in the roadbed of such County road. Such weep holes
shall be dug to a depth of six inches below the shoulder of such County
road and shall be dug for a width of twelve (12) inches, and such weep
holes shall be dug through the piles of dirt to the road ditches, or to such
an elevation that the bottom of the weep holes will discharge its water into
the road ditch. Such weep holes must be maintained free of obstruction
until the pipeline is completed and the pipeline trench backfilled, tamped
and leveled true to the original shoulder grade.
All high pressure pipelines installed across Country roads shall be protected by a 6
inch thick reinforced concrete pad as follows:
1. On curb and gutter streets the pad is to extend from back of curb to
the right-of-way line flush with finished ground level.
2. On roads with open ditch drainage the length of the pad is to be the
with of the ditch bottom plus 2 feet on each side, and the bottom of
the pad to be 6" above the top of the pipe.
3. All pads are to be the outside diameter of the pipe plus 4 feet in
width.
4. Reinforcing is to be No. 4 bars at 6 inch centers both ways.
DB
C:\WP51\INTERPRT\192\707\78-05-24
10

<<<PAGE 11>>>

IX. X. XI. All pipelines laid, constructed, maintained and/or repaired parallel to and
within the right-of-way of any County Road shall be laid, constructed,
maintained, and repaired at a distance of not less than four (4) feet from the
edge of the portion of road considered as normal traveling surface to the
nearest edge of such pipeline; and when possible all pipelines shall laid,
constructed, maintained and repaired in the area considered as the
backslope of the ditch. These underground installations shall be at such
depth so as to provide a minimum of 24" cover above top of pipe.
On curb and gutter sections all installations paralleling the road shall be
behind the curb and gutter.
When installation of any pipeline within County right-of-way requires the
digging of pits or trenching to such depth that the angle of repose created
with respect to the edge of the normal traveling surface of the road exceeds
33m41'24" (1 ½: 1 slope), the owner and/or operator shall at its own
expense furnish the County Engineer with soil testing laboratory reports
indicating if sheeting is required to safely preserve the road. If reports
indicate sheeting is required at various areas or for the entire length of
trench, it shall be installed by owner and/or operator at no expense to
Harris county.
Spacing for soil tests shall be at 1000' intervals unless soil indicated tests
should be made at shorter intervals or as directed by the County Engineer.
The County Engineer will maintain an list of testing laboratories which he
has approved and furnish a copy thereof to any person requesting same.
At least forty-eight (48) hours before commencing construction of any
pipeline in, under, across or along any County road, notice of the time such
construction shall commence shall be given to the County Engineer of
Harris County in order that he might supervise and inspect such
construction; provided however, that in cases of emergency requiring
immediate maintenance or repair of any pipeline, notice should be given to
the County Engineer as soon as possible, and when planned major
maintenance is proposed, notification shall be given as outlined under
Section 1.
Backfilling operations shall be performed as soon as possible. Back fill
material shall be free from large or frozen lumps, wood or other extraneous
material. The backfill shall be placed in uniform layers not to exceed 10
DB
C:\WP51\INTERPRT\192\707\78-05-24
11

<<<PAGE 12>>>

inches depth (loose measurement) and each layer thoroughly compacted to
the density of the surrounding area and to the satisfaction of the County
Engineer. However, if any pit or trench lies outside the angle of repose
defined in Section VIII, backfilling operations may be preformed by the
equipment method so long as compaction is to density of surrounding area.
Operation of equipment on the improved surface of any County road will
not be permitted, except in an instance whereby the laying, constructing,
maintaining, and repairing of pipelines cannot be accomplished by any other
method, and in this event all such equipment shall be equipped with rubber
tires, flat street pads or other similar means to assure complete protection
of the improved surface of the road.
These specifications govern on matters concerning accommodation,
location and methods for the installation, adjustment, relocation and
maintenance of utilities on right-of-way, it does not alter current policies
pertaining to authority for their installation nor determination of financial
responsibilities for placement or adjustment thereof. Where industry or
governmental codes, orders or laws require utilities to provide a higher
degree of protection than provided herein, the higher degree of protection
shall prevail.
Pipe Design
Pipe must be designed with sufficient wall thickness, or must be installed
with adequate protection, to withstand anticipated external pressures and
loads that will be imposed on the pipe after installation.
(a) Design formula for steel pipe
The design pressure for steel pipe is determined in accordance with
the following formula:
2St
P = D XFXEXT
P = Design pressure in pounds per square inch gauge.
S = Yield strength in pounds per square inch determined in
accordance with Sec. 192.107.
DB
C:\WP51\INTERPRT\192\707\78-05-24
12

