PHMSA GT.2023.01
PHMSA GT.2023.01
AR.RCOMprocedurePage 1AR.RCOM.NONCOVERED.POfficial PDFDoes the integrity assessment and maintenance processes include adequate criteria for determining the need for, and timeliness of, pipeline defect repairs in non-covered segments? References: 192.485(a), 192.485(b), 192.485(c), 192.703(b), 192.710, 192.711, 192.713#
AR.RCOMrecordPage 1AR.RCOM.NONCOVERED.RRepair Criteria in Non-Covered Segments From the review of the results of integrity assessments, did the operator repair conditions that posed a threat to pipeline integrity on Non-Covered segments? References: 192.485(a), 192.485(b), 192.485(c), 191.23(a)(1), 192.703(b), 192.710, 192.711, 192.713#
AR.RCOMobservationPage 1AR.RCOM.REMEDIATIONOM.OIs anomaly remediation and documentation of remediation adequate for all segments? References: 192.485(a), 192.485(b), 192.485(c), 192.710, 192.711, 192.713#
AR.RCOMprocedurePage 1AR.RCOM.RCAMAOP.PIf the pipeline operates using an alternative maximum allowable operating pressure per 192.620 (80% SMYS Rule), do the processes meet the requirements of the permit or 192.620? References: 192.620(d)#
AR.RCOMrecordPage 1AR.RCOM.RCAMAOP.RIf the pipeline operates using an alternative maximum allowable operating pressure per 192.620 (80% SMYS Rule), from a review of selected records, were required repairs performed? References: 192.620(d)#
AR.CDAprocedurePage 1AR.CDA.CDAREVQUAL.PWho Evaluate CDA Results Does the process require that operator/vendor personnel (including supervisors) who review and evaluate CDA assessment results meet appropriate training, experience, and qualification criteria? References: 192.915(a), 192.915(b)#
AR.CDArecordPage 1AR.CDA.CDAREVQUAL.RWho Evaluate CDA Results Do records demonstrate that operator/vendor personnel, including supervisors, who conduct assessments or review assessment results, are qualified for the tasks they perform? References: 192.947(h), 192.915(a), 192.915(b)#
AR.CDAobservationPage 2AR.CDA.CDAREVQUAL.OWho Evaluate CDA Results From the observation of selected integrity assessments, are operator and vendor personnel, including supervisors, who conduct assessments or review assessment results, qualified for the tasks they perform? References: 192.915(a), 192.915(b)#
AR.CDAprocedurePage 2AR.CDA.CDAPLAN.PIs an adequate Confirmatory Direct Assessment Plan in place? References: 192.931(a), 192.931(b), 192.931(c), 192.931(d)#
AR.CDArecordPage 2AR.CDA.CDAEXTCORR.RDo records indicate that the external corrosion plan was properly implemented? References: 192.947(h), 192.931(b)#
AR.CDArecordPage 2AR.CDA.CDAINTCORR.RDo records demonstrate that the internal corrosion plan was properly implemented? References: 192.947(h), 192.931(c)#
AR.CDArecordPage 2AR.CDA.CDAINDICATION.RDo records demonstrate that the next assessment should have been accelerated? References: 192.947(h), 192.931(d)#
AR.CDAprocedurePage 2AR.CDA.CDACORR.PDoes the process adequately account for taking required actions to address significant corrosion threats identified using confirmatory direct assessment? References: 192.933, 192.917(e)(5)#
AR.CDArecordPage 2AR.CDA.CDACORR.RDo records demonstrate that required actions are being taken to address significant corrosion threats identified by CDA as required? References: 192.933, 192.917(e)(5)#
AR.ECprocedurePage 2AR.EC.ECDAREVQUAL.PWho Evaluate ECDA Results Does the process require that operator/vendor personnel (including supervisors) who review and evaluate ECDA assessment results meet appropriate training, experience, and qualification criteria? References: 192.915(a), 192.915(b)#
AR.ECrecordPage 3AR.EC.ECDAPREASSESS.RDo records demonstrate that the ECDA pre-assessment process complied with NACE SP0502- 2010 Section 3 and 192.925(b)(1)? References: 192.947(g), 192.925(b)(1)#
AR.ECrecordPage 3AR.EC.ECDAREVQUAL.RWho Evaluate ECDA Results Do records demonstrate that operator/vendor personnel, including supervisors, who conduct ECDA assessments or review and analyze assessment results are qualified for the tasks they perform? References: 192.947(g), 192.915(a), 192.915(b)#
AR.ECobservationPage 3AR.EC.ECDAREVQUAL.OWho Evaluate ECDA Results From the observation of selected integrity assessments, are operator and vendor personnel, including supervisors, who conduct assessments or review assessment results, qualified for the tasks they perform? References: 192.915(a), 192.915(b)#
AR.ECprocedurePage 3AR.EC.ECDAPLAN.PIs an adequate ECDA plan and process in place for conducting ECDA? References: 192.925(a), 192.925(b)#
AR.ECprocedurePage 3AR.EC.ECDAINTEGRATION.PIs the process for integrating ECDA results with other information adequate? References: 192.917(b)#
AR.ECrecordPage 3AR.EC.ECDAINTEGRATION.RDo records demonstrate that the operator integrated other data/information when evaluating data/results? References: 192.947(g), 192.917(b)#
AR.ECrecordPage 3AR.EC.ECDAREGION.RDo records demonstrate that the operator identified ECDA Regions? References: 192.947(g), 192.925(b)(1)#
AR.ECrecordPage 3AR.EC.ECDAINDIRECT.RDo records demonstrate that ECDA indirect inspection process complied with NACE SP 0502-2010 Section 4 and ASME B31.8S-2004, Section 6.4? References: 192.947(g), 192.925(b)(2)#
AR.ECrecordPage 3AR.EC.ECDADIRECT.RDo records demonstrate that excavations, direct examinations, and data collection were performed in accordance with NACE SP 0502-2010, Sections 5 and 6.4.2 and ASME B31.8S-2004, Section 6.4? References: 192.947(g), 192.925(b)(3)#
AR.ECobservationPage 4AR.EC.ECDADIRECT.OECDA Direct Examination Were ECDA direct examinations adequately conducted? References: 192.925(b)(3)#
AR.ECrecordPage 4AR.EC.ECDAANALYSIS.RDo records demonstrate that an analysis of the ECDA data and other information was adequate to identify areas where external corrosion activity is most likely? References: 192.947(g), 192.925(b)(4), 192.933(b)#
AR.ECprocedurePage 4AR.EC.ECDAPLANMOC.PHave criteria and internal notification processes been established and implemented for any changes in the ECDA plan? References: 192.947(g), 192.925(b)(3)(iii), 192.911(k)#
AR.ECrecordPage 4AR.EC.ECDAPLANMOC.RDo records demonstrate that changes in the ECDA plan have been implemented and documented? References: 192.947(g), 192.925(b)(3)(iii)#
AR.ECrecordPage 4AR.EC.ECDAPOSTASSESS.RDo records demonstrate that the requirements for post-assessment were met? References: 192.947(g), 192.925(b)(4)#
AR.ECrecordPage 4AR.EC.ECDAMAOP.RIf ECDA was performed on segments (as allowed by §192.620(d)(9)(iii)), were all ECDA assessment requirements completed? References: 192.947(g), 192.620(d)(9)(iii), 192.620(d)(10)(i), 192.620(d)(10)(iii)#
AR.ECobservationPage 4AR.EC.ECDAMAOP.OIf ECDA was performed on segments (as allowed by §192.620(d)(9)(iii)), were all ECDA assessment requirements completed? References: 192.620(d)(9)(iii), 192.620(d)(10)(i), 192.620(d)(10)(iii)#
AR.ECprocedurePage 4AR.EC.ECCORR.PDoes the process adequately account for taking required actions to address significant external corrosion threats? References: 192.933, 192.917(e)(5)#
AR.ECrecordPage 4AR.EC.ECCORR.RDo records demonstrate that required actions are being taken to address significant external corrosion threats as required? References: 192.933, 192.917(e)(5)#
AR.ICprocedurePage 5AR.IC.ICDAREVQUAL.PWho Evaluate ICDA Results Does the process require that operator/vendor personnel (including supervisors) who review and evaluate ICDA assessment results meet appropriate training, experience, and qualification criteria? References: 192.915(a), 192.915(b)#
AR.ICrecordPage 5AR.IC.ICDAREVQUAL.RWho Evaluate ICDA Results Do records demonstrate that operator/vendor personnel, including supervisors, who conduct ICDA assessments or review and analyze assessment results, are qualified for the tasks they perform? References: 192.947(g), 192.915(a), 192.915(b)#
AR.ICobservationPage 5AR.IC.ICDAREVQUAL.OWho Evaluate ICDA Results From the observation of selected integrity assessments, are operator and vendor personnel, including supervisors, who conduct assessments or review assessment results, qualified for the tasks they perform? References: 192.915(a), 192.915(b)#
AR.ICprocedurePage 5AR.IC.ICDAPLAN.PIs an ICDA plan and process in place for conducting ICDA? References: 192.927(c), 192.927(a), 192.927(b)#
AR.ICrecordPage 5AR.IC.ICDAPREASSESS.RDo records demonstrate that the requirements for an ICDA pre-assessment were met? References: 192.927(c)(1), 192.947(g)#
AR.ICprocedurePage 5AR.IC.ICDAINTEGRATION.PIs the process for integrating ICDA results with other information adequate? References: 192.917(b)#
AR.ICrecordPage 5AR.IC.ICDAINTEGRATION.RDo records demonstrate that other data/information was integrated when evaluating data/results? References: 192.917(b), 192.947(g)#
AR.ICrecordPage 5AR.IC.ICDAREGION.RDo records demonstrate that ICDA Regions were adequately identified? References: 192.947(g), 192.927(c)(2), 192.927(c)(5)#
AR.ICrecordPage 5AR.IC.ICDADIRECT.RDo records demonstrate that sites were identified where internal corrosion may be present? References: 192.947(g), 192.927(c)(3), 192.927(c)(5)#
AR.ICrecordPage 6AR.IC.ICDAPOSTASSESS.RDo records demonstrate that the operator assessed the effectiveness of the ICDA process? References: 192.947(g), 192.927(c)(4)(i), 192.927(c)(4)(ii), 192.477#
AR.ICrecordPage 6AR.IC.ICDAANALYSIS.RDo records demonstrate that sufficient data was used to complete the ICDA analysis to identify the internal corrosion threats to the pipeline? References: 192.947(g), 192.927(c), 192.933(b)#
AR.ICrecordPage 6AR.IC.ICDAMAOP.RIf the pipeline is operated using an alternative maximum allowable operating pressure per 192.620 (80% SMYS Rule) were required ICDA assessments performed? References: 192.947(g), 192.620(d)(9), 192.620(d)(10), 192.927#
AR.ICprocedurePage 6AR.IC.ICCORR.PDoes the process adequately account for taking required actions to address significant internal corrosion threats related to internal corrosion? References: 192.933, 192.917(e)(5)#
AR.ICrecordPage 6AR.IC.ICCORR.RDo records demonstrate that required actions are being taken to address significant internal corrosion threats as required? References: 192.933, 192.917(e)(5)#
AR.SCCprocedurePage 6AR.SCC.SCCDAREVQUAL.PWho Evaluate SCCDA Results Does the process require that operator/vendor personnel (including supervisors) who review and evaluate SCCDA assessment results meet appropriate training, experience, and qualification criteria? References: 192.915(a), 192.915(b)#
AR.SCCrecordPage 6AR.SCC.SCCDAREVQUAL.RWho Evaluate SCCDA Results Do records demonstrate that operator/vendor personnel, including supervisors, who conduct assessments or review assessment results, are qualified for the tasks they perform? References: 192.947(e), 192.915(a), 192.915(b)#
AR.SCCobservationPage 6AR.SCC.SCCDAREVQUAL.OWho Evaluate SCCDA Results From the observation of selected integrity assessments, are operator and vendor personnel, including supervisors, who conduct assessments or review assessment results, qualified for the tasks they perform? References: 192.915(a), 192.915(b)#
AR.SCCprocedurePage 7AR.SCC.SCCDAPLAN.PIs an adequate plan developed for performing SCCDA, if the conditions for SCC were present? References: 192.929(b)#
AR.SCCrecordPage 7AR.SCC.SCCDADATA.RDo records demonstrate that data was collected and evaluated? References: 192.947(g), 192.929(b)(1)#
AR.SCCrecordPage 7AR.SCC.SCCDAMETHOD.RDo records demonstrate that an assessment was performed using one of the methods specified in ASME B31.8S-2004 Appendix A3? References: 192.947(g), 192.929(b)(2)#
AR.SCCobservationPage 7AR.SCC.SCCDAMETHOD.OAssessment Method (High pH SCC) From field observations, was SCCDA performed in accordance with 192.929 and the SCCDA plan? References: 192.929#
AR.SCCrecordPage 7AR.SCC.SCCDANEARNEUTRAL.RAssessing for Near Neutral SCC From the review of the results of selected integrity assessments, was the pipeline evaluated for near neutral SCC? References: 192.947(g), 192.929(b)(2)#
AR.SCCrecordPage 7AR.SCC.SCCDAREASSESSINTRVL.RReassessment Interval From the review of the results of selected integrity assessments, did the operator determine a reassessment interval based on SCCDA results? References: 192.947(d), 192.939(a)(3)#
AR.SCCrecordPage 7AR.SCC.SCCDAAMAOP.RIf the pipeline operates using an alternative maximum allowable operating pressure per 192.620 (80% SMYS Rule), from a review of selected records, were required SCCDA assessments performed? References: 192.620(d), 192.620(d)(9), 192.620(d)(10)#
AR.SCCprocedurePage 7AR.SCC.SCCCORR.PDoes the process adequately account for taking required actions to address significant corrosion threats found following SCCDA? References: 192.933, 192.917(e)(5)#
AR.SCCrecordPage 7AR.SCC.SCCCORR.RDo records demonstrate that required actions are being taken to address significant corrosion threats as required following SCCDA? References: 192.933, 192.917(e)(5)#
AR.ILprocedurePage 8AR.IL.ILIREVIEWQUAL.PWho Evaluate ILI Results Does the process require that operator/vendor personnel (including supervisors) who review and evaluate ILI assessment results meet appropriate training, experience, and qualification criteria? References: 192.915(a), 192.915(b), 192.493#
AR.ILrecordPage 8AR.IL.ILIREVIEWQUAL.RWho Evaluate ILI Results Do records demonstrate that personnel who conduct assessments or review assessment results are qualified per the process requirements? References: 192.947(g), 192.915(a), 192.915(b), 192.493#
AR.ILobservationPage 8AR.IL.ILIREVIEWQUAL.OWho Evaluate ILI Results From the observation of selected integrity assessments, are operator and vendor personnel, including supervisors, who conduct assessments or review assessment results, qualified for the tasks they perform? References: 192.915(a), 192.915(b), 192.493#
AR.ILprocedurePage 8AR.IL.ILISPECS.PDoes the process assure complete and adequate vendor ILI specifications? References: 192.921(a)(1), 192.933(b), 192.493, 192.18#
AR.ILrecordPage 8AR.IL.ILISPECS.RDo records demonstrate that the ILI specifications were complete and adequate? References: 192.947(g), 192.933(b), 192.493#
AR.ILprocedurePage 8AR.IL.ASSESSMETHOD.PDoes the process specify the assessment methods that are appropriate for the pipeline specific integrity threats? References: 192.919(b), 192.921(a), 192.937(c), 192.917, 192.493, 192.506#
AR.ILrecordPage 8AR.IL.ASSESSMETHOD.RDo records demonstrate that the assessment methods shown in the baseline and/or continual assessment plan were appropriate for the pipeline specific integrity threats? References: 192.947, 192.919(b), 192.921(a), 192.937(c)#
AR.ILprocedurePage 8AR.IL.ILIVALIDATE.PDoes the process for validating ILI results ensure that accurate integrity assessment results are obtained? References: 192.921(a)(1), 192.937(c), 192.493#
AR.ILrecordPage 9AR.IL.ILIVALIDATE.RDo records demonstrate that the operator has validated ILI assessment results per their process? References: 192.947, 192.921(a)(1), 192.493#
AR.ILobservationPage 9AR.IL.ILIVALIDATE.OValidation of ILI Results From observation of field activities, do the employees and vendors validate ILI assessment results per their process? References: 192.921(a)(1), 192.493#
AR.ILprocedurePage 9AR.IL.ILIINTEGRATION.PIs the process for integrating ILI results with other information adequate? References: 192.917(b), 192.493#
AR.ILrecordPage 9AR.IL.ILIINTEGRATION.RDo records demonstrate that the operator integrated other data/information when evaluating tool data/results? References: 192.947, 192.917(b), 192.493#
AR.ILprocedurePage 9AR.IL.ILIACCEPCRITERIA.PIs the process for ILI survey acceptance criteria adequate to assure an effective assessment? References: 192.921(a), 192.493#
AR.ILrecordPage 9AR.IL.ILIACCEPCRITERIA.RDo records indicate adequate implementation of the process for ILI survey acceptance? References: 192.947, 192.921(a), 192.493#
AR.ILrecordPage 9AR.IL.ILIDELAY.RDo records indicate that the performance of integrity assessments has been delayed and integrity assessment delays have been justified? References: 192.947(d), 192.909(a), 192.909(b), 192.943(a), 192.943(b), 190.341, 192.18#
AR.ILprocedurePage 9AR.IL.ILIAMAOP.PAlternative Maximum Allowable Operating Pressure per 192.620 (80% SMYS Rule)? For pipelines operating under AMAOP, do processes implement the ILI requirements of 192.620(d)(9) and (10) for the entire segment? References: 192.620(d), 192.493#
AR.ILrecordPage 9AR.IL.ILIAMAOP.RAlternative Maximum Allowable Operating Pressure per 192.620 (80% SMYS Rule)? For pipelines operating under AMAOP, do records indicate the ILI requirements of 192.620(d)(9) and (10) have been implemented for the entire segment? References: 192.620(d), 192.493#
AR.ILobservationPage 10AR.IL.ILIIMPLEMENT.OAre O&M and IMP procedural requirements for the performance of ILI assessments followed? References: 192.921(a)(1), 192.620(d), 192.605(b), 192.493#
AR.ILprocedurePage 10AR.IL.ILCORR.PDoes the process adequately account for taking required actions to address significant corrosion threats identified during in-line inspections? References: 192.933, 192.917(e)(5)#
AR.ILrecordPage 10AR.IL.ILCORR.RDo records demonstrate that required actions are being taken to address significant corrosion threats identified during in-line inspections? References: 192.933, 192.917(e)(5)#
AR.LSRprocedurePage 10AR.LSR.LSRPLAN.PIs the process for performing low stress reassessment adequate? References: 192.941(a), 192.941(b), 192.941(c)#
AR.LSRrecordPage 10AR.LSR.LSRBA.RDo records demonstrate that a baseline assessment meeting the requirements of 192.919 and 192.921 was performed prior to performing a low stress reassessment? References: 192.947(d), 192.919(c), 192.921(d), 192.941(a), 192.506#
AR.LSRrecordPage 10AR.LSR.LSREXTCORR.RDo records demonstrate that the requirements of §192.941(b) were implemented when performing low stress reassessment for external corrosion? References: 192.947(d), 192.941(b)#
AR.LSRrecordPage 10AR.LSR.LSRINTCORR.RDo records demonstrate that the requirements of §192.941(c) were implemented when performing low stress reassessment for internal corrosion? References: 192.947(d), 192.941(c)#
AR.LSRprocedurePage 10AR.LSR.LSRCORR.PDoes the process adequately account for taking required actions to address significant corrosion threats following a LSR? References: 192.933, 192.917(e)(5)#
AR.LSRrecordPage 10AR.LSR.LSRCORR.RDo records demonstrate that required actions are being taken to address significant corrosion threats as required following a LSR? References: 192.933, 192.917(e)(5)#
AR.PTIprocedurePage 11AR.PTI.PRESSTESTREVQUAL.PWho Evaluate Pressure Test Results Does the process require that operator/vendor personnel (including supervisors) who review and evaluate pressure test assessment results meet appropriate training, experience, and qualification criteria? References: 192.915(a), 192.915(b), 192.921(a)(4)#
AR.PTIrecordPage 11AR.PTI.PRESSTESTREVQUAL.RWho Evaluate Pressure Test Results Do records demonstrate that operator/vendor personnel, including supervisors, who conduct or review pressure test assessment results are qualified for the tasks they perform? References: 192.947(g), 192.915(a), 192.915(b)#
AR.PTIprocedurePage 11AR.PTI.PRESSTESTACCEP.PTest Acceptance Criteria and Procedures Were test acceptance criteria and processes sufficient to assure the basis for an References: 192.503(a), 192.503(b), 192.503(c), 192.503(d), 192.505(a), 192.505(b), 192.505(c), 192.505(d), 192.507(a), 192.507(b), 192.507(c), 192.513(a), 192.51#
AR.PTIrecordPage 11AR.PTI.PRESSTESTRESULT.RDo the test records validate the pressure test? References: 192.517(a), 192.505(a), 192.505(b), 192.505(c), 192.505(d), 192.507(a), 192.507(b), 192.507(c), 192.513(a), 192.513(b), 192.513(c), 192.513(d), 192.51#
AR.PTIrecordPage 11AR.PTI.PRESSTESTAMAOP.RIf the pipeline operates using an alternative maximum allowable operating pressure per 192.620 (80% SMYS Rule), from a review of selected records, were required pressure test assessments performed? References: 192.517(a), 192.505(a), 192.517(b), 192.620(c)(4), 192.620(d)(9), 192.620(d)(10)#
AR.PTIobservationPage 11AR.PTI.PRESSTESTCOMPLETE.OPressure Test Completion From field operations was the pressure test performed in accordance with Subpart J requirements and References: 192.503(a), 192.503(b), 192.503(c), 192.503(d), 192.505(a), 192.505(b), 192.505(c), 192.505(d), 192.507(a), 192.507(b), 192.507(c), 192.513(a), 192.51#
AR.PTIprocedurePage 11AR.PTI.PTICORR.PDoes the process adequately account for taking required actions to address significant corrosion threats? References: 192.933, 192.917(e)(5)#
AR.PTIrecordPage 11AR.PTI.PTICORR.RDo records demonstrate that required actions are being taken to address significant corrosion threats as required? References: 192.933, 192.917(e)(5)#
AR.PTIprocedurePage 12AR.PTI.SPIKEHYDRO.PDo the procedures for selecting pipeline assessment methods specifically include spike hydrotests as the assessment method for detecting time-dependent threats? References: 192.506(a), 192.505, 192.710(c)(3), 192.921(a)(3)#
AR.PTIrecordPage 12AR.PTI.SPIKEHYDRO.RWhere time-dependent threats were an identified risk, do the records indicate that a spike hydrotest was performed to “clear” any cracks that might otherwise grow during pressure reductions after the hydrostatic test? References: 192.506(a), 192.505, 192.710(c)(3), 192.921(a)(3)#
AR.OTprocedurePage 12AR.OT.OTPLAN.PHas a process been developed for "other technologies" that provide an equivalent understanding of the condition of the pipe? References: 192.921(a)(4), 192.18#
AR.OTrecordPage 12AR.OT.OTPLAN.RDo records demonstrate that the assessments were performed in accordance with the process and vendor recommendations and that defects were identified and categorized within 180 days, if applicable? References: 192.947(d), 192.921(a)(4), 192.933(b)#
AR.OTprocedurePage 12AR.OT.OTREVQUAL.PWho Evaluate Other Technology Results Does the process require that operator/vendor personnel (including supervisors) who review and evaluate assessment results meet acceptable qualification standards? References: 192.915(a), 192.915(b), 192.921(a)(7), 192.493#
AR.OTrecordPage 12AR.OT.OTREVQUAL.RWho Evaluate Other Technology Results Do records demonstrate that operator/vendor personnel, including supervisors, who conduct assessments or review assessment results are qualified for the tasks they perform? References: 192.947(d), 192.915(a), 192.915(b)#
AR.OTobservationPage 12AR.OT.OTREVQUAL.OWho Evaluate Other Technology Results From the observation of selected integrity assessments, are operator and vendor personnel, including supervisors, who conduct assessments or review assessment results, qualified for the tasks they perform? References: 192.915(a), 192.915(b)#
AR.OTobservationPage 12AR.OT.OTPLAN.OOther Technology Were assessments conducted using "other technology" adequately performed in accordance with the OT process? References: 192.921(a)(4)#
AR.OTprocedurePage 13AR.OT.OTCORR.PDoes the process adequately account for taking required actions to address significant corrosion threats identified using Other Technology? References: 192.933, 192.917(e)(5)#
AR.OTrecordPage 13AR.OT.OTCORR.RDo records demonstrate that required actions are being taken to address significant corrosion threats as required following the use of Other Technology? References: 192.933, 192.917(e)(5)#
AR.PFPprocedurePage 13AR.PFP.ANOMALYMETALLOSS.PDo the procedures for evaluating corrosion metal loss anomalies or defects, ensure that a determination of the predicted failure pressure and the remaining life of the pipeline segment is established at the location of each anomaly or defect, in accordance with §192.712? References: 192.712(b), 192.607, 192.712(a), 192.917(b), 192.933(d), 192.485#
AR.PFPprocedurePage 13AR.PFP.ANOMALYCRACKMODEL.PDo the procedures for evaluating cracks and crack like defects ensure that a determination of the predicted failure pressure and the remaining life of the pipeline segment is established at the location of each anomaly or defect, in accordance with §192.712(d)(1)? References: 192.712(d)(1), 192.607, 192.712(a)#
AR.PFPprocedurePage 13AR.PFP.ANOMALYCRACKGROWTH.PDo the procedures detail the performance of fatigue analysis and remaining life calculations for pipeline segments susceptible to cyclic fatigue or other loading conditions that could lead to fatigue crack growth? References: 192.712(d)(2), 192.607#
AR.PFPprocedurePage 13AR.PFP.ANOMALYCRACKSURVIVEPT.PDo procedures call for the calculation of the largest potential crack defect sizes when analyzing potential cracks that could have survived a pressure test, specifically in the absence of any in- line inspection data in accordance with §192.712(d)(3)? References: 192.712(d)(3), 192.607, 192.712(a), 192.712(d)(1)#
AR.PFPprocedurePage 13AR.PFP.ANOMALYDATAUSE.PDo the procedures detail the use of data when performing analyses of predicted or assumed anomalies or defects, in accordance with §192.712(e)? References: 192.712(e), 192.607#
AR.PFPprocedurePage 13AR.PFP.ANOMALYRECORDS.PDo procedures detail the collection, creation and retention of records including all investigations, analyses, and other actions taken in performing analyses of predicted or assumed anomalies or defects, in accordance with §192.712(g)? References: 192.712(g), 192.607#
AR.PFPrecordPage 14AR.PFP.ANOMALYRECORDS.RDo the records capture all investigations, analyses and other actions taken to support the analysis of predicted failure pressure in accordance with §192.712(g)? References: 192.712(g), 192.712(e)#
AR.RCrecordPage 14AR.RC.DEFECTCAT.RDo records demonstrate that all defects were properly categorized? References: 192.947(f), 192.933(b), 192.933(d)#
AR.RCprocedurePage 14AR.RC.DISCOVERY.PDoes the integrity assessment process properly define discovery and the required time frame? References: 192.933(b)#
AR.RCrecordPage 14AR.RC.DISCOVERY.RDo records demonstrate that discovery was declared in the required time frame or justification was documented? References: 192.947(f), 192.933(b)#
AR.RCprocedurePage 14AR.RC.IMPRC.PDoes the Integrity Management Plan and/or maintenance processes include all of the actions that must be taken to address integrity issues in accordance with 192.933? References: 192.933(a), 192.933(c), 192.933(d), 192.18#
AR.RCrecordPage 14AR.RC.PRESSREDUCE.RDo records demonstrate that an acceptable pressure reduction was promptly taken for each immediate repair condition or when a repair schedule could not be met? References: 192.947(f), 192.933(a)(1), 192.18#
AR.RCrecordPage 14AR.RC.SCHEDULE.RDo records demonstrate that a prioritized schedule was developed? References: 192.947(f), 192.933(c)#
AR.RCrecordPage 14AR.RC.METHOD.RDo records demonstrate that the remediation specified in the prioritized schedule was adequate to ensure the integrity of the pipeline until the next scheduled reassessment? References: 192.947(f), 192.933(a)#
AR.RCprocedurePage 15AR.RC.CRITERIA.PDoes the repair process cover all of the elements for making repairs in covered segments? References: 192.711(b), 192.703(a), 192.703(b), 192.703(c), 192.713(a), 192.713(b)#
AR.RCrecordPage 15AR.RC.SCHEDULEIMPL.RDo records demonstrate that defects in covered segments were remediated (i.e., repair, pressure reduction, or notification to PHMSA) within the applicable mandatory time limits of 192.933(d)? References: 192.947(f), 192.933(d)#
AR.RCobservationPage 15AR.RC.REMEDIATION.OIs anomaly remediation adequate for the covered segments being observed? References: 192.933(c), 192.933(a), 192.933(d)#
AR.RCprocedurePage 15AR.RC.LOOKBEYOND.PDoes the process require an evaluation of all pipeline segments with similar environmental and material coating conditions as segments where corrosion that could adversely affect the integrity of the pipeline was found? References: 192.917(e)(5)#
AR.RCrecordPage 15AR.RC.LOOKBEYOND.R"Look Beyond" Evaluation of Significant Corrosion From the review of the results of integrity assessments, were all pipeline segments evaluated with similar environmental and material coating conditions as segments where corrosion that could adversely affect the integrity of the pipeline was found? References: 192.947(b), 192.917(e)(5), 192.459#
AR.RMPprocedurePage 15AR.RMP.SAFETY.PDoes the process ensure that repairs are made in a safe manner and are made so as to prevent damage to persons and property? References: 192.605(b)(9), 192.713(b)#
AR.RMPobservationPage 15AR.RMP.SAFETY.OAre repairs made in a safe manner and to prevent damage to persons and property? References: 192.605(b)(9), 192.713(b)#
AR.RMPprocedurePage 15AR.RMP.IGNITION.PIs there a process for preventing accidental ignition where gas presents a hazard of fire or explosion? References: 192.605(b)(1), 192.751(a), 192.751(b), 192.751(c)#
AR.RMPrecordPage 16AR.RMP.IGNITION.RDo records indicate adequate steps were taken by the operator to prevent accidental ignition prior to performing work? References: 192.751(a), 192.751(b), 192.751(c)#
AR.RMPobservationPage 16AR.RMP.IGNITION.OPrevention of Accidental Ignition Perform observations of selected locations to verify that adequate steps have been taken by the operator to minimize the potential for accidental ignition. References: 192.751(a), 192.751(b), 192.751(c)#
AR.RMPprocedurePage 16AR.RMP.HOTTAP.PIs the process adequate for tapping pipelines under pressure? References: 192.605(b)(1), 192.627#
AR.RMPrecordPage 16AR.RMP.HOTTAP.RTapping Pipelines Under Pressure From a review of selected records, were the personnel who performed pressure taps on pipelines under pressure qualified? References: 192.627#
AR.RMPobservationPage 16AR.RMP.HOTTAP.OTapping Pipelines Under Pressure Were pressure taps on pipelines under pressure performed in accordance with processes by qualified personnel? References: 192.627#
AR.RMPprocedurePage 16AR.RMP.REPAIRREQT.PDoes the repair process capture the requirements of 192.711 for transmission lines? References: 192.605(b)(1), 192.711(a), 192.711(b), 192.711(c), 192.717(b)(3)#
AR.RMPprocedurePage 16AR.RMP.FIELDREPAIRDEFECT.PIs the process adequate for the permanent field repair of defects in transmission lines? References: 192.605(b)(1), 192.713(a), 192.713(b)#
AR.RMPrecordPage 16AR.RMP.METHOD.RPermissible Repair Methods From the review of records, were all repairs performed in accordance with processes, applicable sections of Part 192, the guidance of ASME B31.8S-2004, Section 7, and the Pipeline Repair Manual, Revision 5? References: 192.709(a), 192.713(a), 192.713(b), 192.717(a), 192.717(b)#
AR.RMPrecordPage 16AR.RMP.REPAIRQUAL.RQualification of Personnel Performing Pipeline Repair From the review of selected records, were personnel performing repairs, other than welding, and post repair tests qualified for the task they performed? References: 192.807(b), 192.805(h)#
AR.RMPprocedurePage 17AR.RMP.FIELDREPAIRWELDS.PIs the process adequate for the permanent field repair of welds? References: 192.605(b), 192.715(a), 192.715(b), 192.715(c)#
AR.RMPrecordPage 17AR.RMP.WELDERQUAL.RWelder Qualification From the review of selected records, were repairs requiring welding performed by qualified welders using qualified welding processes? References: 192.225(a), 192.225(b), 192.227(a), 192.227(b), 192.229(a), 192.229(b), 192.229(c), 192.229(d)#
AR.RMPrecordPage 17AR.RMP.WELDQUAL.RRepair of Weld Defects From the review of records, were weld defects repaired in accordance with 192.245 and 192.715? References: 192.245(a), 192.245(b), 192.245(c), 192.715(a), 192.715(b), 192.715(c)#
AR.RMPrecordPage 17AR.RMP.WELDINSPECT.RInspection of Welds From the review of records, were welds inspected and examined in accordance with 192.241 and 192.243? References: 192.241(a), 192.241(b), 192.241(c), 192.243(a), 192.243(b), 192.243(c), 192.243(d), 192.243(e), 192.243(f)#
AR.RMPobservationPage 17AR.RMP.WELDINSPECT.OInspection of Welds Were welds inspected and examined in accordance with 192.241 and 192.243? References: 192.241(a), 192.241(b), 192.241(c), 192.243(a), 192.243(b), 192.243(c), 192.243(d), 192.243(e), 192.243(f)#
AR.RMPrecordPage 17AR.RMP.PIPECONDITION.RDo repair records document all information needed to understand the conditions of the pipe and its environment and provide the information needed to support the Integrity Management Risk Model? References: 192.709(a), 192.709(b)#
AR.RMPrecordPage 17AR.RMP.REPLACESTD.RReplacement Components From the review of records, were any components that were replaced constructed to the same or higher standards as the original component? References: 192.713(a)#
AR.RMPprocedurePage 17AR.RMP.FIELDREPAIRLEAK.PIs there an adequate process for the permanent field repair of leaks on transmission lines? References: 192.605(b), 192.717(a), 192.717(b)#
AR.RMPrecordPage 17AR.RMP.FIELDREPAIRLEAK.RTransmission Lines Permanent Field Repair of Leaks From the review of records, did the operator properly repair leaks on transmission lines? References: 192.717(a), 192.717(b)#
AR.RMPobservationPage 18AR.RMP.FIELDREPAIRLEAK.ODoes the operator properly repair leaks on transmission lines? References: 192.717(a), 192.717(b)#
AR.RMPprocedurePage 18AR.RMP.WELDTEST.PIs the process adequate for the testing of replacement pipe and repairs made by welding on transmission lines? References: 192.605(b), 192.719(a), 192.719(b)#
AR.RMPrecordPage 18AR.RMP.WELDTEST.RTransmission Lines Testing of Repairs From the review of records, did the operator properly test replacement pipe and repairs made by welding on transmission lines? References: 192.719(a), 192.719(b)#
AR.RMPobservationPage 18AR.RMP.WELDTEST.ODoes the operator properly test replacement pipe and repairs made by welding on transmission lines? References: 192.719(a), 192.719(b)#
AR.RMPprocedurePage 18AR.RMP.CRACKNDT.PWhen Exposed for Repair Does the process require that when a pipeline segment that meets the conditions for cracking and/or possible SCC is exposed (i.e., the coating is removed), an NDE method (e.g., MPI, UT) is employed to evaluate for cracking? References: 192.929(b)#
AR.RMPrecordPage 18AR.RMP.CRACKNDT.RWhen Exposed for Repair From the review of records, when a pipeline segment that meets the conditions of possible cracking and/or SCC is exposed (i.e., the coating is removed), was an NDE method (e.g., MPI, UT) employed to evaluate for cracking and/or SCC? References: 192.947(g), 192.929(b)#
AR.PAprocedurePage 18AR.PA.ASSESSSCHED.PWhat is the process/plan (including the selection criteria, timeline, and use of prior assessments) for performing the initial assessments as required by §192.710(b)(1) and (b)(3)? References: 192.710(b)(1), 192.710(b)(3)#
AR.PArecordPage 18AR.PA.ASSESSSCHED.RDo records demonstrate pipeline segments were initially assessed (and when) per §192.710(b)(1)? References: 192.710(b)(1), 192.710(b)(3)#
AR.PAprocedurePage 19AR.PA.ASSESSMETHODS.PDo the procedures include a methodology for conducting the initial assessment of pipeline segments outside of an HCA per §192.710(c)? References: 192.710(c)#
