# U.S. DOT/PHMSA - Response to Request for Special Permit

- **operation:** document
- **citation:** 0900006480e92734
- **title:** U.S. DOT/PHMSA - Response to Request for Special Permit
- **source type:** rulemaking
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** Not available
- **summary:** PHMSA’s letter (Sept. 1, 2009 Attachment A) sets interim inspection, excavation, testing, removal, remediation, and monitoring requirements that MEP must meet before operating Class 1 pipe above 72% SMYS up to 80% SMYS. Key elements include high-resolution deformation tool runs, removal of pipe joints expanded over specified thresholds (notably >1.50% with elastic loading), mechanical property testing of excavated or removed pipe, calibration digs, limits on class-change ‘one class bump’ at locations with >1.0% expansion until a fitness-for-service plan is accepted, prescribed in-line inspection and survey intervals after operation at the alternative MAOP, enhanced anomaly response/repair criteria tied to failure pressure ratios and percent wall loss, and incorporation of these interim guidelines into MEP’s Operations and Maintenance procedures. The authorization to operate up to 80% SMY
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/regulations-gov-attachment-0900006480e92734.json
- **markdown:** https://regulus.evalyn.ai/document/regulations-gov-attachment-0900006480e92734.md
- **app url:** https://regulus.evalyn.ai/document/regulations-gov-attachment-0900006480e92734
- **source url:** https://downloads.regulations.gov/PHMSA-2007-27842-0012/attachment_1.pdf
**body:**

<<<PAGE 1>>>

U.S. Department of Transportation
1200 New Jersey Ave, S.E.
Safety Administration
Pipeline and Hazardous Materials
Washington, D.C. 20590
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
Mr. M. Dwayne Burton
Vice President, Operations and Engineering
Midcontinent Express Pipeline, LLC
One Allen Center
500 Dallas St
Suite 1000
Houston, TX 77002
RE: Midcontinent Express Pipeline, LLC (MEP); Special Permit: PHMSA-2007-27842
Dear Mr. Burton:
On August 25, 2009, you wrote to the Pipeline and Hazardous Materials Safety Administration
(PHIMSA) requesting to increase the operating pressure of the Midcontinent Express Pipeline,
LLC (MEP) to a pressure corresponding to a maximum hoop stress of 80% of the specified
minimum yield strength (SMYS) in accordance with the alternative maximum allowable
operating pressure (MAOP) Special Permit, Docket No. PHMSA-2007-27842. MEP currently
operates at a pressure corresponding to 72% SMYS. Further, under separate cover, MEP
submitted documents supporting the request.
After a thorough review of the documents and consideration of MEP assertions in your August
25, 2009 letter, this letter responds to your request, providing guidance to attain operating
pressures above 12% SMYS up to 80% SMYS. The requirements contained herein in
"Attachment A"- Integrity Verification of Pipe Properties - September 1, 2009 apply to the
pipeline segments experiencing expansion above 0.60% for 42-inch pipe and 0.75% for pipe
equal to or less than 36-inch diameter.
On May 21, 2009, PHMSA issued an advisory bulletin (PHMSA-2009-0148), for the Potential
for Low and Variable Yield and Tensile Strength and Chemical Compositions in High Strength
Line Pipe (ADB), recommending operators to investigate if certain pipelines contain pipe joints
not meeting minimum specification requirements (74 FR 23930). The observance of pipe
expansions on recently constructed natural gas projects including Kinder Morgan projects led to
PHMSA's issuance of the ADB. PHMSA remains concerned about expansion deformations
exceeding 1.5% and is particularly concerned with any situation where expansion is present in
combination with pipe not meeting mechanical requirements under API 5L. In fact, the basis for
the design formula contained in 49 CFR section 192.111 contains specific material property
requirements which provides the basis for establishing MAOP under 49 CFR section 192.619.

