Mich. Admin. Code R 460.20315
Leaks occurring during uprating; repairs and monitoring required
Snapshot 2026-05-04 Government source
Michigan Public Service CommissionOfficial agency material
View source Rule 315. (1) In addition to the requirements contained in 49 C.F.R. §192.553, which is adopted by reference in R 460.20606, if the new and higher maximum allowable operating pressure will be more than 10 psig, then an operator shall expose and repair and monitor a leak that is detected during the uprating operation.
(2) An operator shall file a complete copy of the written plan described in 49 C.F.R. §192.553(c), which is adopted by reference in R 460.20606, with the commission not less than 30 calendar days before commencement of a project.
History: 1998-2000 AACS; 2014 AACS.