{"operation":"document","citation":"ARSD 20:10:37:18","title":"20:10:37:18 Notice requirements for transmission line construction","source_type":"regulation","agency":"South Dakota Public Utilities Commission","status":"current","official":true,"published_on":null,"effective_on":"2024-05-06","summary":"Notice requirements for transmission line construction. Each transmission pipeline operator within the jurisdiction of the pipeline safety program shall, prior to the construction of a new transmission line, or a relocation or replacement of a transmission line as defined in 49 C.F.R. Part 192 (July 1, 2023):\n\n(1) Submit the information below to the commission's pipeline safety program no later than sixty days pr","machine_formats":{"json":"https://regulus.evalyn.ai/document/sd-arsd-20-10-37-18.json","markdown":"https://regulus.evalyn.ai/document/sd-arsd-20-10-37-18.md"},"app_url":"https://regulus.evalyn.ai/document/sd-arsd-20-10-37-18","source_url":"https://sdlegislature.gov/Rules/Administrative/20%3A10%3A37%3A18","body":"Each transmission pipeline operator within the jurisdiction of the pipeline safety program shall, prior to the construction of a new transmission line, or a relocation or replacement of a transmission line as defined in 49 C.F.R. Part 192 (July 1, 2023):\n\n(1) Submit the information below to the commission's pipeline safety program no later than sixty days prior to the commencement of construction, relocation, or replacement:\n\n(a) Pipeline operator's name and mailing address;\n\n(b) Estimated dates construction is scheduled to begin and end;\n\n(c) Map showing the location and proposed route of pipeline;\n\n(d) Identified gas transmission Integrity Management Program high consequence area, if applicable;\n\n(e) Proposed steel pipeline specifications, including size, weight, grade, wall thickness, and coating;\n\n(f) Proposed plastic pipe specifications, including size and Standard Dimension Ratio;\n\n(g) Proposed design and maximum allowable operating pressure of pipeline;\n\n(h) Pressure test procedures and method of pressure test prior to operations;\n\n(i) Proposed type of cathodic protection;\n\n(j) Minimum burial depths of pipeline at time of construction;\n\n(k) Proposed location and type of pipeline safety equipment;\n\n(l) Proposed type of highway and water crossing, such as whether it will be bored and cased, bored only, or trenched;\n\n(m) Written construction procedures;\n\n(n) Name of construction company if known at the time of filing the Notice; and\n\n(o) Pipeline operator's contact name and phone number;\n\n(2) In the event of an emergency, as defined in the pipeline operator's operations manual, give telephonic notice of emergency construction, relocation, or replacement to the commission's pipeline safety program;\n\n(3) Submit significant construction modifications to the pipeline safety program; and\n\n(4) Submit the information below to the commission's pipeline safety program no later than sixty days prior to the commencement of operation:\n\n(a) Operation and maintenance manual;\n\n(b) Emergency procedures;\n\n(c) Anti-drug and alcohol plan;\n\n(d) Public Awareness plan;\n\n(e) Damage prevention program;\n\n(f) Abnormal operations;\n\n(g) Operator's qualification plan; and\n\n(h) Integrity Management Plan.","truncated":false,"body_characters":2217}