# Gulf South Pipeline Co LP — Pipeline Special Permit

- **operation:** document
- **citation:** PHMSA-2006-26533
- **title:** Gulf South Pipeline Co LP — Pipeline Special Permit
- **source type:** permit
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** current
- **official:** true
- **published on:** 2007-08-24
- **effective on:** 2007-08-24
- **summary:** PHMSA-2006-26533, issued 2007-08-24 for Gulf South Pipeline Co LP's gas transmission system.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-special-permit-phmsa-2006-26533.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-special-permit-phmsa-2006-26533.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-special-permit-phmsa-2006-26533
- **source url:** https://www.regulations.gov/docket/PHMSA-2006-26533
**body:**

PHMSA pipeline special permit PHMSA-2006-26533. Operator: Gulf South Pipeline Co LP. System: Gas Transmission. Issue date: 2007-08-24.

<<<PAGE 1>>>

U.S. Department
of Transportation
Administrator
Washington, DC 20590
1200 New Jersey Ave. SE
Pipeline and Hazardous
Materials Safety
Administration
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
AUG 2 4 2007
Mr. Walt Bennett
Vice President - Operations
Gulf South Pipeline Company, LP
20 East Greenway Plaza, Suite 900
Houston, Texas 77046
Docket No. PHMSA-2006-26533
Dear Mr. Bennett:
On November 16, 2006 you wrote to the Pipeline and Hazardous Materials Safety
Administration (PHMSA) requesting a waiver of compliance from PHMSA's pipeline safety
regulations in 49 CFR 192.111, 192.201 and 192.619 for the Gulf South Pipeline Company
(GSP) East Texas to Mississippi Expansion Project. The regulations establish the design factor
for steel pipe and the required capacity of pressure relieving and limiting stations. PHMSA
determined that a waiver of 192.619 is unnecessary.
The PHMSA is granting this waiver through a special permit, which is enclosed with this letter.
This special permit allows GSP to design, construct and operate the pipeline with design factors
of 0.80 in Class 1 locations, 0.67 in Class 2 locations and 0.56 in Class 3 locations in
accordance with the conditions specified in the special permit. The special permit provides
some relief from the Federal pipeline safety regulations for GSP while ensuring that pipeline
safety is not compromised.
My staff would be pleased to discuss this special permit or any other regulatory matter with
you. Florence Hamn, Director of Regulations (202-366-4595), would be pleased to assist you.
Sincerely,
Buriese
Jeffrey D. Wiese
Acting Associate Administrator
for Pipeline Safety
Enclosure (Special Permit)

<<<PAGE 2>>>

Administrator
400 Seventh Street, S.W.
Washington, D.C. 20590
Pipeline and Hazardous
Materials Safety Administration
DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION (PHMSA)
SPECIAL PERMIT
Docket Number:
PHMSA-2006-26533
Pipeline Operator:
Gulf South Pipeline Company, LP
Date Requested:
November 16, 2006
Code Section(s):
49 CFR 192.111 and 192.201
Grant of Special Permit:
The Pipeline and Hazardous Materials Safety Administration (PHMSA) grants this special
permit to Gulf South Pipeline Company, LP (GSP). The Federal pipeline safety regulations in
49 CFR 192.111 limit the design factors and operating stress levels for natural gas transmission
steel pipelines to 72 percent of the specified minimum yield strength (SMYS) in class 1
locations, 60 percent SMYS in class 2 locations and 50 SMYS percent in class 3 locations.
This special permit allows GSP to design, construct and operate the East Texas to Mississippi
Expansion Project pipeline using design factors and operating stress levels of up to 80 percent
SMYS in class 1 locations, 67 percent SMYS in class 2 locations and 56 percent SMYS in class
3 locations. This special permit also allows GSP to operate up to 67 percent SMYS at class 1
location road crossings and up to 56 percent SMYS at class 2 location road crossings. This
special permit covers approximately 255.4 miles of 42-inch pipe and 3 miles of 36-inch pipe in
class 1 locations, 3.5 miles of 42-inch pipe in class 2 locations and 468 feet of 42-inch pipe in
class 3 locations.
The PHMSA grants this special permit based on the findings set forth in the "Special Permit
Analysis and Findings" document, which can be read in its entirety in Docket # PHMSA-2007-
26533 in the DOT's Docket Management System (DMS) located on the internet at
http://dms.dot.gov.