<<<PAGE 2>>>

2
Therefore, an operator cannot afford to only consider the amount of expansion when reviewing
pipeline in-line inspection deformation tool results since expansion may also be evidence of low
yield or tensile strength line pipe. Until further studies are complete, PHMSA believes that a
conservative approach is necessary that requires the operator to remove excessive pipe expansion
anomalies along with performing mechanical testing to confirm if yield strength is a concern. To
this end, PHMSA requests MEP to confirm if the following interim guidelines in "Attachment A
- Integrity Verification of Pipe Properties" dated September 1, 2009 were met for the MEP
pipeline.
MEP must implement all special permit conditions in PHMSA-2007-27842, for the special
permit pipeline segments. All DCVG/ACVG surveys must be conducted in accordance with the
special permit conditions. The DCVG/ACVG surveys and the pipe coating remediation must be
completed within 6 months after operating at the alternative MAOP (above 72% SMYS up to
80% SMYS operating pressure).
Contingent upon your certification and documentation of compliance with the attached interim
guidelines, PHMSA will grant authorization to increase the operating pressure of the designated
MEP pipeline to a pressure corresponding to 80% SMYS. Please be advised that the interim
Sincerely,
Alan K. Mayberr
Director, Engineering and Emergency Support
Office of Pipeline Safety
Cc:
Jeffrey Wiese
John Gale
Linda Daugherty
Steve Nanney
Rod Seeley

<<<PAGE 3>>>

3
"ATTACHMENT A"- Integrity Verification of Pipe Properties - September 1, 2009
MEP must remove all pipe joints expanded in excess of 1.50% in diameter, with elastic loading
included (i.e., taking into account the pressure on the pipe at the time of measuring the
deformation), or the commensurate adjusted expansion without elastic loading on the pipe when
expansion is verified in the field without pressure on the pipe.
MEP must also comply with the following requirements prior to operation of Class 1 pipe above
72% specified minimum yield strength (SMYS):
1) Unless already completed, MEP must run a deformation tool through all pipeline
segments on the MEP Pipeline. MEP must use a high resolution deformation tool in lieu
of a geometry tool to address the threat of low strength, expanded pipe.
The deformation tool must include multi-finger sensors that contact the pipe
internal diameter and have an accuracy of +/- 1% or less to identify expanded
pipe and dents.
The results of all deformation tool run results for
expanded pipe and dents should be analyzed and submitted to the appropriate
PHMSA Regional Director. All pipe exhibiting an indicated diameter greater
than 0.60% or 0.75% (based upon pipe diameter 42" or ≥ 36" per API SL
above the nominal pipe diameter should be noted on the report of potential
deformations.
Expanded pipe is defined as pipe exhibiting an indicated
diameter greater than 0.60 % or 0.75% (based upon pipe diameter 42" or ≥
36" per API 5L) above the nominal or actual rolled pipe diameter.
MEP must ensure that all deformation tool results are not masked by the
approach used to calculate and compare expanded versus non-expanded pipe
and the percentage of expansion. MEP must employ procedures to review and
compare deformation tool results with other pipe joint diameters to ensure an
entire pipe joint is not expanded
MEP must review with the appropriate PHMSA Regional Director, the
deformation tool reports. This analysis must consider pipe properties and
property distributions, hydrostatic test pressures and reported test behavior,
and pipe end to center variations. Based on local pressure and expecter
›ehavior, any expansion exceeding the diameter by more than 1.5% witl
elastic loading (or the commensurate adjusted expansion with elastic loading
on the pipe, when expansion is verified in the field without pressure on the
pipe) must be investigated by excavation to determine actual expansion, wall
thinning and, if necessary, to verify pipeline special permit segments: tensile
strength, yield
strength, elongation, chemical composition, carbon
equivalent/Pcm, hardness, Charpy - shear area and absorbed energy with full
Charpy curves, and drop weight tear test (DWTT) properties ("properties

