# New Construction Commencement Report

- **operation:** document
- **citation:** 16 TAC § 8.115
- **title:** New Construction Commencement Report
- **source type:** regulation
- **agency:** Railroad Commission of Texas
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** 2024-12-09
- **summary:** (a) An operator shall notify the Commission before the construction of pipelines and other facilities as follows. (1) For construction of a new, relocated, or replacement pipeline 10 miles in length or longer including liquified petroleum gas distribution systems, natural gas distribution systems, a
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/tx-tac-16-8-115.json
- **markdown:** https://regulus.evalyn.ai/document/tx-tac-16-8-115.md
- **app url:** https://regulus.evalyn.ai/document/tx-tac-16-8-115
- **source url:** https://texas-sos.appianportalsgov.com/rules-and-meetings?chapter=8&interface=VIEW_TAC&part=1&title=16
**body:**

(a) An operator shall notify the Commission before the
construction of pipelines and other facilities as follows.
(1) For construction of a new, relocated, or replacement
pipeline 10 miles in length or longer including liquified
petroleum gas distribution systems, natural gas distribution
systems, and master meter systems 10 miles in length or
longer, an operator shall notify the Commission not later
than 60 days before construction.
(2) For construction of a new LNG plant or LNG facility,
an operator shall notify the Commission not later than 60
days before construction.

(3) Except as provided in paragraphs (5) and (6) of this
subsection, for construction of a new, relocated, or
replacement pipeline at least one mile in length but less than
10 miles, an operator shall notify the Commission not later
than 30 days before construction.
(4) For installation of any permanent breakout tank, an
operator shall notify the Commission not later than 30 days
before installation. For installation of mobile, temporary, or
prefabricated breakout tanks, an operator shall notify the
Commission upon placing the mobile, temporary, or
prefabricated breakout tank in service.
(5) For new, relocated, or replacement construction on
liquified petroleum gas distribution systems, natural gas
distribution systems, or master meter systems less than three
miles in length, no construction notification is required
unless new construction results in a new distribution system
ID. If the construction results in a new distribution system
ID, the operator shall either:
(A) notify the Commission not later than 30 days before
construction by filing a Form PS-48 New Construction
Report for every initial construction; or
(B) provide to the Commission a monthly report that
reflects all known projects planned to be completed in the
following 12 months, all projects that are currently in
construction, and all projects completed since the prior
monthly report. The report should provide the status of each
project, the city and county of each project, a description of
each project, and the estimated starting and ending date.
These monthly reports shall be filed by email to PS-
48Reports@rrc.texas.gov.
(6) For new, relocated, or replacement construction on
liquified petroleum gas distribution systems, natural gas
distribution systems, or master meter systems at least three
miles in length but less than 10 miles in length, an operator
shall either:
(A) notify the Commission not later than 30 days before
construction by filing a Form PS-48 New Construction
Report for every relocated or replacement construction; or
(B) provide to the Commission a monthly report that
reflects all known projects planned to be completed in the
following 12 months, all projects that are currently in
construction, and all projects completed since the prior
monthly report. The report should provide the status of each
project, the city and county of each project, a description of
each project, and the estimated starting and ending date.
These monthly reports shall be filed by email to PS-
48Reports@rrc.texas.gov.
(7) For construction of a sour gas pipeline and/or pipeline
facilities, as defined in §3.106 of this title (relating to Sour
Gas Pipeline Facility Construction Permit), an operator shall
notify the Commission not later than 30 days before
construction by filing Form PS-48 and Form PS-79.
(8) Pipelines subject to §8.110(a)(2) and (3) of this title
(relating to Gathering Pipelines) are exempt from the
construction notification requirement.
(b) Any of the notifications required by subsection (a) of
this section, unless an operator elects to use the alternative
notification allowed by subsection (a)(5) or (a)(6) of this
section, shall be made by filing a Form PS-48 New
Construction Report using the Commission's online
application available on the Commission's website. The
report shall include the proposed originating and terminating
points for the pipeline, counties to be traversed, size and type
of pipe to be used, type of service, design pressure, and
length of the proposed line. If a notification is not feasible

because of an emergency, an operator must notify the
Commission as soon as practicable. A Form PS-48 that has
been filed with the Commission shall expire if construction
is not commenced within eight months of date the report is
filed. An operator may submit one extension, which will
keep the report active for an additional six months. Extension
requests shall be made by emailing PS-
48Reports@rrc.texas.gov. After one extension, the Form PS-
48 will expire.
- **truncated:** false
- **body characters:** 4587