<<<PAGE 3>>>

2
Because the proposed operating stress level of 80 percent SMYS is higher than the upper limit
of the required overpressure protection under existing regulations [1.e., ten percent over
maximum allowable operating pressure (MAOP) or 75 percent SMYS], this special permit also
allows GSP to establish the overpressure protection limit up to 104 percent of the pipeline
MAOP in Class 1 locations, which corresponds to 83.2 percent SMYS. The pipeline
overpressure criteria in Class 2 and 3 locations must conform to existing regulations. The
pipeline MAOP will be 1,333 psig.
For the purpose of this special permit, the "special permit area" means the area consisting of
the entire pipeline right-of-way for those segments of the pipeline that will operate above 72
percent of SMYS in Class 1 locations, 60 percent SMYS in Class 2 locations and 50 percent
SMYS in Class 3 locations. This special permit is subject to the conditions set forth below.
Conditions:
The grant of this special permit is subject to the following conditions:
1) Steel Properties: The skelp/plate must be micro alloyed, fine grain, fully killed steel with
calcium treatment and continuous casting.
2)
Manufacturing Standards: The pipe must be manufactured according to American
Petroleum Institute Specification 5L, Specification for Line Pipe (API SL), product
specification level 2 (PSL 2), supplementary requirements (SR) for maximum operating
pressures and minimum operating temperatures. Pipe carbon equivalents must be at or
below 0.23 percent based on the material chemistry parameter (Pcm) formula.
Fracture Control: API 5L, the American Society of Mechanical Engineers B31.8
Standard (ASME B31.8) and other specifications and standards address the steel pipe
toughness properties needed to resist crack initiation, crack propagation and to ensure
crack arrest during a pipeline failure caused by a fracture. GSP must institute an overall
fracture control plan addressing steel pipe properties necessary to resist crack initiation
and crack propagation and to arrest a fracture within eight pipe joints with a 99 percent
occurrence probability or within five pipe joints with a 90 percent occurrence probability.
The plan must include acceptable Charpy Impact and Drop Weight Tear Test values,
which are measures of a steel pipeline's toughness and resistance to fracture. The fracture
control plan, which must be submitted to PHMSA headquarters, must be in accordance
with API 5L, Appendix F and must include the following tests:

<<<PAGE 4>>>

a) SR SA - Fracture Toughness Testing for Shear Area: Test results must indicate at
least 85 percent minimum average shear area for all X- 70 heats and 80 percent
minimum shear area for all X- 80 heats with a minimum result of 80 percent shear
area for any single test. The test results must also ensure a ductile fracture and arrest;
b) SR 5B - Fracture Toughness Testing for Absorbed Energy; and
c) SR 6 - Fracture Toughness Testing by Drop Weight Tear Test: Test results must be
at least 80 percent of the average shear area for all heats with a minimum result of 60
percent of the shear area for any single test. The test results must also ensure a ductile
fracture and arrest.
The above fracture initiation, propagation and arrest plan must account for the entire
range of pipeline operating temperatures, pressures and gas compositions planned for the
pipeline diameter, grade and operating stress levels, including maximum pressures and
minimum temperatures for shut-in conditions associated with the special permit area.
Where the use of stress factors, pipe grade, operating temperatures and gas composition
make fracture toughness calculations non-conservative, correction factors must be used.
If the fracture control plan for the pipe in the special permit area does not meet these
specifications, GSP must submit to PHMSA headquarters an alternative plan providing an
acceptable method to resist crack initiation, crack propagation and to arrest ductile
fractures in the special permit area.
4)
Steel Plate Quality Control: The steel mill and/or pipe rolling mill must incorporate a
comprehensive plate/coil mill and pipe mill inspection program to check for defects and
inclusions that could affect the pipe quality. This program must include a plate or rolled
pipe (body and all ends) ultrasonic testing (UT) inspection program per ASTM A578 to
check for imperfections such as laminations. An inspection protocol for centerline
segregation evaluation using a test method referred to as slab macro-etching must be
employed to check for inclusions that may form as the steel plate cools after it has been
cast. A minimum of one macro-etch or a suitable alternative test must be performed from
the first or second heat (manufacturing run) of each sequence (approximately 4 heats) and
graded on the Mannesmann scale or equivalent. Test results with a Mannesmann scale
rating of one or two out of a possible four or five scale are acceptable.

