View source (a) Each operator shall maintain relevant portions of its response plan at the following locations:
(1) The response plan at the operator's headquarters;
(2) The core plan and relevant response zone appendices for each line section whose pressure may be affected by the operation of a particular pump station, at that pump station; and
(3) The core plan and relevant response zone appendices at any other locations where response activities may be conducted.
(b) Each operator shall provide a copy of its response plan to each qualified individual.