# U.S. DOT/PHMSA - Special Permit Analysis & Findings

- **operation:** document
- **citation:** 0900006480e91c2f
- **title:** U.S. DOT/PHMSA - Special Permit Analysis & Findings
- **source type:** rulemaking
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** Not available
- **summary:** PHMSA describes the special permit application (PHMSA-2008-0330) submitted November 13, 2008, for two segments on Columbia Gulf’s 30-inch Mainline 200 and 36-inch Mainline 300 in Wilson County, TN, where class locations changed to Class 3, and explains the special permit scope, required conditions, evaluative criteria, enforcement history considerations, and PHMSA’s conclusion that granting the special permit under specified conditions is consistent with pipeline safety. Scope includes the two 1,600-foot special permit segments and ~50.30 mile special permit inspection areas on each pipeline. Limitations and conditions noted include threshold requirements, additional inspections and surveys (ILI, DCVG/ACVG, CIS, SCCDA), girth weld records or leakage surveys, coating/cathodic protection remediation, periodic reassessments, training of senior management and technical staff, and PHMSA’s use
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/regulations-gov-attachment-0900006480e91c2f.json
- **markdown:** https://regulus.evalyn.ai/document/regulations-gov-attachment-0900006480e91c2f.md
- **app url:** https://regulus.evalyn.ai/document/regulations-gov-attachment-0900006480e91c2f
- **source url:** https://downloads.regulations.gov/PHMSA-2008-0330-0003/attachment_1.pdf
**body:**

<<<PAGE 1>>>

1
U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION (PHMSA)
Special Permit Analysis and Findings
Special Permit Information:
Docket Number:
PHMSA-2008-0330
Requested By:
Columbia Gulf Transmission Company'
Date Requested:
November 13, 2008
Code Sections:
49 CFR § 192.611
Purpose:
The Pipeline and Hazardous Materials Safety Administration (PHMSA) provides this
information to describe the facts of the subject special permit application submitted by Columbia
Gulf Transmission Company (Columbia Gulf), to discuss any relevant public comments received
with respect to the application, to present the engineering/safety analysis of the special permit
application, and to make findings regarding whether the requested special permit should be
granted and if so under what conditions.
Pipeline System Affected:
This special permit applies to two natural gas pipeline segments on the 30-inch Mainline 200 and
36-inch Mainline 300 pipelines operated by Columbia Gulf in Wilson County, TN, where
changes have occurred from original Class 1 locations to Class 3 locations or a Class 2ª location
to Class 3 location. This special permit allows Columbia Gulf to continue to operate the two
pipeline segments at their current maximum allowable operating pressure (MAOP) of 1008
pounds per square inch gauge (psig) for the 30-inch Mainline 200 and 1008 psig for the 36-inch
Mainline 300.
Columbia Gulf Transmission Company is owned and operated by NiSource Gas Transmission and Storage
(NGT&S).
location in accordance with a § 192.611(a) hydrostatic test.
" The Class 3 location special permit segments were originally a Class 1 location area that was upgraded to a Class 2

<<<PAGE 2>>>

2
This special permit applies to the special permit segments defined as follows using the Columbia
Gulf pipeline survey stationing (Sta.):
• Special Permit Segment I: 30-inch Mainline 200 - 1600 feet, Sta. 3030+43 to Sta. 3046+43
• Special Permit Segment 2: 36-inch Mainline 300 - 1600 feet, Sta. 3025+55 to Sta. 3041+55
This special permit applies to the special permit inspection area(s) defined as follows using the
30-inch Mainline 200 and the 36-inch Mainline 300 pipeline stationing as a reference:
Special permit inspection areas - means the area that extends 220 yards on each side of the
centerline of each pipeline along the entire length of the Columbia Gulf 30-inch Mainline 200
and the 36-inch Mainline 300 pipelines defined as follows:
• Special Permit Inspection Area 1: 30-inch Mainline 200 - Sta. 1710+43 to Sta. 4366+43,
(50.30 miles)
• Special Permit Inspection Area 2: 36-inch Mainline 300 - Sta. 1705+55 to Sta. 4361+55,
(50.30 miles)
Note: The special permit inspection area extends approximately 50.30 miles along each pipeline
(Mainlines 200 and 300) with overlapping areas and includes the special permit segment.
The special permit inspection area is located in Williamson, Davidson, Wilson, Sumner, and
Trousdale Counties, TN. The special permit inspection area extends from approximately 25
miles upstream of the special permit segments to approximately 25 miles downstream of the
special permit segments, a total of approximately 50.30 miles on each pipeline.
Special Permit Request:
Columbia Gulf submitted an application to PHMSA on November 13, 2008, for a special permit
seeking relief from the Federal pipeline safety regulations in 49 CFR § 192.611 for two segments
on the 30-inch Mainline 200 and the 36-inch Mainline 300 natural gas transmission pipelines,
where a change has occurred from a original Class 1 location per 192.611, to a Class 3 location
in Wilson County, Tennessee. This special permit allows Columbia Gulf to continue to operate
the pipeline segments at their current maximum allowable operating pressure (MAOP) of 1008
pounds per square inch gauge (psig) on the Mainlines 200 and 300 pipelines. The Federal