<<<PAGE 5>>>

4
Pipe Seam Quality Control: A quality assurance program must be instituted for pipe weld
seams. The pipe weld seam tests must meet the minimum requirements for tensile
strength in API 5L for the appropriate pipe grade properties. A pipe weld seam hardness
test using the Vickers hardness testing of a cross-section from the weld seam must be
performed on one length of pipe from each heat. The maximum weld seam and heat
affected zone hardness must be a maximum of 280 Vickers hardness (Hv10). The
hardness tests must include a minimum of three readings for each heat affected zone,
three readings in the weld metal and two readings in each section of pipe base metal for a
total of 13 readings. The pipe weld seam must be 100 percent UT inspected after
expansion and hydrostatic testing per APL 5L.
Puncture Resistance: Steel pipe must be puncture resistant to an excavator weighing up
to 65 tons. Puncture resistance will be calculated based on industry established
calculations such as the Pipeline Research Council International's "Reliability Based
Prevention of Mechanical Damage to Pipelines" calculation method.
7)
Mill Hydrostatic Test: The pipe must be subjected to a mill hydrostatic test pressure of
94 percent SMYS or greater for ten seconds.
8)
Pipe Coating: The application of a corrosion resistant coating to the steel pipe must be
subject to a coating application quality control program. The program must address pipe
surface cleanliness standards, blast cleaning, application temperature control, adhesion,
cathodic disbondment, moisture permeation, bending, minimum coating thickness,
coating imperfections and coating repair.
Field Coating: A field girth weld joint coating application specification and quality
standards to ensure pipe surface cleanliness, application temperature control, adhesion
quality, cathodic disbondment, moisture permeation, bending, minimum coating
thickness, holiday detection and repair quality must be implemented in field conditions.
Field joint coatings must be non-shielding to cathodic protection (CP). Field coating
applicators must use valid coating procedures and be trained to use these procedures.
10)
Coatings for Trenchless Installation: Coatings used for directional bore, slick bore and
other trenchless installation methods must resist abrasions and other damages that may
occur due to rocks and other obstructions encountered in this installation technique.

<<<PAGE 6>>>

5
11) Bends Quality: Certification records of factory induction bends and/or factory weld
bends must be obtained and retained. All bends, flanges and fittings must have carbon
equivalents (CE) below 0.42 or a pre-heat procedure must be applied prior to welding for
CE above 0.42.
12) Fittings: All pressure rated fittings and components (including flanges, valves, gaskets,
pressure vessels and compressors) must be rated for a pressure rating commensurate with
the MAOP and class location of the pipeline. Designed fittings (including tees, elbows
and caps) must have the same design factors as the adjacent pipe class location.
13) Design Factor - Pipelines: Pipe installed under this special permit in Class 1, 2 and 3
locations may use design factors of 0.80, 0.67 and 0.56 respectively. Road crossings in
Class 1 and 2 areas may use design factors of 0.67 and 0.56 respectively.
14) Design Factor - Stations: The following compressor and measurement and regulation
stations may use a design factor of 0.54: The affected stations are Carthage Junction
Compressor Station, Vixen Compressor Station, Energy Transfer Corporation
Measurement and Regulation Station. Design of future stations associated with this
pipeline must follow 49 CFR § 192.111.
15) Temperature Control: The compressor station discharge temperature must be limited to
120° Fahrenheit. A temperature above this maximum temperature of 120° Fahrenheit
may be approved, if GSP technical coating operating tests show that the pipe coating will
properly with-stand the higher operating temperature for long term operations.
16) Overpressure Protection Control: Mainline pipeline overpressure protection must be
limited to a maximum of 104 percent MAOP.
17) Welding Procedures: The appropriate PHMSA regional office must be notified within 14
days of the beginning of welding procedure qualification activities. Automated or manual
welding procedure documentation must be submitted to the same PHMSA regional office.
18) Depth of Cover: The soil cover must be a minimum depth of 36 inches in all areas. In
areas where threats from chisel plowing or other activities are threats to the pipeline, the
top of the pipeline must be installed at least one foot below the deepest penetration above