AR.PArecordPage 19AR.PA.ASSESSMETHODS.RDo the records confirm the methodology used for conducting the initial assessment of pipeline segments outside of an HCA per §192.710(c) was selected based on the results of a risk-based prioritization? References: 192.710(c)#
AR.PAprocedurePage 19AR.PA.REASSESSMENTS.PDo the procedures require reassessments to be conducted at least once every 10 years, not to exceed 126 months, or a shorter interval based upon the nature and extent of anomalies discovered in the previous assessment as required by §192.710(b)(2)? References: 192.710(b)(2), 192.710(b)(3), 192.939(a)#
AR.PArecordPage 19AR.PA.REASSESSMENTS.RDo the records indicate adequate documentation of and rationale for the reassessment intervals? References: 192.710(b)(2), 192.710(b)(3), 192.939(a)#
AR.PAprocedurePage 19AR.PA.OTHERTECH.PWhere the operator has elected to use “Other Technology” (or other technical evaluation process) for assessing pipeline segments, does the process demonstrate an equivalent understanding of the condition of the line pipe for each of the threats to which the pipeline is susceptible? References: 192.710(c)(7), 192.18, 192.506(b)#
AR.PArecordPage 19AR.PA.OTHERTECH.RWhere the operator has elected to use “Other Technology” (or other technical evaluation process) for assessing pipeline segments, do the records demonstrate an equivalent understanding of the condition of the line pipe for each of the threats to which the pipeline is susceptible? References: 192.710(c)(7), 192.18, 192.506(b)#
AR.PAprocedurePage 19AR.PA.REMEDIATIONCRITERIA.PDid the operator’s procedures for anomaly investigation and remediation criteria for non-HCA pipeline segments meet the requirements of §§192.485, 192.711, and 192.713? References: 192.710(f)#
AR.PArecordPage 19AR.PA.REMEDIATIONCRITERIA.RDo the remediation records indicate that conducted remediation activities were conducted in accordance with the procedures? References: 192.710(f), 192.933, 192.709#
AR.PAprocedurePage 19AR.PA.THREATID.PDoes the process include requirements to identify and evaluate all potential threats to each covered pipeline segment? References: 192.710#
AR.PArecordPage 20AR.PA.THREATID.RDo records demonstrate that all potential threats to each covered pipeline segment have been identified and evaluated? References: 192.710#
AR.PAprocedurePage 20AR.PA.RAMETHOD.PDoes the process include requirements for a risk assessment and/or risk prioritization, that considers all of the identified threats for each assessable non-HCA pipeline segment? References: 192.710#
AR.PArecordPage 20AR.PA.RAMETHOD.RDo records demonstrate that the operator has performed a risk assessment on the non-HCA pipeline segments? References: 192.710#
AR.PAprocedurePage 20AR.PA.RAFACTORS.PDoes the process include requirements for risk factors that could affect the likelihood of a release, and for factors that could affect the consequences of potential releases, be accounted for and combined in an appropriate manner to produce a risk value for each pipeline segment? References: 192.710#
AR.PArecordPage 20AR.PA.RAFACTORS.RDo records demonstrate that risk analysis data is combined in an appropriate manner to produce a risk value for each pipeline segment? References: 192.710#
AR.SPprocedurePage 20AR.SP.ILISP.PIf the pipeline operates under a special permit have the processes been modified to incorporate the requirements of the permit for required ILI assessments performed? References: 190.341(d)#
AR.SPrecordPage 20AR.SP.ILISP.RIf the pipeline operates under a special permit, from a review of selected records, were required ILI assessments performed? References: 190.341(d)#
AR.SPprocedurePage 20AR.SP.REPAIRSP.PIf the pipeline operates under a special permit have the processes been modified to incorporate the requirements of the permit for required repairs? References: 190.341(d)#
AR.SPrecordPage 20AR.SP.REPAIRSP.RIf the pipeline operates under a special permit, from a review of selected records, were required repairs performed? References: 190.341(d)#
CR.CRMGENprocedurePage 21CR.CRMGEN.CRMCRITERIA.PDo procedures adequately address the process and criteria to determine which facilities are control rooms? References: 192.631(a)(2)#
CR.CRMGENprocedurePage 21CR.CRMGEN.CRMMGMT.PAre CRM procedures formalized and controlled? References: 192.631(a)(2)#
CR.CRMGENrecordPage 21CR.CRMGEN.CRMIMPLEMENT.RAre procedures approved, in place, and implemented? References: 192.631(a)(2)#
CR.CRMGENobservationPage 21CR.CRMGEN.CRMPROCLOCATION.OAre procedures readily available to controllers in the control room? References: 192.631(a)(2)#
CR.CRMRRprocedurePage 21CR.CRMRR.RESPONSIBLE.PAre there clear processes to describe each controller's physical domain of responsibility for pipelines and other facility assets? References: 192.631(b)#
CR.CRMRRprocedurePage 21CR.CRMRR.QUALCONTROL.PAre there provisions in place to assure that only qualified individuals may assume control at any console/desk? References: 192.631(b)#
CR.CRMRRprocedurePage 21CR.CRMRR.DOMAINCHANGE.PIf the physical domain of responsibility periodically changes, has a clear process been established to describe the conditions for when such a change occurs? References: 192.631(b)#
CR.CRMRRprocedurePage 22CR.CRMRR.RESPCHANGE.PDo processes address a controller's role during temporary impromptu (unplanned) changes in controller responsibilities? References: 192.631(b)#
CR.CRMRRprocedurePage 22CR.CRMRR.COMMANDVERIFY.PDo the defined roles and responsibilities require controllers to stay at the console to verify all SCADA commands that have been initiated are fulfilled, and that commands given via verbal communications are acknowledged before leaving the console for any reason? References: 192.631(b)#
CR.CRMRRobservationPage 22CR.CRMRR.PRESSLIMITS.OAre controllers aware of the current MAOPs of all pipeline segments for which they are responsible, and have they been assigned the responsibility to maintain those pipelines at or below the MAOP? References: 192.631(b)(2), 192.619(a), 192.631(e)(1)#
CR.CRMRRprocedurePage 22CR.CRMRR.EVACUATION.PDo processes specifically address the controller's responsibilities in the event the control room must be evacuated? References: 192.631(b)(3)#
CR.CRMRRprocedurePage 22CR.CRMRR.COMMSYSFAIL.PDo processes specifically address the controller's responsibilities in the event of a SCADA system or data communications system failure impacting large sections of the controller's domain of responsibility? References: 192.631(b)(3)#
CR.CRMRRprocedurePage 22CR.CRMRR.HANDOVER.PHave processes been established for the hand-over of responsibility that specify the type of information to be communicated to the oncoming shift? References: 192.631(b)(4), 192.631(c)(5)#
CR.CRMRRobservationPage 22CR.CRMRR.HANDOVER.ODo observations indicate adequate hand-over of responsibility to the oncoming shift? References: 192.631(b)(4), 192.631(c)(5)#
CR.CRMRRprocedurePage 22CR.CRMRR.HANDOVERDOC.PDo processes require that records document the hand-over of responsibility, document the time the actual hand-over of responsibility occurs, and the key information and topics that were communicated during the hand-over? References: 192.631(b)(4), 192.631(c)(5)#
CR.CRMRRrecordPage 23CR.CRMRR.HANDOVERDOC.RAre there records that document the hand-over of responsibility, document the time the actual hand-over of responsibility occurs, and the key information and topics that were communicated during the hand-over? References: 192.631(b)(4), 192.631(c)(5)#
CR.CRMRRprocedurePage 23CR.CRMRR.HANDOVEROVERLAP.PDo processes require the controllers to discuss recent and impending important activities ensuring adequate overlap? References: 192.631(b)(4)#
CR.CRMRRprocedurePage 23CR.CRMRR.HANDOVERALTERNATIVE.PWhen a controller is unable to continue or assume responsibility for any reason, do the shift hand-over processes include alternative shift hand-over actions that specifically address this situation? References: 192.631(b)(4)#
CR.CRMRRprocedurePage 23CR.CRMRR.UNATTENDCONSOLE.PHas the operator established an adequate process for occasions when the console is left temporarily unattended for any reason? References: 192.631(b)(4)#
CR.CRMRRprocedurePage 23CR.CRMRR.CONSOLECOVERAGE.PDo processes maintain adequate console coverage during shift hand-over? References: 192.631(b)(4)#
CR.SCADAprocedurePage 24CR.SCADA.SYSTEMMOC.PDo processes clearly define the types of changes to the SCADA system(s) that constitute additions, expansions, or replacements under the meaning of the CRM rule? References: 192.631(c)(1)#
CR.SCADAprocedurePage 24CR.SCADA.DISPLAYCONFIG.PAre there written processes to implement the API RP 1165 display standards to the SCADA systems that have been added, expanded, or replaced since August 1, 2012? References: 192.631(c)(1)#
CR.SCADAobservationPage 24CR.SCADA.1165HUMANFACTORS.OHas section 4 of API RP 1165 regarding human factors engineering been implemented? References: 192.631(c)(1)#
CR.SCADAobservationPage 25CR.SCADA.DISPLAYOBJECTS.OHas section 8 of API RP 1165 regarding display object characteristics been implemented? References: 192.631(c)(1)#
CR.SCADArecordPage 25CR.SCADA.DISPLAYDYNAMICS.RHas section 9 of API RP 1165 regarding display object dynamics been implemented? References: 192.631(c)(1)#
CR.SCADArecordPage 25CR.SCADA.ADMINISTRATION.RHave applicable paragraphs of section 11 of API RP 1165 administration been implemented? References: 192.631(c)(1)#
CR.SCADArecordPage 25CR.SCADA.1165IMPRACTICAL.RIf any/all applicable paragraph(s) of API RP 1165 have not been implemented, has it been demonstrated and documented that the unimplemented provisions are impractical for the SCADA system used? References: 192.631(c)(1)#
CR.SCADAprocedurePage 25CR.SCADA.SETPOINT.PDoes the process adequately define safety-related points? References: 192.631(c)(2)#
CR.SCADArecordPage 25CR.SCADA.SETPOINT.RDo records indicate safety-related points have been adequately implemented? References: 192.631(c)(2)#
CR.SCADAprocedurePage 25CR.SCADA.POINTVERIFY.PAre there adequate processes to define and identify the circumstances which require a point-to-point verification? References: 192.631(c)(2)#
CR.SCADArecordPage 25CR.SCADA.POINTVERIFY.RHave required point-to-point verifications been performed? References: 192.631(c)(2)#
CR.SCADAprocedurePage 25CR.SCADA.POINTVERIFYEXTENT.PAre there adequate processes for the thoroughness of the point-to-point verification? References: 192.631(c)(2)#
CR.SCADArecordPage 25CR.SCADA.POINTVERIFYEXTENT.RDo records demonstrate adequate thoroughness of the point-to-point verification? References: 192.631(c)(2)#
CR.SCADAprocedurePage 26CR.SCADA.POINTVERFIYINTVL.PIs there an adequate process for defining when the point-to-point verification must be completed? References: 192.631(c)(2)#
CR.SCADArecordPage 26CR.SCADA.POINTVERFIYINTVL.RDo records indicate the point-to-point verification has been completed at the required intervals? References: 192.631(c)(2)#
CR.SCADAobservationPage 26CR.SCADA.POINTVERIFY.OAre point-to-point verifications performed adequately when required? References: 192.631(c)(2)#
CR.SCADAprocedurePage 26CR.SCADA.COMMPLAN.PHas an internal communication plan been established and implemented that is adequate to manually operate the pipeline during a SCADA failure/outage? References: 192.631(c)(3)#
CR.SCADArecordPage 26CR.SCADA.COMMPLAN.RHas the internal communication plan been tested and verified for manual operation of the pipeline safely at least once each calendar year but at intervals not exceeding 15 months? References: 192.631(c)(3)#
CR.SCADAobservationPage 26CR.SCADA.BACKUPSCADA.OIs there a backup SCADA system? References: 192.631(c)#
CR.SCADAprocedurePage 26CR.SCADA.BACKUPSCADADEV.PHas the use of the backup SCADA system for development work been defined? References: 192.631(c)(4)#
CR.SCADAprocedurePage 26CR.SCADA.BACKUPSCADATEST.PIs the backup SCADA system required to be tested at least once each calendar year at intervals not to exceed 15 months? References: 192.631(c)(4)#
CR.SCADArecordPage 26CR.SCADA.BACKUPSCADATEST.RIs the backup SCADA system tested at least once each calendar year at intervals not to exceed 15 months? References: 192.631(c)(4)#
CR.SCADAprocedurePage 26CR.SCADA.BACKUPSCADAVERIFY.PIs testing required to verify adequate processes are in place for decision-making and internal communications to successfully implement a transition from primary SCADA to backup SCADA, and back to primary SCADA? References: 192.631(c)(4)#
CR.SCADArecordPage 27CR.SCADA.BACKUPSCADAVERIFY.RDoes the testing verify that there are adequate processes in place for decision-making and internal communications to successfully implement a transition from primary SCADA to backup SCADA, and back to primary SCADA? References: 192.631(c)(4)#
CR.SCADArecordPage 27CR.SCADA.BACKUPSCADAADEQUACY.RIf the back-up SCADA system is not designed to handle all the functionality of the main SCADA system, does the testing determine whether there are adequate procedures in place to account for displaced and/or different available functions during back-up operations? References: 192.631(c)(4)#
CR.SCADAprocedurePage 27CR.SCADA.BACKUPSCADATRANSFER.PDo processes adequately address and test the logistics of transferring control to a backup control room? References: 192.631(c)(4)#
CR.SCADAprocedurePage 27CR.SCADA.BACKUPSCADARETURN.PDo procedures adequately address and test the logistics of returning operations back to the primary control room? References: 192.631(c)(4)#
CR.SCADArecordPage 27CR.SCADA.BACKUPSCADAFUNCTIONS.RIs a representative sampling of critical functions in the back-up SCADA system being tested to ensure proper operation in the event the backup system is needed? References: 192.631(c)(4)#
CR.SCADAprocedurePage 27CR.SCADA.CMPPRESSRELIEFTEST.PAre processes adequate for inspection and test of each pressure relieving device in a compressor station, including periodic operation to determine opening at the correct set pressure? References: 192.731(a), 192.731(b), 192.731(c), 192.631(b)#
CR.SCADArecordPage 27CR.SCADA.CMPPRESSRELIEFTEST.RDo inspection and test records for each pressure relieving device in a compressor station indicate it was operated periodically to determine that it opens at the correct set pressure? References: 192.731(a)#
CR.SCADAprocedurePage 27CR.SCADA.PRESSRELIEFTEST.PAre there procedures for inspection and test of each pressure relieving device at pressure limiting stations? References: 192.739(a), 192.631(b)#
CR.SCADArecordPage 27CR.SCADA.PRESSRELIEFTEST.RDo records indicate adequate inspection and testing for each pressure relieving device in a pressure limiting station? References: 192.739(a), 192.631(b)#
CR.SCADAprocedurePage 28CR.SCADA.VALVETEST.PIf the valve is monitored by SCADA, does the process account for how valve testing is coordinated with the controller? References: 192.745(a), 192.631(b)#
CR.SCADArecordPage 28CR.SCADA.VALVETEST.RIf SCADA is used to operate valves, do records indicate the SCADA system was adequately involved in the testing to ensure valve operation? References: 192.709(c), 192.745(a)#
CR.CRMFMprocedurePage 28CR.CRMFM.FATIGUEMITIGATION.PDoes the fatigue mitigation process or procedures (plan) identify operator-specific fatigue risks? References: 192.631(d)#
CR.CRMFMprocedurePage 28CR.CRMFM.FATIGUERISKS.PDoes the fatigue mitigation plan adequately address how the program reduces the risk associated with controller fatigue? References: 192.631(d)#
CR.CRMFMprocedurePage 28CR.CRMFM.FATIGUEQUANTIFY.PDo processes require that the potential contribution of controller fatigue to incidents and accidents be quantified during investigations? References: 192.631(d)#
CR.CRMFMprocedurePage 28CR.CRMFM.FATIGUEMANAGER.PIs there a designated fatigue risk manager who is responsible and accountable for managing fatigue risk and fatigue countermeasures, and someone (perhaps the same person) that is authorized to review and approve HOS emergency deviations? References: 192.631(d)#
CR.CRMFMrecordPage 28CR.CRMFM.SHIFTLENGTH.RIs the scheduled shift length less than or equal to 12 hours (not including shift hand-over) or is there a documented technical basis to show that shift lengths and schedule rotations are adequate to provide controllers off- duty time sufficient to achieve 8 hours of continuous sleep? References: 192.631(d)(1)#
CR.CRMFMrecordPage 28CR.CRMFM.SHIFTLENGTHTIME.RDoes the operator factor in all time the individual is working for the company when establishing shift lengths and schedule rotations or is there a documented technical basis to show that shift lengths and schedule rotations are adequate to provide controllers off-duty time sufficient to achieve 8 hours of continuous sleep? References: 192.631(d)(1)#
CR.CRMFMrecordPage 29CR.CRMFM.SCHEDULEDTIMEOFF.RAre all scheduled periods of time off at least one hour longer than 8 hours plus commute time or is there a documented technical basis to show that shift lengths and schedule rotations are adequate to provide controllers off-duty time sufficient to achieve 8 hours of continuous sleep? References: 192.631(d)(1)#
CR.CRMFMprocedurePage 29CR.CRMFM.ONCALLCONTROLLER.POn Call Controllers For controllers who are on call, do processes minimize interrupting the required 8 hours of continuous sleep or require a documented technical basis to show that shift lengths and schedule rotations are adequate to provide controllers off-duty time sufficient to achieve 8 hours of continuous sleep? References: 192.631(d)#
CR.CRMFMrecordPage 29CR.CRMFM.ONCALLCONTROLLER.ROn Call Controllers For controllers who are on call, does the operator minimize interrupting the required 8 hours of continuous sleep or is there a documented technical basis to show that shift lengths and schedule rotations are adequate to provide controllers off-duty time sufficient to achieve 8 hours of continuous sleep? References: 192.631(d)(1)#
CR.CRMFMprocedurePage 29CR.CRMFM.MAXHOS.PDo processes limit the maximum HOS limit in any sliding 7-day period to no more than 65 hours or is there a documented technical basis to show a reduction of the risk associated with controller fatigue? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 29CR.CRMFM.MINTIMEOFF.PMinimum Time Off After HOS Limit Reached After reaching the HOS limit in any sliding 7-day period, is the minimum time off at least 35 hours or is there a documented technical basis to show a reduction of the risk associated with controller fatigue? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 29CR.CRMFM.DOCSCHEDULE.PIs there a formal system to document all scheduled and unscheduled HOS worked, including overtime and time spent performing duties other than control room duties? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 29CR.CRMFM.DAYSOFF.PTime Off Following Successive Days Worked For normal business hour type operations (i.e., five days per week), are no more than five days worked in succession before at least two days off? References: 192.631(d)(4)#
CR.CRMFMrecordPage 29CR.CRMFM.WORKHOURS.RDay Only Work Hours For normal business hour type operations (i.e., five days per week), do records indicate shift start times no earlier than 6:00 a.m. and shift end times no later than 7:00 p.m.? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 29CR.CRMFM.FATIGUECOUNTERMEASURES.PFatigue Countermeasures For shifts longer than 8 hours, have specific fatigue countermeasures been implemented for the ninth and beyond hours? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 30CR.CRMFM.DAILYHOSLIMIT.PDo processes limit the daily maximum HOS limit no more than 14 hours in any sliding 24-hour period? References: 192.631(d)(4)#
CR.CRMFMobservationPage 30CR.CRMFM.CONTROLLERNUMBERS.ODo operations include a sufficient number of qualified controllers? References: 192.631(d)#
CR.CRMFMprocedurePage 30CR.CRMFM.OFFDUTYHOURS.PWhen Limits Reached Do processes ensure that controllers are provided with at least thirty-five (35) continuous off-duty hours when limits are reached following the most recent 35-hour (minimum) off-duty rest period or is there a documented technical basis to show that the maximum limit on controller HOS is adequate to reduce the risk associated with controller fatigue? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 30CR.CRMFM.SHIFTHOLDOVER.PDoes the shift holdover process conform to shift holdover guidelines or is there a documented technical basis to show that the maximum limit on controller HOS is adequate to reduce the risk associated with controller fatigue? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 30CR.CRMFM.SPECIFICCOUNTERMEASURES.PDo processes require specific fatigue countermeasures during applicable time periods, or is there a documented technical basis to show that the maximum limit on controller HOS is adequate to reduce the risk associated with controller fatigue? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 30CR.CRMFM.HOSDEVIATIONS.PIs there a formal process for approving deviations from the maximum HOS limits? References: 192.631(d)(4)#
CR.CRMFMprocedurePage 30CR.CRMFM.FATIGUEEDUCATE.PDoes the program require that fatigue education/training is required for all controllers and control room supervisors? References: 192.631(d)(2), 192.631(d)(3)#
CR.CRMFMrecordPage 30CR.CRMFM.FATIGUEEDUCATE.RIs periodic fatigue education/training documented for all controllers and control room supervisors? References: 192.631(d)(2), 192.631(d)(3)#
CR.CRMFMprocedurePage 30CR.CRMFM.FATIGUEREVIEW.PDo processes require that the effectiveness of the fatigue education/training program be reviewed at least once each calendar year, not to exceed 15 months? References: 192.631(d)(2), 192.631(d)(3), 192.605(a)#
CR.CRMFMprocedurePage 31CR.CRMFM.FATIGUESTRATEGY.PDoes fatigue education address fatigue mitigation strategies (countermeasures)? References: 192.631(d)(2)#
CR.CRMFMprocedurePage 31CR.CRMFM.OFFDUTY.PDoes fatigue education address how off-duty activities contribute to fatigue? References: 192.631(d)(2)#
CR.CRMFMprocedurePage 31CR.CRMFM.FATIGUECONTENT.PIs the content of fatigue training adequate for training controllers and supervisors to recognize the effects of fatigue? References: 192.631(d)(3)#
CR.CRMFMrecordPage 31CR.CRMFM.FATIGUECONTENT.RHas controller and supervisor training to recognize the effects of fatigue been documented? References: 192.631(d)(3)#
CR.CRMAMprocedurePage 31CR.CRMAM.ALARM.PIs the alarm management plan a formal process that specifically identifies critical topical areas included in the program? References: 192.631(e)#
CR.CRMAMprocedurePage 31CR.CRMAM.ALARMMALFUNCTION.PIs there a process to identify and correct inaccurate or malfunctioning alarms? References: 192.631(e)(1)#
CR.CRMAMprocedurePage 31CR.CRMAM.ALARMREVIEW.PDoes the review of safety-related alarms account for different alarm designs and all alarm types/priorities? References: 192.631(e)(1)#
CR.CRMAMprocedurePage 31CR.CRMAM.CONTROLLERPERFORMANCE.PDoes the review of safety-related alarms account for console differences that could affect individual-specific controller qualification and performance? References: 192.631(h), 192.631(e)(1)#
CR.CRMAMprocedurePage 31CR.CRMAM.STALEDATA.PDoes the review of safety-related alarms include specific procedures and practices for managing stale or unreliable data? References: 192.631(e)(1)#
CR.CRMAMprocedurePage 32CR.CRMAM.MONTHLYANALYSIS.PDo processes require the monthly identification, recording, review, and analysis of points that have been taken off scan, have had alarms inhibited, generated false alarms, or that have had forced or manual values for periods of time exceeding that required for associated maintenance or operating activities? References: 192.631(e)(2)#
CR.CRMAMprocedurePage 32CR.CRMAM.PROBLEMCORRECTION.PDoes the alarm management plan include a process for promptly correcting identified problems and for returning these points to service? References: 192.631(e)(2)#
CR.CRMAMrecordPage 32CR.CRMAM.ALARMVERIFY.RDo records verify that monthly reviews and analysis of alarm points have been performed? References: 192.631(e)(2)#
CR.CRMAMprocedurePage 32CR.CRMAM.ALARMSETPOINTS.PIs there a formal process to determine the correct alarm setpoint values and alarm descriptions? References: 192.631(e)(3)#
CR.CRMAMprocedurePage 32CR.CRMAM.SETTINGCONTROL.PHave procedures been established to clearly address how and to what degree controllers can change alarm limits or setpoints, or inhibit alarms, or take points off-scan? References: 192.631(e)(3)#
CR.CRMAMrecordPage 32CR.CRMAM.ALARMVALUEVERIFY.RDo records demonstrate verification of correct safety-related alarm set-point values and alarm descriptors when associated field instruments are calibrated or changed and at least once each calendar year, but at intervals not to exceed 15 months? References: 192.631(e)(3)#
CR.CRMAMprocedurePage 32CR.CRMAM.PLANREVIEW.PAre there processes to review the alarm management plan at least once each calendar year, but at intervals not exceeding 15 months, in order to determine the effectiveness of the plan? References: 192.631(e)(4)#
CR.CRMAMrecordPage 32CR.CRMAM.PLANREVIEW.RDo records indicate review of the alarm management plan at least once each calendar year, but at intervals not exceeding 15 months, in order to determine the effectiveness of the plan? References: 192.631(e)(4)#
CR.CRMAMprocedurePage 32CR.CRMAM.WORKLOAD.PDoes the CRM program have a means of identifying and measuring the work load (content and volume of general activity) being directed to an individual controller? References: 192.631(e)(5)#
CR.CRMAMprocedurePage 33CR.CRMAM.WORKLOADMONITORING.PIs the process of monitoring and analyzing general activity comprehensive? References: 192.631(e)(5)#
CR.CRMAMprocedurePage 33CR.CRMAM.CONTROLLERREACTION.PDoes the process have a means of determining that the controller has sufficient time to analyze and react to incoming alarms? References: 192.631(e)(5)#
CR.CRMAMrecordPage 33CR.CRMAM.PERFORMANCEANALYSIS.RHas an analysis been performed to determine if controller(s) performance is currently adequate? References: 192.631(e)(5)#
CR.CRMAMprocedurePage 33CR.CRMAM.DEFICIENCIES.PIs there a process to address how deficiencies found in implementing 192.631(e)(1) through 192.631(e)(5) will be resolved? References: 192.631(e)(6)#
CR.CRMAMrecordPage 33CR.CRMAM.DEFICIENCIES.RDo records indicate deficiencies found in implementing 192.631(e)(1) through 192.631(e)(5) have been resolved? References: 192.631(e)(6)#
CR.CRMCMGTprocedurePage 33CR.CRMCMGT.EQUIPMENTCHANGES.PIs there a process to assure changes in field equipment that could affect control room operations are coordinated with the control room personnel? References: 192.631(f)(1)#
CR.CRMCMGTprocedurePage 33CR.CRMCMGT.CONTROLLERPARTICIPATE.PAre control room representative(s) required to participate in meetings where changes that could directly or indirectly affect the hydraulic performance or configuration of the pipeline (including routine maintenance and repairs) are being considered, designed and implemented? References: 192.631(f)(1), 192.631(f)(3)#
CR.CRMCMGTrecordPage 33CR.CRMCMGT.CONTROLLERPARTICIPATE.RDo records indicate that control room representative(s) participate in meetings where changes that could directly or indirectly affect the hydraulic performance or configuration of the pipeline (including routine maintenance and repairs) are being considered, designed and implemented? References: 192.631(f)(1), 192.631(f)(3)#
CR.CRMCMGTprocedurePage 34CR.CRMCMGT.EMERGENCYCONTACT.PIs there a process requiring field personnel and SCADA support personnel to contact the control room when emergency conditions exist? References: 192.631(f)(2)#
CR.CRMCMGTprocedurePage 34CR.CRMCMGT.FIELDCONTACT.PDoes the process require field personnel and SCADA support personnel to contact the control room when making field changes (e.g., operating a valve, O&M inspections/calibrations, RTU/PLC modifications) that affect control room operations? References: 192.631(f)(2)#
CR.CRMCMGTrecordPage 34CR.CRMCMGT.FIELDCHANGES.RDo records indicate field personnel and SCADA support personnel contacted the control room when making field changes (e.g., operating a valve, O&M inspections/calibrations, RTU/PLC modifications) that affect control room operations? References: 192.631(f)(2)#
CR.CRMEXPprocedurePage 34CR.CRMEXP.REPORTABLEINCIDENTREVIEW.PIs there a formal, structured approach for reviewing and critiquing reportable events to identify lessons learned? References: 192.631(g)(1)#
CR.CRMEXPrecordPage 34CR.CRMEXP.REPORTABLEINCIDENTREVIEW.RDo records indicate reviews of reportable events specifically analyzed all contributing factors to determine if control room actions contributed to the event, and corrected any deficiencies? References: 192.631(g)(1)#
CR.CRMEXPprocedurePage 34CR.CRMEXP.LESSONSLEARNED.PDoes the program require training on lessons learned from a broad range of events (reportable incidents/accidents, near misses, leaks, operational and maintenance errors, etc.), even though the control room may not have been at fault? References: 192.631(g)(2), 192.631(b)(5)#
CR.CRMEXPrecordPage 34CR.CRMEXP.LESSONSLEARNED.RHas operating experience review training been conducted on lessons learned from a broad range of events (reportable incidents/accidents, near misses, leaks, operational and maintenance errors, etc.)? References: 192.631(g)(2), 192.631(b)(5)#
CR.CRMTRAINprocedurePage 35CR.CRMTRAIN.CONTROLLERTRAIN.PHas a controller training program been established to provide training for each controller to carry out their roles and responsibilities? References: 192.631(h)#
CR.CRMTRAINrecordPage 35CR.CRMTRAIN.CONTROLLERTRAIN.RHas a controller training program been implemented to provide training for each controller to carry out their roles and responsibilities? References: 192.631(h)#
CR.CRMTRAINprocedurePage 35CR.CRMTRAIN.TRAININGREVIEW.PHave processes been established to review the controller training program content to identify potential improvements at least once each calendar year, but at intervals not to exceed 15 months? References: 192.631(h)#
CR.CRMTRAINrecordPage 35CR.CRMTRAIN.TRAININGREVIEW.RHave processes been implemented to review the controller training program content to identify potential improvements at least once each calendar year, but at intervals not to exceed 15 months? References: 192.631(h)#
CR.CRMTRAINrecordPage 35CR.CRMTRAIN.TRAININGCONTENT.RDoes training content address all required material, including training each controller to carry out the roles and responsibilities that were defined by the operator? References: 192.631(h)#
CR.CRMTRAINrecordPage 35CR.CRMTRAIN.AOCLIST.RHas a list of the abnormal operating conditions that are likely to occur simultaneously or in sequence been established? References: 192.631(h)(1)#
CR.CRMTRAINprocedurePage 35CR.CRMTRAIN.TRAININGABNORMAL.PDoes the training program provide controller training on recognizing and responding to abnormal operating conditions that are likely to occur simultaneously or in sequence? References: 192.631(h)(1)#
CR.CRMTRAINrecordPage 35CR.CRMTRAIN.TRAINING.RDo records indicate the training program used a simulator or tabletop exercises to train controllers how to recognize and respond to abnormal operating conditions? References: 192.631(h)(2)#
CR.CRMTRAINobservationPage 35CR.CRMTRAIN.TRAINING.ODoes the training program use a simulator or tabletop exercises to train controllers how to recognize and respond to abnormal operating conditions? References: 192.631(h)(2)#
CR.CRMTRAINprocedurePage 36CR.CRMTRAIN.COMMUNICATIONTRAINING.PDoes the CRM program train controllers on their responsibilities for communication under the operator's emergency response procedures? References: 192.631(h)(3)#
CR.CRMTRAINprocedurePage 36CR.CRMTRAIN.SYSKNOWLEDGE.PDoes the training program provide controllers a working knowledge of the pipeline system, especially during the development of abnormal operating conditions? References: 192.631(h)(4)#
CR.CRMTRAINrecordPage 36CR.CRMTRAIN.INFREQOPSLIST.RHas a list of pipeline operating setups that are periodically (but infrequently) used been established? References: 192.631(h)(5)#
CR.CRMTRAINprocedurePage 36CR.CRMTRAIN.INFREQOPSREVIEW.PDo processes specify that, for pipeline operating set-ups that are periodically (but infrequently) used, the controllers must be provided an opportunity to review relevant procedures in advance of their use? References: 192.631(h)(5)#
CR.CRMTRAINprocedurePage 36CR.CRMTRAIN.TEAMTRAINPERSONNEL.PDo processes establish who, regardless of location, operationally collaborates with control room personnel? References: 192.631(h)(6)#
CR.CRMTRAINprocedurePage 36CR.CRMTRAIN.TEAMTRAINFREQ.PDo processes define the frequency of new and recurring team training? References: 192.631(h)(6)#
CR.CRMTRAINprocedurePage 36CR.CRMTRAIN.TEAMTRAINCOMPLETE.PDo processes address all operational modes and operational collaboration/control? References: 192.631(h)(6)#
CR.CRMTRAINprocedurePage 36CR.CRMTRAIN.TEAMTRAINEXPERIENCE.PDo processes include incorporation of lessons learned from actual historical events and other oil-gas industry events? References: 192.631(h)(6)#
CR.CRMTRAINrecordPage 36CR.CRMTRAIN.TEAMTRAINEXERCISE.RDo records indicate that training exercises were adequate and involved at least one qualified controller? References: 192.631(h)(6)#
CR.CRMTRAINobservationPage 36CR.CRMTRAIN.TEAMTRAINEXERCISE.ODoes implementation of a control room team exercise demonstrate performance in accordance with regulatory and process requirements? References: 192.631(h)(6)#
CR.CRMTRAINrecordPage 37CR.CRMTRAIN.TEAMTRAINIDENTINDIVIDUAL.RDo records demonstrate that individuals identified as of January 23, 2018 received team training by January 23, 2019? References: 192.631(h)(6)#
CR.CRMCOMPprocedurePage 37CR.CRMCOMP.SUBMITPROCEDURES.PAre there adequate processes to assure that the operator is responsive to requests from applicable agencies to submit their CRM procedures? References: 192.631(i)#
CR.CRMCOMPrecordPage 37CR.CRMCOMP.SUBMITPROCEDURES.RHas the operator been responsive to requests from applicable agencies to submit their CRM procedures? References: 192.631(i)#
CR.CRMCOMPrecordPage 37CR.CRMCOMP.CRMCOORDINATOR.RIs there an individual that is responsible and accountable for compliance with requests from PHMSA or other applicable agencies? References: 192.631(i)#
CR.CRMCOMPprocedurePage 37CR.CRMCOMP.RECORDS.PAre records management processes adequate to assure records are sufficient to demonstrate compliance with the CRM rule? References: 192.631(j)(1)#
CR.CRMCOMPrecordPage 37CR.CRMCOMP.RECORDS.RAre records sufficient to demonstrate compliance with the CRM rule? References: 192.631(j)(1)#
CR.CRMCOMPrecordPage 37CR.CRMCOMP.ELECTRONICRECORDS.RAre electronic records properly stored, safeguarded, and readily retrievable? References: 192.631(j)(1)#
CR.CRMCOMPprocedurePage 37CR.CRMCOMP.DEVIATIONS.PAre there processes to demonstrate and provide a documented record that every deviation from any CRM rule requirement was necessary for safe operation? References: 192.631(j)(2)#
CR.CRMCOMPrecordPage 38CR.CRMCOMP.DEVIATIONS.RDeviation Records Were all deviations documented in a way that demonstrates they were necessary for safe operation? References: 192.631(j)(2)#