<<<PAGE 4>>>

4
2. Pipe joints with expansions ≥ 1.5% with elastic loading must be removed and
confirmed for strength serviceability as follows:
a. Perform "properties test" in the transverse direction. MEP must take 2 sets at
3 locations along the pipe section of "properties test" for each removed pipe
joint. The expanded pipe joint should be mapped to identify expanded pipe
minimum and maximum wall thicknesses with at least 10 thickness readings
mapped showing location on the pipe.,
b. If expanded pipe properties tests in (a.) do not meet special permit
requirements, MEP must:
i. Perform "properties test" of at least two (2) expanded pipe joints over
1% with elastic loading and two (2) non-expanded pipe samples from
the steel/pipe supplier of expanded pipe (same OD, wall thickness,
Grade, weld seam, steel supplier, pipe manufacturer and rolling
campaign) to confirm pipe properties. The non-expanded pipe joints
may be from in service or spare pipe inventory.
ii. Submit remediation plans or a technical justification (fitness for
service plan) to PHMSA on how reduced strength pipe meets 49 CFR
Part 192.105.
c. If the deformation tool run in Condition 1 shows no expanded pipe above
1.5% expansion or the pipe "properties test" in Condition 2. b above shows no
reduced pipe properties, MEP must excavate two (2) expanded pipe joints
with expansion above 1% with elastic loading to determine if there is wall loss
or thinning that is detrimental to safe operations, prior to operating at the
alternative MAOP. Any wall loss that would reduce the pipe segment
operating pressure in accordance with §§ 192.103, 192.105 192.111, 192.112
and 192.619 must be remediated. If these excavations show wall loss below
nominal wall thickness, MEP must continue to excavate and remediate
expanded pipe joints above 1% with elastic loading until there are no
detrimental wall loss pipe joints in service.
All deformation tool results, for an initial run on a "pipeline segment", must be
confirmed with at least two calibration digs to validate anomaly sizes and tool
evaluations and remediation.
accuracy. Tool inaccuracies after validation must be considered into expanded pipe
4.
MEP must not use the "one class bump" for class change locations where expansions
exceeded 1.0% with elastic loading until completion of a "fitness for service" plan
and acceptance by PHMSA.
The interim guidelines contained herein must be reviewed with PHMSA, Director of
Engineering and Emergency Support and PHMSA, Southern and Southwestern
Regional Directors at the completion of the investigation, pipe properties testing, and
"fitness for service" plan for technical soundness (including a determination of the
proper pipe grade to meet § § 192.103, 192.105, 192.111, 192.112 and 192.619 in
determining the alternative MAOP or MAOP of the pipeline segment)

<<<PAGE 5>>>

5
MEP must perform the following actions where deformation tool runs indicate expansion
greater than 1.5% or in pipeline segments with low strength pipe.
6. Conduct a re-inspection and remediation of the pipelines with deformation and high
resolution magnetic flux leakage (MFL) tools to evaluate for metal loss and
expansion anomalies:
a. Within 36 months of operating above 72% SMYS up to 80% SMYS on any
given pipeline segment with expanded or remediated pipe.
b. Schedule subsequent in-line inspection with MFL tools (ILI) and close
interval survey re-inspections for the pipelines based on failure pressure ratios
intervals.
(FPKs) calculated after the first re-inspection, but not to exceed 5 year
C.
Manage plain dents (in accordance with ANSI B31.8 and § 192.933) not to
exceed 6% total strain in pipe body and 2% strain contiguous with weld for
future ILl deformation and geometry tool runs
7. Pipeline operations: Pipeline may be operated up to the alternative MAOP (80%
SMYS), after successful completion of the following interim guidelines:
"Properties tests," and a technical review including review of pipe test
pressures to confirm that pipe property results meet API SL
specifications and 49 CFR Part 192 requirements for the alternative
MAOP or MAOP. The "properties tests" must show conformance
with API 5L and alternate MAOP or MAUP criteria.
i. Finise foser bic treplan to operate lining alter ate Mily thor A tre
based upon pipe "properties test" and any effects of elevated test
pressure due to pipe elevation differences may have had on pipe
expansion.
ili. The technical documentation of all "properties test" findings or
"fitness for service" plans must be submitted by MEP to PHMSA,
b. For pipeline operations, MEP must run:
i. ILI initially within 3 years of operating at the alternative MAOP and
on a maximum 5 year interval thereafter. Anomalies must be evaluated
and remediated based upon alternative MAOP or MAOP conditions,
ii. Conduct close interval surveys (CIS) and remediate pipe in each
pipeline segment in accordance with 49 CFR Part 192 on a periodic
basis, not to exceed 3 months of running ILI tools
ili. MEP must operate in accordance with the "interim guidelines of this
document" until PHMSA has developed "go-forward" guidance on
expanded pipe removals based upon technical input from research and
industry. If the PHMSA technical and safety evaluation of pipe
expansion issues results in "go-forward" guidance that differs from
the requirements above, MEP must implement the PHMSA "go-