<<<PAGE 7>>>

6
the pipeline. If routine patrols or other observed conditions indicate the possible loss of
cover over the pipeline, GSP will perform a depth of cover study and replace cover as
necessary to meet the minimum depth of cover requirements specified herein.
19) Construction Quality: A construction quality assurance plan to ensure quality standards
and controls must be maintained throughout the construction phase with respect to:
inspection, pipe hauling and stringing, field bending, welding, non-destructive
examination (NDE) of girth welds, field joint coating, pipeline coating integrity tests,
lowering of the pipeline in the ditch, padding materials to protect the pipeline, backfilling,
alternating current (AC) interference mitigation and CP systems. All girth welds must be
non-destructively examined (NDE) by radiography or alternative means. The NDE
examiner must have all required and current certifications.
20) Interference Currents Control: Control of induced AC from parallel electric transmission
lines and other interference issues that may affect the pipeline must be incorporated into
the design of the pipeline and addressed during the construction phase. Issues identified
and not originally addressed in the design phase must be brought to PHMSA's attention.
An induced AC program to protect the pipeline from corrosion caused by stray currents
must be in place within six months after placing the pipeline in service.
21) Test Level: The pre-in service hydrostatic test must be to a pressure producing a hoop
stress of: 100 percent SMYS and 1.25 X MAOP in areas to operate to 80 percent SMYS;
at least 1.5 X MAOP in areas to operate to 67% SMYS; and at least 1.5 X MAOP in areas
to operate to 56% SMYS.
22) Assessment of Test Failures: Any pipe failure occurring during the pre-in service
hydrostatic test must undergo a root cause failure analysis to include a metallurgical
examination of the failed pipe. The results of this examination must preclude a systemic
pipeline material issue and the results must be reported to PHMSA headquarters and the
appropriate PHMSA regional office.
23) Supervisory Control and Data Acquisition (SCADA) System Capabilities: A SCADA
system to provide remote monitoring and control of the entire pipeline system must be
employed

<<<PAGE 8>>>

7
24) SCADA Procedures: A detailed procedure for establishing and maintaining accurate
SCADA set points must be established to ensure the pipeline operates within acceptable
design limits at all times.
25) Mainline Valve Control: Mainline valves located on either side of a pipeline segment
containing a High Consequence Area (HCA) where personnel response time to the valve
exceeds one hour must be remotely controlled by the SCADA system. The SCADA
system must be capable of opening and closing the valve and monitoring the valve
position, upstream pressure and downstream pressure. As an alternative, a leak detection
system for mainline valve control is acceptable.
26) Pipeline Inspection: The pipeline must be capable of passing ILI tools. All headers and
other segments covered under this special permit that do not allow the passage of an ILI
device must have a corrosion mitigation plan.
27) Gas Quality Monitoring: An acceptable gas quality monitoring and mitigation program
must be instituted to not exceed the following limits:
a) H¿S (1 grain per 100 standard cubic feet or 16 parts per million (ppm), maximum);
b) CO2 (3 percent maximum);
c) H2O (less than or equal to 7 pounds per million standard cubic feet and no free water);
and
d) Other deleterious constituents that may impact the integrity of the pipeline must be
instituted.
e) The pipeline must have an ongoing pigging and liquids sampling plan to identify,
mitigate and remove deleterious constituents.
f) When H¿S is above eight parts ppm, the gas stream constituents must be reviewed for
implementation of a quarterly pigging/inhibitor injection program including follow up
sampling of liquids at receipt points.
29) Gas Quality Control: Filters/separators must be installed at locations where gas is
received into the pipeline where the incoming gas stream quality includes potentially
deleterious constituents to minimize the entry of contaminants and to protect the integrity
of downstream pipeline segments.
30) Gas Quality Monitoring Equipment: Equipment, including moisture analyzer,
chromatograph and semi-annual H¿S sampling (quarterly sampling where H¿S is above

