# ENERGY TRANSFER COMPANY — Integrity Assurance Notification

- **operation:** document
- **citation:** PHMSA 24-306173
- **title:** ENERGY TRANSFER COMPANY — Integrity Assurance Notification
- **source type:** inspection
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2024-04-09
- **effective on:** 2024-04-09
- **summary:** HAZARDOUS LIQUID in TX; PRESSURE; PHMSA status: RESOLVED.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-leading-ian-24-306173-operator-32099.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-leading-ian-24-306173-operator-32099.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-leading-ian-24-306173-operator-32099
- **source url:** https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/data_statistics/pipeline/SRCR_and_Integrity_Assurance_Notifications.zip
**body:**

Per 195.452(h)(1)(ii) Energy Transfer Company (ETC), is notifying PHMSA of a pressure reduction that will exceed 365 days. A Safety Related Condition report (21-210470) was filed on April 16, 2021 for the subject pipeline. Initially, a 20% reduction in operating pressure was taken. On April 8, 2022 and April 13, 2023, ETC notified PHMSA that the pressure reduction will exceed 365 days. Via this correspondence, ETC is notifying PHMSA that the long-term 20% pressure reduction remains in effect. Currently, only one segment of the pipeline remains in service from Nederland, TX to Sour Lake, TX however this segment is planned to be shut down and purged of hydrocarbons in the second quarter of 2024. The remaining segments of this pipeline system from Sour Lake, TX to Longview, TX have been purged of hydrocarbons and are not in active transportation.
- **truncated:** false
- **body characters:** 855