<<<PAGE 3>>>

3
pipeline safety regulations in 49 CFR § 192.611, require natural gas pipeline operators to
confirm or revise the MAOP of a pipeline segment after a change in class location. A special
permit would allow Columbia Gulf to continue to operate each of the two special permit
segments on the 30-inch Mainline 200 and the 36-inch Mainline 300 at its existing MAOP
despite a change in class location. Columbia Gulf did not include the Mainline 100 pipeline in
the special permit request.
In its application, Columbia Gulf suggested that the two special permit segments be included in
separate special permit inspection areas. The special permit inspection areas on the Mainline
200 and the Mainline 300 pipelines, would begin approximately 25 miles upstream of the Special
Permit Segment and end approximately 25 miles downstream of Special Permit Segment for a
total of 50.30 miles.
Public Notice:
On January 23, 2009, PHMSA posted a notice of this special permit request in the Federal
Register (74 FR 4298). PHMSA did not receive any comments for or against this special permit
request as a result of this notice. The request letter, Federal Register notice and all other
pertinent documents are available for review in Docket No. PHMSA-2008-0330 in the Federal
Docket Management System (FDMS) located on the internet at www.Regulations.gov.
Analysis:
Background: On June 29, 2004, PHMSA published in the Federal Register (69 FR 38948) the
criteria it uses for the consideration of class location change waivers, now being granted through
special permits. First, certain threshold requirements must be met for a pipeline section to be
further evaluated for a class location change special permit. Second, the age and manufacturing
process of the pipe; system design and construction; environmental, operating and maintenance
histories; and integrity management program (IMP) elements are evaluated as significant criteria.
These significant criteria are presented in matrix form and can be reviewed in the FDMS, Docket
Number PHMSA-RSPA-2004-17401. Third, such special permits will only then be granted
when pipe conditions and the operator's active integrity management program provides a level of
safety greater than or equal to a pipe replacement or pressure reduction. As described later in
this document, in addition to technical review, PHMSA focused heavily on enforcement history
in reviewing this application.

<<<PAGE 4>>>

4
Threshold Requirements: Each of the threshold requirements published by PHMSA in the
June 29, 2004, FR notice is discussed below in regards to the Columbia Gulf special permit
petition.
1) No pipeline segments in a class location changing to Class 4 location will be considered.
This special permit request is for two segments of the Columbia Gulf pipeline system where
a class location change has occurred from Class 1 or 2 to Class 3. Columbia Gulf has met
this requirement in details submitted in application.
2) No bare pipe will be considered. These Columbia Gulf special permit segments are coated
with coal tar. Columbia Gulf has met this requirement in details submitted in application.
3) No pipe containing wrinkle bends will be considered. There are no wrinkle bends in the
special permit segments. Columbia Gulf has met this requirement in details submitted in
application.
4) No pipe segments operating above 72% of the specified minimum yield strength (SMYS)
will be considered for a Class 3 special permit. These special permit segments operate at or
below 72% SMYS. Columbia Gulf has met this requirement in details submitted in
application.
5) Records must be produced that show a hydrostatic test to at least 1.25 x MAOP and 90% of
SMYS. Columbia Gulf has met this requirement in details submitted in application.
6) In-line inspection (ILI) must have been performed with no significant anomalies identified
that indicate systemic problems. Columbia Gulf has met this requirement in details
submitted in application.
7) Criteria for consideration of class location change waiver, now being granted through special
permit, published by PHMSA in the Federal Register (69 FR 38948), define a waiver
inspection area (special permit inspection area) as up to 25 miles of pipe either side of the
waiver segment (special permit segment). The special permit inspection areas must be
inspected according to Columbia Gulf's integrity management program and periodically
inspected with an in-line inspection technique. The special permit inspection areas are
approximately 50.3 miles long on both the Mainline 200 and Mainline 300 pipelines. This
special permit will be issued contingent upon Columbia Gulf's incorporation of the two
special permit segments in its written integrity management program as "covered segments"
in a "high consequence area" (HCA) per 49 CFR § 192.903.