CR.LDrecordPage 38CR.LD.LDSYS.RDo records demonstrate the operator has identified, considered, or implemented leak detection measures to mitigate the consequences of a pipeline failure? References: 192.631(g)#
CR.LDprocedurePage 38CR.LD.FACILITY.PDoes the process require continuing surveillance of facilities to determine and take appropriate action concerning failures/leakage history? References: 192.605(b)(1), 192.613(a), 192.631(b)#
CR.LDrecordPage 38CR.LD.FACILITY.RDo records indicate continuing surveillance of facilities to determine and take appropriate action concerning failures/leakage history? References: 192.605(b)(1), 192.613(a), 192.631(b)#
DC.COCMPprocedurePage 38DC.COCMP.CMPCOMBUSTIBLE.PDoes the process require that flammable/combustible materials are stored as required, and aboveground oil or gasoline storage tanks, are installed at compressor stations according to 192.735(b)? References: 192.303, 192.735(a), 192.735(b)#
DC.COCMPrecordPage 38DC.COCMP.CMPCOMBUSTIBLE.RDo records demonstrate that flammable/combustible materials are stored as required, and aboveground oil or gasoline storage tanks are installed at compressor stations according to 192.735(b)? References: 192.303, 192.735(a), 192.735(b)#
DC.COCMPobservationPage 39DC.COCMP.CMPCOMBUSTIBLE.ODo field observations demonstrate that flammable/combustible materials are safely stored as required, and aboveground oil or gasoline storage tanks are installed at compressor stations according to 192.735(b)? References: 192.735(a), 192.735(b)#
DC.COCMPprocedurePage 39DC.COCMP.CMPGASDETECT.PDoes the process require compressor buildings to have a fixed gas detection and alarm system installed according to §192.736? References: 192.303, 192.736(a)#
DC.COCMPrecordPage 39DC.COCMP.CMPGASDETECT.RDo records demonstrate that compressor buildings have a fixed gas detection and alarm system installed according to §192.736? References: 192.303, 192.736(a)#
DC.COCMPobservationPage 39DC.COCMP.CMPGASDETECT.ODo field observations confirm that compressor buildings have a fixed gas detection and alarm system installed according to 192.736? References: 192.303, 192.736(a), 192.736(b)#
DC.COprocedurePage 39DC.CO.INSPECTGEN.PDoes the process require the pipeline to be inspected to ensure that it is constructed in accordance with Part 192? References: 192.303, 192.305#
DC.COrecordPage 39DC.CO.INSPECTGEN.RDo records indicate the pipeline is being inspected to ensure it is constructed in accordance with Part 192? References: 192.303, 192.305#
DC.COobservationPage 39DC.CO.INSPECTGEN.ODo field observation verify the pipeline being inspected to ensure it is constructed in accordance with Part 192? References: 192.303, 192.305#
DC.COprocedurePage 39DC.CO.CASING.PDoes the process require railroad or highway casings to be in accordance with the requirements of 192.323? References: 192.303, 192.323(a), 192.323(b), 192.323(c), 192.323(d), 192.467(a), 192.467(b)#
DC.COobservationPage 40DC.CO.CASING.ODo field observations confirm railroad or highway casings are being installed as designed and specified, and in accordance with 192.323? References: 192.323, 192.467(a), 192.467(b)#
DC.COprocedurePage 40DC.CO.NONWELDJOINT.PDoes the process require that pipeline joints (to be made other than by welding) be designed and installed in accordance with 192.273? References: 192.303, 192.273(a), 192.273(b), 192.273(c)#
DC.COprocedurePage 40DC.CO.PLASTICJOINT.PDoes the process require plastic pipe joints to be designed and installed in accordance with 192.281? References: 192.303, 192.281(a), 192.281(b), 192.281(c), 192.281(d), 192.281(e)#
DC.COrecordPage 40DC.CO.PLASTICJOINT.RPlastic Pipe Joints As applicable to the project, do records indicate that plastic pipe joints are installed in accordance with the requirements 192.281? References: 192.281(a), 192.281(b), 192.281(c), 192.281(d), 192.281(e)#
DC.COobservationPage 40DC.CO.PLASTICJOINT.OPlastic Pipe Joints As applicable to the project, are plastic pipe joints installed in accordance with the requirements 192.281? References: 192.281(a), 192.281(b), 192.281(c), 192.281(d), 192.281(e)#
DC.COprocedurePage 40DC.CO.PLASTICJOINTPROCEDURE.PDoes the process require plastic pipe joining procedures to be qualified in accordance with 192.283, prior to making plastic pipe joints? References: 192.283(a), 192.283(b), 192.283(c)#
DC.COprocedurePage 40DC.CO.PLASTICJOINTQUAL.PIs a process in place to ensure that personnel making joints in plastic pipelines are qualified? References: 192.285(d), 192.285(a), 192.285(b), 192.285(c), 192.285(e), 192.805#
DC.COrecordPage 40DC.CO.PLASTICJOINTQUAL.RDo records indicate persons making joints in plastic pipelines are qualified in accordance with §192.285? References: 192.285(e), 192.285(a), 192.285(b), 192.285(c), 192.285(d), 192.807(a), 192.807(b)#
DC.COobservationPage 40DC.CO.PLASTICJOINTQUAL.ODo observations verify persons making joints in plastic pipelines are qualified? References: 192.285(d), 192.285(a), 192.285(b), 192.285(c), 192.285(e), 192.807(b)#
DC.COprocedurePage 41DC.CO.PLASTICJOINTINSP.PIs a process in place to assure that persons who inspect joints in plastic pipes are qualified? References: 192.287, 192.805(h)#
DC.COrecordPage 41DC.CO.PLASTICJOINTINSP.RDo records indicate persons inspecting the making of plastic pipe joints have been qualified? References: 192.287, 192.807(a), 192.807(b)#
DC.COobservationPage 41DC.CO.PLASTICJOINTINSP.ODo person(s) inspecting joints in plastic pipelines demonstrate they are qualified to evaluate the acceptability of plastic pipe joints? References: 192.287, 192.807(b)#
DC.COprocedurePage 41DC.CO.SPECS.PDoes the operator have written construction specifications or standards as required of 192.303? References: 192.303#
DC.COprocedurePage 41DC.CO.INSPECTVISUAL.PDoes the process require pipe and other components to be visually inspected prior to installation? References: 192.303, 192.307#
DC.COrecordPage 41DC.CO.INSPECTVISUAL.RDo records demonstrate each length of pipe and each other component was visually inspected prior to installation in accordance with 192.307? References: 192.303, 192.205, 192.307#
DC.COobservationPage 41DC.CO.INSPECTVISUAL.ODo field observations confirm each length of pipe and each component is being visually inspected for damage according to 192.307? References: 192.303, 192.307#
DC.COprocedurePage 41DC.CO.REPAIR.PDoes the process require repairs to steel pipe in accordance with §192.309? References: 192.303, 192.309, 192.493#
DC.COrecordPage 41DC.CO.REPAIR.RDo records demonstrate that repairs to steel pipe are being made in accordance with §192.309? References: 192.303, 192.309, 192.493#
DC.COobservationPage 41DC.CO.REPAIR.ODo field observations confirm repairs to steel pipe being made in accordance with §192.309? References: 192.303, 192.309#
DC.COprocedurePage 42DC.CO.REPAIRPLASTIC.PDoes the process require imperfections or damage of plastic pipe to be repaired or removed? References: 192.303, 192.311#
DC.COrecordPage 42DC.CO.REPAIRPLASTIC.RDo records indicate that imperfections or damage of plastic pipe are repaired or removed? References: 192.311#
DC.COobservationPage 42DC.CO.REPAIRPLASTIC.OAre imperfections or damage of plastic pipe repaired or removed? References: 192.311#
DC.COprocedurePage 42DC.CO.FIELDBEND.PDoes the process require field bends to be made in accordance with 192.313? References: 192.303, 192.313(a), 192.313(b), 192.313(c), 192.315(a)#
DC.COrecordPage 42DC.CO.FIELDBEND.RDo records indicate that field bends are made in accordance with 192.313? References: 192.313(a), 192.313(b), 192.313(c), 192.315(a)#
DC.COobservationPage 42DC.CO.FIELDBEND.ODo field observations confirm field bends are being made in accordance with 192.313(a)? References: 192.313(a), 192.313(b), 192.313(c), 192.315(a)#
DC.COprocedurePage 42DC.CO.WRINKLEBEND.PDoes the process require that wrinkle bends are made in accordance with 192.315? References: 192.303, 192.315(a), 192.315(b)#
DC.COrecordPage 42DC.CO.WRINKLEBEND.RDo records indicate that wrinkle bends were made in accordance with 192.315? References: 192.315(a), 192.315(b)#
DC.COobservationPage 42DC.CO.WRINKLEBEND.ODo field observations confirm wrinkle bends are made in accordance with 192.315? References: 192.315(a), 192.315(b)#
DC.COprocedurePage 42DC.CO.HAZARD.PDoes the operator have written specifications requiring transmission line or main be protected from hazards in accordance with 192.317? References: 192.303, 192.317(a), 192.317(b), 192.317(c), 192.103#
DC.COrecordPage 43DC.CO.HAZARD.RDo records demonstrate the installed transmission line or main is protected from hazards? References: 192.317(a), 192.317(b), 192.317(c), 192.603, 192.614, 192.709#
DC.COobservationPage 43DC.CO.HAZARD.ODo field observations demonstrate or confirm installed transmission line or main is protected from hazards? References: 192.317, 192.303, 192.614#
DC.DPCprocedurePage 43DC.DPC.CCPROTCOATLOWER.PDo written specifications stipulate that each external protective coating must be inspected just prior to lowering the pipe into the ditch and backfilling, and any damage detrimental to effective corrosion control must be repaired? References: 192.143(b), 192.461(c)#
DC.DPCrecordPage 43DC.DPC.CCPROTCOATLOWER.RDo records indicate that each pipe segment with external protective coating was inspected just prior to lowering into the ditch and backfilling, and any damage detrimental to effective corrosion control was repaired? References: 192.143(b), 192.461(c)#
DC.DPCobservationPage 43DC.DPC.CCPROTCOATLOWER.ODo the field observations confirm that each pipe segment with external protective coating was inspected just prior to lowering into the ditch and backfilling, and any damage detrimental to effective corrosion control was repaired? References: 192.143(b), 192.461(c)#
DC.COprocedurePage 43DC.CO.INSTALL.PDoes the process require that piping be installed such that stresses are minimized and the coating is protected? References: 192.303, 192.319(a), 192.319(b)#
DC.COrecordPage 43DC.CO.INSTALL.RDo records demonstrate that piping was installed such that stresses are minimized and the coating is protected? References: 192.303, 192.319(a), 192.319(b), 192.493#
DC.COobservationPage 43DC.CO.INSTALL.OWhen pipe is placed in the ditch, do field observations confirm pipe is installed so as to fit the ditch, minimize stresses, and protect the pipe coating from damage? References: 192.319(a), 192.319(b)#
DC.COprocedurePage 44DC.CO.INSTALLOFFSHORE.PDoes the process require that certain offshore pipe be installed in accordance with 192.319(c)? References: 192.303, 192.319(c)#
DC.COrecordPage 44DC.CO.INSTALLOFFSHORE.RDo records indicate certain offshore pipe was installed in accordance with 192.319(c)? References: 192.319(c)#
DC.COobservationPage 44DC.CO.INSTALLOFFSHORE.ODo field observations confirm certain offshore pipe is installed in accordance with 192.319(c)? References: 192.319(c)#
DC.COprocedurePage 44DC.CO.INSTALLGOM.PDoes the process require that certain pipe in the Gulf of Mexico and its inlets be installed to the burial depths required by 192.319(c)? References: 192.303, 192.319(c)#
DC.COrecordPage 44DC.CO.INSTALLGOM.RDo records indicate that certain pipe in the Gulf of Mexico and its inlets was installed to the burial depths required by 192.319(c)? References: 192.303, 192.319(c)#
DC.COprocedurePage 44DC.CO.INSTALLPLASTIC.PDoes process require that plastic pipe be installed as required by 192.321? References: 192.303, 192.321(a), 192.321(b), 192.321(c), 192.321(d), 192.321(e), 192.321(f), 192.321(g)#
DC.COrecordPage 44DC.CO.INSTALLPLASTIC.RDo records indicate plastic pipe was installed as required by 192.321? References: 192.321(a), 192.321(b), 192.321(c), 192.321(d), 192.321(e), 192.321(f), 192.321(g)#
DC.COobservationPage 44DC.CO.INSTALLPLASTIC.ODo field observations confirm the plastic pipe is installed as required by 192.321? References: 192.321(a), 192.321(b), 192.321(c), 192.321(d), 192.321(e), 192.321(f), 192.321(g)#
DC.COprocedurePage 44DC.CO.CLEAR.PDoes the process require pipe to be installed with clearances specified in 192.325 and (if plastic) installed as to prevent heat damage to the pipe? References: 192.303, 192.325(a), 192.325(b), 192.325(c), 192.325(d)#
DC.COrecordPage 44DC.CO.CLEAR.RDo records indicate that transmission lines or mains are installed with clearances specified in 192.325, and (if plastic) installed as to prevent heat damage to the pipe? References: 192.325(a), 192.325(b), 192.325(c), 192.325(d)#
DC.COobservationPage 45DC.CO.CLEAR.ODo field observations indicate the transmission lines or mains (and bottles/bottle-type holders) are installed with the clearances specified in 192.325 and (if plastic) installed as to prevent heat damage to the pipe? References: 192.325(a), 192.325(b), 192.325(c), 192.325(d), 192.175(b)#
DC.COprocedurePage 45DC.CO.COVERONSHORE.PDoes the process specify that onshore piping is to be installed with a depth of cover as specified in 192.327? References: 192.303, 192.327(a), 192.327(b), 192.327(c), 192.327(d), 192.327(e)#
DC.COrecordPage 45DC.CO.COVERONSHORE.RIs onshore piping minimum cover provided as specified in 192.327? References: 192.327(a), 192.327(b), 192.327(c), 192.327(d), 192.327(e)#
DC.COobservationPage 45DC.CO.COVERONSHORE.ODo field observations confirm onshore piping was installed with the minimum cover specified in 192.327? References: 192.327(a), 192.327(b), 192.327(c), 192.327(d), 192.327(e)#
DC.COprocedurePage 45DC.CO.COVEROFFSHORE.PDoes the process require that offshore piping is to be installed with a depth of cover as specified in 192.327? References: 192.303, 192.327(f), 192.327(g), 192.612(c)(3)#
DC.COrecordPage 45DC.CO.COVEROFFSHORE.RDo records indicate offshore piping meets the minimum cover requirements specified in 192.327? References: 192.327(a), 192.327(f), 192.327(g), 192.612(c)(3)#
DC.COobservationPage 45DC.CO.COVEROFFSHORE.ODepth of Cover - Offshore To the extent possible, do field observations confirm offshore piping minimum cover as specified in 192.327? References: 192.327(a), 192.327(f), 192.327(g), 192.612(c)(3)#
DC.COprocedurePage 45DC.CO.AMAOPCONST.PAlternative MAOP: Construction For the AMAOP pipeline, does the process include conditions on the application of alternative MAOP? References: 192.303, 192.328, 192.620(b)#
DC.COrecordPage 45DC.CO.AMAOPCONST.RAlternative MAOP: Construction For the AMAOP pipeline, do records indicate the new or existing pipeline segments meet the additional construction requirements of 192.328? References: 192.328, 192.328(a), 192.328(b), 192.328(c), 192.328(d), 192.328(e), 192.620(b)#
DC.COobservationPage 46DC.CO.AMAOPCONST.OAlternative MAOP: Construction For the AMAOP pipeline, do field observations confirm the new or existing pipeline segments meet the additional construction requirements of 192.328? References: 192.328, 192.328(a), 192.328(b), 192.328(c), 192.328(d), 192.328(e), 192.620(b)#
DC.WELDINSPprocedurePage 46DC.WELDINSP.WELDVISUALQUAL.PDoes the operator have comprehensive written specifications or procedures for the inspection and testing of welds that meet the requirements of 192.241? References: 192.241, 192.225, 192.227, 192.229, 192.231, 192.233, 192.243, 192.245#
DC.WELDINSPrecordPage 46DC.WELDINSP.WELDVISUALQUAL.RDoes the operator have records showing that the welding was visually and/or non- destructively tested according to the requirements of 192.241 and the operator’s specifications or procedures? References: 192.241, 192.225, 192.227, 192.229, 192.231, 192.233, 192.243, 192.245#
DC.WELDINSPobservationPage 46DC.WELDINSP.WELDVISUALQUAL.ODo field observations confirm that inspection and testing of welds was being done in accordance with the requirements of 192.241 and the operator's written specifications or procedures? References: 192.241(a), 192.225, 192.227, 192.229, 192.231, 192.233, 192.243, 192.245#
DC.WELDINSPprocedurePage 46DC.WELDINSP.WELDNDT.PIs there a process for nondestructive testing and interpretation in accordance with 192.243? References: 192.243#
DC.WELDINSPrecordPage 46DC.WELDINSP.WELDNDT.RDo records indicate that NDT and interpretation are in accordance with 192.243? References: 192.243#
DC.WELDINSPobservationPage 46DC.WELDINSP.WELDNDT.ODo field observations indicate that welding NDT procedures are being properly followed? References: 192.243#
DC.WELDINSPprocedurePage 46DC.WELDINSP.WELDREPAIR.PDoes the process require welds that are unacceptable to be removed and/or repaired as specified by 192.245? References: 192.245, 192.303#
DC.WELDINSPrecordPage 47DC.WELDINSP.WELDREPAIR.RDo records indicate that unacceptable welds are removed and/or repaired in accordance with 192.245? References: 192.245, 192.303#
DC.WELDINSPobservationPage 47DC.WELDINSP.WELDREPAIR.ODo field observations confirm that unacceptable welds removed and/or repaired in accordance with 192.245? References: 192.245, 192.303#
DC.WELDPROCEDUREprocedurePage 47DC.WELDPROCEDURE.WELD.PDoes the operator have written specifications requiring qualified welding procedures in accordance with 192.225? References: 192.225#
DC.WELDPROCEDURErecordPage 47DC.WELDPROCEDURE.WELD.RDoes the operator have detailed records showing proper qualification of the welding procedures in accordance with 192.225? References: 192.225#
DC.WELDPROCEDUREobservationPage 47DC.WELDPROCEDURE.WELD.ODo field observations indicate proper qualification of the welding procedures in accordance with 192.225? References: 192.225#
DC.WELDPROCEDUREprocedurePage 47DC.WELDPROCEDURE.WELDERQUAL.PDo the written specifications require welders to be qualified in accordance with applicable sections of API Standard 1104 or ASME BPVC, Section IX and cover the limitations in §192.229? References: 192.227, 192.225, 192.229#
DC.WELDPROCEDURErecordPage 47DC.WELDPROCEDURE.WELDERQUAL.RDo the records demonstrate that the welders are qualified in accordance with applicable sections of API Standard 1104 or ASME BPVC, Section IX, and cover the limitations in §192.229? References: 192.227, 192.225, 192.229#
DC.WELDPROCEDUREobservationPage 47DC.WELDPROCEDURE.WELDERQUAL.ODo field observations confirm that the welders are qualified in accordance with applicable sections of API Standard 1104 or ASME BPVC, Section IX, and cover the limitations in §192.229? References: 192.227, 192.225, 192.229#
DC.WELDPROCEDUREprocedurePage 48DC.WELDPROCEDURE.WELDWEATHER.PDoes the operator have written specifications that require the welding operation to be protected from weather conditions that would impair the quality of the completed weld? References: 192.231, 192.225, 192.227#
DC.WELDPROCEDURErecordPage 48DC.WELDPROCEDURE.WELDWEATHER.RDoes the operator have records that document weather conditions, suspension, protective measures, and resumption of the welding processes to prevent impairment of the quality of the completed weld? References: 192.231, 192.225, 192.227#
DC.WELDPROCEDUREobservationPage 48DC.WELDPROCEDURE.WELDWEATHER.ODo field observations indicate that welding operations are protected from weather conditions that would impair the quality of welds? References: 192.231, 192.225, 192.227#
DC.WELDPROCEDUREprocedurePage 48DC.WELDPROCEDURE.MITERJOINT.PDoes the operator have written specifications or procedures that prohibit the use of certain miter joints as required by 192.233? References: 192.233#
DC.WELDPROCEDURErecordPage 48DC.WELDPROCEDURE.MITERJOINT.RMiter Joints In the event that improper miter joints are installed, does the operator have records to indicate that the miter joints were removed as required by 192.233? References: 192.233#
DC.WELDPROCEDUREobservationPage 48DC.WELDPROCEDURE.MITERJOINT.OMiter Joints In the event that miter joints were being used, do field observations show that the miter joints were properly constructed as required by 192.233? References: 192.233#
DC.WELDPROCEDUREprocedurePage 48DC.WELDPROCEDURE.WELDPREP.PDoes the operator have comprehensive written specifications or procedures that require preparations for welding in accordance with 192.235? References: 192.235#
DC.WELDPROCEDURErecordPage 48DC.WELDPROCEDURE.WELDPREP.RDo welding inspection records show that welding preparation was not performed according to 192.235 and the operator’s specifications or procedures, or that identified issues were not corrected? References: 192.235#
DC.WELDPROCEDUREobservationPage 48DC.WELDPROCEDURE.WELDPREP.ODo field observations confirm that welding preparations are being made in accordance with 192.235 and the operator's welding specifications and procedures? References: 192.235, 192.225, 192.227, 192.229, 192.231, 192.233, 192.241, 192.243, 192.245#
DC.DPprocedurePage 49DC.DP.PIPEDESGEN.PDoes the operator have specifications in place for pipe design so that the wall thickness is sufficient or installed with adequate protection to withstand external pressures and loads that will be imposed on the pipe after installation? References: 192.103, 192.105, 192.107, 192.109, 192.111, 192.112, 192.115, 192.121, 192.123, 192.125, 192.303, 192.305, 192.307#
DC.DPprocedurePage 49DC.DP.PIPEDESMAOP.PDoes the operator have written procedures in place for steel pipe design so that the wall thickness is sufficient for the intended maximum operating pressure as required by 192.105? References: 192.105, 192.103, 192.107, 192.109, 192.111, 192.113, 192.115, 192.121, 192.123, 192.125, 192.303, 192.305, 192.307#
DC.DPrecordPage 49DC.DP.PIPEDESMAOP.RDo design records and drawings indicate the design pressure of steel pipe is established in accordance with 192.105(a)? References: 192.105, 192.107, 192.109, 192.111, 192.113, 192.115#
DC.DPprocedurePage 49DC.DP.CLASSLOCATION.PDoes the operator have written procedures for determining the class location for the new (or converted) pipeline immediately prior to design? References: 192.111, 192.5, 192.105, 192.609#
DC.DPrecordPage 49DC.DP.CLASSLOCATION.RDoes the operator have complete records showing the determination of class location(s) for the new (or converted) pipeline? References: 192.111, 192.5, 192.105, 192.609#
DC.DPobservationPage 49DC.DP.CLASSLOCATION.ODo field verifications confirm the operator’s class location determinations for the new pipeline? References: 192.111, 192.5, 192.105, 192.609#
DC.DPprocedurePage 49DC.DP.PIPEDESFACTOR.PDoes the operator have written procedures for determining the Design Factor to be used for steel pipe as required by 192.111? References: 192.111, 192.103, 192.105, 192.107, 192.109, 192.112, 192.115, 192.121, 192.123, 192.125, 192.303, 192.305, 192.307#
DC.DPprocedurePage 49DC.DP.PIPEDESAMAOP.PDoes the operator have written procedures for the additional design requirements needed to be eligible for the alternative maximum allowable operating pressure (AMAOP) covered by 192.112 and calculated using 192.620? References: 192.112, 192.103, 192.105, 192.107, 192.109, 192.111, 192.115, 192.121, 192.123, 192.125, 192.303, 192.305, 192.307#
DC.DPrecordPage 50DC.DP.PIPEDESAMAOP.RDo design records indicate alternative MAOP replacement pipe and components meet the additional design requirements of 192.112? References: 192.112, 192.303#
DC.DPprocedurePage 50DC.DP.DESIGNPRESSPLASTIC.PDoes the process require the design pressure for plastic pipe to be determined in accordance with the formulas in 192.121? References: 192.103, 192.121#
DC.DPrecordPage 50DC.DP.DESIGNPRESSPLASTIC.RDo design records and drawings indicate the design pressure for plastic pipe is determined in accordance with the formulas in 192.121? References: 192.121#
DC.DPprocedurePage 50DC.DP.DESIGNLIMITPLASTIC.PDoes the process require the design limitations of 192.123 be incorporated into the design of plastic pipe? References: 192.103, 192.123(a), 192.123(b), 192.123(c), 192.123(d), 192.123(e), 192.123(f)#
DC.DPrecordPage 50DC.DP.DESIGNLIMITPLASTIC.RDo design records and drawings indicate that the design limitations of 192.123 are incorporated into the design of plastic pipe? References: 192.123(a), 192.123(b), 192.123(c), 192.123(d), 192.123(e), 192.123(f)#
DC.DPCCMPprocedurePage 50DC.DPCCMP.CMPBLDGLOCATE.PDoes the operator have written specifications requiring compressor stations be designed and constructed in accordance with 192.163? References: 192.163, 192.143#
DC.DPCCMPrecordPage 50DC.DPCCMP.CMPBLDGLOCATE.RDo the operator’s records indicate that the compressor station has been designed and constructed to comply with 192.163? References: 192.163, 192.143, 192.163(e)#
DC.DPCCMPobservationPage 50DC.DPCCMP.CMPBLDGLOCATE.ODo field observations confirm that design and construction of compressor station buildings meet the requirements of 192.163? References: 192.163, 192.143#
DC.DPCCMPprocedurePage 51DC.DPCCMP.CMPLIQPROT.PDoes the operator have written specifications that require compressors be protected from liquids? References: 192.165, 192.143, 192.153(e), 192.505(b)#
DC.DPCCMPrecordPage 51DC.DPCCMP.CMPLIQPROT.RDoes the operator have records to indicate that compressors are protected from liquids in accordance with 192.165? References: 192.165(a), 192.615(b), 192.153(e), 192.143#
DC.DPCCMPobservationPage 51DC.DPCCMP.CMPLIQPROT.ODo field observations confirm that compressors are protected from liquids and, as applicable, liquid separators for compressors installed in accordance with 192.165? References: 192.165, 192.143#
DC.DPCCMPprocedurePage 51DC.DPCCMP.CMPESD.PDoes the operator have written specifications requiring that compressor station emergency shutdown systems meet the requirements of 192.167? References: 192.167, 192.143#
DC.DPCCMPrecordPage 51DC.DPCCMP.CMPESD.RDo the operator’s records indicate that compressor station emergency shutdown systems meet the requirements of 192.167? References: 192.167, 192.143#
DC.DPCCMPobservationPage 51DC.DPCCMP.CMPESD.ODo field observations confirm that design and construction of compressor station emergency shutdown systems meet the requirements of 192.167? References: 192.167, 192.143#
DC.DPCCMPprocedurePage 51DC.DPCCMP.CMPPRESSLIMIT.PDoes the operator have written specifications requiring that compressor stations have pressure relief or other suitable protective devices that meet the requirements of 192.169? References: 192.169, 192.141, 192.143, 192.199#
DC.DPCCMPrecordPage 51DC.DPCCMP.CMPPRESSLIMIT.RDoes the operator have records to indicate that compressor stations have pressure relief or other suitable protective devices in accordance with 192.169? References: 192.169, 192.141, 192.143, 192.199#
DC.DPCCMPobservationPage 51DC.DPCCMP.CMPPRESSLIMIT.ODo field observations confirm design and construction of compressor station pressure limiting devices meet the requirements of 192.169? References: 192.169, 192.141, 192.143, 192.199#
DC.DPCCMPprocedurePage 52DC.DPCCMP.CMPSAFETYEQUIP.PDoes the operator have written specifications requiring additional compressor station safety equipment be designed and constructed in accordance with 192.171? References: 192.171, 192.143, 192.167(a)(3)#
DC.DPCCMPrecordPage 52DC.DPCCMP.CMPSAFETYEQUIP.RDo the operator’s records indicate that additional compressor station safety equipment is designed and constructed in accordance with 192.171? References: 192.171, 192.143#
DC.DPCCMPobservationPage 52DC.DPCCMP.CMPSAFETYEQUIP.ODo field observations confirm that design and construction of additional compressor station safety equipment meet the requirements of 192.171? References: 192.171, 192.141, 192.143#
DC.DPCCMPprocedurePage 52DC.DPCCMP.CMPVENTILATE.PDoes the operator have written specifications requiring ventilation of compressor buildings in accordance with 192.173? References: 192.173, 192.143#
DC.DPCCMPrecordPage 52DC.DPCCMP.CMPVENTILATE.RDo operator records indicate that the design and construction of compressor buildings meet the ventilation requirements of 192.173? References: 192.173, 192.143#
DC.DPCCMPobservationPage 52DC.DPCCMP.CMPVENTILATE.ODo field observations confirm that design and construction of compressor buildings meet the ventilation requirements of 192.173? References: 192.173, 192.143#
DC.DPCOPPprocedurePage 52DC.DPCOPP.OVERPRESSURE.PDoes the process require the pipeline have pressure relieving or pressure required of 192.195(a), and that they meet the requirements of 192.199 and 192.201? References: 192.303, 192.143(b), 192.195(a), 192.199(a), 192.199(b), 192.199(c), 192.199(d), 192.199(e), 192.199(f), 192.199(g), 192.199(h), 192.201(a), 192.20#
DC.DPCOPPrecordPage 52DC.DPCOPP.OVERPRESSURE.RDo records indicate that the pipeline has pressure relieving or pressure limiting devices that are required by 192.195(a), and that they meet the requirements of 192.199 and 192.201? References: 192.195(a), 192.199(a), 192.199(b), 192.199(c), 192.199(d), 192.199(e), 192.199(f), 192.199(g), 192.199(h), 192.201(a), 192.201(b), 192.201(c)#
DC.DPCOPPobservationPage 53DC.DPCOPP.OVERPRESSURE.OAre required pressure relieving or pressure limiting devices being installed, and do they meet the requirements of 192.199 and 192.201? References: 192.195(a), 192.199(a), 192.199(b), 192.199(c), 192.199(d), 192.199(e), 192.199(f), 192.199(g), 192.199(h), 192.201(a), 192.201(b), 192.201(c)#
DC.DPCOPPprocedurePage 53DC.DPCOPP.PRESSLIMIT.PDoes the process require that pressure relieving or pressure limiting devices meet the requirements of 192.199? References: 192.303, 192.143(b), 192.199(a), 192.199(b), 192.199(c), 192.199(d), 192.199(e), 192.199(f), 192.199(g), 192.199(h), 192.143(a)#
DC.DPCOPPrecordPage 53DC.DPCOPP.PRESSLIMIT.RDo records indicate that pressure relieving or pressure limiting devices meet the requirements of 192.199? References: 192.199(a), 192.199(b), 192.199(c), 192.199(d), 192.199(e), 192.199(f), 192.199(g), 192.199(h)#
DC.DPCOPPobservationPage 53DC.DPCOPP.PRESSLIMIT.ODo field observations confirm pressure relieving or pressure limiting devices meet the requirements of 192.199? References: 192.199(a), 192.199(b), 192.199(c), 192.199(d), 192.199(e), 192.199(f), 192.199(g), 192.199(h)#
DC.DPCOPPprocedurePage 53DC.DPCOPP.PRESSLIMITCAP.PDoes the process require that pressure relief or pressure limiting stations being installed comply with 192.201? References: 192.201(a), 192.143(a), 192.143(b), 192.201(b), 192.201(c)#
DC.DPCOPPrecordPage 53DC.DPCOPP.PRESSLIMITCAP.RDo records indicate that pressure relief or pressure limiting stations being installed comply with 192.201? References: 192.201(a), 192.201(b), 192.201(c)#
DC.DPCOPPobservationPage 53DC.DPCOPP.PRESSLIMITCAP.ODo field observations verify pressure relief or pressure limiting stations comply with the requirements of 192.201? References: 192.201(a), 192.201(b), 192.201(c)#
MO.GMprocedurePage 53MO.GM.TRAPSAFETY.PDo the procedures require all launchers and receivers to have adequate safety devices in accordance with 192.750 and to ensure the safety devices are working properly just prior to each use? References: 192.750, 192.605(b), 192.801, 192.805#
MO.GMrecordPage 54MO.GM.TRAPSAFETY.RDoes the operator have records to demonstrate whether all launchers and receivers have safety devices that were utilized prior to each use? References: 192.750, 192.605(b), 192.801, 192.805#
MO.GMobservationPage 54MO.GM.TRAPSAFETY.ODo field observations confirm selected launchers and receivers have safety devices installed and whether the safety devices were inspected prior to each use? References: 192.750, 192.605(b), 192.801, 192.805#
DC.DPCprocedurePage 54DC.DPC.METALCOMPONENT.PDo the procedures require certain metallic components to be qualified for use in accordance with 192.144? References: 192.144, 192.607#
DC.DPCrecordPage 54DC.DPC.METALCOMPONENT.RDo records indicate that certain metallic components are qualified for use in accordance with §192.144 and §192.205? References: 192.144(a), 192.144(b), 192.205, 192.607#
DC.DPCprocedurePage 54DC.DPC.VALVE.PDo the procedures require that valves comply with the requirements of §192.145? References: 192.145, 192.145(a), 192.145(b), 192.145(c), 192.145(d), 192.145(e), 192.145(f), 192.607#
DC.DPCrecordPage 54DC.DPC.VALVE.RDo records indicate valves comply with the requirements of §192.145 and §192.205? References: 192.145, 192.145(a), 192.145(b), 192.145(c), 192.145(d), 192.145(e), 192.145(f), 192.205, 192.607#
DC.DPCobservationPage 54DC.DPC.VALVE.ODo valves comply with the requirements of 192.145? References: 192.141, 192.145(a), 192.145(b), 192.145(c), 192.145(d), 192.145(e), 192.145(f), 192.607#
DC.DPCprocedurePage 54DC.DPC.FLANGE.PDo the procedures require that flanges and flange accessories meet the requirements of §192.147? References: 192.147, 192.147(a), 192.147(b), 192.147(c), 192.607#
DC.DPCrecordPage 55DC.DPC.FLANGE.RDo records indicate flanges and flange accessories meet the requirements of §192.147 and §192.205? References: 192.147, 192.147(a), 192.147(b), 192.147(c), 192.205, 192.607#
DC.DPCobservationPage 55DC.DPC.FLANGE.ODo flanges and flange accessories meet the requirements of 192.147? References: 192.147, 192.147(a), 192.147(b), 192.147(c), 192.607#
DC.DPCprocedurePage 55DC.DPC.STANDARDFITTING.PDo procedures require that standard fittings are in compliance with §192.149? References: 192.149, 192.149(a), 192.149(b), 192.149(c), 192.607#
DC.DPCrecordPage 55DC.DPC.STANDARDFITTING.RDo records indicate standard fittings are in compliance with §192.149 and §192.205? References: 192.149, 192.149(a), 192.149(b), 192.149(c), 192.205, 192.607#
DC.DPCobservationPage 55DC.DPC.STANDARDFITTING.ODo field observations confirm standard fittings are in compliance with §192.149? References: 192.149, 192.149(a), 192.149(b), 192.149(c), 192.607#
DC.DPCprocedurePage 55DC.DPC.ILIPASS.PDoes the process require that certain transmission pipeline components are designed and constructed to accommodate the passage of instrumented internal inspection devices? References: 192.103, 192.150(a), 192.150(c)#
DC.DPCrecordPage 55DC.DPC.ILIPASS.RDo records indicate that certain transmission pipeline components are designed and constructed to accommodate the passage of instrumented internal inspection devices? References: 192.150, 192.150(a), 192.150(c), 192.493#
DC.DPCobservationPage 55DC.DPC.ILIPASS.OAre certain transmission pipeline components designed and constructed to accommodate the passage of instrumented internal inspection devices? References: 192.150, 192.150(a), 192.150(c)#
DC.DPCprocedurePage 55DC.DPC.TAP.PDoes the process require pipeline hot taps (or taps) and tapping fittings to comply with the requirements of 192.151? References: 192.143, 192.151(a), 192.151(b), 192.151(c)#
DC.DPCrecordPage 56DC.DPC.TAP.RDo records indicate that tapping fittings and taps comply with the requirements of §192.151 and §192.205? References: 192.151, 192.151(a), 192.151(b), 192.151(c), 192.205#
DC.DPCobservationPage 56DC.DPC.TAP.ODo field observations confirm each length of pipe and each tapping component are being visually inspected for sufficient installation of taps in accordance with 192 192.151? References: 192.141, 192.151(a), 192.151(b), 192.151(c)#
DC.DPCprocedurePage 56DC.DPC.WELDFABRICATE.PDoes the process require components fabricated by welding, such as branch connections, assemblies of standard pipe, or prefabricated units utilized in the construction of a pipeline, are to be in accordance with 192.153? References: 192.143(a), 192.153(a), 192.153(b), 192.153(c), 192.153(d)#
