NTSB safety recommendation P-74-007.
THE NTSB RECOMMENDS THAT THE UGI CORPORATION: INITIATE MORE CONTROLLING INSPECTION PROCEDURES ON CONSTRUCTION PROJECTS IN THE VICINITY OF ALL GAS FACILITIES. WHERE THESE PROJECTS INVOLVE BLASTING, THE UGI INSPECTOR SHOULD OBSERVE THE SHOT HOLE LOADINGS AND OBTAIN A COPY OF THE BLASTER'S "DIARY" FOR UGI RECORDS.
Priority: CLASS II
Overall Status: Closed - Acceptable Action
Issued Date: 1974-02-07
Adopted Date: 1974-02-07
Overall Date Closed: 1976-09-10
Synopsis: IN COOPERSBURG, PA., ON FEBRUARY 21, 1973, A GAS PIPELINE WAS RUPTURED BY DYNAMITE AND GAS AT 50 PSIG ENTERED AN APARTMENT HOUSE AND EXPLODED. FIVE PERSONS WERE KILLED, 16 PERSONS WERE INJURED, AND 2 BUILDINGS WERE DESTROYED.
Ntsbnumber: PLD73XR003
Report Number: PAR-74-01
Addressee Name: UGI Corporation
Addressee Status: Closed--No Longer Applicable
Addressee Date Closed: 1976-09-10
Addressee Organization Type: P-Private Industry
Communication Date: 1974-12-31
Communication Type: Official Correspondence
Communication Contents: LETTER FROM UGI CORPORATION: OUR PEOPLE ARE INSTRUCTED TO OBSERVE THAT BLASTING IS CARRIED OUT IN ACCORDANCE WITH THE PENNSYLVANIA DER TITLE 25 REGULATIONS. CORRESPONDENCE DOCUMENTATION INCOMPLETE.