<<<PAGE 5>>>

5
The two special permit segments meet the seven threshold requirements. Additional ILI tool
runs will be required in the special permit conditions.
Criteria Matrix: The original and supplemental data submitted by Columbia Gulf for the two
special permit segments have been compared to the class location change special permit criteria
matrix. The two special permit segments falls in the probable acceptance column of the criteria
matrix for all criteria except for:
Possible Acceptance: Pipe material (low or unknown toughness), pipe coating
(coal tar), and pipe manufacture (1963 and 1968, DSAW).
b. Requires substantial justification: Columbia Gulf has no records of performing
non-destructive testing of girth welds, direct assessment (ECDA and SCCDA),
and has outstanding inspection findings from a CAO on its pipelines. Moreover,
the enforcement history for Columbia Gulf indicates outstanding inspection
findings from Corrective Action Orders (CAO) on its pipelines.
The data findings below fall within the "probable acceptance" or the "requires substantial
justification" columns of the criteria matrix:
1) Pipe design and construction, including pipe manufacture, material and design stress:
Mainline 200 and Mainline 300 pipelines were installed in 1963 & 1968 and consists of
American Petroleum Institute Specification 5L, Specification for Line Pipe (API 5L),
submerged arc welded (SAW), X-60 steel pipe manufactured by National Tube and double
submerged arc welded (DSAW), X-65 steel pipe manufactured by U.S. Steel. These pipes
are of unknown toughness but Columbia Gulf has addressed this risk in their integrity
management plan. Moreover, none of these pipelines have any known systemic
manufacturing issues. This places the two special permit segments in the "possible
acceptance" column of the criteria matrix
2) Girth welds: Columbia Gulf does not know if the girth welds were nondestructively tested
during initial construction and has been unable to locate any supporting documentation thus
far. This places both special permit segments in the "requires substantial justification"
column of the criteria matrix. While there have been no reported problems with girth welds

<<<PAGE 6>>>

on these pipelines in the special permit inspection area, to address the girth weld issue this
special permit will include a condition requiring Columbia Gulf to provide girth weld
inspection records, or to certify that there have been no in-service leaks or breaks in the girth
welds on Mainline 200 and Mainline 300 pipelines in the special permit inspection area. In
the absence of records, Columbia Gulf will also be required to perform leakage surveys using
leak detection equipment along the entire length of each special permit segment within 60
days atter the grant of this special permit. Columbia Gulf must prepare and follow a girth
weld remediation plan for both special permit segments.
3) ILl Time Frame: Mainline 200 was last inspected with a high-resolution MFL and a
geometry tool in July 2004, and in October 2005. Mainline 300 was last inspected with a
high-resolution MFL and a geometry tool in July and August 2004. This places both special
permit segments in the "possible acceptance" column of the criteria matrix. To address ILI
issues, this special permit will be conditioned upon Columbia Gulf treating both special
permit segments as a "covered segment" in a "high consequence area" per 49 CFR
$ 192.903. The special permit conditions specify the time intervals between ILI runs.
4) Direct Assessment (ECDA & SCCDA): Columbia Gulf has not completed an external direct
assessment (ECDA) or a stress corrosion cracking assessment (SCCDA) of the special permit
segments. This places both special permit segments in the "requires substantial justification"
column of the criteria matrix. To address these issues, this special permit will be conditioned
upon Columbia Gulf completing a Direct Current Voltage Gradient (DCVG) survey or an
Alternating Current Voltage Gradient (ACVG) survey; a close interval survey (CIS); and a
SCCA along Mainline 200 and Mainline 300 pipelines not later than one year after the
grant of this special permit.
PHMSA has determined that imposing the special permit conditions will address these concerns
and provide equivalent safety for these areas.
Operational Integrity Compliance: PHMSA has reviewed this special permit request to ensure
that integrity threats to the pipeline in the special permit segments and special permit inspection
areas are addressed in the operator's operations and management plan (O&M Plan). Columbia
Gulf must have a systematic program to review and remediate the pipeline for safety concerns.

