# PSC 133.06 Commission procedure.

- **operation:** document
- **citation:** Wis. Admin. Code § PSC 133.06
- **title:** PSC 133.06 Commission procedure.
- **source type:** regulation
- **agency:** Public Service Commission of Wisconsin
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** 2007-11-01
- **summary:** Complete current PSC 133.06 from official Wisconsin Legislature sources (pipeline-construction-and-siting).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/wi-psc-133-06.json
- **markdown:** https://regulus.evalyn.ai/document/wi-psc-133-06.md
- **app url:** https://regulus.evalyn.ai/document/wi-psc-133-06
- **source url:** https://docs.legis.wisconsin.gov/document/administrativecode/PSC%20133.06
**body:**

PSC 133.06 Commission procedure.

(1) Hearing requirements. The commission is not required to hold a hearing on a gas public utility application for a certificate of authority unless any of the following apply:

(a) The application proposes a change in the type of gas or proposes the construction, installation, or the placing in operation of plant that contemplate a change in the type of gas.

(b) The application is treated as a contested case.

(c) The proposed project requires the preparation of an environmental impact statement under s. 1.11, Stats.

(d) The commission determines that a hearing is necessary.

(2) Commission authority. The commission may grant or deny an application in whole or in part, subject to any modification or condition the general public interest or public convenience and necessity may require.