# Southern Natural Gas Company, LLC — Pipeline Special Permit

- **operation:** document
- **citation:** PHMSA-2020-0007
- **title:** Southern Natural Gas Company, LLC — Pipeline Special Permit
- **source type:** permit
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** current
- **official:** true
- **published on:** 2022-07-27
- **effective on:** 2022-07-27
- **summary:** PHMSA-2020-0007, issued 2022-07-27 for Southern Natural Gas Company, LLC's gas transmission system.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-special-permit-phmsa-2020-0007.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-special-permit-phmsa-2020-0007.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-special-permit-phmsa-2020-0007
- **source url:** https://www.regulations.gov/docket/PHMSA-2020-0007
**body:**

PHMSA pipeline special permit PHMSA-2020-0007. Operator: Southern Natural Gas Company, LLC. System: Gas Transmission. Issue date: 2022-07-27. Renewal: Extension.

<<<PAGE 1>>>

U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
Special Permit Analysis and Findings
Class 1 to 3 Locations
Special Permit Information:
Docket Number: PHMSA-2020-0007
Requested By: Southern Natural Gas Company, LLC
Operator ID#: 18516
Original Date Requested: December 23, 2019
Original Issuance Date: July 27, 2022
Code Section(s): 49 CFR 192.611(a) and (d) and 192.619(a)
Purpose:
The Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline
Safety (OPS),
1 provides this information to describe the facts of the subject special permit
application submitted by Southern Natural Gas Company, LLC (SNG),
2 to discuss any relevant
public comments received with respect to the application, to present the engineering and safety
analysis of the special permit application, and to make findings regarding whether the requested
special permit should be granted and, if so, under what conditions. SNG requested that PHMSA
waive compliance from the 49 Code of Federal Regulations (CFR) 192.611(a) and (d) and
192.619(a) for natural gas transmission pipeline segments, where the class location has changed
from Class 1 to a Class 3 locations.
Pipeline System Affected:
This special permit application applies to the SNG request for a waiver of the class location
change requirements in 49 CFR 192.611(a) and (d) and 192.619(a) for approximately 0.621
1 Throughout this special permit the usage of “PHMSA” or “PHMSA OPS” means the U.S. Department of
Transportation’s Pipeline and Hazardous Materials Safety Administration Office of Pipeline Safety.
2 Southern Natural Gas Company, LLC is owned by Kinder Morgan, Inc.
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 1 of 11

<<<PAGE 2>>>

miles of gas transmission pipelines located in Effingham and Harris Counties, Georgia; and
Clarke County, Mississippi.
Pipe specifications including outside diameter, year installed, seam type, coating type, pipe
grade, wall thickness, maximum allowable operating pressure (MAOP), minimum pressure test
pressure, and pressure test factor based on the minimum test pressure are detailed in Table 1 –
Pipe Specifications by Line Name.
Table 1 – Pipe Specifications by Line Name
Outside
Wall
Min Test
Pressure
Year
Seam
Line Name
Diameter
Installed
Type
Coating
Type MAOP
Grade
Thickness
Pressure
Test
(psig)
(inches)
(inches)
(psig)
Factor
Cypress
Line 24 2007 ERW-HF FBE X70 0.298 1,250 1,602 1.28
South Main
2nd Loop
Line
26 1967 DSAW Coal Tar
Enamel X60 0.375 1,200 1,600 1.33
South Main
3rd Loop
Line
36 2003 /
2004 DSAW Polymer
Concrete X70 0.562 0.438 /
1,200 1,552 /
1,881 1.29
Notes: ERW-HF is Electric Resistance Welded-High Frequency.
DSAW is double submerged arc welded pipe weld seam type.
PSIG is pounds per square inch gauge.
Without this special permit, 49 CFR 192.611(a) would require SNG to replace the special permit
segments with stronger pipe or reduce the pipeline MAOP for a Class 1 to Class 3 location
change.
Special Permit Request:
On December 23, 2019, SNG applied to PHMSA for a special permit seeking relief from 49 CFR
192.611(a) and (d) and 192.619(a) for the below-listed special permit segments, where a class
location change occurred from the original Class 1 to a Class 3 location on the 24-inch diameter
Cypress Line, 26-inch diameter South Main 2nd Loop Line, and 36-inch diameter South Main 3rd
Loop Line Pipelines in Effingham and Harris Counties, Georgia; and Clarke County,
Mississippi.
This special permit applies to the special permit segments and special permit inspection areas
described and defined as follows, using the SNG survey station references:
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 2 of 11

