P-80-021
P-80-021
NTSB safety recommendation P-80-021.
THE NTSB RECOMMENDS THAT THE SHELL OIL COMPANY: REQUIRE THAT A SURVEYOR BE ON LOCATION TO DIRECT ANY CHANGES IN ANCHOR POSITION WHICH MAY EXCEED THE ESTABLISHED MARGIN OF SAFETY.
Priority: CLASS II
Overall Status: Closed - Acceptable Action
Issued Date: 1980-03-13
Adopted Date: 1980-02-21
Overall Date Closed: 1983-05-17
Synopsis: ON JULY 15, 1979, 95 MILES SOUTHEAST OF NEW ORLEANS, LOUISIANA, ON THE OUTER CONTINENTAL SHELF (OCS) IN SHELL OIL COMPANY'S (SHELL) SOUTH PASS, BLOCK 62, FIELD, A 14-INCH SOUTHERN NATURAL GAS COMPANY TRANSMISSION LINE OPERATING AT A PRESSURE OF 900 PSIG WAS SNAGGED AND RUPTURED BY A GRAPPLING HOOK FROM THE ANCHOR-HANDLING VESSEL PETE TIDE II, WHILE THE VESSEL WAS GRAPPLING FOR AN ANCHOR PENDANT FROM THE SEMI SUBMERSIBLE DRILLING RIG OCEAN QUEEN. THE RESULTING EXPLOSION AND FIRE CAUSED THE DEATH OF TWO PERSONS AND INJURIES TO FOUR OTHERS. DAMAGE TOTALED OVER $1,500,000.
Probable Cause: None
Ntsbnumber: DCA79MP023
Report Number: PAR-80-01
Addressee Name: Shell Oil Company
Addressee Status: Closed--No Longer Applicable
Addressee Date Closed: 1983-05-17
Addressee Organization Type: P-Private Industry
Communication Date: 1982-10-18
Communication Type: Official Correspondence
Communication Contents: SHELL OIL COMPANY LETTER: A SURVEY CREW IS REQUESTED TO INITIALLY SET OUT OR MAKE ANY SUBSEQUENT MOVEMENT OF ANCHORS ARE PLACED WITHIN 500 FEET OF A HAZARD.
Addressee Organization Type: P-Private Industry
Communication Date: 1983-05-17
Communication Type: Official Correspondence
Addressee Organization Type: P-Private Industry
Communication Date: 1982-10-08
Communication Type: Official Correspondence
This material provides agency context. It does not replace binding regulatory text, and its legal effect depends on the underlying authority and facts.