49 CFR 192.721
Distribution systems: Patrolling.
(a)The frequency of patrolling mains must be determined by the severity of the conditions which could cause failure or leakage, and the consequent hazards to public safety.#
(b)Mains in places or on structures where anticipated physical movement or external loading could cause failure or leakage must be patrolled—#
(1)In business districts, at intervals not exceeding 4 1/2 months, but at least four times each calendar year; and#
(2)Outside business districts, at intervals not exceeding 7 1/2 months, but at least twice each calendar year.#