# Public Service Commission — Pipeline Safety Interpretation

- **operation:** document
- **citation:** PI-86-004
- **title:** Public Service Commission — Pipeline Safety Interpretation
- **source type:** guidance
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** guidance
- **official:** true
- **published on:** 1986-07-24
- **effective on:** Not available
- **summary:** PI-86-004 response to Public Service Commission concerning 192.467.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-86-004.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-86-004.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-86-004
- **source url:** https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/1986/PI86004.pdf
**body:**

<<<PAGE 1>>>

July 24, 1986
Mr. E. Scott Smith
Chief Engineer
Public Service Commission
730 Schenkel Lane
Post Office Box 615
Frankfort, Kentucky 40602
Dear Mr. Smith:
Your letter of June 17, 1986, asks, "should a distribution company have a specific program
whereby the inspection and electrical test of cased road crossings on cathodically protected lines
would be conducted annually, or can compliance with the 192.467(c) and (d) be achieved by
complying with 192.465(a), even though test stations are not always located at the cased
crossings and test of the bare casing is not taken?"
When properly conducted the testing under §192.465(a) would also establish compliance with
§192.467(c) and (d).
Section 192.465(a) states "Each pipeline that is under cathodic protection must be tested at least
once each calendar year, but with intervals not exceeding 15 months, to determine whether the
cathodic protection meets the requirements of §192.463...." The tests under §192.465(a) must be
sufficient to determine whether the cathodic protection meets the requirements of §192.463 for
the entire pipeline, including any cathodically protected segments inside casings. If the tests under
§192.465(a) show that the cathodic protection of a cased segment is adequate, then §192.467(d)
has been satisfied because the electrical isolation must also be adequate, and compliance with
§§192.467(a) and (c) has been achieved. If §192.465(a) tests show inadequate protection of any
cased segment, then additional inspection and tests would be needed under §192.467(d) to
determine the adequacy of electrical isolation.
For your information we are enclosing a copy of the "Regulation Enforcement Guidelines" for
§192.467 that was prepared by OPS enforcement staff in 1983.
Sincerely,
Richard L. Beam
Associate Director
Pipeline Safety Regulation
dal\192\467\86-07-24
1

<<<PAGE 2>>>

REGULATION ENFORCEMENT GUIDELINES
192.467 EXTERNAL CORROSION CONTROL: ELECTRICAL ISOLATION
Electrically shorted casing
1. A violation of Paragraph 192.467(c) exists if:
A cathodically protected transmission or distribution pipeline, other than unprotected
copper inserted into ferrous pipe, is electrically connected to metallic casings that are a
part of the underground system and within six months of discovery of the electrical short
between the casing and pipeline, the operator has not initiated corrective action in
accordance with Paragraph 3 below. Discovery shall be presumed upon conduct of on
[sic] electrical survey with results as described in Paragraphs 2(a) and 2(b).
The operators Operation and Maintenance Plan should also be investigated to:
A. determine that the operator has a procedure to per 192.605, and;
react to shorted casings
B. follows that procedure per 192.13(c)
2. Evidence of violation - Paragraph 192.467(c):
A. Documentation and dates of pipe-to-soil potential surveys made pursuant to
Section 192.465 that show pipe-to-soil and adjacent casing-to-soil potentials to be
essentially the same, indicating an electrical short between casing and pipe.
B. Documentation and dates of casing-to-soil potential measurements which are more
negative than normal, but not as negative as adjacent pipe-to-soil potential
measurements, indicating a "partial" electrical short between casing and pipe.
Notes:
A zero resistant short, as in (a) prevents cathodic protection from reaching the
pipeline inside the casing and thus prevents the operator from complying with
Paragraphs 192.455(a)(2), and 192.457(a) for those pipe sections.
A "partial" short, as in (b) reduces the amount of cathodic protection current to the
pipeline. It is not practical to determine the degree of protection
received by the pipe inside a "partially" shorted casing for compliance with
Paragraph 192.463(a).
dal\192\467\86-07-24
2

<<<PAGE 3>>>

C. Field checks:
i). At locations where pipe-to-soil and adjacent casing-to-soil measurements are
essentially the same, the presence of an electrical short can be readily
checked by connecting one output terminal of pipe locator transmitter to
the pipeline and the other to the casing (this utilizes the conductive mode).
Then move the receiver out to a point over the pipeline about 50 to 100
feet away from the casing. If no signal is picked up, the casing is shorted
to the pipe. Also, determine if connecting test leads from casing and pipe
together has any effect on signal strength. It should not. However, there
will be a change in signal strength if the casing is partially shorted to the
pipeline.
ii). Have operator interrupt rectifier located some distance away from shorted or
partially shorted casing; at least a mile away would be preferable. If it has
to be closer, be sure that casing pipe at point of measurement is not within
the voltage gradient of the rectifier groundbed.
These interrupted voltage checks will serve to verify the presence of a
short or partial short between casing and pipe.
D. Operator records:
A. Pipe-to-soil and casing-to-soil potential measurements should be retained
by the operator in accordance with Paragraph 192.491(b)(2).
E. Operator's O&M Plan:
A. To comply with the requirements of Sections
192.467(c), 192.453, and 192.605, the operator's O&M Plan must
incorporate procedures to be used for correcting or negating the adverse
effects of shorted casings. Then, consistent with Paragraph 192.13(c), the
operator is to follow the procedures that it has established.
dal\192\467\86-07-24
3