DC.DPCrecordPage 56DC.DPC.WELDFABRICATE.RDo records indicate that components fabricated by welding, such as branch connections, assemblies of standard pipe, or prefabricated units utilized in the construction of a pipeline, are in accordance with §192.153 and §192.205? References: 192.153(a), 192.153(b), 192.153(c), 192.153(d), 192.205#
DC.DPCobservationPage 56DC.DPC.WELDFABRICATE.ODo field observations confirm that components fabricated by welding, such as branch connections, assemblies of standard pipe, or prefabricated units, are in accordance with §192.153? References: 192.141, 192.153(a), 192.153(b), 192.153(c), 192.153(d)#
DC.DPCrecordPage 56DC.DPC.WELDEDBRANCH.RDo records demonstrate that each welded branch connection in the form of a single connection, or in a header or manifold as a series of connections, were designed in accordance to §192.155 and §192.205? References: 192.155, 192.205#
DC.DPCobservationPage 56DC.DPC.WELDEDBRANCH.OWelded Branch Connections As applicable to the project, do field observations verify that each welded branch connection in the form of a single connection, or in a header or manifold as a series of connections, was installed as designed in accordance to §192.155? References: 192.155#
DC.DPCprocedurePage 56DC.DPC.EXTRUDEOUTLET.PDoes the process require each extruded outlet to be suitable for anticipated service conditions and designed in accordance to §192.157? References: 192.149(b), 192.157#
DC.DPCprocedurePage 56DC.DPC.FLEXIBLE.PDoes the process require pipeline and pipe components to be designed for flexibility in accordance with §192.159? References: 192.143(a), 192.159#
DC.DPCrecordPage 57DC.DPC.FLEXIBLE.RDo records indicate pipeline and pipe components are designed for flexibility in accordance with §192.159? References: 192.143(a), 192.159#
DC.DPCobservationPage 57DC.DPC.FLEXIBLE.ODo field observations verify that observed pipe and pipe components meet the flexibility design for thermal expansion/contraction and unusual loading or forces? References: 192.143(a), 192.159#
DC.DPCprocedurePage 57DC.DPC.SUPPORT.PDoes the process require piping and associated equipment to have sufficient anchors or supports to prevent undue strain on connected equipment, resist longitudinal forces, and prevent or dampen excessive vibration in accordance with §192.161? References: 192.161#
DC.DPCrecordPage 57DC.DPC.SUPPORT.RDo records indicate piping and associated equipment have sufficient anchors or supports to prevent undue strain on connected equipment, to resist longitudinal forces, and to prevent or dampen excessive vibration in accordance with §192.161? References: 192.161(a), 192.161(b), 192.161(c), 192.161(d), 192.161(e), 192.161(f), 192.205#
DC.DPCobservationPage 57DC.DPC.SUPPORT.ODo field observations confirm each length of pipe and each component is being visually inspected for sufficient installation of anchors or supports to prevent undue strain on connected equipment, to resist longitudinal forces, to prevent or dampen excessive vibration, and is in accordance with §192.161? References: 192.141, 192.161(a), 192.161(b), 192.161(c), 192.161(d), 192.161(e), 192.161(f)#
DC.DPCprocedurePage 57DC.DPC.VALVESPACE.PDoes the process require transmission line valve spacing to be accordance with §192.179( References: 192.143, 192.179(a), 192.179(a)(1), 192.179(a)(2), 192.179(a)(3), 192.179(a)(4), 192.179(b), 192.179(c), 192.179(d), 192.179(e), 192.179(f), 192.17#
DC.DPCrecordPage 57DC.DPC.VALVESPACE.RDo records indicate that transmission line valve spacing is in accordance with 192.179(a)? References: 192.179(a), 192.179(a)(1), 192.179(a)(2), 192.179(a)(3), 192.179(a)(4), 192.179(b), 192.179(c), 192.179(d)#
DC.DPCobservationPage 57DC.DPC.VALVESPACE.OAre transmission line valves being installed as required by 192.179? References: 192.141, 192.179(a), 192.179(b), 192.179(c), 192.179(d)#
DC.DPCprocedurePage 57DC.DPC.PLASTICFITTING.PDoes the process require plastic fittings conform to the standards referenced in 192.191? References: 192.191(a), 192.191(b)#
DC.DPCrecordPage 58DC.DPC.PLASTICFITTING.RDo records indicate that plastic fittings conform to the standards referenced in 192.191? References: 192.191(a), 192.191(b)#
DC.DPCprocedurePage 58DC.DPC.HOLDERS.PPipe and Bottle Type Holders As applicable to the project, does the process require that pipe and bottle type holders are designed to meet requirements? References: 192.143(a), 192.143(b), 192.175(a), 192.175(b), 192.177(a), 192.177(b)#
DC.DPCrecordPage 58DC.DPC.HOLDERS.RPipe and Bottle Type Holders As applicable to the project, do records indicate that pipe and bottle type holders are designed to meet requirements? References: 192.175(a), 192.175(b), 192.177(a), 192.177(b)#
DC.DPCobservationPage 58DC.DPC.HOLDERS.OPipe and Bottle Type Holders As applicable to the project, are pipe-type and bottle-type holders installed as designed and in accordance with 192.175? References: 192.141, 192.175(a), 192.175(b), 192.177(a), 192.177(b)#
DC.DPCprocedurePage 58DC.DPC.VAULT.PVaults Structural Design Requirements As applicable to the project, does the process require that vaults and valve pits are designed in accordance with 192.183? References: 192.143(a), 192.143(b), 192.183(a), 192.183(b), 192.183(c)#
DC.DPCrecordPage 58DC.DPC.VAULT.RVaults Structural Design Requirements As applicable to the project, do records indicate that vaults and valve pits are designed in accordance with 192.183? References: 192.183(a), 192.183(b), 192.183(c)#
DC.DPCobservationPage 58DC.DPC.VAULT.OVaults Structural Design Requirements As applicable to the project, are vaults/pits installed as designed, and per the requirements of 192.183? References: 192.141, 192.183(a), 192.183(b), 192.183(c)#
DC.DPCprocedurePage 58DC.DPC.VAULTACCESS.PVaults Accessibility As applicable to the project, does the process require that vaults are located in an accessible location? References: 192.143(a), 192.143(b), 192.185(a), 192.185(b), 192.185(c)#
DC.DPCrecordPage 58DC.DPC.VAULTACCESS.RVaults Accessibility As applicable to the project, do records indicate that vaults are located in an accessible location? References: 192.185(a), 192.185(b), 192.185(c)#
DC.DPCobservationPage 59DC.DPC.VAULTACCESS.OVaults Accessibility As applicable to the project, are vaults located in an accessible location? References: 192.141, 192.185(a)#
DC.DPCprocedurePage 59DC.DPC.VAULTSEAL.PVaults Sealing, Venting, and Ventilation As applicable to the project, does the process require that underground vaults or closed top pits are to be sealed, vented or ventilated as required by 192.187? References: 192.187(a), 192.187(b), 192.187(c)#
DC.DPCrecordPage 59DC.DPC.VAULTSEAL.RVaults Sealing, Venting, and Ventilation As applicable to the project, do records indicate that underground vaults or closed top pits are to be sealed, vented or ventilated as required by 192.187? References: 192.187(a), 192.187(b), 192.187(c)#
DC.DPCobservationPage 59DC.DPC.VAULTSEAL.OVaults Sealing, Venting, and Ventilation As applicable to the project, are vaults/pits sealed, ventilated, or vented as required of 192.187? References: 192.141, 192.187(a), 192.187(b), 192.187(c)#
DC.DPCprocedurePage 59DC.DPC.VAULTWATER.PVaults Drainage and Waterproofing As applicable to the project, does the process require that underground vaults or pits are protected from water intrusion as required of 192.189? References: 192.143(a), 192.143(b), 192.189(a), 192.189(b), 192.189(c)#
DC.DPCrecordPage 59DC.DPC.VAULTWATER.RVaults Drainage and Waterproofing As applicable to the project, do records indicate that underground vaults or pits are protected from water intrusion as required of 192.189? References: 192.189(a), 192.189(b), 192.189(c)#
DC.DPCobservationPage 59DC.DPC.VAULTWATER.OVaults Drainage and Waterproofing As applicable to the project, are vaults installed to minimize water entrance, and have proper electrical equipment? References: 192.141, 192.189(a), 192.189(b), 192.189(c)#
DC.DPCprocedurePage 59DC.DPC.INSTRUMENTPIPE.PInstrument, Control, and Sampling Pipe and Components As applicable to the project, does the process require that instrument, control, and sampling pipe and components are to be designed in accordance with 192.203? References: 192.143(a), 192.143(b), 192.203(a), 192.203(b)#
DC.DPCobservationPage 60DC.DPC.INSTRUMENTPIPE.OInstrument, Control, and Sampling Pipe and Components As applicable to the project, do field observations confirm that instrument, control, and sampling pipe and components are installed as designed and in accordance with 192.203? References: 192.141, 192.203(a), 192.203(b)#
DC.DPCprocedurePage 60DC.DPC.INTCORRODE.PDoes the process require that the transmission line project has features incorporated into its design and construction to reduce the risk of internal corrosion, as required of 192.476? References: 192.453, 192.476(a), 192.476(b), 192.476(c)#
DC.DPCrecordPage 60DC.DPC.INTCORRODE.RDo records demonstrate the transmission line project has features incorporated into its design and construction to reduce the risk of internal corrosion, as required of 192.476? References: 192.476(d), 192.476(b), 192.476(c), 192.476(a)#
DC.DPCobservationPage 60DC.DPC.INTCORRODE.ODoes the transmission project's design and construction comply with 192.476? References: 192.476(a), 192.476(b), 192.476(c)#
DC.DPCprocedurePage 60DC.DPC.CCPROTCOATSURFPREP.PDo the procedures and/or written specifications stipulate that each protective coating applied for the purpose of external corrosion control must be applied on a properly prepared surface? References: 192.143(b), 192.461(a), 192.303, 192.309(a)#
DC.DPCrecordPage 60DC.DPC.CCPROTCOATSURFPREP.RDo records indicate that each protective coating applied for the purpose of external corrosion control was applied on a properly prepared surface? References: 192.143(b), 192.461(a), 192.309(a), 192.491(c)#
DC.DPCobservationPage 60DC.DPC.CCPROTCOATSURFPREP.ODo field observations confirm that each protective coating applied for the purpose of external corrosion control was applied on a properly prepared surface in accordance of the operator’s written specifications? References: 192.143(b), 192.461(a), 192.309(a)#
DC.DPCprocedurePage 60DC.DPC.CCPROTCOATPROP.PDo the operator’s written specifications stipulate that each protective coating applied for the purpose of external corrosion control will have sufficient adhesion to the metal surface to effectively resist underfilm migration of moisture; sufficient ductility to resist cracking; sufficient strength to resist damage due to handling and soil stress; properties compatible with any supplemental cathodic protection; and, electrically insulating type with low moisture absorption and high electrical resistance? References: 192.143(b), 192.461(a)(2), 192.461(a)(3), 192.461(a)(4), 192.461(a)(5), 192.461(b)#
DC.DPCrecordPage 61DC.DPC.CCPROTCOATPROP.RDo records indicate that that each protective coating applied for the purpose of external corrosion control has sufficient adhesion to the metal surface to effectively resist underfilm migration of moisture; sufficient ductility to resist cracking; sufficient strength to resist damage due to handling and soil stress; properties compatible with any supplemental cathodic protection; and, electrically insulating type with low moisture absorption and high electrical resistance? References: 192.143(b), 192.461(a)(2), 192.461(a)(3), 192.461(a)(4), 192.461(a)(5), 192.461(b)#
DC.DPCobservationPage 61DC.DPC.CCPROTCOATPROP.ODo field observations confirm that each protective coating applied for the purpose of external corrosion control has sufficient adhesion to the metal surface to effectively resist underfilm migration of moisture; sufficient ductility to resist cracking; sufficient strength to resist damage due to handling and soil stress; properties compatible with any supplemental cathodic protection; and, electrically insulating type with low moisture absorption and high electrical resistance? References: 192.143(b), 192.461(a)(2), 192.461(a)(3), 192.461(a)(4), 192.461(a)(5), 192.461(b)#
DC.DPCprocedurePage 61DC.DPC.CCPROTCOATLOWER.PDo written specifications stipulate that each external protective coating must be inspected just prior to lowering the pipe into the ditch and backfilling, and any damage detrimental to effective corrosion control must be repaired? References: 192.143(b), 192.461(c)#
DC.DPCrecordPage 61DC.DPC.CCPROTCOATLOWER.RDo records indicate that each pipe segment with external protective coating was inspected just prior to lowering into the ditch and backfilling, and any damage detrimental to effective corrosion control was repaired? References: 192.143(b), 192.461(c)#
DC.DPCobservationPage 61DC.DPC.CCPROTCOATLOWER.ODo the field observations confirm that each pipe segment with external protective coating was inspected just prior to lowering into the ditch and backfilling, and any damage detrimental to effective corrosion control was repaired? References: 192.143(b), 192.461(c)#
DC.DPCprocedurePage 61DC.DPC.CCPROTCOATINGINDITCH.PDo operator’s written specifications stipulate that each external protective coating must be protected from damage resulting from adverse ditch conditions or damage from supporting blocks? References: 192.143(b), 192.461(d)#
DC.DPCrecordPage 61DC.DPC.CCPROTCOATINGINDITCH.RDo operator’s records indicate that each external protective coating was protected from damage resulting from adverse ditch conditions or damage from supporting blocks? References: 192.143(b), 192.461(d)#
DC.DPCobservationPage 62DC.DPC.CCPROTCOATINGINDITCH.ODo field observations verify that each external protective coating was protected from damage resulting from adverse ditch conditions or damage from supporting blocks? References: 192.143(b), 192.461(d)#
DC.DPCprocedurePage 62DC.DPC.CCPROTCOATBORING.PDo operator’s written specifications stipulate that precautions must be taken to minimize damage to the coating during installation, if coated pipe is installed by boring, driving, or other similar method? References: 192.143(b), 192.461(e)#
DC.DPCrecordPage 62DC.DPC.CCPROTCOATBORING.RDo records indicate that precautions were taken to minimize damage to the coating during installation, if coated pipe is installed by boring, driving, or other similar method? References: 192.143(b), 192.461(e)#
DC.DPCobservationPage 62DC.DPC.CCPROTCOATBORING.ODo field observations confirm that precautions were taken to minimize damage to the coating during installation, if coated pipe was installed by boring, driving, or other similar method? References: 192.143(b), 192.461(e)#
DC.DPCprocedurePage 62DC.DPC.CORROSIONQUAL.PDo the operator’s written specifications stipulate that the design and installation of cathodic protection systems, must be carried out by, or under the direction of, a person qualified in pipeline corrosion control methods? References: 192.303, 192.143(b), 192.453#
DC.DPCrecordPage 62DC.DPC.CORROSIONQUAL.RDo records verify that the design and installation of cathodic protection systems, were carried out by, or under the direction of, a person qualified in pipeline corrosion control methods? References: 192.491, 192.143(b), 192.453#
DC.DPCobservationPage 62DC.DPC.CORROSIONQUAL.ODo field observations confirm that the design and installation of cathodic protection systems, were carried out by, or under the direction of, a person qualified in pipeline corrosion control methods? References: 192.143(b), 192.453#
DC.DPCprocedurePage 62DC.DPC.CCCATHPROTDES.PDo operator’s written specifications stipulate that the cathodic protection system must be designed and installed to comply with one or more of the applicable criteria contained in Appendix D of Part 192? References: 192.463(a), 192.143(b)#
DC.DPCrecordPage 62DC.DPC.CCCATHPROTDES.RDo operator’s records indicate that the cathodic protection system was designed and installed to comply with one or more of the applicable criteria contained in Appendix D of Part 192? References: 192.463(a), 192.143(b)#
DC.DPCobservationPage 63DC.DPC.CCCATHPROTDES.ODo field observations confirm that the cathodic protection system was designed and installed to comply with one or more of the applicable criteria contained in Appendix D of Part 192? References: 192.463(a), 192.143(b)#
DC.DPCprocedurePage 63DC.DPC.CCCATHPROTLEVEL.PDo the operator’s written specifications stipulate that amount of cathodic protection must be designed so as not to damage the protective coating or the pipe? References: 192.303, 192.143, 192.463(c)#
DC.DPCrecordPage 63DC.DPC.CCCATHPROTLEVEL.RDo records verify that the amount of cathodic protection was designed and installed so as not to damage the protective coating or the pipe? References: 192.491, 192.143(b), 192.463(c)#
DC.DPCobservationPage 63DC.DPC.CCCATHPROTLEVEL.ODo field observations confirm that the cathodic protection system was designed and installed so that the amount of cathodic protection would not damage the protective coating or the pipe? References: 192.143(b), 192.463(c)#
DC.DPCprocedurePage 63DC.DPC.CCELECTRICALISOL.PDo operator’s written specifications stipulate that each pipeline must be electrically isolated from metallic casings that are a part of the underground system? References: 192.467(c), 192.143(b)#
DC.DPCrecordPage 63DC.DPC.CCELECTRICALISOL.RDo operator’s records indicate that each pipeline was electrically isolated from metallic casings that are a part of the underground system? References: 192.467(c), 192.143(b)#
DC.DPCobservationPage 63DC.DPC.CCELECTRICALISOL.ODo field observations confirm that each pipeline was electrically isolated from metallic casings that are a part of the underground system? References: 192.467(c), 192.143(b)#
DC.DPCprocedurePage 63DC.DPC.CCELECTRISOLSTRUCT.PDo written specifications stipulate that each buried or submerged pipeline must be electrically isolated from other underground metallic structures? References: 192.143(b), 192.467(a), 192.467(b), 192.467(d), 192.467(e), 192.467(f)#
DC.DPCrecordPage 64DC.DPC.CCELECTRISOLSTRUCT.RDo records indicate that each buried or submerged pipeline was electrically isolated from other underground metallic structures? References: 192.143(b), 192.467(a), 192.467(b), 192.467(d), 192.467(e), 192.467(f)#
DC.DPCobservationPage 64DC.DPC.CCELECTRISOLSTRUCT.ODo field observations confirm that each buried or submerged pipeline was designed and installed so that it was electrically isolated from other underground metallic structures or where electrical isolation of a portion of a pipeline is necessary to facilitate the application of corrosion control? References: 192.143(b), 192.467(a), 192.467(b), 192.467(d), 192.467(e), 192.467(f)#
DC.DPCprocedurePage 64DC.DPC.CCEXTRNLPROT.PDo the written specifications stipulate that each buried or submerged pipeline installed after July 31, 1971, must be protected against external corrosion within 1 year after completion of construction, conversion to service, or becoming jurisdictional onshore gathering? References: 192.303, 192.143(b), 192.455(a)#
DC.DPCrecordPage 64DC.DPC.CCEXTRNLPROT.RDo records document that each buried or submerged pipeline installed after July 31, 1971, has been protected against external corrosion with a cathodic protection system within one year after completion of construction, conversion to service, or becoming jurisdictional onshore gathering? References: 192.143(b), 192.455(a)#
DC.DPCprocedurePage 64DC.DPC.AMPHOTERIC.PDo the operator’s written specifications describe criteria to be used for cathodic protection of amphoteric metals (e.g., aluminum, copper, zinc, tin, lead, and beryllium) that are included in a pipeline containing a metal or different anodic potential (e.g., steel, etc.)? References: 192.303, 192.143, 192.463(b)#
DC.DPCrecordPage 64DC.DPC.AMPHOTERIC.RDo records verify adequate cathodic protection of amphoteric metals (e.g., aluminum, etc.) that are included in a pipeline containing a metal or different anodic potential (e.g., steel, etc.)? References: 192.491(a), 192.491(b), 192.463(b)#
DC.DPCrecordPage 64DC.DPC.AMAOP.RDo records indicate alternative MAOP replacement facilities/components meet the design and test factor requirements listed in §192.620(a)? References: 192.620(a), 192.620(b), 192.205#
DC.DPCprocedurePage 64DC.DPC.RMVINSTALLHCA.PDo the operator’s specifications require RMVs or AETs located in an HCA or in Class 3 or 4 locations to be installed to meet the appropriate valve spacing requirements? References: 192.605(b), 192.634, 192.636#
DC.DPCrecordPage 65DC.DPC.RMVINSTALLHCA.RDo records demonstrate RMVs or AETs were located in an HCA and Class 3 or 4 areas to meet the appropriate valve spacing requirements? References: 192.709(c), 192.634, 192.636#
DC.DPCprocedurePage 65DC.DPC.ASVFLOWMODEL.PDo the operator’s procedures adequately describe and require flow modeling for ASVs? References: 192.605(b), 192.636(f)#
DC.DPCrecordPage 65DC.DPC.ASVFLOWMODEL.RDo the records demonstrate the flow modeling was conducted as required in accordance with §192.636(f)? References: 192.709(c), 192.636(f), 192.745#
DC.GAprocedurePage 65DC.GA.COMPLIANCE.PDoes evidence demonstrate compliance with the design and installation requirements of Part 192 for certain gathering lines? References: 192.9(a), 192.9(b), 192.9(c), 192.9(d)#
DC.GAobservationPage 65DC.GA.COMPLIANCE.ODoes evidence demonstrate compliance with the design and installation requirements of Part 192 for certain gathering lines? References: 192.9(a), 192.9(b), 192.9(c), 192.9(d)#
DC.MOprocedurePage 65DC.MO.ICEXAMINE.PDoes the process direct personnel to examine removed pipe for evidence of internal corrosion? References: 192.605(b), 192.475(a), 192.475(b), 192.475(c)#
DC.MOrecordPage 65DC.MO.ICEXAMINE.RDo records indicate examination of removed pipe for evidence of internal corrosion? References: 192.491(c), 192.475(a), 192.475(b), 192.475(c)#
DC.MOobservationPage 65DC.MO.ICEXAMINE.OIs examination of removed pipe conducted to determine any evidence of internal corrosion? References: 192.475(a), 192.475(b), 192.475(c)#
DC.MOprocedurePage 66DC.MO.MAOPLIMIT.PDoes the process include procedures for starting up and shutting down any part of the pipeline system in a manner designed to assure operation within the MAOP limits prescribed by Part 192, plus the build-up allowed for operation of pressure-limiting and control devices? References: 192.605(b)(5)#
DC.MOrecordPage 66DC.MO.MAOPLIMIT.RDo records indicate that the pressure limitations on the pipeline are not exceeded? References: 192.605(b)(5)#
DC.MOobservationPage 66DC.MO.MAOPLIMIT.OStart-Stop Procedures During startup or shut-in, is it assured that the pressure limitations on the pipeline were not exceeded? References: 192.605(b)(5)#
DC.MOprocedurePage 66DC.MO.IGNITION.PPrevention of Accidental Ignition As applicable to the project, is a process in place for preventing accidental ignition where gas presents a hazard of fire or explosion? References: 192.605(b), 192.751(a), 192.751(b), 192.751(c)#
DC.MOobservationPage 66DC.MO.IGNITION.OIf applicable to the project, were processes followed where there exists the potential for accidental ignition? References: 192.751(a), 192.751(b), 192.751(c)#
DC.MOprocedurePage 66DC.MO.HOTTAP.PAre there processes for tapping pipelines under pressure? References: 192.605(b), 192.627#
DC.MOrecordPage 66DC.MO.HOTTAP.RDo records indicate that hot taps are performed in accordance with hot tap procedures? References: 192.627#
DC.MOobservationPage 66DC.MO.HOTTAP.OAre hot taps are performed in accordance with hot tap procedures? References: 192.627#
DC.MOprocedurePage 66DC.MO.SAFETY.PDoes the process ensure that pipeline maintenance construction and testing activities are made to provide safety, as required of 192.605(b)? References: 192.605(b), 192.605(b)(9)#
DC.MOrecordPage 66DC.MO.SAFETY.RDo records indicate that pipeline maintenance construction and testing activities are performed in a safe manner? References: 192.605(b), 192.605(b)(9)#
DC.MOobservationPage 67DC.MO.SAFETY.OAre pipeline maintenance construction and testing activities made in a safe manner? References: 192.605(b), 192.605(b)(9)#
DC.MOprocedurePage 67DC.MO.OMPROCEDURES.PDoes the process require that procedures for operations, abnormal operations, maintenance, and emergencies be completed and implemented prior to the pipeline going into service? References: 192.605(a)#
DC.MAprocedurePage 67DC.MA.GEN.PDoes the operator have written specifications or procedures that require that materials for pipe and components meet the requirements of 192.53? References: 192.53, 192.55, 192.59, 192.63#
DC.MArecordPage 67DC.MA.GEN.RDo records demonstrate that materials for pipe and components have met the requirements of §192.53 and §192.205? References: 192.53, 192.55, 192.59, 192.63, 192.205#
DC.MAprocedurePage 67DC.MA.STEELPIPE.PDoes the operator have written procedures or specifications that require steel pipe be qualified for use under Part 192 according to 192.55? (see considerations for requirements of 192.55) References: 192.55, 192.53#
DC.MArecordPage 67DC.MA.STEELPIPE.RDoes the operator have records showing that the steel pipe is qualified for use under Part 192 according to 192.55? (see considerations for requirements of 192.55) References: 192.55(a), 192.55(b), 192.55(c), 192.55(d), 192.55(e)#
DC.MAobservationPage 67DC.MA.STEELPIPE.ODo field observations confirm the steel pipe is qualified in accordance with 192.55? References: 192.55(a), 192.55(b), 192.55(c), 192.55(d), 192.55(e)#
DC.MAprocedurePage 67DC.MA.PLASTIC.PDoes the operator have specifications that require plastic pipe meet the requirements of 192.53, 192.59, and other applicable requirements of this sub-part? References: 192.53, 192.59#
DC.MArecordPage 68DC.MA.PLASTIC.RDo records indicate that plastic pipe is qualified in accordance with 192.59? References: 192.53, 192.59#
DC.MAobservationPage 68DC.MA.PLASTIC.ODo field observations confirm the plastic pipe meets the requirements of 192.53 and applicable requirements of this subpart? References: 192.53, 192.59#
DC.MAprocedurePage 68DC.MA.MARKING.PDoes the operator have specifications requiring pipe, valves, and fittings to be marked according to the requirements of 192.63? References: 192.63#
DC.MArecordPage 68DC.MA.MARKING.RDo records indicate that pipe, valves, and fittings were marked as required? References: 192.63#
DC.MAobservationPage 68DC.MA.MARKING.ODo field observations confirm the pipe, valves, and fittings are marked according to the requirements of 192.63? References: 192.63#
DC.MAprocedurePage 68DC.MA.RAILTRANSPORT.PDoes the operator have specifications requiring that railroad transportation for certain pipe (see considerations) is in accordance with 192.65(a) and API RP 5L1? References: 192.65(a), 192.53(a)#
DC.MArecordPage 68DC.MA.RAILTRANSPORT.RDoes the operator have records showing that railroad transportation for certain pipe (see considerations) was in accordance with 192.65(a) and API RP 5L1? References: 192.65(a)#
DC.MAobservationPage 68DC.MA.RAILTRANSPORT.ODo field observations confirm that railroad transportation for certain pipe (see considerations) was in accordance with 192.65(a) and API RP 5L1? References: 192.65(a)#
DC.MAprocedurePage 68DC.MA.BARGETRANSPORT.PDoes the operator have specifications requiring that ship or barge transportation for certain pipe (see considerations) is in accordance with 192.65(b) and API RP 5LW? References: 192.65(b)#
DC.MArecordPage 68DC.MA.BARGETRANSPORT.RDoes the operator have records showing that ship or barge transportation for certain pipe (see considerations) is in accordance with 192.65(b) and API RP 5LW? References: 192.65(b)#
DC.MAobservationPage 69DC.MA.BARGETRANSPORT.ODo field observations confirm that the operator has used ship or barge transportation for certain pipe (see considerations) in accordance with 192.65(b) and API RP 5LW? References: 192.65(b)#
DC.MAprocedurePage 69DC.MA.TRUCKTRANSPORT.PDoes the operator have specifications requiring that truck transportation for certain pipe (see considerations) is in accordance with 192.65(c) and API RP 5LT? References: 192.65(c)#
DC.MArecordPage 69DC.MA.TRUCKTRANSPORT.RDoes the operator have records showing that truck transportation for certain pipe (see considerations) is in accordance with 192.65(c) and API RP 5LT? References: 192.65(c)#
DC.MAobservationPage 69DC.MA.TRUCKTRANSPORT.ODo field observations confirm that the operator has performed truck transportation for certain pipe (see considerations) in accordance with 192.65(c) and API RP 5LT? References: 192.65(c)#
DC.PTprocedurePage 69DC.PT.PRESSTEST.PDoes the process require pressure testing to be conducted for new segments of pipeline, or return to service segments of pipeline that are being relocated or replaced? References: 192.605(b), 192.303, 192.503(a), 192.503(b), 192.503(c), 192.503(d), 192.503(e)#
DC.PTrecordPage 69DC.PT.PRESSTEST.RDo records indicate that pressure testing is conducted in accordance with 192.503? References: 192.503(a), 192.503(b), 192.503(c), 192.503(d), 192.503(e)#
DC.PTobservationPage 69DC.PT.PRESSTEST.OIs pressure testing conducted in accordance with 192.503? References: 192.503(a), 192.503(b), 192.503(c), 192.503(d), 192.503(e)#
DC.PTprocedurePage 70DC.PT.PRESSTESTHIGHSTRESS.PDoes the process require that, as applicable to the project, sections of a pipeline operating at a hoop stress equal to or greater than 30% of SMYS be strength tested in accordance with the requirements of 192.505? References: 192.505(a), 192.143(a), 192.505(b), 192.505(c), 192.505(d), 192.143(b), 192.143(c)#
DC.PTrecordPage 70DC.PT.PRESSTESTHIGHSTRESS.RDo records indicate that the sections of a pipeline operating at a hoop stress equal to or greater than 30% of SMYS were strength tested in accordance with the requirements of 192.505? References: 192.505(a), 192.143(a), 192.517(a), 192.505(b), 192.505(c), 192.505(d), 192.143(b), 192.143(c)#
DC.PTobservationPage 70DC.PT.PRESSTESTHIGHSTRESS.ODo field observations confirm that sections of a pipeline operating at a hoop stress equal to or greater than 30% of SMYS are strength tested in accordance with the requirements of 192.505? References: 192.505(a), 192.143(a), 192.505(b), 192.505(c), 192.505(d), 192.143(b), 192.143(c)#
DC.PTprocedurePage 70DC.PT.PRESSTESTPLASTIC.PDoes the process require that, as applicable to the project, sections of a plastic pipel must be tested in accordance with the requirements of 192.513? References: 192.513(a), 192.143(a), 192.121(a), 192.513(b), 192.513(c), 192.513(d), 192.143(b), 192.143(c), 192.121(b), 192.121(c), 192.121(d), 192.121(e), 192.12#
DC.PTrecordPage 70DC.PT.PRESSTESTPLASTIC.RDo records indicate that the sections of a plastic pipeline were tested in accordance with the requirements of 192.513? References: 192.513(a), 192.143(a), 192.517(b), 192.513(c), 192.513(d), 192.143(b), 192.143(c)#
DC.PTobservationPage 70DC.PT.PRESSTESTPLASTIC.ODo field observations confirm that sections of a plastic pipeline are tested in accordance with the requirements of 192.513? References: 192.513(a), 192.143(a), 192.513(b), 192.513(c), 192.513(d), 192.143(b), 192.143(c)#
DC.PTprocedurePage 70DC.PT.PRESSTESTENVIRON.PDoes the process require that, as applicable to the project, while conducting tests under Subpart J – Test Requirements, the test medium will be disposed of in a manner that will minimize damage to the environment? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTrecordPage 70DC.PT.PRESSTESTENVIRON.RDo records indicate while conducting tests under Subpart J – Test Requirements, the test medium disposal was conducted in a manner that minimized damage to the environment? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTobservationPage 71DC.PT.PRESSTESTENVIRON.ODo field observations confirm while conducting tests under Subpart J – Test Requirements, the test medium was disposed of in an environmentally sound manner? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTprocedurePage 71DC.PT.PRESSTESTSAFETY.PDoes the process require that, as applicable to the project, while conducting tests under Subpart J – Test Requirements, every reasonable precaution is taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTrecordPage 71DC.PT.PRESSTESTSAFETY.RDo records indicate while conducting tests under Subpart J – Test Requirements, every reasonable precaution was taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTobservationPage 71DC.PT.PRESSTESTSAFETY.ODo field observations confirm while conducting tests under Subpart J – Test Requirements, every reasonable precaution is taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTprocedurePage 71DC.PT.PRESSTESTRECORD.PDoes the process require that, as applicable to the project, creation and retention of a record of each Subpart J test for the required duration? References: 192.517(a), 192.517(b)#
DC.PTrecordPage 71DC.PT.PRESSTESTRECORD.RDo records indicate creation and retention of a record for each Subpart J test performed for the required duration? References: 192.517(a), 192.517(b)#
DC.SPTprocedurePage 72DC.SPT.SPIKEPRESSTEST.PDo the operator’s procedures provide adequate instruction for conducting a Spike hydrotest, if applicable, according to the regulations? References: 192.605(b), 192.506#
DC.SPTrecordPage 72DC.SPT.SPIKEPRESSTEST.RDo records indicate that spike pressure testing is/was conducted in accordance with §192.506? References: 192.709, 192.506, 192.517#
DC.SPTobservationPage 72DC.SPT.SPIKEPRESSTEST.ODo field observations verify pressure testing is conducted in accordance with §192.506? References: 192.506, 192.503#
DC.PTprocedurePage 72DC.PT.PRESSTESTENVIRON.PDoes the process require that, as applicable to the project, while conducting tests under Subpart J – Test Requirements, the test medium will be disposed of in a manner that will minimize damage to the environment? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTrecordPage 72DC.PT.PRESSTESTENVIRON.RDo records indicate while conducting tests under Subpart J – Test Requirements, the test medium disposal was conducted in a manner that minimized damage to the environment? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTobservationPage 72DC.PT.PRESSTESTENVIRON.ODo field observations confirm while conducting tests under Subpart J – Test Requirements, the test medium was disposed of in an environmentally sound manner? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTprocedurePage 72DC.PT.PRESSTESTSAFETY.PDoes the process require that, as applicable to the project, while conducting tests under Subpart J – Test Requirements, every reasonable precaution is taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTrecordPage 73DC.PT.PRESSTESTSAFETY.RDo records indicate while conducting tests under Subpart J – Test Requirements, every reasonable precaution was taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTobservationPage 73DC.PT.PRESSTESTSAFETY.ODo field observations confirm while conducting tests under Subpart J – Test Requirements, every reasonable precaution is taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTprocedurePage 73DC.PT.PRESSTESTRECORD.PDoes the process require that, as applicable to the project, creation and retention of a record of each Subpart J test for the required duration? References: 192.517(a), 192.517(b)#