<<<PAGE 7>>>

7
Additional operational integrity review and remediation requirements will be required by this
special permit for this special permit segment class location change. The pipeline operational
integrity requirements are to ensure that the operator has an ongoing program to locate and
remediate safety threats. Some of these threats to integrity and safety are the pipe coating
quality, cathodic protection effectiveness, operations damage prevention program for third party
damage, weld seam and girth weld integrity, anomalies in the pipe steel, and material and
structures either along, or near the pipeline that could cause the cathodic protection system to be
ineffective. PHMSA carefully designed a comprehensive set of conditions that Columbia Gulf
would be required to meet in order for the special permit to be granted. Among other things, the
conditions include:
• A close interval survey to determine the effectiveness of the cathodic protection system
must be performed within the special permit segments and special permit inspection area
and all areas with inadequate cathodic protection must be remediated.
• A coating survey to determine the quality of the pipe coating must be conducted and in-
effective coating areas must be remediated within the special permit segments.
• Stress corrosion cracking surveys on the pipeline will be required to ensure that the pipe
steel is not cracking due to the effects of high and near neutral pH SCC, within the
special permit segments and special permit inspection area.
• The latest methods of damage prevention must be incorporated by the operator, such as
the best practices of the Common Ground Alliance (CGA), within the special permit
inspection areas.
• Interference currents from electric transmission lines and other interfering structures in
the special permit segments and special permit inspection area must be identified,
controlled and mitigated by conducting surveys and installing grounding systems where
required.
• An analysis of pipeline field coated girth weld coatings that could have shielding coatings
that could cause corrosion of the pipe steel must be undertaken in the special permit
segments and special permit inspection area, and indications from in-line inspection logs
showing 30% or greater wall loss corrosion on shielding or unknown coatings must be
exposed and evaluated.

<<<PAGE 8>>>

8
• Anomalies and dents on the pipeline must be repaired based upon the special permit
repair criteria.
• Girth welds in the special permit segments must have had a non-destructive test plan
during construction, or a quality review and remediation program must be implemented
by the pipeline operator.
• All shorted casing (either metallic or electrolytic) at road crossings and railroad crossings
in the special permit segments and special permit inspection areas must be cleared to
prevent corrosion.
• Pipeline longitudinal seams within the special permit segments and special permit
inspection area must have an engineering analysis to determine if there are any threats
and remediated if integrity threats are determined.
• Periodic close interval surveys and in-line inspection surveys (pipeline internal surveys to
determine corrosion in the pipeline) must be performed on the special permit segments
and special permit inspection area at the applicable reassessment intervals.
• Training of Senior Executive Management (Executive Vice President and Group CEO,
Vice President of Operations and Vice President of Engineering), Engineering and
Operations Managers and Supervisors, and Technical Personnel (Engineers and
Operations Technicians) in natural gas pipeline integrity management, corrosion control,
and anomaly evaluation, validation and repairs to meet Part 192 and these special permit
conditions.
• Columbia Gulf must maintain an open and transparent relationship with PHMSA to
ensure effective implementation of special permit conditions, and must make records and
applicable information available to PHMSA upon request. Columbia Gulf must fully
execute the special permit conditions and proactively respond to findings encountered
throughout implementation.
The special permit will contain numerous conditions to ensure Columbia Gulf meets or exceeds
the threshold requirements with equivalent safety, and to ensure that granting the special permit
will not be inconsistent with safety.