<<<PAGE 4>>>

3. Reasonable time allowance and method for operator's correction of shorted casings:
A. After the cathodic protection survey has been completed and a shorted
casing has been identified, the operator should determine a course of action intended
to correct or negate the adverse effects of shorted casings. The
operator's plan of action should be initiated within six months of completion of
the survey and should include one of the following options:
i). Clear the short if practical;
ii). Fill the casing/pipe interstice with high dielectric casing filler or other material which
provides a corrosion inhibiting environment.
iii). If options i or ii would be impracticable and, if in the judgement of the operator the risk of
corrosion is minimized by conditions including the location and condition of the
pipe, the risk of overpressure, and environmental factors, the operator may choose
to monitor the casing with leak detection instruments at intervals not exceeding the
requirements of 192.705 and 192.721 until such time as options i or ii become
practicable or conditions change which render option iii inadequate to minimize the
risk of corrosion.
If the operator chooses to monitor the shorted casing with leak detection
instruments, immediate corrective action must be taken if and when a leak is
discovered. A corrosion leak is a condition that would render option iii
inadequate.
E. In connection with the use of inhibitors in the water between shorted casing and
pipe, the operator should demonstrate that galvanic currents cannot flow.
Otherwise, corrosion will take place.
If the inhibitor is effective, the operator should also be able to demonstrate by
periodic sampling that the inhibitor will stay in the casing/pipe interstice without
leaching out the ends into the soil during low water tables.
dal\192\467\86-07-24
4

<<<PAGE 5>>>

4. Road and Railroad casings are in areas where continuing considered to be detrimental to public safety.
pipeline corrosion is
A. The OOE Pipeline Safety Enforcement Manual, page 14d (Rev. 1/19/81),
under Part D relative to definition and enforcement guidelines for
Paragraph 192.457(c), provide the following guide material:
"In order to achieve uniform enforcement policy, all regions should
consider continuing corrosion occurring in the following areas to be
detrimental to public safety (active corrosion):
1. . . .
2. . . .
3. 4. . . .
At highway and railroad crossings.
B. Thus, all highway and railroad crossings involving cathodically protected
gas pipelines must be electrically isolated from the casing, or other
measures must be used to miticate [sic] or monitor galvanic corrosion of
the pipeline inside the shorted casings.
5. General notes:
A. To cathodically protect a pipeline means to cathodically protect it in its
entirety. It should be noted that a pipeline is not protected in its entirely, as
required by 192.455 or 192.457, whenever casings are shorted to the
pipelines because of the shielding effect of the casings that prevents
cathodic protection current from reaching the pipeline inside the casing.
dal\192\467\86-07-24
5

<<<PAGE 6>>>

COMMONWEALTH OF KENTUCKY
PUBLIC SERVICE COMMISSION
730 SCHENKEL LANE
POST OFFICE BOX 615
FRANKFORT, KY 40602
(502) 564-3940
June 17, 1986
Mr. Richard L. Beam, Director
Office of Pipeline Safety Regulation
Materials Transportation Bureau
400 Seventh Street, S.W.
Washington, D.C. 20590
Dear Mr. Beam:
Columbia Gas of Kentucky, Inc. (Columbia) is an intrastate natural gas distribution
company and is jurisdictional to this Commission through our 5a agreement. While conducting a
comprehensive inspection of one of its districts, our inspector discovered that Columbia does not
have a specific program of inspecting and electrically testing carrier pipe at cased crossings or the
casing to assure that it is not shorted or partially shorted.
To comply with 192.467(c) and (d), it appears that specific tests must be conducted at
these locations on a periodic (annual) basis.
This is a request for interpretation of the following regulations:
49 CFR 192.467(a) states:
"Each buried or submerged pipeline must be electrically isolated from other underground
metallic structures, unless the pipeline and the other structures are electrically
interconnected and cathodically protected as a single unit."
49 CFR 192.467(c) states:
"Except for unprotected copper inserted in ferrous pipe, each pipeline must be electrically
isolated from metallic casings that are a part of the underground system. However, if
isolation is not achieved because it is impractical, other measures must be taken to
minimize corrosion of the pipeline inside the casing."
dal\192\467\86-07-24
6

<<<PAGE 7>>>

49 CFR 192.467(d) states:
adequate."
"Inspection and electrical tests must be made to assure that electrical isolation is
Should a distribution company have a specific program whereby the inspection and
electrical test of cased road crossings on cathodically protected lines would be conducted
annually, or can compliance with the 192.467(c) and (d) be achieved by complying with
192.465(a), even though test stations are not always located at the cased crossings and test of the
bare casing is not taken?
Sincerely,
E. Scott Smith, Chief Engineer
dal\192\467\86-07-24
7
- **truncated:** false
- **body characters:** 10745