DC.PTrecordPage 73DC.PT.PRESSTESTRECORD.RDo records indicate creation and retention of a record for each Subpart J test performed for the required duration? References: 192.517(a), 192.517(b)#
DC.PTprocedurePage 73DC.PT.PRESSTEST.PDoes the process require pressure testing to be conducted for new segments of pipeline, or return to service segments of pipeline that are being relocated or replaced? References: 192.605(b), 192.303, 192.503(a), 192.503(b), 192.503(c), 192.503(d), 192.503(e)#
DC.PTrecordPage 73DC.PT.PRESSTEST.RDo records indicate that pressure testing is conducted in accordance with 192.503? References: 192.503(a), 192.503(b), 192.503(c), 192.503(d), 192.503(e)#
DC.PTobservationPage 74DC.PT.PRESSTEST.OIs pressure testing conducted in accordance with 192.503? References: 192.503(a), 192.503(b), 192.503(c), 192.503(d), 192.503(e)#
DC.PTLOWPRESSprocedurePage 74DC.PTLOWPRESS.PRESSTESTLOWSTRESS.PDoes the process require that, as applicable to the project, sections of a pipeline operating at a hoop stress less than 30% of SMYS and at or above 100 psig be tested in accordance with the requirements of 192.507? References: 192.507, 192.505, 192.515#
DC.PTLOWPRESSrecordPage 74DC.PTLOWPRESS.PRESSTESTLOWSTRESS.RDo records indicate that, as applicable to the project, sections of a pipeline operating at a hoop stress less than 30% of SMYS and at or above 100 psig were tested in accordance with the requirements of 192.507? References: 192.507, 192.505, 192.515, 192.517#
DC.PTLOWPRESSobservationPage 74DC.PTLOWPRESS.PRESSTESTLOWSTRESS.ODo field observations confirm that sections of a pipeline operating at a hoop stress less than 30% of SMYS and at or above 100 psig are tested in accordance with the requirements of 192.507? References: 192.507, 192.505, 192.515#
DC.PTLOWPRESSprocedurePage 74DC.PTLOWPRESS.PRESSTEST100PSIG.PDoes the process require that, as applicable to the project, sections of a pipeline operated below 100 psig shall be leak tested in accordance with the section requirements of 192.509 (except for service lines and plastic pipelines)? References: 192.509, 192.143#
DC.PTLOWPRESSrecordPage 74DC.PTLOWPRESS.PRESSTEST100PSIG.RDo records indicate that the sections of a pipeline operated below 100 psig were leak tested in accordance with the section requirements of 192.509 (except for service lines and plastic pipelines)? References: 192.509, 192.143, 192.517#
DC.PTLOWPRESSobservationPage 74DC.PTLOWPRESS.PRESSTEST100PSIG.ODo field observations confirm that sections of a pipeline operated below 100 psig are leak tested in accordance with the requirements of 192.509 (except for service lines and plastic pipelines)? References: 192.509, 192.143#
DC.PTLOWPRESSprocedurePage 74DC.PTLOWPRESS.PRESSTESTSERVICE.PDoes the process require that, as applicable to the project, service line segments (other than plastic) shall be leak tested before being placed in service in compliance with the requirements of 192.511? References: 192.511(a), 192.143(a), 192.511(b), 192.511(c), 192.143(b)#
DC.PTLOWPRESSrecordPage 75DC.PTLOWPRESS.PRESSTESTSERVICE.RDo records indicate that service line segments (other than plastic) were leak tested before being placed in service in compliance with the requirements of 192.511? References: 192.511(a), 192.143(a), 192.517(b), 192.143(b), 192.511(b), 192.511(c)#
DC.PTLOWPRESSobservationPage 75DC.PTLOWPRESS.PRESSTESTSERVICE.ODo field observations confirm that service line segments (other than plastic) are leak tested before being placed in service in compliance with the requirements of 192.511? References: 192.511(a), 192.143(a), 192.511(b), 192.143(b), 192.511(c)#
DC.PTprocedurePage 75DC.PT.PRESSTESTENVIRON.PDoes the process require that, as applicable to the project, while conducting tests under Subpart J – Test Requirements, the test medium will be disposed of in a manner that will minimize damage to the environment? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTrecordPage 75DC.PT.PRESSTESTENVIRON.RDo records indicate while conducting tests under Subpart J – Test Requirements, the test medium disposal was conducted in a manner that minimized damage to the environment? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTobservationPage 75DC.PT.PRESSTESTENVIRON.ODo field observations confirm while conducting tests under Subpart J – Test Requirements, the test medium was disposed of in an environmentally sound manner? References: 192.515(b), 192.629(a), 192.629(b)#
DC.PTprocedurePage 75DC.PT.PRESSTESTSAFETY.PDoes the process require that, as applicable to the project, while conducting tests under Subpart J – Test Requirements, every reasonable precaution is taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTrecordPage 75DC.PT.PRESSTESTSAFETY.RDo records indicate while conducting tests under Subpart J – Test Requirements, every reasonable precaution was taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTobservationPage 76DC.PT.PRESSTESTSAFETY.ODo field observations confirm while conducting tests under Subpart J – Test Requirements, every reasonable precaution is taken to protect its employees and the general public throughout the testing? References: 192.515(a), 192.629(a), 192.629(b)#
DC.PTprocedurePage 76DC.PT.PRESSTESTRECORD.PDoes the process require that, as applicable to the project, creation and retention of a record of each Subpart J test for the required duration? References: 192.517(a), 192.517(b)#
DC.PTrecordPage 76DC.PT.PRESSTESTRECORD.RDo records indicate creation and retention of a record for each Subpart J test performed for the required duration? References: 192.517(a), 192.517(b)#
DC.SPobservationPage 76DC.SP.SP.OIs the pipeline and applicable facilities being replaced in accordance with the design and construction requirements of Part 192 and the conditions of the Special Permit? References: 190.341(d)(2)#
DC.TQprocedurePage 76DC.TQ.OQCONSTMAINT.PDoes the process include covered tasks relating to "construction- type" maintenance? References: 192.805(a), 192.493#
DC.TQrecordPage 76DC.TQ.ABNORMAL.RDo records show evaluation of qualified individuals for recognition and reaction to AOCs? References: 192.807(a), 192.803#
DC.TQrecordPage 77DC.TQ.OQCONTRACTOR.RAre qualification records maintained for contractor personnel? References: 192.807(a)#
DC.TQobservationPage 77DC.TQ.OQCONTRACTOR.ODo selected contractor individuals performing covered tasks demonstrate adequate skills and knowledge? References: 192.805(b)#
DC.TQrecordPage 77DC.TQ.RECORDS.RAre qualification records maintained for operator personnel? References: 192.807(a)#
DC.TQobservationPage 77DC.TQ.OQPLANEMPLOYEE.ODo selected operator individuals performing covered tasks demonstrate adequate skills and knowledge? References: 192.805(b)#
DC.TQrecordPage 77DC.TQ.EXCAVATE.RWho Oversee and Perform Excavations and Backfilling Operations Do records demonstrate individuals who oversee marking, trenching and backfilling operations are qualified? References: 192.807(a)#
DC.TQobservationPage 77DC.TQ.EXCAVATE.OWho Oversee and Perform Excavations and Backfilling Operations Do selected individuals who oversee marking, trenching and backfilling operations demonstrate adequate skills and knowledge? References: 192.805(b)#
DC.TQrecordPage 77DC.TQ.HOTTAP.RDo records document the qualification of personnel performing hot taps? References: 192.807(a), 192.627#
DC.TQobservationPage 77DC.TQ.HOTTAP.ODo personnel performing hot taps demonstrate adequate skills and knowledge? References: 192.805(b), 192.627#
DC.CONVrecordPage 78DC.CONV.NOTIFICATION.RDo records indicate operator provided required notifications to PHMSA not later than 60 days before the conversion began as required by §191.22(c)? References: 191.22(c)(1), 192.14(c), 191.17(a)#
DC.CONVprocedurePage 78DC.CONV.PROCEDURE.PDid the operator prepare a comprehensive written Conversion to Service procedure that includes all of the requirements of §192.14? References: 192.14(a)(1)#
DC.CONVrecordPage 78DC.CONV.INTEGRITYMGMT.RDo the records indicate the pipeline's Integrity Management history and related activities were reviewed? References: 192.14(a)(1)#
DC.CONVprocedurePage 78DC.CONV.PHYSICALDEFECTS.PDoes the conversion procedure include requirement to visually inspect aboveground segments of the pipeline for physical defects and operating conditions which could be expected to impair the strength of the pipeline, as required by §192.14(a)(2)? References: 192.14(a)(2)#
DC.CONVrecordPage 78DC.CONV.PHYSICALDEFECTS.RDo the records indicate the aboveground segments of the pipeline was were visually inspected for physical defects and operating conditions which could be expected to impair the strength of the pipeline, as required by §192.14(a)(2)? References: 192.14(a)(2)#
DC.CONVprocedurePage 78DC.CONV.UNSAFEDEFECTS.PDoes the conversion procedure include requirement to identify and correct all known unsafe defects and conditions as required by §192.14(a)(3)? References: 192.14(a)(3)#
DC.CONVrecordPage 78DC.CONV.UNSAFEDEFECTS.RDo the records indicate operator corrected (or has plans to correct) all known unsafe defects and conditions as required by §192.14(a)(3) and conducted in accordance with Part 192? References: 192.14(a)(3)#
DC.CONVprocedurePage 78DC.CONV.HCAID.PDoes the process include an HCA analysis (per the methods defined in §192.903) to the converted pipeline for the identification of High Consequence Areas? References: 192.905(a), 192.903#
DC.CONVrecordPage 78DC.CONV.HCAID.RDo records demonstrate that the identification of pipeline segments in HCAs was completed in accordance with process requirements? References: 192.947(d), 192.903, 192.905(a)#
DC.CONVprocedurePage 79DC.CONV.HCAPIR.PIs the process for defining and applying potential impact radius (PIR) for establishment of high consequence areas consistent with the requirements of 192.903? References: 192.903, 192.905(a)#
DC.CONVrecordPage 79DC.CONV.HCAPIR.RDo records demonstrate the use of potential impact radius (PIR) for establishment of high consequence areas was consistent with requirements of §192.903? References: 192.947(d), 192.903, 192.905(a)#
DC.CONVprocedurePage 79DC.CONV.RISKASSESSMENT.PDoes the conversion procedure require a Risk Assessment to be performed to identify threats and hazards associated with the conversion to the new service? References: 192.14(a)(1), 192.911(b), 192.911(c), 192.917(a), 192.917(b)#
DC.CONVrecordPage 79DC.CONV.RISKASSESSMENT.RDo records demonstrate a Risk Assessment was performed to identify threats and hazards associated with the conversion to the new service and the measures taken/planned to mitigate reduce those risks? References: 192.14(a)(1), 192.911(b), 192.911(c), 192.917(a), 192.917(b)#
DC.CONVrecordPage 79DC.CONV.DESIGN.RDo records indicate the Conversion-to-Service DESIGN elements were reviewed and applied in accordance with §192.14(a)? References: 192.14(a)(1)#
DC.CONVrecordPage 79DC.CONV.CONSTRUCTION.RDo the records indicate the Conversion-to-Service related CONSTRUCTION elements were reviewed in accordance with §192.14(a) and applied in accordance with Part 192? References: 192.14(a)(1)#
DC.CONVrecordPage 79DC.CONV.OPSMAINTENANCE.RDo the records indicate the Conversion-to-Service realted Operations & Maintenance elements were reviewed in accordance with §192.14(a) and applied in accordance with Part 192? References: 192.14(a)(1), 192.605#
DC.CONVprocedurePage 79DC.CONV.OPSMAINTMODIF.PDoes the Conversion procedure require the Operations and Maintenance Manual procedures to be reviewed, and modified or expanded as necessary to accommodate the Part 192 requirements as applied to this Conversion to Service? References: 192.605, 192.14(a)#
DC.CONVrecordPage 79DC.CONV.OPSMAINTMODIF.RDo the records indicate the Conversion-to-Service related Operations & Maintenance elements were reviewed and the necessary modifications were made in accordance with §192.14(a)? References: 192.605, 192.14(a)#
DC.CONVrecordPage 80DC.CONV.HISTORICALRECORDS.RHistorical Records Review For the operator's written procedure to review the pipeline historical records as required by §192.14(a), were adequate / appropriate records reviewed? References: 192.605, 192.14(a)#
DC.CONVrecordPage 80DC.CONV.MISSINGRECORDS.RHistorical Records Review - Missing Records For the operator's review of the pipeline history (historical records) as required by §192.14(a), do records indicate operator determined what necessary records were either missing or deemed not sufficient and how the operator plans to test to obtain the missing records or insufficient data? References: 192.14(a)(1)#
DC.CONVprocedurePage 80DC.CONV.STRENGTHTESTING.PDoes the conversion procedure include the requirement to strength test the pipeline, in accordance with Part 192, Subpart J to substantiate the MAOP permitted by Part 192, Subpart L? References: 192.14(a)(4)#
DC.CONVrecordPage 80DC.CONV.STRENGTHTESTING.RDo the records indicate the pipeline was tested in accordance with Part 192, Subpart J to substantiate the new Maximum Allowable Operating Pressure permitted by Subpart L? References: 192.14(a)(4)#
DC.CONVprocedurePage 80DC.CONV.IMPROGRAM.PDoes the conversion procedure require the operator to apply the Integrity Management Program requirements, including HCAs, from Part 192, Subpart O? References: 192.901, 192.907(a)#
DC.CONVrecordPage 80DC.CONV.IMPROGRAM.RDo the records indicate operator developed and implemented an Integrity Management Program for the converted pipeline as required by Part 192, Subpart O? References: 192.947, 192.901#
DC.CONVprocedurePage 80DC.CONV.PMMEASURES.PDoes the conversion procedure require additional measures, beyond those already required by Part 192, to prevent a pipeline failure and to mitigate the consequences of a pipeline failure in a high consequence area? References: 192.935#
DC.CONVrecordPage 80DC.CONV.PMMEASURES.RWhere applicable, do the records indicate operator applied preventative and mitigative measures to prevent a pipeline failure and to mitigate the consequences of a pipeline failure in a high consequence area? References: 192.947, 192.935#
DC.CONVprocedurePage 80DC.CONV.RECORDS.PDoes the operator’s conversion procedure require a record of all of the investigations, tests, repairs, replacements, and alterations made under §192.14(a) to be maintained for the life of the pipeline/facility? References: 192.14(b), 192.607, 192.712#
DC.CONVrecordPage 81DC.CONV.RECORDS.RDoes the operator’s conversion procedure require a record of all of the investigations, tests, repairs, replacements, and alterations made under §192.14(a) to be maintained for the life of the pipeline/facility? References: 192.14(b), 192.607, 192.712#
DC.CONVprocedurePage 81DC.CONV.COMMISSIONING.PHas the operator prepared a written Commissioning Plan which details the requirements, parameters, and procedures for a safe startup of the converted pipeline under Part 192? References: 192.603#
DC.CONVrecordPage 81DC.CONV.COMMISSIONING.RDo records indicate operator followed its written Commissioning Plan to ensure a safe startup of the converted pipeline under Part 192? References: 192.603(b), 192.603(a), 192.605#
EP.ERGprocedurePage 81EP.ERG.REVIEW.PDoes the process include a requirement to review the manual at intervals not exceeding 15 months, but at least once each calendar year? References: 192.605(a)#
EP.ERGrecordPage 81EP.ERG.REVIEW.RHave annual reviews been conducted of the emergency plans and procedures as required, and any updates completed as appropriate? References: 192.605(a)#
EP.ERGobservationPage 81EP.ERG.LOCATION.OAre supervisors provided the applicable portions of the emergency plan and procedures? References: 192.615(b)(1)#
EP.ERGprocedurePage 81EP.ERG.INCIDENTDATA.PDoes the process include the steps necessary for the gathering of data needed for reporting incidents under Part 191 of this chapter in a timely and effective manner? References: 192.605(b)(4), 191.5(a)#
EP.ERGprocedurePage 81EP.ERG.NOTICES.PDoes the emergency plan include procedures for receiving, identifying, and classifying notices of events which need immediate response? References: 192.615(a)(1)#
EP.ERGrecordPage 82EP.ERG.NOTICES.RDo records indicate receiving, identifying, classifying and communication of notices of events requiring immediate response in accordance with procedures? References: 192.615(a)(1)#
EP.ERGprocedurePage 82EP.ERG.COMMSYS.PDoes the emergency plan include procedures for establishing and maintaining adequate means of communication with appropriate fire, police, and other public officials? References: 192.615(a), 192.615(a)(2)#
EP.ERGprocedurePage 82EP.ERG.RESPONSE.PDoes the emergency plan include procedures for making a prompt and effective response to a notice of each type of emergency, including gas detected inside or near a building, a fire or explosion near or directly involving a pipeline facility, operational failure (including Cyber-attacks), or a natural disaster? References: 192.615(a), 192.615(a)(3), 192.615(a)(11), 192.615(b)(1)#
EP.ERGprocedurePage 82EP.ERG.READINESS.PDoes the process include procedures for ensuring the availability of personnel, equipment, tools, and materials as needed at the scene of an emergency? References: 192.615(a), 192.615(a)(4)#
EP.ERGobservationPage 82EP.ERG.READINESS.OAre personnel, equipment, tools, and materials needed at the scene of an emergency available as required by the procedures? References: 192.615(a)(4)#
EP.ERGprocedurePage 82EP.ERG.PUBLICPRIORITY.PDoes the emergency plan include procedures for taking actions directed toward protecting people first and then property? References: 192.615(a), 192.615(a)(5)#
EP.ERGprocedurePage 82EP.ERG.PRESSREDUCESD.PDoes the emergency plan include procedures for the emergency shutdown, valve shut-off, or pressure reduction in any section of pipeline system necessary to minimize hazards to life or property? References: 192.615(a), 192.615(a)(6)#
EP.ERGprocedurePage 82EP.ERG.PUBLICHAZ.PDoes the emergency plan include procedures for making safe any actual or potential hazard to life or property? References: 192.605(a), 192.615(a)(7)#
EP.ERGprocedurePage 83EP.ERG.NOTIFY911.PDoes the emergency plan define the operator’s designated person(s) (e.g., controller or other personnel) responsible to directly notify 911 or the phone number of appropriate local emergency officials to report emergencies and possible pipeline ruptures to first responder agencies/authorities? References: 192.615(a), 192.615(a)(8)#
EP.ERGrecordPage 83EP.ERG.NOTIFY911.RDo records indicate that immediate and direct notification was made to 911 emergency call centers (or local emergency responder agency) for the communities and jurisdictions in which pipelines were located for situations when an emergency or possible rupture of a pipeline was indicated? References: 192.615(a), 192.615(a)(8)#
EP.ERGprocedurePage 83EP.ERG.OUTAGERESTORE.PDoes the emergency plan include procedures for safely restoring any service outage? References: 192.615(a), 192.615(a)(9)#
EP.ERGprocedurePage 83EP.ERG.POSTEVNTREVIEW.PDoes the process include detailed steps for reviewing employee activities to determine whether the procedures were effectively followed in each emergency? References: 192.615(b)(3)#
EP.ERGrecordPage 83EP.ERG.POSTEVNTREVIEW.RDo records indicate review of employee activities to determine whether the procedures were effectively followed in each emergency? References: 192.605(a), 192.615(b)(1), 192.615(b)(3)#
EP.ERGprocedurePage 83EP.ERG.LIAISON.PDoes the process include steps for establishing and maintaining liaison with appropriate fire, police and other public officials and utility owners? References: 192.615(a)(2), 192.615(c)(1), 192.615(c)(2), 192.615(c)(3), 192.615(c)(4), 192.616(c)#
EP.ERGrecordPage 83EP.ERG.LIAISON.RDo records indicate that liaison has been established and maintained with appropriate fire, police, public officials, and utility owners? References: 192.605(a), 192.615(c)(1), 192.615(c)(2), 192.615(c)(3), 192.615(c)(4), 192.616(c)#
EP.ERGprocedurePage 83EP.ERG.NOTIFPOTRUPTURE.PDoes the operator have procedures to identify and notify operator personnel of a potential rupture? References: 192.635#
EP.ERGprocedurePage 84EP.ERG.VALVESHUTOFF.PDoes the operator have procedures requiring shut-off of RMVs or AETs following identification of a release? References: 192.605(b), 192.636(b)#
EP.ERGrecordPage 84EP.ERG.VALVESHUTOFF.RDo the records demonstrate RMVs or AETs were shut-off in accordance with §192.636(b) following identification of a release? References: 192.605(b), 192.636(b)#
EP.ERGrecordPage 84EP.ERG.NOTIFPOTRUPTURE.RDo the records indicate the operator properly identified and notified operator's personnel of a potential rupture? References: 192.635#
EP.ERGprocedurePage 84EP.ERG.RUPTUREIDENTIF.PDoes the operator have procedures to evaluate and identify if a potential rupture is an actual rupture event? References: 192.615(a)(12)#
EP.FIIprocedurePage 84EP.FII.INCIDENTANALYSIS.PDoes the operator’s processes include steps for analyzing pipeline incidents to determine their causes? References: 192.617(a)#
EP.FIIprocedurePage 84EP.FII.INCIDENTRMVANALYSIS.PIncident RMV Analysis For incidents that involve an RMV, does the operator’s procedures require a post-incident analysis of all the factors that may have impacted the release volume and consequences of the release and identify and implement operators and maintenance measures to minimize future incidents? References: 192.617(a), 192.617(c)#
EP.FIIprocedurePage 84EP.FII.INCIDENTSUMMARY.PIncident Summary For incidents that involve an RMV, does the operator’s procedures require an incident summary? References: 192.617(a), 192.617(d)#
EP.FIIrecordPage 84EP.FII.INCIDENTANALYSIS.RDo records indicate pipeline incidents were analyzed to determine their causes? References: 192.617(d)#
EP.FIIprocedurePage 85EP.FII.FAILUREANALYSIS.PDo the operator’s processes include steps for analyzing pipeline failures to determine their causes? References: 192.617(a)#
EP.FIIprocedurePage 85EP.FII.FAILURERMVANALYSIS.PFailure RMV Analysis For failures that involve an RMV, do the operator’s procedures require a post-failure analysis and the identification and implementation of operations and maintenance measures to minimize future failures? References: 192.617(c)#
EP.FIIprocedurePage 85EP.FII.FAILURESUMMARY.PFailure Summary For failures that involve an RMV, does the operator’s procedures require a failure summary? References: 192.617(d)#
EP.FIIrecordPage 85EP.FII.FAILUREANALYSIS.RDo records indicate pipeline failures were analyzed to determine their causes? References: 192.617(d)#
FS.CSSYSPROTobservationPage 85FS.CSSYSPROT.CMPFP.ODo compressor stations have adequate fire protection facilities? References: 192.171(a)#
FS.CSSYSPROTobservationPage 85FS.CSSYSPROT.CMPGASDET.OHave adequate gas detection and alarm systems been installed in selected applicable compressor buildings? References: 192.736(a), 192.736(b)#
FS.CSSYSPROTobservationPage 85FS.CSSYSPROT.CMPGASENGMFL.OAre gas engines in compressor stations equipped with mufflers that prevent gas from being trapped in the muffler? References: 192.171(e)#
FS.CSSYSPROTobservationPage 85FS.CSSYSPROT.CMPGASENGSD.OAre compressor station gas engines that operate with pressure gas injection equipped so that stoppage of the engine will result in the fuel being automatically shut off and the engine distribution manifold being vented? References: 192.171(d)#
FS.CSSYSPROTobservationPage 85FS.CSSYSPROT.CMPLUBPROT.ODo compressor units have shutdown or alarm devices that will operate in the event of inadequate heating or lubrication? References: 192.171(c)#
FS.CSSYSPROTobservationPage 86FS.CSSYSPROT.CMPOVSPD.ODo compressor stations' prime movers other than electrical induction or synchronous motors have automatic shutdown devices that will prevent over-speed of the prime mover or the unit being driven? References: 192.171(b)#
FS.CSSYSPROTobservationPage 86FS.CSSYSPROT.CMPRELIEF.OAre pressure relief/limiting devices inside a compressor station designed, installed, and inspected properly? References: 192.199, 192.731(a), 192.731(b), 192.731(c)#
FS.CSSYSPROTobservationPage 86FS.CSSYSPROT.ESDDISTSD.ODoes each compressor station that supplies gas directly to a distribution system (with no other adequate sources of gas available) have an emergency shutdown system that will not function at the wrong time or cause unintended outages? References: 192.167(b)#
FS.CSSYSPROTobservationPage 86FS.CSSYSPROT.ESDELECSD.ODoes each compressor station have an emergency shutdown system that is capable of shutting down electrical facilities (except emergency and equipment protection circuits) near gas headers and within compressor buildings? References: 192.167(a)(3)(i), 192.167(a)(3)(ii)#
FS.CSSYSPROTobservationPage 86FS.CSSYSPROT.ESDGASBLK.ODoes each compressor station have an emergency shutdown system that is capable of blocking gas out of the station and blow down the station piping? NOTE: Not required for field compressor stations of 1,000 horsepower (746 kilowatts) or less. References: 192.167(a)(1)#
FS.CSSYSPROTobservationPage 86FS.CSSYSPROT.ESDGASDISCH.ODoes each compressor station have an emergency shutdown system that is capable of safely discharging blowdown gas from the blowdown piping at a location where the gas will not create a hazard? References: 192.167(a)(2)#
FS.CSSYSPROTobservationPage 86FS.CSSYSPROT.ESDGASSD.ODoes each compressor station have an emergency shutdown system that is capable of shutting down gas compressing equipment and gas fires in the vicinity of gas headers and compressor buildings? References: 192.167(a)(3)#
FS.CSSYSPROTobservationPage 86FS.CSSYSPROT.ESDLOCATION.ODoes each compressor station have an emergency shutdown system that is capable of being operated from at least two locations which are: 1) Outside the gas area of the station, 2) Near the exit gates, if the station is fenced, or near emergency exits, if not fenced, 3) And not more than 500 feet (153 meters) from the limits of the station? References: 192.167(a)(4)#
FS.CSSYSPROTobservationPage 87FS.CSSYSPROT.UNATTPLATCMPSD.ODoes each unattended platform compressor station located offshore or in inland navigable waters have an emergency shutdown system that will actuate automatically in the event of the following occurrences? 1) When gas pressure equals the MAOP plus 15 percent and, 2) When an uncontrolled fire occurs on the platform. References: 192.167(c)(1)#
FS.CSSYSPROTobservationPage 87FS.CSSYSPROT.PLATCMPSD.ODoes each platform compressor station, located offshore or in inland navigable waters, within a building have an emergency shutdown system that will actuate automatically in the event of the following occurrences? 1) When an uncontrolled fire occurs in the building and, 2) When the concentration of gas in the air within the building reaches 50 percent of the lower explosive limit that has a source of ignition. References: 192.167(c)(2)#
FS.CSSYSPROTobservationPage 87FS.CSSYSPROT.CMPMAOP.ODo compressor stations have pressure relief or other suitable protective devices with sufficient capacity and sensitivity so as to protect station piping from exceed 110% of MAOP? References: 192.169(a)#
FS.CSSYSPROTobservationPage 87FS.CSSYSPROT.RELIEFDISCH.ODo pressure relief valves exhaust gas to a location where the gas will not cause a hazard? References: 192.169(b)#
FS.CSSYSPROTprocedurePage 87FS.CSSYSPROT.CMPRELIEF.PDoes the process provide adequate detail for inspection and testing of compressor station pressure relief devices with the exception of rupture disks? References: 192.605(b)(1), 192.731(a), 192.731(b), 192.731(c)#
FS.CSSYSPROTrecordPage 87FS.CSSYSPROT.CMPRELIEF.RDo records document with adequate detail that all inspection and testing of compressor station pressure relief devices with the exception of rupture disks have occurred at the required interval? References: 192.709(b), 192.709(c), 192.731(a), 192.731(b), 192.731(c)#
FS.CSSYSPROTobservationPage 87FS.CSSYSPROT.RELIEFCAPC.ODo pressure relieving/limiting stations located within the confines of a compressor station have sufficient capacity and are they set to limit the pressures to no more than allowed? References: 192.201(a), 192.201(b), 192.201(c)#
FS.CSSYSPROTprocedurePage 87FS.CSSYSPROT.CMPESDTEST.PDoes the process provide adequate detail for inspecting and testing compressor station emergency shutdown devices at the required frequency? References: 192.605(b), 192.731(c)#
FS.CSSYSPROTrecordPage 88FS.CSSYSPROT.CMPESDTESTDEV.RDo records document the inspection and testing of all compressor station emergency shutdown devices at the required frequency? References: 192.709(c), 192.731(c)#
FS.CSSYSPROTprocedurePage 88FS.CSSYSPROT.CMPGASDETREQ.PDoes the process adequately detail requirements of permanent gas detectors and alarms at compressor buildings? References: 192.605(b), 192.736(b)#
FS.CSSYSPROTprocedurePage 88FS.CSSYSPROT.CMPGASDETOM.PDoes the process give detail how gas detection and alarm systems in compressor stations will be maintained to function properly and do procedures require performance tests? References: 192.605(b), 192.736(c), 192.736(b)#
FS.CSSYSPROTrecordPage 88FS.CSSYSPROT.CMPGASDETOM.RDo records document that all compressor station gas detection and alarm systems are being maintained and tested as required? References: 192.709(c), 192.736(c), 192.736(b)#
FS.CSobservationPage 88FS.CS.BLDGLOC.OAre onshore compressor buildings located on property under the control of the operator? References: 192.163(a), 192.163(b)#
DC.COCMPobservationPage 88DC.COCMP.CMPCOMBUSTIBLE.ODo field observations demonstrate that flammable/combustible materials are safely stored as required, and aboveground oil or gasoline storage tanks are installed at compressor stations according to 192.735(b)? References: 192.735(a), 192.735(b)#
FS.CSobservationPage 88FS.CS.BLDGADJ.OAre onshore main compressor buildings far enough from adjacent property to minimize the possibility of fire being conveyed to the compressor buildings from adjacent property? References: 192.163(a)#
FS.CSobservationPage 89FS.CS.BLDGEXITS.ODoes each main compressor building operating floor have at least two separated, easily accessed and unobstructed exits to a place of safety, main compressor building exits that have door latches that can be readily opened without a key, and main compressor building exit doors mounted to swing outward? References: 192.163(c)#
FS.CSobservationPage 89FS.CS.BLDGSPACE.ODo onshore main compressor buildings have enough open space around them to allow for free movement of fire-fighting equipment. References: 192.163(a)#
FS.CSobservationPage 89FS.CS.CMPNFPA70.ODoes the equipment and wiring within compressor stations conform to National Electric Code, ANSI/NFPA 70, including the required posting or ready access of the permit? References: 192.163(e)#
FS.CSobservationPage 89FS.CS.FENCEGATES.ODo fenced areas around compressor stations have at least two gates that provide for easy escape to place of safety, and do gates located within 200 feet of any compressor plant open outward and able to be opened from the inside without a key when the station is occupied? References: 192.163(d)#
FS.CSobservationPage 89FS.CS.BLDGCMBST.OIs each building on the compressor station site constructed of noncombustible materials if it contains either pipe that is more than 2 inches in diameter that contains gas under pressure or contains gas handling equipment other than gas utilization equipment used for station domestic purposes? References: 192.163(b)#
FS.CSobservationPage 89FS.CS.SPTRLIQ.ODoes each separator used to remove entrained liquids at compressor stations have: 1) manually operable means to remove liquids, and 2) have a means to handle slugs of liquid where there is a possibility that liquid slugs could be carried into compressors? References: 192.165(b)(1), 192.165(b)(2)#
FS.CSrecordPage 89FS.CS.SPTRCODE.RDo records indicate each separator used to remove entrained liquids at compressor stations is manufactured in accordance with applicable codes or requirements? References: 192.165(b)(3)#
FS.CSobservationPage 89FS.CS.SPTRCODE.OIs each separator used to remove entrained liquids at compressor stations manufactured in accordance with applicable codes or requirements? References: 192.165(b)(3)#
FS.CSobservationPage 90FS.CS.CMPBLDGVENT.OAre compressor station buildings ventilated to ensure employees are not endangered by accumulation of gas in enclosed areas? References: 192.173#
FS.CSobservationPage 90FS.CS.HOLDER.OAre bottle and pipe type holders designed and installed properly? References: 192.175(a), 192.175(b)#
FS.CSobservationPage 90FS.CS.HOLDERLOC.OAre bottle type and pipe type holders located and constructed properly? References: 192.177(a), 192.177(b)#
FS.CSobservationPage 90FS.CS.CMPERP.OAre emergency response plans for selected compressor stations kept on site? References: 192.605(a), 192.615(b)#
FS.CSprocedurePage 90FS.CS.CMPSUSD.PDoes the process for start-up and shut-down have sufficient detail to ensure start-up and shut-down of compressor units in a manner designed to assure operation within the MAOP limits prescribed by this part, plus the build-up allowed for operation of pressure-limiting and control devices? References: 192.605(b)(5), 192.605(b)(7)#
FS.CSprocedurePage 90FS.CS.CMPMAINT.PDoes the process have sufficient detail for maintaining compressor stations, including provisions for isolating units or sections of pipe and for purging before returning to service? References: 192.605(b)(6)#
DC.COCMPprocedurePage 90DC.COCMP.CMPCOMBUSTIBLE.PDoes the process require that flammable/combustible materials are stored as required, and aboveground oil or gasoline storage tanks, are installed at compressor stations according to 192.735(b)? References: 192.303, 192.735(a), 192.735(b)#
DC.COCMPrecordPage 90DC.COCMP.CMPCOMBUSTIBLE.RDo records demonstrate that flammable/combustible materials are stored as required, and aboveground oil or gasoline storage tanks are installed at compressor stations according to 192.735(b)? References: 192.303, 192.735(a), 192.735(b)#
MO.GMprocedurePage 91MO.GM.ABANDONPIPE.PDoes the process include adequate requirements for the abandonment and deactivation of pipelines and facilities? References: 192.605(b)(1), 192.727(a), 192.727(b), 192.727(c), 192.727(d), 192.727(e), 192.727(f), 192.727(g)#
MO.GMrecordPage 91MO.GM.ABANDONPIPE.RDo records indicate pipelines and facilities were abandoned or deactivated in accordance with requirements? References: 192.709(c), 192.727(a), 192.727(b), 192.727(c), 192.727(d), 192.727(e), 192.727(f), 192.727(g)#
FS.FGprocedurePage 91FS.FG.VAULTINSPECT.PWhat are process requirements for inspecting vaults having a volumetric internal content ≥200 cubic feet (5.66 cubic meters) that house pressure regulating/limiting equipment? References: 192.605(b)(1), 192.749(a), 192.749(b), 192.749(c), 192.749(d)#