<<<PAGE 9>>>

9
Past Enforcement History - 2000 through 2009
The enforcement history is an important reflection of how Columbia Gas has been observed to
follow pipeline safety regulations, and was a major area of focus for the review of this
application. A review of PHMSA enforcement actions against Columbia Gulf and Columbia
Gas from 2000 through 2009, shows the following enforcement actions against the companies.
The existence of these actions requires substantial justification pursuant to the Class Location
Special Permit Criteria, as confidence is necessary that conditions contained in the special permit
would be closely followed. Columbia Gulf and Columbia Gas are owned and operated by
NiSource Gas Transmission and Storage (NGT&S).
Below is a listing of PHMSA closed enforcement matters of all types in all PHMSA Regions for
Columbia Gulf and Columbia Gas from 2000 through 2009:
• Letters - of Concern or Warning - 30 matters
• Notices - of Amendment or of Probable Violation - 20 matters
• Fines - $1,221,000 collected, additional penalties have been proposed
The preceding enforcement history summary reveals a number of compliance issues, including
pipeline maintenance issues.
PHMSA initially was inclined to deny this special permit application based on the enforcement
history. PHMSA notified Columbia Gulf senior management of the agency's enforcement
history concerns prior to taking final action to deny the special permit application. Columbia
Gulf acknowledged performance issues and requested a meeting with PHMSA, to explain
improvements the company had made to its pipeline safety programs that were designed to
improve compliance with the regulations. In a meeting with PHMSA on July 28, 2009,
Columbia Gulf's senior management gave a presentation entitled "Integrity Management
Improvements," which described changes made by Columbia Gulf to improve compliance with
pipeline safety regulations. In an August 27, 2009, meeting with PHMSA, Columbia Gulf
presented its "Special Permit Management Plan," which described an organizational structure
and plan to manage special permit compliance. The presentations from the meetings listed above
are posted on the docket.

<<<PAGE 10>>>

10
In analyzing whether or not to grant a special permit, PHMSA considered the organizational,
management and procedural changes described by Columbia Gulf. PHMSA believes that some
of these changes are positive and necessary for pipeline safety, and will incorporate additional
conditions into the special permit to capture the company's commitments. These additional
conditions will require Columbia Gulf (NGT&S) Executive Management, Mid-Level
Management and Technical Support Personnel to make improvements in integrity management,
training, and operating procedures. The additional conditions include:
Columbia Gulf (NGT&S) must complete the training of Senior Executive Management
(Executive Vice President/Group CEO, Vice President of Operations and Vice President of
Engineering), Engineering and Operations Managers and Supervisors, and Technical Personnel
(Engineers and Operations Technicians) in natural gas pipeline integrity management, corrosion
control, anomaly evaluation, validation and repairs to meet Part 192 and the special permit
conditions as follows:
• Columbia Gulf Senior Executive Management Level Commitment to:
a) Execution of Special Permit Requirements for Class Location Changes in
accordance with letter from Mr. Chris Helms, Executive Vice President and Group
CEO, of NGT&S (Columbia Gulf) to PHMSA dated September 21, 2009 and
b) completion of all outstanding Corrective Action Orders (CAO) on the Columbia
Gulf System.
• Columbia Gulf (NGT&S) must maintain a transparent relationship with PHMSA to
ensure implementation of all conditions.
• Columbia Gulf 's Executive Vice President/Group CEO, will require letters of
commitment from responsible employees throughout Columbia Gulf (NGT&S),
requiring that these individuals commit in writing to specific special permit
conditions, to reinforce and demonstrate the full commitment to compliance with the
special permit throughout the organization.
PHMSA has determined that imposing the special permit conditions summarized in this
document will ensure that granting the special permit will not be inconsistent with safety.

<<<PAGE 11>>>

11
Findings:
Based on the information submitted by Columbia Gulf and PHMSA's analysis of the technical,
operational, and safety issues, and given the conditions that will be imposed in the special
permit, PHMSA finds that granting this special permit to Columbia Gulf to operate special.
permit segments of the Mainline 200 and 300 natural gas transmission pipelines at the current
MAOP, where a change in class location has occurred from an original Class 1 location to a
Class 3 location is consistent with pipeline safety.
Completed in Washington DC on:
APR 1 3 2010
Prepared By: PHMSA - Engineering and Emergency Support
- **truncated:** false
- **body characters:** 22797