<<<PAGE 3>>>

Special Permit Segments:
This special permit applies to the special permit segments in Table 2 – Special Permit
Segments and are identified using the SNG mile post (MP) and survey station (SS) references.
Table 2 – Special Permit Segments
Special Permit
Outside
Start Survey
End Survey
Segment
Diameter
Line Name Number3
Length
(feet)
County,
No.
Year
Seam
MAOP
Station (MP
Station (MP
State
Dwellings
Installed
Type
(psig)
(inches)
- SS)
- SS)
1
(KM 555) 24 Cypress Line 1,503.00 2 – 3968 3 – 191 GA Effingham,
1 2007 ERW-
HF 1,250
2
(KM 556) 26 South Main 2nd
Loop Line 224.78 77 – 1899 77 – 2124 Clarke,
MS 3 1967 DSAW 1,200
4
(KM 558) 36 South Main 3rd
Loop Line 329.96 77 – 1728 77 – 2058 Clarke,
MS 4 2003 DSAW 1,200
5
(KM 559) 36 South Main 3rd
Loop Line 1,220.32 315 – 1862 315 – 3083 Harris, GA 7 2004 DSAW 1,200
Note: ERW-HF is a high frequency electric resistance welded pipe longitudinal seam.
DSAW is double submerged arc welded pipe longitudinal seam.
Special Permit Inspection Areas:
The special permit inspection areas are defined as the area that extends 220 yards on each side
of the centerline as listed in Table 3 – Special Permit Inspection Areas.
Table 3 – Special Permit Inspection Areas
Special
Special
Permit
Outside
Start Survey
End Survey
Permit
Length4
Inspection
Diameter
Line Name Master Segment
Station
Station
Segment(s)
(miles)
Area
(inches)
(SS)
(SS)
Included
Number
24 87.63
1 1
(KM 555) Cypress Line Cypress Line 1 00 – 24.78 87 – 4810 2 2
(KM 556) 26 South Main 2nd Loop Line Enterprise to York 67 – 1394 102 – 4372 35.57
3 4
(KM 558) 36 South Main 3rd Loop Line Enterprise Station 67 – 1631 97 – 2268 30.06
4 5
(KM 559) 36 South Main 3rd Loop Line D/S of Ellerslie 311 - 3355 328 - 1743 16.46
Public Notice:
On January 22, 2021, PHMSA posted a notice of this special permit request in the Federal
Register (86 FR 6737) with a closing date of February 22, 2021. PHMSA received no comments
3 On February 3, 2022, SNG rescinded requested special permit segments number 3 (KM 557) and 6 (KM 560).
These segments were withdrawn at the request of PHMSA
4 If the special permit inspection area footage does not extent from launcher to receiver then the special permit
inspection area would need to be extended.
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 3 of 11

<<<PAGE 4>>>

on this special permit application during the comment period.
PHMSA has reviewed this special permit application to ensure the special permit conditions
address pipeline safety and integrity threats to the pipeline in the special permit segments and
special permit inspection areas. The special permit will require SNG’s Operations and
Maintenance (O&M) Manual and Procedures to provide a systematic program to review and
remediate the pipeline for safety concerns. Additional operational integrity reviews and
remediation requirements will be required by this special permit for these special permit
segments for Class 1 to 3 location changes.
The SNG special permit application letter, Federal Register notice, Final Environmental
Assessment and Finding of No Significant Impact, special permit with conditions, special permit
analysis and findings document, and all other pertinent documents are available for review in
Docket No. PHMSA-2020-0007 in the Federal Docket Management System (FDMS) located on
the internet at www.Regulations.gov.
Analysis:
Background: On June 29, 2004, PHMSA published in the Federal Register (69 FR 38948) the
criteria it uses for the consideration of applications for class location change waivers, now being
granted or denied through a special permit. First, certain threshold requirements should be met
on a pipeline special permit segment for a class location change special permit to be granted.
Second, the age and manufacturing process of the pipe; system design, and construction;
environmental, operating and maintenance histories; and integrity management program
elements are evaluated as significant criteria. These significant criteria are presented in matrix
form and can be reviewed in the FDMS, Docket No. PHMSA–RSPA-2004-17401. Third,
special permits will only be granted when pipe conditions and active integrity management
provides a level of safety greater than or equal to a pipe replacement or pressure reduction. The
operator’s Federal pipeline safety regulation compliance history is also evaluated as part of the
criteria matrix for acceptability prior to issuance of a special permit.
Threshold Requirements: Each of the threshold requirements published by PHMSA in the June
29, 2004, Federal Register notice is discussed below regarding the SNG special permit request.
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 4 of 11