FS.FGrecordPage 91FS.FG.VAULTINSPECT.RDo records document the adequacy of inspections of all vaults having an internal volume ≥200 cubic feet (5.66 cubic meters) that house pressure regulating/limiting equipment? References: 192.709(c), 192.749(a), 192.749(b), 192.749(c), 192.749(d)#
FS.FGobservationPage 91FS.FG.VAULTINSPECT.OAre inspections of selected vaults with internal volume ≥ 200 cubic feet housing pressure regulating/limiting equipment adequate? References: 192.749(a), 192.749(b), 192.749(c), 192.749(d)#
DC.DPCobservationPage 91DC.DPC.VAULT.OVaults Structural Design Requirements As applicable to the project, are vaults/pits installed as designed, and per the requirements of 192.183? References: 192.141, 192.183(a), 192.183(b), 192.183(c)#
DC.DPCobservationPage 92DC.DPC.VAULTACCESS.OVaults Accessibility As applicable to the project, are vaults located in an accessible location? References: 192.141, 192.185(a)#
DC.DPCobservationPage 92DC.DPC.VAULTSEAL.OVaults Sealing, Venting, and Ventilation As applicable to the project, are vaults/pits sealed, ventilated, or vented as required of 192.187? References: 192.141, 192.187(a), 192.187(b), 192.187(c)#
DC.DPCobservationPage 92DC.DPC.VAULTWATER.OVaults Drainage and Waterproofing As applicable to the project, are vaults installed to minimize water entrance, and have proper electrical equipment? References: 192.141, 192.189(a), 192.189(b), 192.189(c)#
FS.GSprocedurePage 92FS.GS.STORAGEATM.PDoes the process give adequate instruction for the inspection of aboveground pipeline segments located in storage fields for atmospheric corrosion? References: 192.605(b)(2), 192.481(a), 192.481(b), 192.481(c)#
FS.GSrecordPage 92FS.GS.STORAGEATM.RDo records document inspection of aboveground pipe located in storage fields for atmospheric corrosion? References: 192.491(c), 192.481(a), 192.481(b), 192.481(c)#
FS.GSprocedurePage 92FS.GS.STORAGECP.PAre external corrosion monitoring procedures established for the field piping and related storage field facilities? References: 192.605(b)(2), 192.463(a)#
FS.GSrecordPage 92FS.GS.STORAGECP.RDo records indicate that field piping and related storage field facilities are cathodically protected? References: 192.491(c), 192.455(a), 192.457(a), 192.465(a)#
FS.GSobservationPage 92FS.GS.STORAGECP.OAre the cathodic protection practices for field piping and related storage field facilities adequate? References: 192.463(a)#
FS.GSprocedurePage 93FS.GS.STORAGEIC.PAre internal corrosion monitoring procedures established for the field piping and related storage field facilities? References: 192.605(b)(2), 192.475(a), 192.475(b), 192.475(c), 192.477#
FS.GSrecordPage 93FS.GS.STORAGEIC.RDo records indicate that field piping and related storage field facilities are being protected from internal corrosion? References: 192.491(c), 192.475(a)#
FS.GSrecordPage 93FS.GS.GASVELOCITY.RHave target flow rates been determined for the field piping system? References: 192.491(c), 192.475(a)#
FS.GSrecordPage 93FS.GS.INHIBITOR.RHas a corrosion inhibitor program been established for the field piping and related storage field facilities? References: 192.491(c), 192.477#
FS.GSrecordPage 93FS.GS.MAINTENANCEPIG.RIs maintenance pigging used to sweep the lines of sediments and/or scale? References: 192.491(c), 192.477#
FS.GSrecordPage 93FS.GS.FACILITYUPSET.RStorage Field Gas and Liquid Handling Facility Upsets Number of upsets - past 3 years? References: 192.709(c)#
FS.GSrecordPage 93FS.GS.FAILURERUPTURE.RHave any failures or ruptures occurred over the past 5 years? References: 192.709(c)#
FS.GSrecordPage 93FS.GS.OMHISTORY.RHave any storage field pipelines been repaired over the past 5 years? References: 192.709(a)#
FS.GSrecordPage 93FS.GS.LINEREPLACE.RHave any storage field pipelines been replaced over the past 5 years? References: 192.709(a)#
FS.GSprocedurePage 93FS.GS.LEAKSURVEY.PAre leak surveys in the storage field required to be conducted? References: 192.605(e), 192.706#
FS.GSrecordPage 94FS.GS.LEAKSURVEY.RDo records document storage field leak surveys? References: 192.709(c), 192.706#
FS.GSrecordPage 94FS.GS.OVERPRESSURE.RHave a system safety analysis and safety analysis function evaluation chart been performed for the field piping and related storage facilities? References: 192.709(c), 192.739(a), 192.739(b)#
FS.GSrecordPage 94FS.GS.VALVEREPLACE.RHave any valves been replaced over the past 5 years? References: 192.709(b), 192.745(b)#
FS.VAprocedurePage 94FS.VA.CMPVLVTEST.PDoes the process have requirements for transmission line valves that might be used in an emergency? References: 192.605(b), 192.745(a), 192.745(b)#
FS.VArecordPage 94FS.VA.CMPVLVTEST.RDo records adequately document that compressor transmission line valves have been inspected and partially operated at the correct interval? References: 192.709(c), 192.745(a), 192.745(b)#
FS.VAobservationPage 94FS.VA.CMPVLVMAINT.OAre transmission line valves maintained as required? References: 192.745(a), 192.745(b)#
IM.HCprocedurePage 94IM.HC.HCAID.PDoes the process include the methods defined in 192.903 High Consequence Area (Method 1) and/or 192.903 High Consequence Area (Method 2) to be applied to each pipeline for the identification of high consequence areas? References: 192.905(a)#
IM.HCrecordPage 95IM.HC.HCAID.RDo records demonstrate that the identification of pipeline segments in high consequence areas was completed in accordance with process requirements? References: 192.947(d), 192.905(a), 192.907(a), 192.911(a)#
IM.HCprocedurePage 95IM.HC.HCAMETHOD1.PIs the integrity management process adequate for identification of 192.903 High Consequence Areas using Method (1) for identification of HCAs? References: 192.903(1)(i), 192.903(1)(ii), 192.903(1)(iii), 192.903(1)(iv)#
IM.HCprocedurePage 95IM.HC.HCAMETHOD2.PIs the integrity management process adequate for identification of 192.903 High Consequence Areas using Method (2)? References: 192.903(2)(i), 192.903(2)(ii)#
IM.HCprocedurePage 95IM.HC.HCANEW.PDoes the process include a requirement for evaluation of new information that impacts, or creates a new, high consequence area? References: 192.905(c)#
IM.HCrecordPage 95IM.HC.HCANEW.RDo records demonstrate new information that impacts, or creates a new, high consequence area has been integrated with the integrity management program? References: 192.947(d), 192.905(c)#
IM.HCprocedurePage 95IM.HC.HCAPIR.PIs the process for defining and applying potential impact radius (PIR) for establishment of high consequence areas consistent with the requirements of 192.903? References: 192.903, 192.905(a)#
IM.HCrecordPage 95IM.HC.HCAPIR.RDo records demonstrate the use of potential impact radius (PIR) for establishment of high consequence areas consistent with requirements of 192.903? References: 192.947(d), 192.903, 192.905(a)#
IM.HCprocedurePage 95IM.HC.HCASITES.PDoes the process for identification of identified sites include the sources listed in 192.905(b) for those buildings or outside areas meeting the criteria specified by 192.903 and require the source(s) of information selected to be documented? References: 192.903, 192.905(b)#
IM.HCrecordPage 95IM.HC.HCASITES.RDo records indicate identification of identified sites being performed as required? References: 192.947(d), 192.903, 192.905(b)#
IM.HCrecordPage 96IM.HC.HCAMETHOD1.RDo records demonstrate that identification of 192.903 High Consequence Areas using Method (1) was adequate? References: 192.947(d), 192.903(1)(i), 192.903(1)(ii), 192.903(1)(iii), 192.903(1)(iv)#
IM.HCrecordPage 96IM.HC.HCAMETHOD2.RDo records demonstrate that the identification of 192.903 High Consequence Areas using Method (2) was adequate? References: 192.947(d), 192.905(a), 192.903(2)(ii)#
IM.HCobservationPage 96IM.HC.HCADATA.OAre HCAs correctly identified per up-to-date information? References: 192.905(c)#
IM.RAprocedurePage 96IM.RA.RADATA.PDoes the process include requirements to gather and integrate existing data and information on the entire pipeline that could be relevant to covered segments? References: 192.917(b), 192.917(e)(1), 192.911(k)#
IM.RAprocedurePage 96IM.RA.RAMETHOD.PDoes the process include requirements for a risk assessment that considers all of the identified threats for each covered segment, including the requirements of ASME B31.8S-2004 (Section 5) and the need to address potential risk of a compromised operations control system (e.g., cyber-attack)? References: 192.917(c), 192.917(d)#
IM.RArecordPage 96IM.RA.THREATID.RDo records demonstrate that all potential threats to each covered pipeline segment have been identified and evaluated? References: 192.947(b), 192.917(a), 192.917(e), 192.913(b)(1), 192.632#
IM.RArecordPage 96IM.RA.RADATA.RDo records demonstrate that existing data and information on the entire pipeline that could be relevant to covered segments being adequately gathered and integrated? References: 192.947(b), 192.917(b), 192.917(e)(1), 192.911(k), 192.607#
IM.RAprocedurePage 96IM.RA.THREATID.PDoes the process include requirements to identify and evaluate all potential threats to each covered pipeline segment? References: 192.917(a), 192.917(e), 192.913(b)(1)#
IM.RArecordPage 97IM.RA.RAMETHOD.RDo records demonstrate that the risk assessment follows ASME B31.8S-2004, Section 5, and considers the identified threats for each covered segment? References: 192.947(b), 192.917(c), 192.917(d)#
IM.RAprocedurePage 97IM.RA.RAFACTORS.PDoes the process include requirements for factors that could affect the likelihood of a release, and for factors that could affect the consequences of potential releases, be accounted for and combined in an appropriate manner to produce a risk value for each pipeline segment? References: 192.917(c)#
IM.RArecordPage 97IM.RA.RAFACTORS.RDo records demonstrate that risk analysis data is combined in an appropriate manner to produce a risk value for each pipeline segment? References: 192.947(b), 192.917(c)#
IM.RAprocedurePage 97IM.RA.RAMOC.PDoes the process provide for revisions to the risk assessment if new information is obtained or conditions change on the pipeline segments? References: 192.917(c)#
IM.RArecordPage 97IM.RA.RAMOC.RRisk Analysis - Validation and Updates Was the risk assessment revised as necessary as new information is obtained or conditions change on the pipeline segments? References: 192.947(b), 192.917(c)#
IM.RAobservationPage 97IM.RA.RAMOC.OAre conditions on the pipeline segments accurately reflected in the appropriate risk assessment data and information? References: 192.917(c)#
IM.BAprocedurePage 97IM.BA.BAENVIRON.PDoes the process include requirements for conducting integrity assessments in a manner that minimizes environmental and safety risks? References: 192.911(o), 192.919(e), 192.750#
IM.BArecordPage 97IM.BA.BAENVIRON.RDo records demonstrate that integrity assessments have been conducted in a manner that minimizes environmental and safety risks? References: 192.947(d), 192.911(o), 192.919(e), 192.750#
IM.BAprocedurePage 98IM.BA.BAMETHODS.PDoes the process include requirements for specifying an assessment method(s) that is best suited for identifying anomalies associated with specific threats identified for the covered segment? References: 192.919(b), 192.921(a), 192.921(c), 192.921(h), 192.937(c)#
IM.BArecordPage 98IM.BA.BAMETHODS.RDo records demonstrate that the assessment method(s) specified is best suited for identifying anomalies associated with specific threats identified for the covered segment? References: 192.947(c), 192.919(b), 192.921(a), 192.921(c), 192.921(h), 192.947(d), 192.937(c)#
IM.BAprocedurePage 98IM.BA.BANEW.PDoes the process include requirements for updating the assessment plan for newly identified areas and newly installed pipe? References: 192.911(p), 192.905(c), 192.921(f), 192.921(g)#
IM.BArecordPage 98IM.BA.BANEW.RDo records demonstrate that the assessment plan has been adequately updated for new HCAs and newly installed pipe? References: 192.947(d), 192.905(c), 192.911(p), 192.921(f), 192.921(g), 192.620#
IM.BAprocedurePage 98IM.BA.BASCHEDULE.PDid the BAP process require a schedule for completing the assessment activities for all covered segments and consideration of applicable risk factors in the prioritization of the schedule? References: 192.917(c), 192.919(c), 192.921(b)#
IM.BArecordPage 98IM.BA.BASCHEDULE.RDo records demonstrate that all BAP required assessments were completed as scheduled? References: 192.947(c), 192.921(d), 192.947(d)#
IM.BAobservationPage 98IM.BA.BAENVIRON.OIM Assessments - Environmental & Safety Risks From field observations, are integrity assessments conducted in a manner that minimizes environmental and safety risks? References: 192.911(o), 192.919(e), 192.750#
IM.CAprocedurePage 98IM.CA.LOWSTRESSREASSESS.PDoes the process include requirements for the "low stress reassessment" method to address threats of external and/or internal corrosion for pipelines operating below 30% SMYS? References: 192.941(a), 192.941(b), 192.941(c)#
IM.CAprocedurePage 99IM.CA.REASSESSINTERVAL.PIs the process for establishing the reassessment intervals consistent with §192.939 and ASME B31.8S-2004? References: 192.937(a), 192.939(a), 192.939(b), 192.913(c)#
IM.CArecordPage 99IM.CA.LOWSTRESSREASSESS.RDo records demonstrate that the implementation of "low stress reassessment" method to address threats of external and/or internal corrosion is adequate and being performed as required? References: 192.947, 192.941(a), 192.941(b), 192.941(c)#
IM.CAprocedurePage 99IM.CA.PERIODICEVAL.PDoes the process include requirements for a periodic evaluation of pipeline integrity based on data integration and risk assessment to identify the threats specific to each covered segment and the risk represented by these threats? References: 192.937(b), 192.917(a), 192.917(b), 192.917(c), 192.917(d), 192.917(e)#
IM.CArecordPage 99IM.CA.PERIODICEVAL.RDo records demonstrate that periodic evaluations of pipeline integrity have been performed based on data integration and risk assessment to identify the threats specific to each covered segment and the risk represented by these threats? References: 192.947(d), 192.917(a), 192.917(b), 192.917(c), 192.917(d), 192.917(e), 192.937(b)#
IM.CArecordPage 99IM.CA.REASSESSINTERVAL.RDo records demonstrate that reassessment intervals were established consistent with the requirements of the operator's processes? References: 192.947(d), 192.937(a), 192.939(a), 192.939(b), 192.913(c)#
IM.CAprocedurePage 99IM.CA.REASSESSMETHOD.PIs the approach for establishing reassessment method(s) consistent with the requirements in 192.937(c)? References: 192.937(c), 192.931, 192.937(d), 192.493, 192.506#
IM.CArecordPage 99IM.CA.REASSESSMETHOD.RDo records document the assessment methods to be used and the rationale for selecting the appropriate assessment method? References: 192.947(d), 192.937(c), 192.937(d), 192.506, 192.493#
IM.CAprocedurePage 99IM.CA.REASSESSWAIVER.PDoes the process include requirements for reassessment interval waivers (special permit per 190.341)? References: 192.943(a), 192.943(b)#
IM.CArecordPage 99IM.CA.REASSESSWAIVER.RDo records demonstrate that reassessment interval waivers (special permit per §190.341) have been adequately implemented, if applicable? References: 192.947(d), 192.943(a), 192.943(b)#
IM.CAprocedurePage 100IM.CA.REASSESSEXCPERF.PDoes the process include requirements for deviations from reassessment requirements based on exceptional performance? References: 192.913(a), 192.913(b), 192.913(c)#
IM.CArecordPage 100IM.CA.REASSESSEXCPERF.RDo records demonstrate that deviations from reassessment requirements are based on exceptional performance and have been adequately handled, if applicable? References: 192.947, 192.913(a), 192.913(b), 192.913(c)#
IM.PMprocedurePage 100IM.PM.PMMGENERAL.PDoes the process include requirements to identify additional measures to prevent a pipeline failure and to mitigate the consequences of a pipeline failure in a high consequence area? References: 192.935(a)#
IM.PMrecordPage 100IM.PM.PMMGENERAL.RDo records demonstrate that additional measures have been identified and implemented (or scheduled) beyond those already required by Part 192 to prevent a pipeline failure and to mitigate the consequences of a pipeline failure in an HCA? References: 192.947, 192.935(a)#
IM.PMprocedurePage 100IM.PM.PMMTPD.PDoes the preventive and mitigative measure process include requirements that threats due to third party damage be addressed? References: 192.917(e)(1), 192.935(b)(1), 192.935(e)#
IM.PMrecordPage 100IM.PM.PMMTPD.RDo records demonstrate that preventive & mitigative measures have been implemented regarding threats due to third party damage as required by the process? References: 192.947, 192.917(e)(1), 192.935(b)(1), 192.935(e)#
IM.PMprocedurePage 100IM.PM.PMMREVQUAL.PDoes the process require that persons who implement preventive and mitigative measures or directly supervise excavation work be qualified? References: 192.915(c)#
IM.PMrecordPage 100IM.PM.PMMREVQUAL.RDo records demonstrate that personnel who implement preventive and mitigative measures or directly supervise excavation work are qualified? References: 192.947(e), 192.915(c)#
IM.PMprocedurePage 101IM.PM.PMMTPDSMYS.PDoes the process include requirements for preventive and mitigative measures for pipelines operating below 30% SMYS? References: 192.935(d), 192.935(e)#
IM.PMrecordPage 101IM.PM.PMMTPDSMYS.RDo records demonstrate that preventive and mitigative measures for pipelines operating below 30% SMYS are being performed as required? References: 192.947(d), 192.935(d), 192.935(e)#
IM.PMprocedurePage 101IM.PM.PMMOF.PDoes the process adequately address significant threats due to outside force (e.g., earth movement, floods, unstable suspension bridge)? References: 192.935(b)(2)#
IM.PMrecordPage 101IM.PM.PMMOF.RDo records demonstrate that significant threats due to outside force (e.g., earth movement, floods, unstable suspension bridge) are being adequately addressed? References: 192.947(d), 192.935(b)(2)#
IM.PMprocedurePage 101IM.PM.PMMRMV.PDoes the process include requirements to decide if RMVs or AETs represent an efficient means of adding protection to potentially affected HCAs? References: 192.935(c)#
IM.PMrecordPage 101IM.PM.PMMRMV.RDo records demonstrate that the operator has determined, based on risk, whether RMVs or AETs should be added to protect high consequence areas? References: 192.947(d), 192.935(c)#
IM.PMobservationPage 101IM.PM.PMMIMPLEMENT.OHave identified additional preventive and mitigative measures to reduce the likelihood or consequence of a pipeline failure in an HCA been implemented? References: 192.935(a)#
IM.PMprocedurePage 101IM.PM.PMCORR.PDoes the process adequately account for taking required actions to address significant corrosion threats? References: 192.933, 192.917(e)(5)#
IM.PMrecordPage 101IM.PM.PMCORR.RDo records demonstrate that required actions are being taken to address significant corrosion threats as required? References: 192.933, 192.917(e)(5)#
IM.QAprocedurePage 102IM.QA.QARM.PAre quality assurance processes in place for risk management applications that meet the requirements of ASME B31.8S-2004, Section 12? References: 192.911(l)#
IM.QAprocedurePage 102IM.QA.IMNONMANDT.PDoes the process include requirements that non- mandatory requirements (e.g., "should" statements) from industry standards or other documents invoked by Subpart O (e.g., ASME B31.8S-2004 and NACE SP0502-2010) be addressed by an appropriate approach? References: 192.7(a)#
IM.QAprocedurePage 102IM.QA.IMPERSONNEL.PDoes the process include requirements to assure personnel involved in the integrity management program are qualified for their assigned responsibilities in accordance with the quality control plan and Part 192? References: 192.915(a), 192.915(b), 192.915(c), 192.935(b)(1)(i), 192.907(b), 192.493, 192.710(d)#
IM.QArecordPage 102IM.QA.IMPERSONNEL.RDo records demonstrate that personnel involved in the integrity management program are qualified for their assigned responsibilities? References: 192.947(e), 192.915(a), 192.915(b), 192.915(c), 192.493, 192.710(d)#
IM.QArecordPage 102IM.QA.QARM.RDo records demonstrate that the quality assurance process for risk management applications is being completed as required by ASME B31.8S-2004, Section 12? References: 192.947(d), 192.911(l)#
IM.QAprocedurePage 102IM.QA.RECORDS.PIs the process adequate to assure that required records are maintained for the useful life of the pipeline? References: 192.947(a), 192.947(b), 192.947(c), 192.947(d), 192.947(e), 192.947(f), 192.947(g), 192.947(h), 192.947(i), 192.517(a)#
IM.QAprocedurePage 102IM.QA.IMMOC.PIs the process for management of changes that may impact pipeline integrity adequate? References: 192.911(k), 192.909(a), 192.909(b)#
IM.QArecordPage 102IM.QA.IMMOC.RDo records demonstrate that changes that may impact pipeline integrity are being managed as required? References: 192.947(d), 192.909(a), 192.909(b), 192.911(k)#
IM.QAprocedurePage 102IM.QA.IMPERFEFECTIVE.PDoes the process for measuring IM program effectiveness include the elements necessary to conduct a meaningful evaluation? References: 192.945(a), 192.913(b), 192.951#
IM.QArecordPage 103IM.QA.IMPERFEFECTIVE.RDo records demonstrate that the methods to measure Integrity Management Program effectiveness provide effective evaluation of program performance and result in program improvements where necessary? References: 192.947(d), 192.913(b), 192.945(a), 192.951#
IM.QAprocedurePage 103IM.QA.IMPERFMETRIC.PDoes the process to evaluate IM program effectiveness include an adequate set of performance metrics to provide meaningful insight into IM program performance? References: 192.945(a), 192.913(b), 192.951#
IM.QArecordPage 103IM.QA.IMPERFMETRIC.RDo records demonstrate that performance metrics are providing meaningful insight into integrity management program performance? References: 192.947(d), 192.913(b), 192.945(a), 192.951#
IM.QArecordPage 103IM.QA.RECORDS.RAre required records being maintained for the life of the pipeline? References: 192.947(a), 192.947(b), 192.947(c), 192.947(d), 192.947(e), 192.947(f), 192.947(g), 192.947(h), 192.947(i), 192.517(a)#
MO.GCprocedurePage 103MO.GC.CONVERSION.PIf any pipelines were converted into Part 192 service, was a process developed addressing all the applicable requirements? References: 192.14(a), 192.14(b), 192.14(c)#
MO.GCrecordPage 103MO.GC.CONVERSION.RDo records indicate the process was followed for converting any pipelines into Part 192 service? References: 192.14(a), 192.14(b), 192.14(c)#
MO.GOABNORMALprocedurePage 103MO.GOABNORMAL.ABNORMAL.PDoes the process fully address the responsibilities during and after an abnormal operation? References: 192.605(a), 192.605(c)(1)#
MO.GOABNORMALrecordPage 103MO.GOABNORMAL.ABNORMAL.RDid personnel respond to indications of abnormal operations as required by the process? References: 192.605(a), 192.605(c)(1)#
MO.GOABNORMALprocedurePage 104MO.GOABNORMAL.ABNORMALCHECK.PDoes the process include requirements for checking variations from normal operation after abnormal operation has ended at sufficient critical locations in the system to determine continued integrity and safe operation? References: 192.605(a), 192.605(c)(2)#
MO.GOABNORMALprocedurePage 104MO.GOABNORMAL.ABNORMALNOTIFY.PDoes the process include requirements for notifying responsible operator personnel when notice of an abnormal operation is received? References: 192.605(a), 192.605(c)(3)#
MO.GOABNORMALprocedurePage 104MO.GOABNORMAL.ABNORMALREVIEW.PDoes the process include requirements for periodically reviewing the response of operator personnel to determine the effectiveness of the processes controlling abnormal operation and taking corrective action where deficiencies are found? References: 192.605(a), 192.605(c)(4)#
MO.GOABNORMALrecordPage 104MO.GOABNORMAL.ABNORMALREVIEW.RDo records indicate periodic review of work done by operator personnel to determine the effectiveness of the abnormal operation processes and corrective action taken where deficiencies are found? References: 192.605(a), 192.605(c)(4)#
MO.GOCLASSprocedurePage 104MO.GOCLASS.CLASSLOCATESTUDY.PDoes the process include a requirement that the operator conduct a study whenever an increase in population density indicates a change in the class location of a pipeline segment operating at a hoop stress that is more than 40% SMYS, or indicates that the hoop stress corresponding to the established maximum allowable operating pressure for a segment of existing pipeline is not commensurate with the present class location? References: 192.605(b)(1), 192.609(a), 192.609(b), 192.609(c), 192.609(d), 192.609(e), 192.609(f)#
MO.GOCLASSrecordPage 104MO.GOCLASS.CLASSLOCATESTUDY.RDo records indicate performance of the required study whenever the population along a pipeline increased or there was an indication that the pipe hoop stress was not commensurate with the present class location? References: 192.605(b)(1), 192.609(a), 192.609(b), 192.609(c), 192.609(d), 192.609(e), 192.609(f)#
MO.GOCLASSprocedurePage 104MO.GOCLASS.CLASSLOCATEREV.PDoes the process include a requirement that the MAOP of a pipeline segment be confirmed or revised within 24 months whenever the hoop stress corresponding to the established MAOP is determined not to be commensurate with the existing class location? References: 192.605(b)(1), 192.609, 192.611(a), 192.611(b), 192.611(c), 192.611(d)#
MO.GOCLASSrecordPage 105MO.GOCLASS.CLASSLOCATEREV.RChange in Class Location Confirmation or Revision of MAOP Was the MAOP in a pipeline segment confirmed or revised within 24 months as required? References: 192.605(b)(1), 192.609, 192.611(a), 192.611(b), 192.611(c), 192.611(d)#
MO.GOCLASSobservationPage 105MO.GOCLASS.CLASSLOCATEREV.ODo field observations verify that current population density and operator-determined class locations are consistent? References: 192.611(a), 192.609#
MO.GOprocedurePage 105MO.GO.CONTSURVEILLANCE.PAre there processes for performing continuing surveillance of pipeline facilities, and also for reconditioning, phasing out, or reducing the MAOP in a pipeline segment that is determined to be in unsatisfactory condition but on which no immediate hazard exists? References: 192.605(e), 192.613(a), 192.613(b), 192.703(b), 192.703(c)#
MO.GOrecordPage 105MO.GO.CONTSURVEILLANCE.RDo records indicate performance of continuing surveillance of facilities as required, and also the reconditioning, phasing out, or MAOP reduction in any pipeline segment that was determined to be in unsatisfactory condition but on which no immediate hazard existed? References: 192.709(c), 192.613(a), 192.613(b), 192.703(b), 192.703(c)#
MO.GOobservationPage 105MO.GO.CONTSURVEILLANCE.OAre unsatisfactory conditions being captured and addressed by continuing surveillance of facilities and the pipeline as required by 192.613? References: 192.613(a), 192.613(b), 192.703(a), 192.703(b), 192.703(c)#
MO.GOMAOPprocedurePage 105MO.GOMAOP.MAOPDETERMINE.PDoes the process include requirements for determining the maximum allowable operating pressure for a pipeline segment in accordance with 192.619? References: 192.605(b)(1), 192.619(a), 192.619(b), 192.619(f)#
MO.GOMAOPprocedurePage 105MO.GOMAOP.MAOPLIMIT.PDoes the process include requirements for starting up and shutting down any part of the pipeline in a manner to assure operation with the MAOP limits, plus the build-up allowed for operation of pressure-limiting and control devices? References: 192.605(a), 192.605(b)(5)#
MO.GOMAOPrecordPage 106MO.GOMAOP.MAOPDETERMINE.RDo records indicate determination of the MAOP of pipeline segments in accordance with 192.619 and limiting of the operating pressure as required? References: 192.709(c), 192.619(a), 192.619(b), 192.619(f), 192.517#
MO.GOMAOPrecordPage 106MO.GOMAOP.MAOPLIMIT.RDo records indicate operation within MAOP limits, plus the build-up allowed for operation of pressure-limiting and control devices, was assured while starting up and shutting down any part of the pipeline? References: 192.603(b), 192.605(b)(5)#
MO.GMprocedurePage 106MO.GM.ABANDONPIPE.PDoes the process include adequate requirements for the abandonment and deactivation of pipelines and facilities? References: 192.605(b)(1), 192.727(a), 192.727(b), 192.727(c), 192.727(d), 192.727(e), 192.727(f), 192.727(g)#
MO.GMrecordPage 106MO.GM.ABANDONPIPE.RDo records indicate pipelines and facilities were abandoned or deactivated in accordance with requirements? References: 192.709(c), 192.727(a), 192.727(b), 192.727(c), 192.727(d), 192.727(e), 192.727(f), 192.727(g)#
MO.GMrecordPage 106MO.GM.DYNAMICRISER.RDo records for Dynamic Riser Inspection, Maintenance, and Monitoring on Offshore Floating Facilities document the safe and reliable operation of these systems? References: 192.709(c)#
MO.GMprocedurePage 106MO.GM.RECORDS.PDoes the process include a requirement that the operator maintain a record of each pipe/"other than pipe" repair, NDT required record, and (as required by subparts L or M) patrol, survey, inspection or test? References: 192.605(b)(1), 192.709(a), 192.709(b), 192.709(c)#
MO.GMrecordPage 107MO.GM.RECORDS.RDo records indicate that records are maintained of each pipe/"other than pipe" repair, NDT required record, and (as required by subparts L or M) patrol, survey, inspection or test? References: 192.605(b)(1), 192.243(f), 192.709(a), 192.709(b), 192.709(c)#
MO.GMprocedurePage 107MO.GM.IGNITION.PAre there processes for minimizing the danger of accidental ignition where gas constitutes a hazard of fire or explosion? References: 192.605(b)(1), 192.751(a), 192.751(b), 192.751(c)#
MO.GMrecordPage 107MO.GM.IGNITION.RDo records indicate personnel followed processes for minimizing the danger of accidental ignition where the presence of gas constituted a hazard of fire or explosion? References: 192.709, 192.751(a), 192.751(b), 192.751(c)#
MO.GMobservationPage 107MO.GM.IGNITION.OAre the operator’s precautionary measures adequate on a gas transmission line where there exists the potential for accidental ignition? References: 192.751(a), 192.751(b), 192.751(c)#
MO.GMprocedurePage 107MO.GM.VALVEINSPECT.PAre there processes for inspecting and partially operating each transmission line valve that might be required in an emergency at intervals not exceeding 15 months, but at least once each calendar year and for taking prompt remedial action to correct any valve found inoperable? References: 192.605(b)(1), 192.745(a), 192.745(b)#
MO.GMrecordPage 107MO.GM.VALVEINSPECT.RDo records indicate proper inspection and partial operation of transmission line valves that may be required during an emergency as required and prompt remedial actions taken if necessary? References: 192.709(c), 192.745(a), 192.745(b)#
MO.GMobservationPage 107MO.GM.VALVEINSPECT.OAre field inspection and partial operation of transmission line valves adequate? References: 192.745(a), 192.745(b)#
MO.GMprocedurePage 107MO.GM.TRAPSAFETY.PDo the procedures require all launchers and receivers to have adequate safety devices in accordance with 192.750 and to ensure the safety devices are working properly just prior to each use? References: 192.750, 192.605(b), 192.801, 192.805#
MO.GMrecordPage 108MO.GM.TRAPSAFETY.RDoes the operator have records to demonstrate whether all launchers and receivers have safety devices that were utilized prior to each use? References: 192.750, 192.605(b), 192.801, 192.805#
MO.GMobservationPage 108MO.GM.TRAPSAFETY.ODo field observations confirm selected launchers and receivers have safety devices installed and whether the safety devices were inspected prior to each use? References: 192.750, 192.605(b), 192.801, 192.805#
FS.FGprocedurePage 108FS.FG.VAULTINSPECT.PWhat are process requirements for inspecting vaults having a volumetric internal content ≥200 cubic feet (5.66 cubic meters) that house pressure regulating/limiting equipment? References: 192.605(b)(1), 192.749(a), 192.749(b), 192.749(c), 192.749(d)#
FS.FGrecordPage 108FS.FG.VAULTINSPECT.RDo records document the adequacy of inspections of all vaults having an internal volume ≥200 cubic feet (5.66 cubic meters) that house pressure regulating/limiting equipment? References: 192.709(c), 192.749(a), 192.749(b), 192.749(c), 192.749(d)#
FS.FGobservationPage 108FS.FG.VAULTINSPECT.OAre inspections of selected vaults with internal volume ≥ 200 cubic feet housing pressure regulating/limiting equipment adequate? References: 192.749(a), 192.749(b), 192.749(c), 192.749(d)#
MO.GMprocedurePage 108MO.GM.HOLDER.PDoes the process include systematic and routine testing and inspection of pipe-type or bottle-type holders? References: 192.605(a), 192.605(b)(10)#
MO.GMrecordPage 108MO.GM.HOLDER.RDo records indicate systematic and routine testing and inspection of pipe-type or bottle-type holders? References: 192.603(b), 192.605(b)(10)#
MO.GMprocedurePage 109MO.GM.EQUIPPLASTICJOINT.PDoes the process require maintaining equipment used in joining plastic pipe in accordance with the manufacturer's recommended practices or with written procedures that have been proven by test and experience to produce acceptable joints? References: 192.605(b), 192.756#
MO.GMrecordPage 109MO.GM.EQUIPPLASTICJOINT.RDo records indicate equipment used in joining plastic pipe was maintained in accordance with the manufacturer's recommended practices or with written procedures that have been proven by test and experience to produce acceptable joints? References: 192.603(b), 192.756#
MO.GMobservationPage 109MO.GM.EQUIPPLASTICJOINT.OIs proper maintenance being performed on equipment used in joining plastic pipe in accordance with the manufacturer's recommended practices or with written procedures that have been proven by test and experience to produce acceptable joints? References: 192.756#
MO.GMprocedurePage 109MO.GM.AETREQUIREMENT.PDo the procedures specify the requirements necessary to be achieved when operator installs an AET? References: 192.605(b), 192.745(d)#
MO.GMrecordPage 109MO.GM.AETREQUIREMENT.RDo the records demonstrate that the operator complied with the requirements for AET response drills? References: 192.709(c), 192.709(b), 192.745(d)#
MO.GMprocedurePage 109MO.GM.RMVREMEDIAL.PDo the procedures adequately describe the remedial measures required for RMVs or AETs found inoperable or unable to maintain shut-off? References: 192.605(b), 192.179, 192.745(e)#
MO.GMrecordPage 109MO.GM.RMVREMEDIAL.RDo the records demonstrate the remedial measure requirements for RMVs or AETs were met? References: 192.709(b), 192.179, 192.745(e)#
MO.GMprocedurePage 109MO.GM.ASVSHUTINPRESS.PDo the procedures adequately describe the process for confirming ASV shut-in pressures? References: 192.605(b), 192.636(f), 192.745(f)#
MO.GMrecordPage 109MO.GM.ASVSHUTINPRESS.RDo the records demonstrate the process for confirming ASV shut-in pressures? References: 192.709(b), 192.636(f), 192.745(f)#
MO.GOODORprocedurePage 110MO.GOODOR.ODORIZE.PDoes the process ensure appropriate odorant levels are contained in its combustible gases in accordance with 192.625? References: 192.605(b)(1), 192.625(a), 192.625(b), 192.625(c), 192.625(d), 192.625(e), 192.625(f)#
