# Southwest Gas Corporation — Pipeline Safety Interpretation

- **operation:** document
- **citation:** PI-93-025
- **title:** Southwest Gas Corporation — Pipeline Safety Interpretation
- **source type:** guidance
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** guidance
- **official:** true
- **published on:** 1993-05-26
- **effective on:** Not available
- **summary:** PI-93-025 response to Southwest Gas Corporation concerning 192.605.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-93-025.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-93-025.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-interpretation-pi-93-025
- **source url:** https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/1993/PI93025.pdf
**body:**

<<<PAGE 1>>>

May 26, 1993
Mr. Marti Marek
Manager, Compliance and Operations Audit Staff
Southwest Gas Corporation
P.O. Box 98510
5241 Spring Mountain Road
Las Vegas, NV 89193-8510
Dear Marti Marek:
I am sorry to have taken so long to respond to your letter of November 23, 1992. You asked
whether meter turn-on operations must be included within an operation and maintenance plan
under 49 CFR 192.605.
We received a letter on this subject from Dan Weaklend of the Arizona Corporation Commission
(enclosed). We are of the same opinion as Mr. Weaklend that the plan must cover turn-on
operations. However, it is §192.605(a), not §192.605(b), that requires inclusion of the operations
within the plan.
Sincerely,
Cesar De Leon
Director, Regulatory Programs
Office of Pipeline Safety
Enclosure
dal\192.605\93-05-26