49 CFR 179.5
Certificate of construction.
(a) Except as provided in paragraph (b) of this section, before a tank car is placed in service, the party assembling the completed car shall furnish a Certificate of Construction, Form AAR 4-2 to the owner, the Bureau of Explosives (as required by § 179.5(d)), and the Secretary, Mechanical Division, AAR, certifying that the tank, equipment, and car completed comply with all the requirements of the specification.
(b) Before a tank of Class DOT-106A, 107A, or 110A is placed in service, the builder must furnish a Certificate of Construction, Form AAR 4-2 to the owner, the Bureau of Explosives (as required by paragraph (d) of this section), and the Secretary, Mechanical Division, AAR, in addition to a Certificate of Inspector's Report as required in § 179.300-20 and § 179.500-18 in prescribed form certifying that the tank and appurtenances comply with all the requirements of the specifications.
(c) If the owner elects to furnish the appurtenances such as valves and safety devices, the owner shall furnish to the Bureau of Explosives, and to the Secretary, Mechanical Division, AAR, a report in prescribed form, certifying that the appurtenances comply with all the requirements of the specifications.
(d) When cars or tanks which are covered on one application and are identical in all details are built in series, one certificate shall suffice for each series when submitted to the Secretary. One copy of the Certificate of Construction must be furnished to the Bureau of Explosives for each car number of consecutively numbered group or groups covered by the original application.
[Amdt. 179-10, 36 FR 21344, Nov. 6, 1971]