<<<PAGE 5>>>

1) No pipeline segments in a class location changing to Class 4 location will be considered.
• This special permit request is for the special permit segments the 24-inch diameter
Cypress Line, 26-inch diameter South Main 2nd Loop Line, and 36-inch diameter South
Main 3rd Loop Line Pipelines, where a change has occurred from a Class 1 location to a
Class 3 location.
• SNG has met this requirement.
2) No bare pipe will be considered.
• The special permit segments are externally coated with poly concrete, epoxy, coal tar
enamel, or fusion bonded epoxy.
• SNG has met this requirement.
3) No pipe containing wrinkle bends will be considered.
• There are no wrinkle bends in the special permit segments.
• SNG has met this requirement.
4) No pipe segments operating above 72% of the specified minimum yield strength (SMYS)
will be considered for a Class 3 special permit.
• The special permit segments operate at or below 72% SMYS.
• SNG has met this requirement.
5) Records must be produced that show a hydrostatic test to at least 1.25 times MAOP and 90%
of SMYS. The records should include test pressure, year of the test, test duration, and
pressure test percent of MAOP for each pipeline:
• The special permit segments on the Cypress Line, South Main 2nd Loop Line, and
South Main 3rd Loop Line Pipeline were all pressure tested for 8 hours to at least 1.25
times the pipeline MAOP.
• SNG has met this requirement.
6) Inline inspection (ILI) must have been performed with no significant anomalies identified
that indicate systemic problems such as stress corrosion cracking (SCC).
• SNG ran ILI tools on the Cypress Line Pipeline in 2016.
• SNG ran ILI tools on the South Main 2nd Loop Line Pipeline in 2010.
• SNG ran ILI tools on the South Main 3rd Loop Line Pipeline one segment was
completed in 2014 and the other in 2019.
• SNG has met this requirement.
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 5 of 11

<<<PAGE 6>>>

7) Criteria for consideration of a class location change waiver, being considered through the
special permit, published by PHMSA in the Federal Register (69 FR 38948), define a waiver
inspection area (special permit inspection area) as up to 25 miles of pipe on either side of
the waiver segment (special permit segment).
• A special permit would be contingent upon SNG’s incorporation of the special permit
segments in its written integrity management program as covered segments in a high
consequence area in accordance with 49 CFR 192.903 and to assess and remediate
threats to the special permit inspection areas.
Criteria Matrix: The data submitted by SNG for the special permit segments have been
compared to the class location change special permit criteria matrix and are as follows:
• The special permit segments fall in the probable acceptance column of the criteria
matrix for:
o Design stress, test failures, pressure fluctuations, safety related condition reports,
program, ILI type, direct assessment, coating assessment, and damage prevention.
• The special permit segments fall in the possible acceptance column of the criteria
matrix for:
o Class 1 to 3 location, pipe manufacture, pipe girth welds, pipe coating, test
pressure, depth of cover, local geology, leaks and failures, service, cathodic
protection (CP), ILI timeframe, and inspection findings.
• The special permit segments fall in the requires substantial justification column of the
criteria matrix for:
o Kinder Morgan, Inc. overall enforcement findings fall in the requires substantial
justification category. SNG’s 11-year enforcement findings do not fall within this
category.
o This special permit requires SNG to implement the special permit conditions that
include safety requirements on the operations, maintenance, and integrity
management of the special permit segments (approximately 0.621 miles) and the
special permit inspection areas (169.72 miles). Therefore, the safety benefits are
obtained well beyond the portion of the pipeline that experienced a class location
change.
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 6 of 11