MO.GOODORrecordPage 110MO.GOODOR.ODORIZE.RDo records indicate appropriate odorization of its combustible gases in accordance with its processes and conduct of the required testing to verify odorant levels met requirements? References: 192.709(c), 192.625(a), 192.625(b), 192.625(c), 192.625(d), 192.625(e), 192.625(f)#
MO.GOODORobservationPage 110MO.GOODOR.ODORIZE.OIs sampling of combustible gases adequate using an instrument capable of determining the percentage of gas in air at which it becomes readily detectable? References: 192.625(f)#
MO.GOprocedurePage 110MO.GO.CONTSURVEILLANCE.PAre there processes for performing continuing surveillance of pipeline facilities, and also for reconditioning, phasing out, or reducing the MAOP in a pipeline segment that is determined to be in unsatisfactory condition but on which no immediate hazard exists? References: 192.605(e), 192.613(a), 192.613(b), 192.703(b), 192.703(c)#
MO.GOrecordPage 110MO.GO.CONTSURVEILLANCE.RDo records indicate performance of continuing surveillance of facilities as required, and also the reconditioning, phasing out, or MAOP reduction in any pipeline segment that was determined to be in unsatisfactory condition but on which no immediate hazard existed? References: 192.709(c), 192.613(a), 192.613(b), 192.703(b), 192.703(c)#
MO.GOobservationPage 110MO.GO.CONTSURVEILLANCE.OAre unsatisfactory conditions being captured and addressed by continuing surveillance of facilities and the pipeline as required by 192.613? References: 192.613(a), 192.613(b), 192.703(a), 192.703(b), 192.703(c)#
MO.GOprocedurePage 110MO.GO.PURGE.PDoes the process include requirements for purging of pipelines in accordance with 192.629? References: 192.605(b)(1), 192.629(a), 192.629(b)#
MO.GOprocedurePage 111MO.GO.OMANNUALREVIEW.PDoes the process include a requirement to review the manual at intervals not exceeding 15 months, but at least once each calendar year? References: 192.605(a)#
MO.GOrecordPage 111MO.GO.OMANNUALREVIEW.RHas the operator conducted annual reviews of the written procedures or processes in the manual as required? References: 192.605(a)#
MO.GOprocedurePage 111MO.GO.OMEFFECTREVIEW.PDoes the process include requirements for periodically reviewing the work done by operator personnel to determine the effectiveness, and adequacy of the processes used in normal operations and maintenance and modifying the processes when deficiencies are found? References: 192.605(a), 192.605(b)(8)#
MO.GOrecordPage 111MO.GO.OMEFFECTREVIEW.RDo records indicate periodic review of the work done by operator personnel to determine the effectiveness, and adequacy of the processes used in normal operations and maintenance and modifying the processes when deficiencies are found? References: 192.605(a), 192.605(b)(8)#
MO.GOprocedurePage 111MO.GO.OMHISTORY.PDoes the process include requirements for making construction records, maps and operating history available to appropriate operating personnel? References: 192.605(a), 192.605(b)(3)#
MO.GOrecordPage 111MO.GO.OMHISTORY.RAre construction records, maps, and operating history available to appropriate operating personnel? References: 192.605(a), 192.605(b)(3)#
MO.GOobservationPage 111MO.GO.OMHISTORY.OAre construction records, maps and operating history available to appropriate operating personnel? References: 192.605(b)(3)#
MO.GOobservationPage 111MO.GO.OMLOCATION.OAre appropriate parts of the manual kept at locations where operations and maintenance activities are conducted? References: 192.605(a)#
MO.GOprocedurePage 111MO.GO.CUSTNOTIFY.PIs a customer notification process in place that satisfies the requirements of 192.16? References: 192.13(c), 192.16(a), 192.16(b), 192.16(c), 192.16(d)#
MO.GOrecordPage 112MO.GO.CUSTNOTIFY.RDo records indicate the customer notification process satisfies the requirements of 192.16? References: 192.16(d), 192.16(a), 192.16(b), 192.16(c)#
MO.GOprocedurePage 112MO.GO.ODDOR.PDoes the process require prompt response to the report of a gas odor inside or near a building? References: 192.605(a), 192.605(b)(11)#
MO.GOprocedurePage 112MO.GO.UPRATE.PIs the pressure uprating process consistent with the requirements of 192.553? References: 192.13(c), 192.553(a), 192.553(b), 192.553(c), 192.553(d)#
MO.GOrecordPage 112MO.GO.UPRATE.RDo records indicate the pressure uprating process was implemented per the requirements of 192.553? References: 192.553(b), 192.553(a), 192.553(c), 192.553(d)#
MO.GOrecordPage 112MO.GO.OCS.RDo records indicate specific point(s) at which operating responsibility transfers to a producing operator, as applicable? References: 192.10#
MO.GOobservationPage 112MO.GO.OCS.OAre specific point(s) at which operating responsibility transfers to a producing operator identified, as applicable? References: 192.10#
MO.GOprocedurePage 112MO.GO.CLASSCHNGVALVSPACE.PDoes the process include the installation of RMVs or AETs whenever pipe replacements occur due to a class location change? References: 192.605(b), 192.610#
MO.GOrecordPage 112MO.GO.CLASSCHNGVALVSPACE.RDo records indicate the installation of RMVs or AETs occurred whenever pipe replacements occurred due to a class location change? References: 192.709(c), 192.610#
MO.GOobservationPage 112MO.GO.CLASSCHNGVALVSPACE.ODo field observations verify RMVs or AETs were installed whenever pipe replacements occurred due to a class location change? References: 192.709(c), 192.610#
MO.GMprocedurePage 113MO.GM.RECORDS.PDoes the process include a requirement that the operator maintain a record of each pipe/"other than pipe" repair, NDT required record, and (as required by subparts L or M) patrol, survey, inspection or test? References: 192.605(b)(1), 192.709(a), 192.709(b), 192.709(c)#
MO.GMrecordPage 113MO.GM.RECORDS.RDo records indicate that records are maintained of each pipe/"other than pipe" repair, NDT required record, and (as required by subparts L or M) patrol, survey, inspection or test? References: 192.605(b)(1), 192.243(f), 192.709(a), 192.709(b), 192.709(c)#
MO.GMOPPprocedurePage 113MO.GMOPP.PRESSREGCAP.PDoes the process include procedures for ensuring that the capacity of each pressure relief device at pressure limiting stations and pressure regulating stations is sufficient? References: 192.605(b)(1), 192.743(a), 192.743(b), 192.743(c)#
MO.GMOPPrecordPage 113MO.GMOPP.PRESSREGCAP.RDo records indicate testing or review of the capacity of each pressure relief device at each pressure limiting station and pressure regulating station as required? References: 192.709(c), 192.743(a), 192.743(b), 192.743(c)#
MO.GMOPPprocedurePage 113MO.GMOPP.PRESSREGTEST.PDoes the process include procedures for inspecting and testing each pressure limiting station, relief device, and pressure regulating station and their equipment? References: 192.605(b)(1), 192.739(a), 192.739(b)#
MO.GMOPPrecordPage 113MO.GMOPP.PRESSREGTEST.RDo records indicate inspection and testing of pressure limiting, relief devices, and pressure regulating stations? References: 192.709(c), 192.739(a), 192.739(b)#
MO.GMOPPobservationPage 113MO.GMOPP.PRESSREGTEST.OAre field or bench tests or inspections of regulating stations, pressure limiting stations or relief devices adequate? References: 192.739(a), 192.739(b), 192.743#
MO.RWprocedurePage 114MO.RW.PATROL.PDoes the process adequately cover the requirements for patrolling the ROW and conditions reported? References: 192.705(a), 192.705(b), 192.705(c)#
MO.RWrecordPage 114MO.RW.PATROL.RDo records indicate that ROW surface conditions have been patrolled as required? References: 192.709(c), 192.705(a), 192.705(b), 192.705(c)#
MO.RWobservationPage 114MO.RW.ROWMARKER.OAre line markers placed and maintained as required? References: 192.707(a), 192.707(b), 192.707(c), 192.707(d)#
MO.RWobservationPage 114MO.RW.ROWCONDITION.OAre the ROW conditions acceptable for the type of patrolling used? References: 192.705(a), 192.705(c)#
MO.RWprocedurePage 114MO.RW.ROWMARKER.PDoes the process adequately cover the requirements for placement of ROW markers? References: 192.707(a), 192.707(b), 192.707(c), 192.707(d)#
MO.RWprocedurePage 114MO.RW.LEAKAGE.PDoes the process require leakage surveys to be conducted? References: 192.706, 192.706(a), 192.706(b), 192.935(d)#
MO.RWrecordPage 114MO.RW.LEAKAGE.RDo records indicate leakage surveys conducted as required? References: 192.709(c), 192.706, 192.706(a), 192.706(b), 192.935(d)#
MO.RWobservationPage 115MO.RW.LEAKAGE.OAre leakage surveys being implemented as required? References: 192.706, 192.706(a), 192.706(b)#
MO.RWprocedurePage 115MO.RW.LEAKAGE30SMYS.PLeak Survey (<30% SMYS Gas Transmission) For pipelines operating below 30% SMYS in a Class 3 or 4 locations, but not in an HCA, is there a process for performing leak surveys? References: 192.935(d), 192.935(b)(1)(i), 192.935(b)(1)(iii)#
MO.RWrecordPage 115MO.RW.LEAKAGE30SMYS.RLeak Survey (<30% SMYS Gas Transmission) For pipelines operating below 30% SMYS in a Class 3 or 4 locations, but not in an HCA, do records indicate performance of leak surveys? References: 192.935(d), 192.935(b)(1)(i), 192.935(b)(1)(iii)#
MO.RWprocedurePage 115MO.RW.GOMHAZARD.PDoes the process require identification of pipelines in the Gulf of Mexico at risk of being exposed underwater or hazards to navigation? References: 192.612(a), 192.612(c)(2), 192.612(c)(3)#
MO.RWrecordPage 115MO.RW.GOMHAZARD.RDo records indicate steps taken to identify and inspect pipelines in the Gulf of Mexico at risk of being exposed underwater pipelines or hazards to navigation? References: 192.709(c), 192.612(a), 192.612(b)#
MO.RWobservationPage 115MO.RW.GOMHAZARD.OAre pipelines in the Gulf of Mexico at risk of being exposed underwater pipelines or hazards to navigation marked as required? References: 192.612(c)(2)#
MO.MCAprocedurePage 115MO.MCA.MCADEF.PIs the operator's MCA definition consistent with the §192.3 Definition? References: 192.624(a)(2), 192.710(a)(2), 192.3#
MO.MCAprocedurePage 116MO.MCA.MCAIDENTIF.PWhat is the methodology being used for identifying MCAs? References: 192.624(a)(2), 192.710(a)(2)#
MO.MCArecordPage 116MO.MCA.MCAIDENTIF.RDo the records demonstrate MCAs are properly identified and documented with the physical characteristics/attributes, operating conditions, and surrounding environmental conditions of the pipeline? References: 192.624(a)(2), 192.710(a)(2)#
MO.MCAobservationPage 116MO.MCA.MCAIDENTIF.ODo field observations of select locations indicate MCAs in the field are consistent with operator’s most recent documented MCAs? References: 192.624(a)(2), 192.710(a)(2)#
MO.MCArecordPage 116MO.MCA.MCAIDENTIFROAD.RDo records demonstrate the operator properly identified and applied “covered” roadways that could be affected by the PIR, and therefore considered a “pipeline with an MCA”? References: 192.3, 192.624, 192.712#
MO.MCAprocedurePage 116MO.MCA.MCAPIR.PIs the process for calculating and applying potential impact radius (PIR) for establishment of Moderate Consequence Areas (MCAs) consistent with the requirements of 192.3 and 192.903? References: 192.903, 192.3, 192.624(a)(2), 192.710#
MO.MCArecordPage 116MO.MCA.MCAPIR.RDo records demonstrate the application of potential impact radius (PIR) for establishment of Moderate Consequence Areas (MCAs) is consistent with the requirements of 192.3 and 192.903? References: 192.903, 192.3, 192.624(a)(2), 192.710#
MO.MCAprocedurePage 116MO.MCA.MCANEW.PDoes the process include a requirement for periodic evaluation of new information that creates a new Moderate Consequence Area? References: 192.613(a), 192.624(a)(2), 192.903, 192.5(d), 192.3#
MO.MCArecordPage 116MO.MCA.MCANEW.RDo records demonstrate new information that creates a new Moderate Consequence Area was periodically collected and evaluated? References: 192.613(a), 192.624(a)(2), 192.903, 192.5(d), 192.3#
MO.MCAprocedurePage 116MO.MCA.MAOPRECONFIRM.PWhat is the written procedure for identifying legacy (grandfathered) pipeline segments affecting MCAs which must have their MAOP reconfirmed? References: 192.624(a)(2), 192.632(a)#
MO.MCArecordPage 117MO.MCA.MAOPRECONFIRM.RDo the records adequately identify legacy (grandfathered) pipeline segments affecting MCAs which must have their MAOP reconfirmed? References: 192.624(d), 192.603(b), 192.605(b)(1), 192.624(a)(2), 192.632(a)#
MO.RECONFMATVprocedurePage 117MO.RECONFMATV.PROGRAM.PWhat is the process (or program) for determining and collecting material verification records for line pipe to meet the requirements of §§ 192.619(a)(4), 192.624, 192.607, and 192.712? References: 192.607, 192.613, 192.619, 192.624, 192.632, 192.712#
MO.RECONFMATVrecordPage 117MO.RECONFMATV.PROGRAM.RDoes the line pipe material verification documentation (records) of material properties and attributes demonstrate compliance with §192.607(b)? References: 192.607(b)#
MO.RECONFMATVprocedurePage 117MO.RECONFMATV.COMPONENTS.PDoes the process (or program) include determining which mainline pipeline components other than line pipe are subject to the verification of material properties and attributes requirements of 192.607(f)? References: 192.607(f), 192.607, 192.624, 192.712#
MO.RECONFMATVrecordPage 117MO.RECONFMATV.COMPONENTS.RDoes the verification documentation (records) of material properties and attributes for mainline pipeline components other than line pipe demonstrate compliance with §192.607(f)? References: 192.607(f)#
MO.RECONFMATVprocedurePage 117MO.RECONFMATV.OPPORTUNISTIC.PDo the procedures define when an open excavation requires material verification and when it does not? (i.e., what meets the criteria of an opportunistic dig?) References: 192.607(c), 192.607, 192.624, 192.632, 192.712#
MO.RECONFMATVobservationPage 117MO.RECONFMATV.OPPORTUNISTIC.ODo field observations indicate that the opportunistic digs and testing conducted in the field meet the requirements of the procedures? References: 192.607(c), 192.607, 192.624, 192.632, 192.712#
MO.RECONFMATVprocedurePage 117MO.RECONFMATV.TESTMETHODS.PWhat type(s) of NDT or destructive testing methods (i.e., ILI, in situ testing, etc.) is/are included in the procedures? References: 192.607(c), 192.607(d), 192.624, 192.712#
MO.RECONFMATVrecordPage 118MO.RECONFMATV.TESTMETHODS.RDo the records indicate the type(s) of NDT or destructive testing methods used to comply with the procedures? References: 192.607(b)#
MO.RECONFMATVprocedurePage 118MO.RECONFMATV.POPULGROUPS.PIf the operator plans to establish population groups, does the method employed meet the requirements of 192.607(e)? References: 192.607(e), 192.624, 192.607, 192.712#
MO.RECONFMATVrecordPage 118MO.RECONFMATV.POPULGROUPS.RWhere the operator has established population groups, do the records support operator’s approved methods and comply with 192.607(e)? References: 192.607(e)#
MO.RECONFrecordPage 118MO.RECONF.MAOPMETHODORIG.RDo records demonstrate what method(s) from §192.619 were used to determine the pipeline original MAOP on a segment-by-segment basis? References: 192.619, 192.624(a)#
MO.RECONFprocedurePage 118MO.RECONF.RECONFIRMAPPLIC.PDo procedures indicate the pipeline segments for which MAOP reconfirmation is applicable and must be conducted as required by §192.624(a)? References: 192.624(a), 192.619(f)#
MO.RECONFprocedurePage 118MO.RECONF.RECONFIRMTIMING.PHave the procedures been developed and implemented for pipeline segments determined to require MAOP reconfirmation, including timeline and complete dates, as required by §192.624(b)? References: 192.624(b), 192.18#
MO.RECONFrecordPage 118MO.RECONF.RECONFIRMTIMING.RDo the records indicate that the operator is making adequate progress towards their implementation timeline / schedule as required by §192.624(b)? References: 192.624(b), 192.614(a)#
MO.RECONFprocedurePage 118MO.RECONF.RECONFIRMMETHODS.PAre the procedures for conducting MAOP reconfirmation adequate for the methods used (or intended to be used) as required by §192.624(c)? References: 192.624(c), 192.18, 192.619(a)(2), 192.632#
MO.RECONFprocedurePage 119MO.RECONF.COMPONENTS.PDo the MAOP reconfirmation methods for the applicable portions of the facilities (i.e., Compressor Stations, Meter & Regulating Stations) ensure that material properties are available to support the MAOP? References: 192.624, 192.607(e), 192.607(f), 192.619#
MO.RECONFrecordPage 119MO.RECONF.COMPONENTS.RDo the records identify all non-line pipe components requiring MAOP reconfirmation (e.g., compressor and meter stations)? References: 192.624, 192.607(e), 192.607(f), 192.619#
MO.RECONFprocedurePage 119MO.RECONF.RECONFIRMRECORDS.PDo the MAOP reconfirmation procedures require recordkeeping in accordance with §192.624(d) for the life of the pipeline? References: 192.624(b), 192.624(d), 192.619(f)#
MO.RECONFrecordPage 119MO.RECONF.RECONFIRMRECORDS.RDo the MAOP reconfirmation records meet the requirements of §192.624(d) and are they retained for the life of the pipeline? References: 192.624(d), 192.517, 192.624(b), 192.619(f)#
MO.RECONFobservationPage 119MO.RECONF.RECONFIRMATION.ODo field observations of selected MAOP reconfirmation method(s) or related activities verify that the method employed conforms with the operator-established procedures? References: 192.624(c), 192.505, 192.506, 192.607#
MO.RECONFM1procedurePage 119MO.RECONFM1.METHOD1.PWhere the operator has elected Method 1 for the MAOP reconfirmation, do the procedures for conducting a pressure test for MAOP reconfirmation meet the requirements of §192.624(c)(1)? References: 192.624(c)(1), 192.18, 192.619(c)#
MO.RECONFM1recordPage 119MO.RECONFM1.METHOD1.RWhere the operator has elected Method 1 for the MAOP reconfirmation, are the records adequate for a pressure test for MAOP reconfirmation as required by §192.624(c)(1)? References: 192.624(d), 192.624(c)(1), 192.619(c)#
MO.RECONFM2procedurePage 120MO.RECONFM2.METHOD2.PWhere the operator has elected Method 2 for the MAOP reconfirmation, do the procedures for conducting a pressure reduction for MAOP reconfirmation meet the requirements of §192.624(c)(2)? References: 192.624(c)(2), 192.18, 192.619(c)#
MO.RECONFM2recordPage 120MO.RECONFM2.METHOD2.RWhere the operator has elected Method 2 for the MAOP reconfirmation, do the records confirm the pressure reduction for MAOP reconfirmation meet the requirements of §192.624(c)(2)? References: 192.624(d), 192.624(c)(2), 192.18, 192.619(c)#
MO.RECONFM3procedurePage 120MO.RECONFM3.ECAASSESSMENT.PWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the procedures provide sufficient detail to ensure the ECA Assessment is conducted in accordance with §192.632? References: 192.632#
MO.RECONFM3procedurePage 120MO.RECONFM3.ECAANALYSIS1.PWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the procedures provide sufficient detail to ensure the ECA Analysis is conducted in accordance with §192.632(a) for methods and data collection? References: 192.632(a), 192.624(c), 192.712#
MO.RECONFM3procedurePage 120MO.RECONFM3.ECAANALYSIS2.PWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the procedures provide sufficient detail to ensure the ECA Analysis is conducted in accordance with §192.632(a) for crack analysis and predicted failure pressure (including Charpy V-notch)? References: 192.632(a), 192.624(c), 192.712#
MO.RECONFM3procedurePage 120MO.RECONFM3.ECAREMAINDEFECTS.PWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the procedures provide sufficient detail to ensure the ECA Assessment is conducted in accordance with §192.632(b) for determining remaining defects? References: 192.632(b), 192.624(c), 192.712#
MO.RECONFM3procedurePage 120MO.RECONFM3.ECAREMAINDEFECTSILI.PWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the procedures provide sufficient detail to ensure the ECA Analysis is conducted in accordance with §192.632(c) for selecting appropriate ILI tools? References: 192.632(c), 192.624(c), 192.712#
MO.RECONFM3procedurePage 121MO.RECONFM3.ECAREMAINPIPELINELIFE.PWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the procedures provide sufficient detail to ensure the ECA Analysis is performed in accordance with §192.632(d) for estimating remaining life of the pipeline? References: 192.632(d), 192.624(c), 192.712#
MO.RECONFM3recordPage 121MO.RECONFM3.ECAASSESSMENT.RWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the records indicate the ECA Analysis was conducted in accordance with their procedures and §192.632? References: 192.632#
MO.RECONFM3recordPage 121MO.RECONFM3.ECAANALYSIS1.RWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the records indicate the ECA Analysis was conducted in accordance with §192.632(a) for methods and data collection? References: 192.632(a), 192.624(c), 192.712#
MO.RECONFM3recordPage 121MO.RECONFM3.ECAANALYSIS2.RWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the records indicate the ECA Analysis was conducted in accordance with §192.632(a) for crack analysis and predicted failure pressure (including Charpy V-notch)? References: 192.632(a), 192.624(c), 192.712#
MO.RECONFM3recordPage 121MO.RECONFM3.ECAREMAINDEFECTS.RWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the records indicate the ECA Assessment was conducted in accordance with §192.632(b) for determining remaining defects? References: 192.632(b), 192.624(c), 192.712#
MO.RECONFM3recordPage 121MO.RECONFM3.ECAREMAINDEFECTSILI.RWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the records indicate the ECA Analysis was conducted in accordance with §192.632(c) for selecting appropriate ILI tools? References: 192.632(c), 192.624(c), 192.712#
MO.RECONFM3recordPage 121MO.RECONFM3.ECAREMAINPIPELINELIFE.RWhen the operator elects to use ECA for MAOP reconfirmation (per §192.624(c)(3)), do the records indicate the ECA Analysis was performed in accordance with §192.632(d) for estimating remaining life of the pipeline? References: 192.632(d), 192.624(c), 192.712#
MO.RECONFM5procedurePage 121MO.RECONFM5.METHOD5.PWhere the operator has elected Method 5 for the MAOP reconfirmation, do the procedures for conducting a pressure reduction for pipeline segments with small PIR meet the requirements of §192.624(c)(5)? References: 192.624(c)(5), 192.18, 192.619(c)#
MO.RECONFM5recordPage 122MO.RECONFM5.METHOD5.RWhere the operator has elected Method 5 for the MAOP reconfirmation, are the records for pressure reduction on pipeline segments with a small PIR for MAOP reconfirmation adequate as required by §192.624(c)(5)? References: 192.624(d), 192.624(c)(5), 192.18, 192.619(c)#
MO.RECONFM6procedurePage 122MO.RECONFM6.METHOD6.PWhere the operator has elected Method 6 for the MAOP reconfirmation, do the procedures for the alternative technical evaluation process meet the requirements of §192.624(c)(6)? References: 192.624(c)(6), 192.18, 192.619(c)#
MO.RECONFM6recordPage 122MO.RECONFM6.METHOD6.RWhere the operator has elected Method 6 for the MAOP reconfirmation, do the records for the alternative technical evaluation process meet the requirements of §192.624(c)(6)? References: 192.624(d), 192.624(c)(6), 192.18, 192.619(c)#
MO.AMAOPprocedurePage 122MO.AMAOP.ADDITIONALOM.PDoes the AMAOP process include additional O&M requirements? References: 192.605(a), 192.620(d)#
MO.AMAOPrecordPage 122MO.AMAOP.ADDITIONALOM.RDo records indicate the additional AMAOP O&M requirements were met? References: 192.605(a), 192.620(d)#
MO.AMAOPprocedurePage 122MO.AMAOP.CALC.PDoes the AMAOP process include appropriate factors and considerations for calculating the alternative MAOP? References: 192.605(a), 192.620(a)#
MO.AMAOPrecordPage 122MO.AMAOP.CALC.RDo records indicate appropriate calculation of the alternative MAOP? References: 192.605(a), 192.620(a)#
MO.AMAOPprocedurePage 123MO.AMAOP.CONDITIONS.PDoes the AMAOP process include conditions on the application of alternative MAOP? References: 192.605(a), 192.620(b)#
MO.AMAOPrecordPage 123MO.AMAOP.CONDITIONS.RDo records indicate the AMAOP process satisfied the conditions on application of an alternative MAOP? References: 192.605(a), 192.620(b)#
MO.AMAOPprocedurePage 123MO.AMAOP.REQUIREMENTS.PDoes the AMAOP process include AMAOP requirements? References: 192.605(a), 192.620(c)#
MO.AMAOPrecordPage 123MO.AMAOP.REQUIREMENTS.RDo records indicate the AMAOP requirements were met? References: 192.605(a), 192.620(c)#
MO.AMAOPprocedurePage 123MO.AMAOP.OVERPRESS.PDoes the AMAOP process include overpressure protection requirements? References: 192.605(a), 192.620(e)#
MO.AMAOPrecordPage 123MO.AMAOP.OVERPRESS.RDo records indicate that overpressure protection requirements were met? References: 192.605(a), 192.620(e)#
PD.DPprocedurePage 123PD.DP.PDPROGRAM.PIs a damage prevention program approved and in place? References: 192.614(a)#
PD.DPprocedurePage 123PD.DP.ONECALL.PDoes the process require participation in qualified one-call systems? References: 192.614(b)#
PD.DPprocedurePage 123PD.DP.EXCAVATEMARK.PDoes the process require marking proposed excavation sites to CGA Best Practices or use more stringent and accurate requirements? References: 192.614(c)(5)#
PD.DPprocedurePage 124PD.DP.TPD.PDoes the process specify how reports of Third Party Activity and names of associated contractors or excavators are input back into the mail-outs and communications with excavators along the system? References: 192.614(c)(1)#
PD.DPprocedurePage 124PD.DP.TPDONECALL.PDoes the process specify how reports of TPD are checked against One-Call tickets? References: 192.614(c)(3)#
PD.DPobservationPage 124PD.DP.ONECALL.OParticipation in Qualified One Call Systems Observe operator process a "One Call" ticket. References: 192.614(c)(3)#
PD.DPrecordPage 124PD.DP.PDPROGRAM.RDoes the damage prevention program meet minimum requirements specified in 192.614(c)? References: 192.614(c)#
PD.DPprocedurePage 124PD.DP.DPINFOGATHER.PDoes the process require critical damage prevention information be gathered and recorded during pipeline patrols, leak surveys, and integrity assessments? References: 192.917(b), 192.935(b)(1)(ii)#
PD.DPrecordPage 124PD.DP.DPINFOGATHER.RDo records demonstrate that critical damage prevention information is being gathered and recorded during pipeline patrols, leakage surveys, and integrity assessments? References: 192.947(b), 192.917(b), 192.935(b)(1)(ii)#
PD.PAprocedurePage 124PD.PA.ASSETS.PDoes the program clearly identify the specific pipeline systems and facilities to be included in the program, along with the unique attributes and characteristics of each? References: 192.616(b)#
PD.PAprocedurePage 124PD.PA.AUDIENCEID.PDoes the program establish methods to identify the individual stakeholders in the four affected stakeholder audience groups: (1) affected public, (2) emergency officials, (3) local public officials, and (4) excavators, as well as affected municipalities, school districts, businesses, and residents? References: 192.616(d), 192.616(e), 192.616(f)#
PD.PAprocedurePage 125PD.PA.MGMTSUPPORT.PDoes the operator's program documentation demonstrate management support? References: 192.616(a)#
PD.PAprocedurePage 125PD.PA.PROGRAM.PHas the continuing public education (awareness) program been established as required? References: 192.616(a), 192.616(h)#
PD.PArecordPage 125PD.PA.AUDIENCEID.RDo records identify the individual stakeholders in the four affected stakeholder audience groups: (1) affected public, (2) emergency officials, (3) local public officials, and (4) excavators, as well as affected municipalities, school districts, businesses, and residents to which it sends public awareness materials and messages? References: 192.616(d), 192.616(e), 192.616(f)#
PD.PAprocedurePage 125PD.PA.MESSAGES.PDoes the program define the combination of messages, delivery methods, and delivery frequencies to comprehensively reach all affected stakeholder audiences in all areas where gas is transported? References: 192.616(c)#
PD.PAprocedurePage 125PD.PA.SUPPLEMENTAL.PConsideration of Supplemental Enhancements Were relevant factors considered to determine the need for supplemental public awareness program enhancements for each stakeholder audience, as described in API RP 1162? References: 192.616(c)#
PD.PArecordPage 125PD.PA.EDUCATE.RDid delivered messages specifically include provisions to educate the public, emergency officials, local public officials, and excavators on: (1) Use of a one-call notification system prior to excavation and other damage prevention activities; (2) Possible hazards associated with unintended releases from a gas pipeline facility; (3) Physical indications of a possible release; (4) Steps to be taken for public safety in the event of a gas pipeline release; and (5) Procedures to report such an event? References: 192.616(d), 192.616(f)#
PD.PArecordPage 125PD.PA.LOCATIONMESSAGE.RMessages on Pipeline Facility Locations Were messages developed and delivered to advise affected municipalities, school districts, businesses, and residents of pipeline facility locations? References: 192.616(e), 192.616(f)#
PD.PArecordPage 125PD.PA.MESSAGEFREQUENCY.RDid the delivery of materials and messages meet or exceed the baseline delivery frequencies specified in API RP 1162, Table 2-1 through Table 2.3? References: 192.616(c)#
EP.ERGrecordPage 126EP.ERG.LIAISON.RDo records indicate that liaison has been established and maintained with appropriate fire, police, public officials, and utility owners? References: 192.605(a), 192.615(c)(1), 192.615(c)(2), 192.615(c)(3), 192.615(c)(4), 192.616(c)#
PD.PAprocedurePage 126PD.PA.LANGUAGE.PDoes the program require that materials and messages be provided in other languages commonly understood by a significant number and concentration of non-English speaking populations in the operator's areas? References: 192.616(g)#
PD.PArecordPage 126PD.PA.LANGUAGE.ROther Languages Were materials and messages developed and delivered in other languages commonly understood by a significant number and concentration of non-English speaking populations in the operator's areas? References: 192.616(g)#
PD.PAprocedurePage 126PD.PA.EVALPLAN.PDoes the program include a process that specifies how program implementation and effectiveness will be periodically evaluated? References: 192.616(i), 192.616(c)#
PD.PArecordPage 126PD.PA.EVALIMPL.RHas an audit or review of the operator's program implementation been performed annually since the program was developed? References: 192.616(c), 192.616(i)#
PD.PArecordPage 126PD.PA.AUDITMETHODS.RAcceptable Methods for Program Implementation Audits Was one or more of the three acceptable methods (i.e., internal assessment, 3rd-party contractor review, or regulatory inspections) used to complete the annual audit or review of program implementation? References: 192.616(c), 192.616(i)#
PD.PArecordPage 126PD.PA.PROGRAMIMPROVE.RProgram Changes and Improvements Were changes made to improve the program and/or the implementation process based on the results and findings of the annual audit(s)? References: 192.616(c)#
PD.PArecordPage 126PD.PA.EVALEFFECTIVENESS.RHave effectiveness evaluation(s) of the program been performed for all stakeholder groups in all notification areas along all systems covered by the program? References: 192.616(c)#
PD.PArecordPage 126PD.PA.MEASUREOUTREACH.RMeasure Program Outreach In evaluating effectiveness, was actual program outreach for each stakeholder audience tracked? References: 192.616(c)#
PD.PArecordPage 127PD.PA.MEASUREUNDERSTANDABILITY.RMeasure Understandability of Message Content In evaluating program effectiveness, was the percentage of each stakeholder audience that understood and retained the key information from the messages determined? References: 192.616(c)#
PD.PArecordPage 127PD.PA.MEASUREBEHAVIOR.RMeasure Desired Stakeholder Behavior In evaluating program effectiveness, was evaluation made of whether appropriate preventive, response, and mitigative behaviors were understood and likely to be exhibited? References: 192.616(c)#
PD.PArecordPage 127PD.PA.MEASUREBOTTOM.RMeasure Bottom-Line Results Were bottom-line results of the program measured by tracking third-party incidents and consequences including: (1) near misses, (2) excavation damages resulting in pipeline failures, (3) excavation damages that do not result in pipeline failures? References: 192.616(c)#
PD.PArecordPage 127PD.PA.CHANGES.RProgram Changes Were needed changes and/or modifications to the program identified and documented based on the results and findings of the program effectiveness evaluations? References: 192.616(c)#
MO.RWprocedurePage 127MO.RW.PATROL.PDoes the process adequately cover the requirements for patrolling the ROW and conditions reported? References: 192.705(a), 192.705(b), 192.705(c)#
MO.RWrecordPage 127MO.RW.PATROL.RDo records indicate that ROW surface conditions have been patrolled as required? References: 192.709(c), 192.705(a), 192.705(b), 192.705(c)#
MO.RWobservationPage 127MO.RW.ROWMARKER.OAre line markers placed and maintained as required? References: 192.707(a), 192.707(b), 192.707(c), 192.707(d)#
MO.RWobservationPage 128MO.RW.ROWCONDITION.OAre the ROW conditions acceptable for the type of patrolling used? References: 192.705(a), 192.705(c)#
MO.RWprocedurePage 128MO.RW.ROWMARKER.PDoes the process adequately cover the requirements for placement of ROW markers? References: 192.707(a), 192.707(b), 192.707(c), 192.707(d)#
MO.RWprocedurePage 128MO.RW.GOMHAZARD.PDoes the process require identification of pipelines in the Gulf of Mexico at risk of being exposed underwater or hazards to navigation? References: 192.612(a), 192.612(c)(2), 192.612(c)(3)#
MO.RWrecordPage 128MO.RW.GOMHAZARD.RDo records indicate steps taken to identify and inspect pipelines in the Gulf of Mexico at risk of being exposed underwater pipelines or hazards to navigation? References: 192.709(c), 192.612(a), 192.612(b)#
MO.RWobservationPage 128MO.RW.GOMHAZARD.OAre pipelines in the Gulf of Mexico at risk of being exposed underwater pipelines or hazards to navigation marked as required? References: 192.612(c)(2)#
PD.SPprocedurePage 128PD.SP.REPAIR.PIf the operator operates a pipeline under a special permit have the processes been modified to incorporate the requirements of the permit for required repairs? References: 190.341(d)(2)#
PD.SPprocedurePage 128PD.SP.BESTPRACTICE.PIf the operator operates a pipeline under a special permit, do the processes specify implementation of applicable CGA Best Practices? References: 190.341(d)(2)#
PD.SPrecordPage 129PD.SP.REPAIR.RIf the operator operates a pipeline under a special permit, do records indicate that required repairs were performed? References: 190.341(d)(2)#
PD.SPobservationPage 129PD.SP.REQUIREMENT.OIf the operator operates a pipeline under a special permit verify that the requirements have been implemented. References: 190.341(d)(2)#
PD.SPprocedurePage 129PD.SP.AMAOP.PIf the operator operates a pipeline under an AMAOP special permit have the processes been modified to incorporate the requirements of the permit? References: 190.341(d)(2)#
PD.SPrecordPage 129PD.SP.AMAOP.RIf the operator operates a pipeline under an AMAOP special permit, do records indicate that required repairs were performed? References: 190.341(d)(2), 192.605(b)#
RPT.NRprocedurePage 129RPT.NR.NOTIFYOQ.PDoes the OQ Program require the Administrator or state agency to be notified if the operator significantly modifies its program? References: 192.805(i), 192.18#