<<<PAGE 13>>>

D = Nominal outside diameter of the pipe in inches.
t = Nominal wall thickness of the pipe in inches. If this is unknown,
it is determined in accordance with Sec. 192.109. Additional wall
thickness required for concurrent external loads in accordance with
Sec. 192.103 may not be included in computing design pressure.
F = Design factor determined in accordance with Sec. 192.111.
E = Longitudinal joint factor determined in accordance with Sec.
192.113.
T = Temperature derating factor determined in accordance with
Sec. 192.115.
NOTE: All items 191, 192 or 195 referred to in these
specifications refer to the regulations for the transportation of
natural and other gas by pipelines as revised October 1, 1973 by the
Dept. of Transportation Office of Pipeline Safety.
Design factor for steel pipe
(a) Except as otherwise provided in paragraph (b) of this
section, the design factor to be used in the design formula in
Sec. 192.105 is determined in accordance with the following
table:
(b) Class Design
location factor (f)
1 0.72
2 0.60
A design factor of 06.0 or less must be used in the design
formula in Sec. 192.105 for steel pipe in Class 1 locations
that:
(1) (2) Crosses the right-of-way of an unimproved public
road, without a casing:
Crosses without a casing, or makes parallel
encroachment on the right-of-way of either a hard
surfaced road, a highway, a public street, or a
railroad.
UTILITIES
DB
C:\WP51\INTERPRT\192\707\78-05-24
13

<<<PAGE 14>>>

This term, where used herein, applies to all lines and or their
accessories within the roadway rights-of-way.
LOW VOLUME ROADWAYS
Any roadways which carry traffic volumes of 750 vehicles per day
or less and upon which projected traffic volume at the design year
are not anticipated to exceed 1,300 vehicles per day.
HIGH AND LOW PRESSURE GAS LINES
High pressure gas lines are pipelines which carry a gaseous
substance and which are operated or may reasonably be expected in
the future to operates at a pressure of over 60 pounds per square
inch. Conversely, low pressure gas lines are those with an
operating pressure not expected to exceed 60 pounds per square
inch.
LOCATION
(1) (2) Utility lines shall be located to avoid or minimize the need
for adjustment for future roadway improvements and to
permit access to the utilities for their maintenance with
minimum interference to roadway traffic.
Utility lines crossing the roadway should be located at
approximate right angles to the road.
(3) Methods of Installation. Lines placed under any existing
roadway shall ne installed by boring or tunneling in
accordance with appropriate specifications. Jacking may be
used only when approved by the County Engineer. When
installed by jacking or boring, encasement of the line may be
required. Bore pits should be located at least thirty feet
from the edge of the nearest through traffic lane and not less
than twenty feet from the edge of pavement. On low traffic
roadways, bore pits should not be less than ten feet from the
edge of pavement or five feet from face of curb. Adequate
warning devices, barricades and protective devices will be
DB
C:\WP51\INTERPRT\192\707\78-05-24
14

<<<PAGE 15>>>

used to prevent creation of a traffic hazard. Where
circumstances necessitate the excavation of a bore pit closer
to the edge of pavement than set forth above, guard fence
or other approved protective devices will be installed for
protection of the traveling public in accordance with current
Harris County standards. Bore pits should be located and
constructed in such a manner as not to interfere with
roadway structural footings, safe roadside clearance or
traffic operations. If necessary, shoring shall be utilized.
Crossings Pipeline installations across roadways may be
encased or un-encased. Where encasement is to be employed such
encasement shall be provided under center medians and from top of
backslope to top of backslope for cut sections (or five feet beyond
the toe of slope for fill sections, or face of curb) of all roadways
including side streets, and five feet beyond any overpass or other
structures where the line passes under it. Encasement may be
omitted under center medians where their with is appreciably
greater than normal standards.
Where encasement is not employed the welded steel carrier pipe
shall provide sufficient strength to withstand the internal design
pressure and the dead and live loads of the pavement structure and
traffic. Additional protective measures should include the
following:
(a) Heavier wall thickness and/or higher factor of safety in
design
(b) Adequate coating and wrapping
(c) Cathodic protection
(d) Other measures as required by Title 49, CFR, Part 192 or
Part 195 as published by the Department of Transportation.
The minimum length of the additional protection as set forth above
shall be the same as that required by encasement.
Existing lines may be permitted to remain in place without
encasement or extension of encasement if they are protected by a
reinforced concrete slab or equivalent protection or if they are
located at a depth of six feet under the pavement surface and not
DB
C:\WP51\INTERPRT\192\707\78-05-24
15