<<<PAGE 7>>>

o SNG will be required to submit to PHMSA an annual report for this special
permit on integrity threats to the pipeline in the special permit segment and the
special permit inspection area.
Operational Integrity Compliance:
To inform PHMSA’s decision about whether a special permit could provide a level of safety
greater than or equal to a pipe replacement or pressure reduction and is consistent with pipeline
safety, PHMSA reviewed this special permit request to understand the known type of integrity
threats that are in the special permit segments and special permit inspection areas. This
integrity information was used to design special permit conditions to provide a systematic
program to review and remediate the pipeline for safety concerns. Additional operational
integrity review and remediation requirements are required by this special permit to ensure that
the operator has an ongoing program to locate and remediate safety threats. These threats to
integrity and safety include any issues with the pipe coating quality, CP effectiveness, operations
damage prevention program, pipe depth of soil cover, weld seam and girth weld integrity,
anomalies in the pipe steel and welds, and material and structures either along or near the
pipeline that could cause the CP system to be ineffective. PHMSA has carefully designed a
comprehensive set of conditions that SNG must implement to comply with this special permit.
Past Enforcement History – January 1, 2011 through January 31, 2022:
During January 1, 2011 through January 31, 2022, SNG was cited in four (4) enforcement actions.
PHMSA issued one (1) Notice of Amendment, one (1) Notice of Probable Violation and two (2)
Warning Letters to SNG. Tables 4 and 5 below show PHMSA’s enforcement actions and civil
penalties for SNG:
Table 4: SNG Enforcement Matters from
January 1, 2011, through January 31, 2022
Notice of
Status Corrective
Action Order
Notice of
Safety
Probable
Amendment
Order
Warning
Letter Total
Violation
CLOSED 0 1 1 0 2 4
OPEN 0 0 0 0 0 0
Total 0 0 1 0 2 4
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 7 of 11

<<<PAGE 8>>>

Table 5: SNG Enforcement Civil Penalty Status
January 1, 2011 through January 31, 2022
Proposed Awaiting Order Assessed Withdrawn/Reduced Collected
$72,900 $0 $72,900 $0 $72,900
Summary of Enforcement Findings for SNG includes: Reporting, welding, conversion of
service, operations and maintenance procedures, records, and integrity management:
• 49 CFR 192.161, 192.163, 192.3, 192.465, 192.475, 192.605, 192.705, 192.709, 192.735,
192.745, and 192.911,
Table 6 below shows PHMSA’s enforcement actions and civil penalties for SNG and the specific 49
CFR Part 191 and 192 violations:
Table 6: Summary of Enforcement Findings for SNG
January 1, 2011 through January 31, 2022
Notice of Amendment
OME Procedural Manual 4 Integrity Management 7
Notice of Amendment Total: 11
Notice of Probable Violation
Corrosion Control 2 Operation and/or Maintenance 1 Integrity Management 3
OME Procedural Manual 2 Design 1
Notice of Probable Violation Total: 10
Warning Letter
Design 1 Operation and/or Maintenance 2
Warning Letter Total: 3
Grand Total: 24
Summary of Enforcement Findings for the Kinder Morgan Gas Pipelines Companies - CIG,
EPNG, NGPL, SNG, TEJAS, and TGP:
From January 1, 2011, through January 31, 2022, Kinder Morgan, the operator of NGPL, was cited in
64 enforcement actions with a total of $1,077,800 in assessed civil penalties on its Colorado Interstate
Gas Company (CIG), El Paso Natural Gas Company (EPNG), Natural Gas Pipeline of America
(NGPL), Southern Natural Gas Company (SNG), Tejas Pipeline (TEJAS), and Tennessee Gas Pipeline
Company (TGP) pipeline systems. PHMSA issued sixteen (16) Notice of Amendments, twenty-two
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 8 of 11