<<<PAGE 9>>>

8
eight ppm), must be installed to permit the operator to manage and limit the introduction
of contaminants and free liquids into the pipeline.
31) Cathodic Protection: The initial CP system must be operational within 12 months of
placing any pipeline segment in service.
32) Interference Current Surveys: Interference surveys must be performed within six months
of placing the pipeline in service to ensure compliance with applicable NACE
International Standard Recommended Practices 0169 and 0177 (NACE RP 0169 and
NACE RP 0177) for interference current levels. If interference currents are found, GSP
will determine if there have been any adverse affects to the pipeline and mitigate the
affects as necessary. GSP will report to PHMSA the results of any negative finding and
the associated mitigative efforts to the appropriate PHMSA regional office.
33) Corrosion Surveys: Corrosion surveys of the affected pipeline must be completed within
six months of placing the respective CP system (s) in operation to ensure adequate
external corrosion protection per NACE RP 0169. The survey will also address the
proper number and location of CP test stations as well as AC interference mitigation and
AC grounding programs per NACE RP 0177.
34) Verification of Cathodic Protection: An interrupted close interval survey (CIS) must be
performed in concert and integrated with ILI in accordance with 49 CFR 192 Subpart O
reassessment intervals for all HCA pipeline mileage. At least one CP test station must be
located within each HCA with a maximum spacing between test stations of one-half mile
within an HCA. If any annual test station reading fails to meet 49 CFR 192 Subpart I
requirements, remedial actions must occur within six months. Remedial actions must
include a close interval survey (CIS) on each side of the affected test station and all
modifications to the CP system necessary to ensure adequate external corrosion control.
35) Initial Close Interval Survey (CIS) - Initial: A CIS must be performed on the pipeline
within two years of the pipeline in- service date. The CIS results must be integrated with
the baseline ILI to determine whether further action is needed.
36) Pipeline Markers: GSP must employ line-of-sight markings on the pipeline in the special
permit area except in agricultural areas or large water crossings such as lakes where line
of sight markers are not practical. The marking of pipelines is also subject to Federal
Energy Regulatory Commission orders or environmental permits and local restrictions.

<<<PAGE 10>>>

9
37) Pipeline Patrolling: Pipeline patrolling must be conducted at least monthly (12 times per
calendar year), not to exceed 45 days, to inspect for excavation activities, ground
movement, wash-outs, leakage or other activities and conditions affecting the safe
operation of the pipeline.
38) Monitoring of Ground Movement: An effective monitoring/mitigation plan must be in
place to monitor for and mitigate issues of unstable soil and ground movement.
39) Initial ILI: GSP must perform a baseline ILI in association with the construction of the
pipeline using a high-resolution Magnetic Flux Leakage (MFL) tool to be completed
within three years of placing a pipeline segment in service. GSP must perform a baseline
geometry tool run after completion of the hydrostatic strength test and backfill of the
pipeline, (just prior to placing the pipeline in service) but no later than six months after
placing the pipeline in service under a special permit.
40) Future ILI: A second high-resolution MFL inspection must be performed and completed
on the pipe subject to this waiver within the first reassessment interval required by
49 CFR Subpart O, regardless of HCA classification. Future ILI must be performed on a
frequency consistent with Subpart O for the entire pipeline covered by this waiver.
41) Direct Assessment Plan: Headers, mainline valve bypasses and other sections covered by
this special permit that cannot accommodate ILI tools must be part of a Direct
Assessment (DA) plan or other acceptable integrity monitoring method using External
and Internal Corrosion Direct Assessment criteria (ECDA/ICDA).
42) Damage Prevention Program: The Common Ground Alliance (CGA) Alliance's damage
prevention best practices applicable to pipelines must be incorporated into the GSP
damage prevention program.
43) Anomaly Evaluation and Repair: Anomaly evaluations and repairs in the special permit
area must be performed based upon the following:
a) Anomaly Response Time: Repair Immediately
- Any anomaly within a waiver area operating up to 80% SMYS with a failure
pressure ratio (FPR) equal to or less than 1.1
- Any anomaly within a waiver area operating up to 67% SMYS with a FPR equal
to or less than 1.25