<<<PAGE 16>>>

Width Cover Backfill XII. less than four feet under the roadway ditch. If a reinforced
concrete slab is to be used, it should meet the following standards:
Three times the diameter of the pipe or five foot
minimum whichever is greater
Thickness six inch minimum
Reinforcement #4 bars at twelve inch centers each way or
equivalent wire mesh
the cushion between the bottom of slab and top of
pipe shall be not less than six inches
will be 1.5 sacks Cement Stabilized Sand full
width of cut and from pad to bottom of
subgrade,
Vents. One or more vents shall be provided for each casing or series of
casings. For casings longer than 150 feet vents should be provided at both
ends. On shorter casings a vent should be located at the high end with a
marker placed at the low end. Vents shall be placed at the right-of-way
line immediately above the pipeline, situated so as not to interfere with
highway maintenance or concealed by vegetation. Ownership of the lines
shall be shown on the vents.
Markers. The utility company shall place a readily identifiable and suitable
marker at each right-of-way line where it is crossed by any high pressure
gas or liquid petroleum line except where marked by a vent.
The authorized pipeline shall save and hold harmless Harris County against
any and all liability that it may have or appear to have to any person or
persons whomsoever by reason of any act or thing that pipeline, its agents,
servants, employee and contractors may do or cause to be done on the
premises.
Any authorized pipeline as used herein, violating any one or all of the
above regulations and provisions set forth shall be deemed to be in
contempt of this Court, and shall be called to show cause before this Court
why he should not be held in and punished for contempt for his conduct in
violation of the above orders and regulations of this Court.
DB
C:\WP51\INTERPRT\192\707\78-05-24
16

<<<PAGE 17>>>

XIII. XIV. XV. XVI. If any provisions, section, subsection, sentence, clause or phrase of this order, or
the application of same to any person, firm, limited partnership, joint stock
association, or corporation, or set of circumstances is for any reason held
to be unconstitutional, void or invalid (or for any reason unenforceable),
the validity of the remaining portions of this order or their application to
other persons, firm, limited partnerships, joint stock associations, or
corporations, or set circumstances shall not be affected thereby, it being the
intent of the Commissioners' Court of Harris County, Texas, in ordering
the above regulations and provisions that no portion hereof or provision or
regulations contained herein shall become inoperative or fail by reason of
any unconstitutionality or invalidity of any other portion, provision or
regulation, and to this end, all provisions of this order are declared to be
separable.
Evidence of review by the Commissioners' Court shall be kept on the
jobsite at all times and failure to do so constitutes grounds for job
shutdown.
Owners and/or operators of public utility pipelines and/or mains shall not
be required to submit formal notice when installing service connections.
However, owners and/or operators shall install these connections in
accordance with the construction requirements set out herein, and if
unusual conditions exist that require variation from the requirements, work
shall not begin until approved by the County Engineer.
One of the following bonds payable to Harris County shall accompany
"Notice of Proposed Public Utility Pipeline and/or Main Activity within
Harris County Road Right of Way" unless one perpetual bond is executed
as stipulated in following paragraph (3).
(1) A bond with two good and sufficient personal sureties, a corporate
surety bond, or a personal bond, if acceptable to the
Commissioners' Court of Harris County, Texas, acting in its sole
discretion upon proof being furnished to the satisfaction of said
Court as to the financial responsibility of such authorized pipeline
desiring to make such crossing and/or crossings, for each crossing
of such pipeline over a County road right-of-way or for each one
mile or part of one mile such pipeline runs parallel with and within
the boundaries of such County road right-of-way.
DB
C:\WP51\INTERPRT\192\707\78-05-24
17

<<<PAGE 18>>>

(2) In the event the construction of one continuous pipeline is to be
made in, over, across and along several County road rights-of-way,
one such bond covering all construction of such pipeline in, under,
across, or along the several County road rights-of-way affected by
such continuous pipeline construction.
(3) One perpetual bond, executed solely by such authorized pipeline, if
acceptable to the Commissioners' Court of Harris County, Texas,
acting in its sole discretion upon proof being furnished to the
satisfaction of said Court as to the financial responsibility of such
authorized pipeline, such perpetual bond to cover all pipelines
thereafter laid or constructed by such authorized pipeline in, under,
across or along any County road in Harris County, Texas, under the
jurisdiction of the Commissioners' Court of Harris County, Texas.
The amount and terms of each of the above bonds to be determined by the
Commissioners' Court of Harris County, Texas, or the County Engineer of
Harris County, Texas, and each of the bonds to be conditioned that the
pipeline or pipelines covered thereby be laid, constructed, maintained and
repaired so as to comply with the herein established minimum requirements
and conditions for such laying, constructing, maintaining and repairing of
such pipeline or pipelines, in, under, across, and along such County road
right-of-way.
DB
C:\WP51\INTERPRT\192\707\78-05-24
18
- **truncated:** false
- **body characters:** 31862