<<<PAGE 9>>>

(22) Notices of Probable Violations, twenty-one (21) Warning Letters, one (1) Safety Order, and six
(6) Corrective Action Orders to Kinder Morgan.
Tables 7 and 8 below show PHMSA’s enforcement actions and civil penalties for Kinder
Morgan on these pipeline systems – CIG, EPNG, NGPL, SNG, TEJAS, and TGP with operator
identification numbers (OPID#) 2564, 4280, 13120, 18516, 4900, and 19160.
Table 7 - Kinder Morgan Enforcement Matters from
January 1, 2011, through January 31, 2022
Notice of
Status Corrective
Action Order
Notice of
Safety
Probable
Amendment
Order
Warning
Letter Total
Violation
CLOSED 5 16 21 1 21 64
OPEN 3 1 1 0 0 5
Total 8 17 22 1 21 69
Table 8 - Kinder Morgan Enforcement Civil Penalty Status
January 1, 2011 through January 31, 2022
Proposed Awaiting Order Assessed Withdrawn/Reduced Collected
$1,461,500 $0 $1,077,800 $383,700 $1,077,800
The type of 49 CFR Part 192 enforcement violations against Kinder Morgan on these six (6)
pipeline systems from January 1, 2011, through January 31, 2022, were as follows:
Summary of Enforcement Findings for CIG, EPNG, NGPL, SNG, TEJAS, and TGP
includes: reporting, design, welding, compliance with specifications or procedures, corrosion
control, operations and maintenance procedures, continuing surveillance, public awareness,
emergency plans, maximum allowable operating pressure, control room management, relief
devices, maintenance of valves, qualification of operating personnel, and integrity management:
• 49 CFR 191.5, 191.14, 191.15, 191.22, 191.25, 191.27, 192.12, 192.14, 192.161, 192.199,
192.225, 192.227, 192.229, 192.303, 192.459, 192.463, 192.465, 192.469, 192.475, 192.479,
192.481, 192.603, 192.605, 192.613, 192.615, 192.616, 192.619, 192.625, 192.631, 192.705,
192.706, 192.707, 192.709, 192.713, 192.735, 192.736, 192.739, 192.743, 192.745, 192,805,
192.807, 192.905, 192.911, 192.917, 192.921, 192.933, 192.935, and 192.937.
Table 9 below gives a complete summary of the findings and the specific 49 CFR Part 191 and 192
violation:
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 9 of 11

<<<PAGE 10>>>

Table 9 – Summary of Enforcement Findings for CIG, EPNG, Tejas, NGPL, SNG, and TGP
January 1, 2011 through January 31, 2022
Notice of Amendment
OME Procedural Manual 11 Operation and/or Maintenance 2 Operator Qualification 3
Public Awareness 8 Reporting 3 Transportation of Gas 5
Integrity Management 10 Control Room Management 4 Construction 1
Welding of Steel in Pipelines 3
Notice of Amendment Total: 50
Notice of Probable Violation
Corrosion Control 13 OME Procedural Manual 14 Operation and/or Maintenance 26
Operator Qualification 7 Public Awareness 2 Reporting 5
Integrity Management 10 Control Room Management 1 Welding of Steel in Pipelines 1
Design 2
Notice of Probable Violation Total: 81
Warning Letter
Corrosion Control 10 OME Procedural Manual 9 Operation and/or Maintenance 31
Operator Qualification 2 Public Awareness 4 Reporting 1
Transportation of Gas 1 Integrity Management 1 Design 1
Notice of Amendment Total: 60
Grand Total: 191
Findings:
Based on the information submitted by SNG and PHMSA’s analysis of the technical,
operational, and safety issues, PHMSA finds that granting this special permit to SNG to operate
the special permit segments on the 24-inch diameter Cypress Line, 26-inch diameter South Main
2nd Loop Line, and 36-inch diameter South Main 3rd Loop Line Pipelines in Harris and
Effingham Counties, Georgia, and Clarke County, Mississippi, for approximately 0.621 miles of
Class 1 location pipe in a Class 3 location is consistent with pipeline safety.
PHMSA has designed the special permit conditions to effectively assess and remediate threats to
the special permit segments and special permit inspection areas, including pressure testing,
obtaining pipe material records, and conducting assessments to evaluate pipe girth welds that
have not been non-destructively tested, any pipe with missing material records, and SCC. To
ensure SNG properly implements the special permit conditions, SNG will be required to give
PHMSA an annual review of their compliance with the special permit.
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 10 of 11

<<<PAGE 11>>>

PHMSA finds that no significant negative impact to human safety and the environment will
result from the issuance and full implementation of a special permit that waives the requirements
of 49 CFR 192.611 for class location changes to a Class 3 location. This special permit requires
SNG to implement the special permit conditions that include safety requirements on the
operations, maintenance, and integrity management of the special permit segments and the
special permit inspection areas. SNG will be required to implement the special permit
conditions along the special permit segments and special permit inspection areas in pipeline
segments that are not high consequence areas and would not normally be required by 49 CFR
Part 192 to be assessed on a periodic interval for threats.
Completed in Washington DC on: July 27, 2022
Prepared by: PHMSA - Engineering and Research Division
Final Page of the Special Permit Analysis and Findings
PHMSA-2020-0007 – Southern Natural Gas Company, LLC Special Permit Analysis and Findings – Class 1 to Class 3 Locations – MS and GA
Page 11 of 11