<<<PAGE 6>>>

6
forward" guidance for the alternative MAOP or MAOP pipeline
segments.
8. For expanded pipe only not meeting 49 CFR Part 192.105 and special permit
requirements, implement enhanced corrosion anomaly response and repair criteria:
a. Anomaly Response Time: Repair Immediately
• Any anomaly within a pipeline segment operating up to 80% SMYS with
either: (1) a failure pressure ratio (FPR) equal to or less than 1.15; (2) an
anomaly depth equal to or greater than 50% wall thickness loss.
• Any anomaly within a pipeline segment operating up to 72% SMYS with
either: (1) a failure pressure ratio (FPR) equal to or less than 1.25; (2) an
anomaly depth equal to or greater than 50% wall thickness loss.
• Any anomaly within a pipeline segment operating up to 60% SMYS with
either: (1) an FPR equal to or less than 1.40; (2) an anomaly depth equal to
or greater than 50% wall thickness loss.
• Any anomaly within a pipeline segment operating up to 50% SMYS with
either: (1) an FPR equal to or less than 1.5; (2) an anomaly depth equal to
or greater than 50% wall thickness loss.
b. Anomaly Response Time: Repair Within One Year
• Any anomaly within a pipeline segment operating at up to 80% SMYS
with either: (1) an FPR equal to or less than 1.25; (2) an anomaly depth
equal to or greater than 40% wall thickness loss.
• Any anomaly within a pipeline segment operating at up to 72% SMYS
with either: (1) an FPR equal to or less than 1.39; (2) an anomaly depth
equal to or greater than 40% wall thickness loss.
• Any anomaly within a pipeline segment operating at up to 60% SMYS
with either: (1) an FPR equal to or less than 1.67; (2) an anomaly depth
equal to or greater than 40% wall thickness loss.
• Any anomaly within a pipeline segment operating at up 50% SMYS with
either: (1) an FPR equal to or less than 2.0; (2) an anomaly depth equal to
or greater than 40% wall thickness loss.
c. Anomaly Assessment Methods:
• MEP must use the most conservative anomaly repair method and take into
count a lowest pipe proponyes basell pon in a algoro ton,
steel source, pipe manufacturer, wall thickness, and grade.
9. MEP must review and document all areas along the pipeline to ensure pipe loadings
at all crossings meet combined stress limits for all equipment, farm machinery, roads,
highways, and railroads to maintain Special Permit design factors based upon the
lowest pipe strengths for that pipe grade, wall thickness, design factor, maximum
loadings, and depth of cover. MEP must add a provision in its Operations and
Maintenance Manual for annual reviews to account for combined stresses.
10. MEP's Operations and Maintenance Procedures must include the interim guidelines
of this document within three months of operating at the alternative MAOP. Submit
and must be certified by an officer of MEP to the PHMSA, Director of Engineering
Directors.
and Emergency Support and the PHMSA Southern and Southwestern Regional
- **truncated:** false
- **body characters:** 15016