<<<PAGE 11>>>

10
- Any anomaly within a waiver area operating up to 56% SMYS with a FPR equal
to or less than 1.4
b) Anomaly Response Time: Repair Within One Year
- Any anomaly within a waiver area operating at up to 80% SMYS with a FPR
equal to or less than 1.25
- Any anomaly within a waiver area operating at up to 67% SMYS with a FPR
equal to or less than 1.5
- Any anomaly within a waiver area operating at up to 56% SMYS with a FPR
equal to or less than 1.8
c) Anomaly Response Time: Monitored Conditions
- Anomalies not requiring immediate or one year repairs must be reassessed
according to CFR 49, Part 192, Subpart O and the American Society of
Mechanical Engineers (ASME) standard B31.8S requirements and class location
factor.
- Each anomaly not repaired under the immediate repair requirements must have a
corrosion growth rate and ILI tool tolerance assigned per the Gas Integrity
Management Program (IMP) to determine the maximum re-inspection interval.
d) Anomaly Assessment Methods
- GSP must confirm the remaining strength (R-STRENG) effective area method, R-
STRENG - 0.85dL, and ASME B31G assessment methods are valid for the pipe
diameter, wall thickness, grade, operating pressure, operating stress level and
operating temperature. GSP must also use the most conservative method until
confirmation of the proper method is made to PHMSA headquarters.
- Dents in the pipe in the waiver area must be evaluated and repaired per 49 CFR
§ 192.309(b) for initial ILI and per 49 CFR 192.933(d) for future ILI.
44) Potential Impact Radius Calculation Updates: If the pipeline operating pressures and gas
quality are determined to be outside the parameters of the C-FER Study, a revised study
with the updated parameters must be incorporated into the IMP.
45) Reporting - Immediate: GSP must notify the appropriate PHMSA regional office within
24 hours of any non-reportable leaks occurring in the special permit area.

<<<PAGE 12>>>

11
46) Reporting - 180 Day: Within 180 days of the pipeline in- service date under a special
permit, GSP shall report on its compliance with special permit conditions to PHMSA
headquarters and the appropriate regional office.
47) Annual Reporting: Following approval of the special permit, GSP must annually report
the following:
a) The results of any in-line inspection (ILI) or direct assessment results performed
within the special permit area during the previous year;
b) Any new integrity threats identified within the special permit area during the previous
year,
c) Any encroachment in the special permit area, including the number of new residences
or public gathering areas;
d) Any class or HCA changes in the special permit area during the previous year;
e) Any reportable incidents associated with the special permit area that occurred during
the previous year;
f) Any leaks on the pipeline in the special permit area that occurred during the previous
year;
g) A list of all repairs on the pipeline in the special permit area made during the previous
year;
h) On-going damage prevention initiatives on the pipeline in the special permit area and
a discussion of their success or failure;
i) Any changes in procedures used to assess and/or monitor the pipeline operating under
this special permit; and
j) Any company mergers, acquisitions, transfers of assets, or other events affecting the
regulatory responsibility of the company operating the pipeline to which this special
permit applies.
Limitations:
The PHMSA has the sole authority to make all determinations on whether GSP has complied
with the specified conditions. Should GSP fail to comply with any conditions of this special
permit, or should PHMSA determine this special permit is no longer appropriate or that this

<<<PAGE 13>>>

12
special permit is inconsistent with pipeline safety, PHMSA may revoke this special permit and
require GSP to comply with the regulatory requirements in 49 CFR §§ 192.111 and 192.201.
AUTHORITY: 49 U.S.C. 60118(c) and 49 CFR § 1.53.
AUG 2 4 2007
Issued in Washington, DC on
Jeffrey D. Wiese,
Associate Administrator for Pipeline Safety
- **truncated:** false
- **body characters:** 26700