<<<PAGE 1>>>

U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety
Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
July 27, 2022
Mr. Kenneth W. Grubb
Chief Operating Officer
Kinder Morgan Natural Gas Division
1001 Louisiana Street, Suite 1000
Houston, Texas 77002
Re: Docket No. PHMSA-2020-0007
Special Permit from July 27, 2022 to July 27, 2032
Dear Mr. Grubb:
On December 23, 2019, pursuant to 49 Code of Federal Regulations (CFR) § 190.341, Southern
Natural Gas Company, LLC (SNG)1 applied to the Pipeline and Hazardous Materials Safety
Administration (PHMSA) for a special permit. SNG requested a special permit to waive
compliance with 49 CFR §§ 192.611(a) and (d), and 192.619(a) for Class 1 to Class 3 location
changes on four (4) pipeline segments for approximately 0.621 miles of 24-inch, 26-inch, and
36-inch diameter gas transmission pipelines (Pipelines) located in Effingham and Harris
Counties, Georgia; and Clarke County, Mississippi. A gas transmission pipeline operator is
required by 49 CFR § 192.611 to confirm or revise the maximum allowable operating pressure of
a pipeline segment where the class location has changed as defined in 49 CFR § 192.5.
On January 22, 2021, PHMSA published a Federal Register notice (86 FR 6737) announcing the
Special Permit Request. The Special Permit Request letter, Final Environmental Assessment
(FEA) and Finding of No Significant Impact (FONSI), Special Permit Analysis and Findings
(SPAF), and all other pertinent documents for this special permit are available in Docket No.
PHMSA-2020-0007 in the Federal Docket Management System located at
www.regulations.gov.
2
Subject to the stated terms and conditions, PHMSA grants this special permit (enclosed) based
on the information provided by SNG and the findings set forth in the SPAF, FEA, and FONSI.
This special permit provides relief from certain provisions of the Federal pipeline safety
1 Southern Natural Gas Company, LLC is owned by Kinder Morgan, Inc.
2 https://www.regulations.gov/docket?D=PHMSA-2020-0007.

<<<PAGE 2>>>

regulations for the Pipelines and requires SNG to comply with conditions and limitations
designed to maintain pipeline safety as defined in the special permit. Note that in accordance
with 49 CFR § 190.341(j), PHMSA reserves the right to revoke, suspend, or modify this special
permit if circumstances occur in which its continuance would be inconsistent with safety. If
SNG elects not to implement the special permit conditions, SNG must notify PHMSA within 60
days and comply with 49 CFR § 192.611 within 18 months of the date of this letter.
My staff would be pleased to discuss this special permit or any other regulatory matter with you.
Sentho White, Director of PHMSA Engineering and Research Division, may be contacted at
(202) 366-2415, on technical matters; and James Urisko, Director, Office of Pipeline Safety,
Southern Region, may be contacted at (404) 832-1150, for operational matters specific to this
special permit.
Sincerely,
LINDA GAIL
DAUGHERTY
Digitally signed by LINDA
GAIL DAUGHERTY
Date: 2022.07.27 15:42:54
-04'00'
(on behalf of)
Alan K. Mayberry
Associate Administrator for Pipeline Safety
Enclosure: Special Permit – PHMSA-2020-0007
Special Permit: PHMSA-2020-0007 – Southern Natural Gas Company, LLC Letter of Decision – Class 1 to 3 – Georgia and Mississippi
Page 2 of 2

<<<PAGE 1>>>

1200 New Jersey Avenue, SE
Washington, D.C. 20590
U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety
Administration
December 19, 2025
Zach Ragain
Director – Engineering: Codes and Standards
Kinder Morgan
1001 Louisiana St, Suite 1000
Houston, TX 77002
Re: Docket No. 2020-0007 – Southern Natural Gas Company, LLC –
Harris County, Georgia
Dear Mr. Ragain:
On September 26, 2024, pursuant to 49 Code of Federal Regulations (CFR) § 190.341, Southern
Natural Gas Company, LLC1 (SNG) applied to the Pipeline and Hazardous Materials Safety
Administration (PHMSA) seeking an extension to a special permit segment to be incorporated in
the special permit PHMSA-2020-0007, effective through July 27, 2032. The special permit
waives compliance with 49 CFR §§ 192.611(a) and (d) and 192.619 for Class 3 pipeline
segments and allows SNG to continue operation of the original Class 1 design pipe in Class 3
locations subject to the conditions set forth in the special permit.
SNG has requested one special permit segment extension, 0.19 miles of 36-inch-diameter natural
gas transmission pipeline located in Harris County, Georgia. The amended special permit would
consist of two special permit segments of 0.70 miles in total of 24-inch and 36-inch-diameter
natural gas transmission pipeline located in Effingham and Harris Counties, Georgia.
On October 31, 2025, PHMSA published a Federal Register notice (90 FR 209) announcing the
special permit request and seeking public comment. The special permit amendment request letter
and other pertinent documents are available for review under Docket No. PHMSA-2020-0007 in
the Federal Docket Management System (FDMS) located at www.regulations.gov.
2
Summary of Public Comments: PHMSA received two public comments submitted by
anonymous commenters during the 30-day comment period. Both commenters opposed the
modification request; one commenter cited concerns of pipeline incidents related to deregulation,
1 Southern Natural Gas Company, LLC is a subsidiary of Kinder Morgan Inc.
2 https://www.regulations.gov/docket?D=PHMSA-2020-0007
Modification of Class Location Special Permit PHMSA-2020-0007
Letter of Decision and Special Permit Findings and Analysis – Georgia Page 1

<<<PAGE 2>>>

and the other communicated concerns of increased risk associated with grant of waivers from the
Federal pipeline safety regulations in areas of population growth.
PHMSA Response: PHMSA has authority to grant amendments to waivers from compliance
with class location change requirements to applicants who demonstrate that their request is not
inconsistent with pipeline safety. PHMSA has conducted a review of this request and decided
that the incorporation of the extended special permit segments would not require a material
change in conditions. Based on the information provided by SNG, PHMSA decided that
amendment of the special permit would not be inconsistent with pipeline safety. Details of the
incorporated segments and access to maps were published previously and can be viewed in the
FDMS.
On September 25, 2025, PHMSA reviewed the special permit request for compliance with the
National Environmental Policy Act (NEPA). PHMSA determined that the following Categorical
Exclusion (CE) is applicable to the special permit segment extension: Granting, renewing, or
denying a special permit related to waiving class location or odorization requirements, following
the procedures set forth in 49 CFR § 190.341, including the identification of any enforceable
conditions, imposed pursuant to 49 CFR § 190.341(d)(2), that are required to prevent and
address pipeline safety and environmental risk. PHMSA has further determined that no
extraordinary circumstances apply. In order to ensure continued human and environmental
safety, the operator must fulfill the mitigation conditions of the special permit; continue to
employ good operating practices; and continue to follow any additional applicable permitting
requirements, State laws, or other pre-existing Federal requirements related to environmental
protection. Should conditions change, or should extraordinary circumstances materialize, the
operator must contact PHMSA for reevaluation. The proposed action is hereby categorically
excluded from further NEPA review, and the finalized CE will be published online.3
Accordingly, pursuant to 49 CFR § 190.341, by this Order—and as outlined in the existing
special permit—PHMSA grants the amendment of special permit PHMSA-2020-0007, effective
through July 27, 2032, to SNG. This special permit amendment Order continues to waive
compliance with certain Federal regulations in 49 CFR §§ 192.611(a) and (d) and 192.619(a).
My staff would be pleased to discuss this special permit or any other regulatory matter with you.
Max Kieba, Director of Engineering and Research Division, may be contacted at (202) 420-9169
for technical matters; and James Urisko, Director, Office of Pipeline Safety, Southern Region,
may be contacted at (404) 832-1150 for operational matters specific to this special permit.
Sincerely,
Linda Daugherty
Acting Associate Administrator for Pipeline Safety
3 https://www.phmsa.dot.gov/planning-and-analytics/environmental-analysis-and-compliance/implementing-procedures
Modification of Class Location Special Permit PHMSA-2020-0007
Letter of Decision and Special Permit Findings and Analysis – Georgia Page 2
- **truncated:** false
- **body characters:** 31440