RPT.NRrecordPage 129RPT.NR.NOTIFYOQ.RDo records indicate the Administrator or state agency was notified when the OQ Program was significantly modified? References: 192.805(i), 192.18#
RPT.NRrecordPage 129RPT.NR.AMAOPTEMP.RDo records indicate coating information was provided to PHMSA and state authorities at least 60 days prior to operating above 120 deg. F? References: 192.112(h)(2)#
RPT.NRrecordPage 129RPT.NR.AMAOPCOAT.RDo records indicate coating monitoring program provided to PHMSA and state authorities? References: 192.112(h)(3)#
RPT.NRrecordPage 129RPT.NR.AMAOPTESTFAIL.RDo records indicate the results of root cause analyses of pipe test failures reported to PHMSA and state authorities, at least 60 days prior to operating at the alternative MAOP? References: 192.328(d)(1)#
RPT.NRprocedurePage 130RPT.NR.AMAOPOPFAIL.PAlternative MAOP - Operating Failure Prior to using the alternative maximum allowable pressure option on a pipeline that have been previously operated at lower pressures, do processes require reporting the results of root cause analyses of operational failures to PHMSA and state authorities, at least 60 days prior to operation at the alternative MAOP? References: 192.605(b)(1), 192.620(b)(6)#
RPT.NRrecordPage 130RPT.NR.AMAOPOPFAIL.RDo records indicate results of root cause analyses of operational failures reported to PHMSA and state authorities for those pipelines using the alternative maximum allowable pressure option on a pipeline that have been previously operated at lower pressures, at least 60 days prior to operation at the alternative MAOP? References: 192.603(b), 192.620(b)(6)#
RPT.NRprocedurePage 130RPT.NR.AMAOPNOTIFY.PDoes the process require notification to PHMSA and the state pipeline safety authorities of the election to use the alternative MAOP? References: 192.620(c)(1)#
RPT.NRrecordPage 130RPT.NR.AMAOPNOTIFY.RDo records indicate notification to PHMSA and the state pipeline safety authorities of the election to use the alternative MAOP? References: 192.603(b), 192.620(c)(1)#
RPT.NRprocedurePage 130RPT.NR.AMAOPCERT.PDoes the process require certified copies required by 192.620(c)(2) be sent to applicable PHMSA region offices and state pipeline safety authorities? References: 192.620(c)(3)#
RPT.NRrecordPage 130RPT.NR.AMAOPCERT.RDo records indicate certified copies required by 192.620(c)(2) were sent to applicable PHMSA region offices and state pipeline safety authorities? References: 192.603(b), 192.620(c)(3)#
RPT.NRprocedurePage 130RPT.NR.AMAOPCP.PDoes the process require notification to PHMSA and the state pipeline safety authorities of certain annual test station readings that do not meet cathodic protection criteria if remedial action cannot be completed within 6 months? References: 192.620(d)(8)#
RPT.NRrecordPage 130RPT.NR.AMAOPCP.RDo records indicate notification to PHMSA and the state pipeline safety authorities of certain annual test station readings that do not meet cathodic protection criteria if remedial action could not be completed within 6 months? References: 192.603(b), 192.620(d)(8)#
RPT.NRprocedurePage 130RPT.NR.NOTIFYIMCHANGE.PIs the process for notifying PHMSA and/or state/local authorities of significant changes to the Integrity Management Program adequate? References: 192.909(b), 192.921(a)(7), 192.937(c)(7), 192.18#
RPT.NRrecordPage 131RPT.NR.NOTIFYIMCHANGE.RDo records demonstrate that PHMSA and/or state/local authorities were notified of substantial or significant changes to the Integrity Management Program? References: 192.947(i), 192.909(b), 192.921(a)(7), 192.937(c)(7)#
RPT.NRprocedurePage 131RPT.NR.NOTIFYIMPRESS.PDo processes require notifying PHMSA and/or state/local authorities: 1) if the schedule for evaluation and remediation required under paragraph 192.933(c) cannot be met and safety cannot be provided through temporary reduction in operating pressure or other action, and 2) when a pressure reduction exceeds 365 days? References: 192.933(a)(1)#
RPT.NRrecordPage 131RPT.NR.NOTIFYIMPRESS.RDo records demonstrate that PHMSA and/or state/local authorities were notified with the required information when one of the following occurred: 1) schedule for evaluation and remediation could not be met and safety could not be provided through a temporary reduction in operating pressure, or 2) when a pressure reduction exceeded 365 days? References: 192.947(i), 192.933(a)(1)#
RPT.NRprocedurePage 131RPT.NR.IMDEVIATERPT.PIs there a process for reporting integrity management program performance measures if deviating from certain IMP requirements (exceptional performance)? References: 192.913(b)(1)(vii)#
RPT.NRrecordPage 131RPT.NR.IMDEVIATERPT.RDo records demonstrate adequate reporting of integrity management program performance measures if deviating from certain IMP requirements (exceptional performance)? References: 192.947(i), 192.913(b)(1)(vii)#
RPT.NRprocedurePage 131RPT.NR.IMPERFRPT.PIs there a process for annual reporting of integrity management performance data? References: 192.947(i), 192.945(a), 191.17#
RPT.NRrecordPage 131RPT.NR.IMPERFRPT.RDo annual reports demonstrate that integrity management performance data were reported? References: 192.947(i), 192.945(a), 191.17#
RPT.NRprocedurePage 131RPT.NR.19218NOTIF.PDo the procedures include provisions for each of the required types of notificati References: 192.18(c), 192.506(b), 192.607(e)(4), 192.607(e)(5), 192.624(c)(2)(iii), 192.624(c)(6), 192.632(b)(3), 192.710(c)(7), 192.712(d)(3)(iv), 192.712(e)(2)#
RPT.NRrecordPage 131RPT.NR.19218NOTIF.RDo the records indicate proper and timely notifications to PHMSA for each notifi §192.18(c)? References: 192.18(c), 192.506(b), 192.607(e)(4), 192.607(e)(5), 192.624(c)(2)(iii), 192.624(c)(6), 192.632(b)(3), 192.710(c)(7), 192.712(d)(3)(iv), 192.712(e)(2)#
RPT.RRrecordPage 132RPT.RR.ANNUALREPORT.RHave complete and accurate Annual Reports utilizing the most recent form F 7 100.2-1 been submitted? References: 191.17(a)#
RPT.RRprocedurePage 132RPT.RR.IMMEDREPORT.PIs there a process to immediately report incidents to the National Response Center? References: 191.5(b), 191.7#
RPT.RRrecordPage 132RPT.RR.IMMEDREPORT.RDo records indicate immediate notifications of incidents were made in accordance with 191.5? References: 191.5(a), 191.7(a)#
RPT.RRprocedurePage 132RPT.RR.TELREPORTGOM.PDoes the process include telephonic notification to the National Response Center of exposed or navigation hazard pipe in the Gulf of Mexico and its inlets? References: 192.605(b)(1), 192.612(c)(1)#
RPT.RRrecordPage 132RPT.RR.TELREPORTGOM.RDo records indicate telephonic notification of exposed pipes in the Gulf of Mexico and its inlets was made? References: 192.612(c)(1)#
RPT.RRprocedurePage 132RPT.RR.INCIDENTREPORT.PDoes the process require preparation and filing of an incident report as soon as practicable but no later than 30 days after discovery of a reportable incident? References: 191.15(a), 192.624(a)(1), 192.624(a)(2)#
RPT.RRprocedurePage 132RPT.RR.INCIDENTREPORTSUPP.PDoes the process require preparation and filing of supplemental incident reports? References: 191.15(d), 192.624(a)#
RPT.RRrecordPage 132RPT.RR.INCIDENTREPORT.RDo records indicate reportable incidents were identified and reports were submitted to DOT on the most recent Form within the required timeframe? References: 191.15(a), 192.624(a)(1), 192.624(a)(2)#
RPT.RRrecordPage 132RPT.RR.INCIDENTREPORTSUPP.RDo records indicate accurate supplemental incident reports were filed and within the required timeframe using the most recent Form? References: 191.15(d)#
RPT.RRprocedurePage 133RPT.RR.SRCR.PDo processes require reporting of safety-related conditions? References: 192.605(a), 191.23(a), 191.23(b), 191.25(a), 191.25(b), 191.25(c)#
RPT.RRprocedurePage 133RPT.RR.SRC.PDoes the process include instructions enabling personnel who perform operation and maintenance activities to recognize conditions that may potentially be safety-related conditions, including MAOP Exceedances? References: 192.605(a), 192.605(d), 191.23(a)#
RPT.RRrecordPage 133RPT.RR.SRCR.RDo records indicate Safety-Related Condition Reports were filed as required? References: 191.23(a), 191.23(b), 191.25(a), 191.25(b), 191.25(c)#
RPT.RRprocedurePage 133RPT.RR.NOTIFYPERMITGOM.PDo the process require PHMSA notification when federal or state permits cannot be obtained in time? References: 192.605(b)(1), 192.612(c)(3)(ii)#
RPT.RRrecordPage 133RPT.RR.NOTIFYPERMITGOM.RDo records indicate required notification was provided when permitting delayed reburial of pipe in Gulf of Mexico waters found to be a hazard to navigation? References: 192.612(c)(3)(ii)#
RPT.RRprocedurePage 133RPT.RR.ABANDONWATERFACILITY.PDoes the process require reports to be filed for each abandoned offshore pipeline facility or each abandoned onshore pipeline facility that crosses over, under or through a commercially navigable waterway? References: 192.605(b)(1), 192.727(g)#
RPT.RRrecordPage 133RPT.RR.ABANDONWATERFACILITY.RDo records indicate reports were filed for abandoned offshore pipeline facilities or abandoned onshore pipeline facilities that crosses over, under or through a commercially navigable waterway? References: 192.727(g)#
RPT.RRrecordPage 133RPT.RR.NPMSANNUAL.RDo records indicate NPMS submissions were completed each year, on or before March 15, representing all in service, idle and retired assets as of December 31 of the previous year (excludes distribution lines and gathering lines) occurred, and that if no modifications occurred, an email was submitted stating that fact? References: 191.29(a), 191.29(b)#
RPT.RRprocedurePage 133RPT.RR.OPID.PDoes the process require the obtaining, and appropriate control, of Operator Identification Numbers (OPIDs), including changes in entity, acquisition/divestiture, and construction/update/uprate? References: 191.22(a), 191.22(c), 191.22(d)#
RPT.RRrecordPage 134RPT.RR.OPID.RDo records indicate appropriate obtaining, and control of, Operator Identification Numbers (OPIDs), including changes in entity, acquisition/divestiture, and construction/update/uprate? References: 191.22(a), 191.22(c), 191.22(d)#
RPT.SPrecordPage 134RPT.SP.SPWAIVER.RHas the operator complied with all reporting requirements contained within its special permit or waiver? References: 190.341(d)(2)#
SRN.GENERALsupplementalPage 134SRN.GENERAL.PROCEDORG.SHow are the procedures organized?#
SRN.GENERALsupplementalPage 134SRN.GENERAL.RECORDLOCATE.SHow are records organized and stored, and are there limitations to reviewing them?#
SRN.GENERALsupplementalPage 134SRN.GENERAL.ASSETCHANGE.SAsset Acquisition and Divestiture Describe the significant asset acquisitions, mergers, and divestitures in the last five years.#
SRN.GENERALsupplementalPage 134SRN.GENERAL.FACILITIES.SWhat types of facilities (compressor stations, regulator/meter stations, valve sites, laterals, etc.) are components of the pipeline system?#
SRN.GENERALsupplementalPage 134SRN.GENERAL.SYSTEMCHGS.SHave there been any significant changes in the pipeline system configuration in the last 5 years?#
SRN.GENERALsupplementalPage 135SRN.GENERAL.IDLEPIPE.SIdle & Inactive Pipelines - Current and Returned to Service For any pipelines or pipeline segments currently identified as "idle," "inactive," or “returned to service,” how are those segments managed in relevant Programs and/or Procedures? (Provide details)#
SRN.GENERALsupplementalPage 135SRN.GENERAL.ENFORCEMENT.SDiscussion of Enforcement Discussion of enforcement.#
SRN.GENERALsupplementalPage 135SRN.GENERAL.INCIDENREPORT.SDiscussion of Incident Reports Discussion of Incident Reports.#
SRN.GENERALsupplementalPage 135SRN.GENERAL.SRCR.SHave there been any Safety Related Conditions (SRCs) or Maximum Allowable Operating Pressure Exceedances for this pipeline in the last 5 years? (Provide details)#
SRN.GENERALsupplementalPage 135SRN.GENERAL.ADB.SHas the guidance of ADBs (Advisory Bulletins) been implemented in relevant program areas?#
SRN.GENERALsupplementalPage 135SRN.GENERAL.GRANDFATHER.SAre there any facilities or components grandfathered under various code requirements? (Provide details)#
SRN.GENERALsupplementalPage 135SRN.GENERAL.EXCLUSIONS.SExclusion Groups Confirmation of asset "Exclusions" (See Considerations).#
SRN.GENERALsupplementalPage 135SRN.GENERAL.TRIBALLANDS.SDoes the pipeline cross tribal lands?#
SRN.AR-RCOMsupplementalPage 135SRN.AR-RCOM.REPAIROM.SAre repair criteria in non-covered segments different than in covered segments? (provide details)#
SRN.AR-CDAsupplementalPage 136SRN.AR-CDA.CDA.SHas the operator utilized CDA on this pipeline system? (If Yes, provide details.)#
SRN.AR-ECsupplementalPage 136SRN.AR-EC.ECDA.SHas the operator utilized ECDA on this pipeline system?#
SRN.AR-ICsupplementalPage 136SRN.AR-IC.ICDA.SHas the operator utilized ICDA on this pipeline system?#
SRN.AR-ILsupplementalPage 136SRN.AR-IL.INTEGASSMNTS.SIntegrity Assessments Describe integrity issues or new threats discovered by the most recent integrity assessments.#
SRN.AR-ILsupplementalPage 136SRN.AR-IL.ILIUSE.SWhat process was used to select the ILI assessment tool(s)?#
SRN.AR-LSRsupplementalPage 137SRN.AR-LSR.LSR.SIf Low Stress Reassessment is used, was a baseline assessment conducted, and, if so, what were the results?#
SRN.AR-OTsupplementalPage 137SRN.AR-OT.OT.SWhat, if any, Other Technology(ies) have been used to assess the integrity of the pipeline in the last 7 years? (provide details)#
SRN.AR-PAsupplementalPage 137SRN.AR-PA.ASSESSNONHCA.SWhat is the status of your program to assess transmission lines outside of an HCA?#
SRN.AR-PTIsupplementalPage 137SRN.AR-PTI.PRESSTEST.SWhere pressure testing was utilized to assess the integrity of the pipeline, what was the extent and nature of any pipeline failures? (provide details)#
SRN.AR-RCsupplementalPage 137SRN.AR-RC.REPCRIT.SHas the nature and/or severity of required repairs found during the most recent assessment changed significantly as compared to the previous assessments? (Provide details)#
SRN.DC-COsupplementalPage 138SRN.DC-CO.MOVEREPLACE.SHave any pipeline movement or replacement projects been performed in the last 5 years? If so, identify the projects and locations.#
SRN.AR-RMPsupplementalPage 138SRN.AR-RMP.METHODS.SHave repairs to the pipeline been made in the past 5 years due to Integrity Management assessments?#
SRN.AR-SCCsupplementalPage 138SRN.AR-SCC.SCC.SWhat indications or instances of Stress Corrosion Cracking (SCC) have been identified and remediated in the last 5 years, and what is the resulting SCC program? (provide details)#
SRN.AR-SCCsupplementalPage 138SRN.AR-SCC.SCCDA.SHas the operator utilized SCCDA on this pipeline system?#
SRN.CR-CRMGENsupplementalPage 138SRN.CR-CRMGEN.CONTROLCNTR.SWhat is the assignment of the pipeline and its facilities to one or more control rooms (including their locations)?#
SRN.CR-CRMRRsupplementalPage 139SRN.CR-CRMRR.CONTROLLERS.SHave there been any revisions or changes to the CRM roles and responsibilities or staffing levels as a result of any AOCs or emergencies? (Provide details)#
SRN.CR-SCADAsupplementalPage 139SRN.CR-SCADA.SCADASYSTEMS.SHow many SCADA Systems and/or other remote/field automation units utilized for the pipeline? (Provide details)#
SRN.CR-CRMFMsupplementalPage 139SRN.CR-CRMFM.FATIGMGMT.SWhat type of shift schedule does the operator utilize and has it changed in the past five years?#
SRN.CR-CRMAMsupplementalPage 139SRN.CR-CRMAM.ALARMS.SWhat changes have been made to the alarm management process of receiving and logging/recording system events, alarms, and commands in the last 5 years? (Provide details)#
SRN.CR-CRMCMGTsupplementalPage 139SRN.CR-CRMCMGT.CHANGE.SHow are changes to pipeline equipment or configuration coordinated between the control room and associated field personnel?#
SRN.CR-CRMEXPsupplementalPage 140SRN.CR-CRMEXP.OPEREXP.SWhat changes, if any, have been made to the CRM procedures in the last 5 years?#
SRN.CR-CRMTRAINsupplementalPage 140SRN.CR-CRMTRAIN.CNTRLRTRAIN.SWhat controller training program updates or improvements were made in the last 5 years?#
SRN.CR-CRMCOMPsupplementalPage 140SRN.CR-CRMCOMP.COMPLVALID.SWhat deviations from the control room procedures have occurred in the last 5 years? (provide details)#
SRN.CR-LDsupplementalPage 140SRN.CR-LD.LEAKDETMETHOD.SIf a computational pipeline monitoring (CPM) leak detection system (LDS) is not used, then how are leaks detected? (Describe the LDS system in place)#
SRN.DC-COCMPsupplementalPage 140SRN.DC-COCMP.CMPSTA.SWhat compressor station construction activities are scheduled to occur within the next 6 months? (provide details)#
SRN.DC-DPCCMPsupplementalPage 141SRN.DC-DPCCMP.CMPSTA.SWhat is the process for ensuring that compressor station protective & safety devices and emergency shutdowns are designed in accordance with the code and applicable industry standards, and installed where needed?#
SRN.DC-DPCOPPsupplementalPage 141SRN.DC-DPCOPP.PRESSPROT.SWhat is the process for establishing and documenting each pressure limiting device and overpressure safety device on the pipeline system?#
SRN.DC-PTLOWPRESSsupplementalPage 141SRN.DC-PTLOWPRESS.PRESSTEST.SWhat pressure tests related to Low Pressure pipelines (below 30% SMYS) construction projects are planned to occur within the next 6 months on the pipeline or pipeline components? (provide details)#
SRN.DC-WELDINSPsupplementalPage 141SRN.DC-WELDINSP.WELDINSP.SConstruction Weld Inspection For recent construction projects, what was the approximate weld rejection rate? (Provide details)#
SRN.DC-WELDPROCEDUREsupplementalPage 141SRN.DC-WELDPROCEDURE.WELDPROCEDURE.SConstruction Welding Procedures For any recent or upcoming construction activities, what was/is the process for approving welding procedures?#
SRN.DC-COsupplementalPage 142SRN.DC-CO.CONSTRUCTION.SHave any new pipeline and/or facilities construction has taken place within the last 5 years, is presently underway, or is planned to occur within the next six months? (provide details)#
SRN.DC-COsupplementalPage 142SRN.DC-CO.MOVEREPLACE.SHave any pipeline movement or replacement projects been performed in the last 5 years? If so, identify the projects and locations.#
SRN.DC-DPsupplementalPage 142SRN.DC-DP.PIPEDESIGN.SHave there been any pipeline design process changes in the last 5 years to ensure that all appropriate design requirements from Part 192 and Industry Standards for line pipe are followed? (provide details)#
SRN.DC-DPCsupplementalPage 142SRN.DC-DPC.COMPDESIGN.SWhat is the process for ensuring that pipe components and devices (i.e., fittings, flanges, valves, instrumentation, ancillary fittings/piping, etc.) are designed in accordance with the code and applicable industry standards, and are installed where needed?#
SRN.DC-GAsupplementalPage 142SRN.DC-GA.GATHERING.SWhat processes have been established for the Design & Construction of gathering pipelines?#
SRN.DC-MAsupplementalPage 143SRN.DC-MA.MATERIALSCONSTR.SMaterials - Qualification, Marking, and Transport For pipeline projects in the last 5 years, what were the steel pipe (and plastic pipe) qualification, marking, and transportation requirements?#
SRN.DC-MOsupplementalPage 143SRN.DC-MO.MAINTOM.SWhat parts of the O&M procedures are utilized when conducting the following activities: internal corrosion examination, project related shutdown/start-up, accidental ignition controls, hot tapping, and conducting activities in a safe manner?#
SRN.DC-PTsupplementalPage 143SRN.DC-PT.PRESSURETEST.SWhat post-project pressure tests for O&M construction projects are planned to occur within the next 6 months on the pipeline or pipeline components? (provide details)#
SRN.DC-PTsupplementalPage 143SRN.DC-PT.CONSTHYDROFAIL.SHave there been any O&M construction (pre-commissioning, including replacement projects) hydrostatic pressure test or other pressure test failures within the last 5 years? (provide details)#
SRN.DC-TQsupplementalPage 143SRN.DC-TQ.CONSTOQTASK.SWhat are the identified OQ program covered tasks for O&M construction projects?#
SRN.DC-CONVsupplementalPage 144SRN.DC-CONV.CONVERSION.SWhat is the pipeline system (or segment) for which operator is planning to do a Conversion-to-Service?#
SRN.EP-ERGsupplementalPage 144SRN.EP-ERG.MANUALMOC.SWhat revisions to the Emergency Response procedures have been made in the last 5 years?#
SRN.EP-ERGsupplementalPage 144SRN.EP-ERG.RELEASEVOL.SHave any releases occurred in the last five years where the release volume and/or release rate exceeded the operator’s maximum calculated release volume or rate used for emergency preparedness?#
SRN.EP-ERGsupplementalPage 144SRN.EP-ERG.EPACTIVATE.SWhat emergency events (or drills if not actual events) have occurred in the past 5 years that required activation of an emergency response in accordance with procedures? (please explain)#
SRN.EP-FIIsupplementalPage 144SRN.EP-FII.FAILUREINVEST.SFailure & Incident Investigation Discuss with the operator their program to track and investigate failures.#
SRN.FS-CSsupplementalPage 144SRN.FS-CS.CMPSTA.SHave there been any changes to the compressor station site(s) that could impact the following: site layout, personnel movement/egress, NFPA70 requirements, separators, ventilation, bottle/pipe type holders, and flammable materials storage? (Provide details)#
SRN.FS-CSsupplementalPage 145SRN.FS-CS.CMPEQUIPOPS.SHave there been any changes to the compressor station sites that could impact normal/emergency operations procedures and equipment configuration? (Provide details)#
SRN.FS-CSsupplementalPage 145SRN.FS-CS.CMPSTATIONDIST.SDo any compressor stations serve as the sole gas supply for a gas distribution system, and if so, have any of these compressor stations been modified or undergone other construction within the last 5 years? (Provide details)#
SRN.FS-CSSYSPROTsupplementalPage 145SRN.FS-CSSYSPROT.CMPSTA.SWhat processes are in place for ensuring that compressor station protective and safety devices and emergency shutdowns (ESD) are installed where needed and inspected?#
SRN.FS-CSSYSPROTsupplementalPage 145SRN.FS-CSSYSPROT.HCAFACILITY.SAre any compressor stations located in a High Consequence Area (HCA)? (provide details)#
SRN.FS-FGsupplementalPage 145SRN.FS-FG.FACILCHGS.SWhat changes, including abandonment and deactivation, have been made to the non-compressor station facilities operations and equipment configuration in the last 5 years? (Provide details)#
SRN.FS-GSsupplementalPage 145SRN.FS-GS.STORAGEFIELD.SWhat, if any, gas storage fields are operated associated with the pipeline? (Provide details)#
SRN.FS-VAsupplementalPage 146SRN.FS-VA.VALVES.SWhat is the process for ensuring that facility valves are installed where needed and maintained for the safe operation of the pipeline different from mainline valves?#
SRN.IM-BAsupplementalPage 146SRN.IM-BA.BAPSCHEDULE.SHas there been any newly identified HCAs or newly installed pipe in HCAs identified in the last 5 years?#
SRN.IM-CAsupplementalPage 146SRN.IM-CA.PERIODICEVALMOC.SIM Periodic Evaluation Actions Describe the actions implemented in the last 5 years to address the threats identified and the risk represented by these threats as a result of a periodic evaluation for a specific covered segment.#
SRN.IM-CAsupplementalPage 146SRN.IM-CA.ASSESSDELAY.SHas the performance of any integrity assessments been delayed such that a schedule or required timeframe was exceeded? (Provide details)#
SRN.IM-HCsupplementalPage 146SRN.IM-HC.IMPLANMOD.SIMP - Process and Procedure Changes Describe the most significant changes to the Integrity Management processes and procedures since the last IMP-focused PHMSA inspection.#
SRN.IM-HCsupplementalPage 146SRN.IM-HC.HCANEW.SIM HCAs - Newly Identified HCAs Describe the method or process that identifies any new segments that are in an HCA and incorporates them into the Integrity Management Program.#
SRN.IM-HCsupplementalPage 147SRN.IM-HC.FACILHCA.SAre any non-compressor station facilities located in a High Consequence Area (HCA)? (Provide details)#
SRN.GENERALsupplementalPage 147SRN.GENERAL.IDLEPIPE.SIdle & Inactive Pipelines - Current and Returned to Service For any pipelines or pipeline segments currently identified as "idle," "inactive," or “returned to service,” how are those segments managed in relevant Programs and/or Procedures? (Provide details)#
SRN.IM-PMsupplementalPage 147SRN.IM-PM.PMIMPGENERAL.SIM Preventive & Mitigative Measures - General Requirements Describe the preventive measures & mitigative measures that have been implemented in the last 5 years or are planned to be implemented in the future to protect HCAs.#
SRN.IM-QAsupplementalPage 147SRN.IM-QA.PERFMEASURE.SWhat are the methods employed to measure the Integrity Management Program's effectiveness?#
SRN.IM-QAsupplementalPage 147SRN.IM-QA.MOC.SIM Management of Change (MOC) Describe the most significant changes that have been implemented outside of the IMP processes as a result of IMP decisions and moved through the Management of Change (MOC) process in the last 5 years.#
SRN.IM-RAsupplementalPage 147SRN.IM-RA.RAMOD.SRisk Analysis - Comprehensiveness of Approach Describe the most significant modifications that have been made to the IM processes in the last 5 years to identify and evaluate all potential threats to each covered pipeline segment.#
SRN.IM-RAsupplementalPage 148SRN.IM-RA.INFOMGMT.SHow is the information gathered (related to potential excavation damage) during pipeline patrols, monitoring, and leakage surveys analyzed and used by the integrity management information / risk analysis?#
SRN.MO-AMAOPsupplementalPage 148SRN.MO-AMAOP.AMAOP.SAre any segments of the pipeline operated under the Alternate MAOP limitations (ref. 192.620)?#
SRN.MO-GCsupplementalPage 148SRN.MO-GC.192CONV.SWhat pipelines or pipeline segments have undergone a conversion to Part 192 service in the last 5 years? (provide details)#
SRN.MO-GOABNORMALsupplementalPage 148SRN.MO-GOABNORMAL.ABPROCESS.SWhat abnormal operations events has the pipeline experienced in the last 5 years and how were lessons learned incorporated? (Provide details)#
SRN.MO-GOCLASSsupplementalPage 148SRN.MO-GOCLASS.CLASSLOCATEMAOPREV.SHas there been a class location change occur in the past 3 years that required a study and the subsequent confirmation or revision of the pipeline segment's MAOP?#
SRN.MO-GOMAOPsupplementalPage 149SRN.MO-GOMAOP.MAOPCHGS.SIf there have been any changes in the pipeline MAOP or in startup/shutdown procedures to ensure that operations are within MAOP, in the last 5 years, what was the nature of the changes?#
SRN.MO-GOMAOPsupplementalPage 149SRN.MO-GOMAOP.MAOPVALID.SAre records available that fully validate the current pipeline MAOP, and if not, what is the process for addressing this issue?#
SRN.MO-GOMAOPsupplementalPage 149SRN.MO-GOMAOP.MAOPDETERMINATION.SDoes the operator have any pipelines where the MAOP was determined by §192.619(a)(2) or §192.619(c)?#
SRN.MO-RECONFsupplementalPage 149SRN.MO-RECONF.MAOPMETHODS.SWhich MAOP Reconfirmation Methods do you plan to use or have used?#
SRN.MO-MCAsupplementalPage 149SRN.MO-MCA.MCAIDENTIFY.SHas the operator completed their review and identification of Moderate Consequence Areas (MCAs)?#
SRN.DC-COsupplementalPage 149SRN.DC-CO.MOVEREPLACE.SHave any pipeline movement or replacement projects been performed in the last 5 years? If so, identify the projects and locations.#
SRN.MO-GMsupplementalPage 150SRN.MO-GM.GASMTCE.SWhat significant changes have been made to the pipeline maintenance program in the last 5 years?#
SRN.MO-GOODORsupplementalPage 150SRN.MO-GOODOR.ODORIZE.SAre any portions of the pipeline system(s) non-odorized? (Provide details)#
SRN.MO-GOsupplementalPage 150SRN.MO-GO.NEARMISS.SAre "near misses" tracked, and if so, how are they reviewed and potentially incorporated into revised procedures or revised programs?#
SRN.MO-GOsupplementalPage 150SRN.MO-GO.OMPLANMOD.SWhat, if any, changes or improvements have been made to the O&M manuals, processes, or procedures in the last 5 years?#
SRN.MO-GOsupplementalPage 150SRN.MO-GO.OPERATERESTRICT.SAre there any operational restrictions (for example, reduced operational pressure) that have been put on the pipeline system or any system components? (Provide details)#
SRN.GENERALsupplementalPage 150SRN.GENERAL.IDLEPIPE.SIdle & Inactive Pipelines - Current and Returned to Service For any pipelines or pipeline segments currently identified as "idle," "inactive," or “returned to service,” how are those segments managed in relevant Programs and/or Procedures? (Provide details)#
SRN.MO-GMOPPsupplementalPage 151SRN.MO-GMOPP.PRESSPROTECT.SHave any pressure limiting device or overpressure safety device settings been changed for the pipeline system in the last 5 years? (Provide details)#
SRN.MO-GMOPPsupplementalPage 151SRN.MO-GMOPP.MAOPSEGPROTECT.SAre there any segment-specific MAOP protection controls in place? (provide details)#
SRN.MO-GMOPPsupplementalPage 151SRN.MO-GMOPP.MAOPEXCEED.SHave there been any MAOP exceedances in the last 5 years? (please describe)#
SRN.MO-RWsupplementalPage 151SRN.MO-RW.ROWISSUES.SWhat, if any, issues have occurred in the last 5 years regarding pipeline ROW monitoring, marking, leakage surveys, and patrolling?#
SRN.PD-DPsupplementalPage 151SRN.PD-DP.DPPROGRAM.SHow is the effectiveness of the Damage Prevention Program measured, and what issues have been discovered in the last 5 years?#
SRN.MO-GOsupplementalPage 151SRN.MO-GO.NEARMISS.SAre "near misses" tracked, and if so, how are they reviewed and potentially incorporated into revised procedures or revised programs?#
SRN.PD-DPsupplementalPage 152SRN.PD-DP.ONECALL.SHow is the effectiveness of the One-Call system response measured, and what issues have been identified in the last 5 years?#
SRN.GENERALsupplementalPage 152SRN.GENERAL.IDLEPIPE.SIdle & Inactive Pipelines - Current and Returned to Service For any pipelines or pipeline segments currently identified as "idle," "inactive," or “returned to service,” how are those segments managed in relevant Programs and/or Procedures? (Provide details)#
SRN.PD-PAsupplementalPage 152SRN.PD-PA.PAPROGRAM.SWhat, if any, changes or improvements have been made to the Public Awareness manuals, processes, or procedures in the last 5 years?#
SRN.PD-PAsupplementalPage 152SRN.PD-PA.PAPROGRAMEFF.SHow is the effectiveness of the Public Awareness Program measured, and what issues have been identified in the last 5 years?#
SRN.MO-RWsupplementalPage 152SRN.MO-RW.ROWISSUES.SWhat, if any, issues have occurred in the last 5 years regarding pipeline ROW monitoring, marking, leakage surveys, and patrolling?#
SRN.GENERALsupplementalPage 152SRN.GENERAL.IDLEPIPE.SIdle & Inactive Pipelines - Current and Returned to Service For any pipelines or pipeline segments currently identified as "idle," "inactive," or “returned to service,” how are those segments managed in relevant Programs and/or Procedures? (Provide details)#
SRN.TD-CPEXPOSEDsupplementalPage 153SRN.TD-CPEXPOSED.EXPOSEDPIPE.SHave any exposed portions of buried pipe been discovered in the last 5 years? (Provide details)#
SRN.TD-CPMONITORsupplementalPage 153SRN.TD-CPMONITOR.CATHODICPROT.SWhat issues have been discovered during cathodic protection monitoring in the last 5 years? (provide details)#
SRN.TD-CPMONITORsupplementalPage 153SRN.TD-CPMONITOR.CPSEPARATE.SAre there any separately protected short sections of mains or transmission line, not in excess of 100 feet for which monitoring CP once each calendar year is impractical?#
SRN.TD-ICCGsupplementalPage 153SRN.TD-ICCG.CORRGAS.SWhere corrosive gas is transported, what changes have been made to minimize internal corrosion in the last 5 years?#
SRN.MO-AMAOPsupplementalPage 153SRN.MO-AMAOP.AMAOP.SAre any segments of the pipeline operated under the Alternate MAOP limitations (ref. 192.620)?#
SRN.TD-ATMsupplementalPage 154SRN.TD-ATM.ATMCORRODE.SWhat, if any, specific corrosion control projects in response to discovering atmospheric external corrosion have been conducted in the last 5 years? (Provide details)#
SRN.TD-COATsupplementalPage 154SRN.TD-COAT.COATINGS.SWhat, if any, coating issues have been discovered in the last 5 years? (Provide details)#
SRN.TD-CPsupplementalPage 154SRN.TD-CP.CP.SWhat, if any, portion of the pipeline is not effectively protected from external corrosion by a cathodic protection system? (describe details)#
SRN.TD-CPsupplementalPage 154SRN.TD-CP.EXTCORROSION.SWhat, if any, specific projects in response to discovering external corrosion related to cathodic protection have been conducted in the last 5 years? (Provide details)#
SRN.TD-ICPsupplementalPage 154SRN.TD-ICP.INTCORROSION.SWhat, if any, internal corrosion issues have been discovered in the last 5 years? (provide details)#
SRN.TD-SCCsupplementalPage 155SRN.TD-SCC.SCC.SWhat indications or instances of Stress Corrosion Cracking (SCC) has the pipeline experienced in the last 5 years, and what is the resulting SCC program? (Provide details)#
SRN.TQ-QUIMsupplementalPage 155SRN.TQ-QUIM.IMREQMNTS.SHave there been any changes in the last 5 years to the process to ensure that individuals (operator and contractor) are qualified to perform integrity management program activities and integrity management quality control?#
SRN.TQ-QUOMCONSTsupplementalPage 155SRN.TQ-QUOMCONST.OMCONSTREQMNTS.SWhat significant changes have been made in the last 5 years to the processes regarding the qualifications of individuals involved in welding and joining pipe?#
SRN.TQ-OQsupplementalPage 155SRN.TQ-OQ.OQPLANMOD.SWhat, if any, changes or improvements have been made to the OQ Plan in the last 5 years?#
SRN.TQ-OQsupplementalPage 155SRN.TQ-OQ.OQPERSONNEL.SHave there been changes in the number of personnel (both company and contractor) covered by the OQ Plan in the last 5 years?#
SRN.TQ-OQsupplementalPage 155SRN.TQ-OQ.OQREMOVAL.SHave any OQ-qualified individuals (operator and contractor) been removed from performing a covered task, and what were the circumstances for the removal(s)?#
SRN.TQ-QUsupplementalPage 156SRN.TQ-QU.REQMNTS.SHave there been any changes in the last 5 years to the process to ensure that individuals (operator and contractor) are qualified to perform the following activities? - corrosion control processes, - hot tapping, and - individuals who oversee and perform marking, trenching, and backfilling operations.#
SRN.TQ-TRsupplementalPage 156SRN.TQ-TR.TRAINING.SHave there been any changes in the last 5 years to the process to ensure that emergency response personnel (operator and contractor) are qualified to perform their activities?#
TD.AMAOPprocedurePage 156TD.AMAOP.AMAOP.PIs there a process for controlling internal corrosion on pipelines that may operate under the Alternative Maximum Operating Pressure rule? References: 192.605(b)(2), 192.620(d)(5)#
TD.AMAOPrecordPage 156TD.AMAOP.AMAOP.RDo records document that the operator is following a process for controlling internal corrosion on pipelines they may operate under the Alternative Maximum Operating Pressure rule? References: 192.709(c), 192.620(d)(5)#
TD.AMAOPobservationPage 156TD.AMAOP.AMAOP.OIs the process being followed for controlling internal corrosion on pipelines operated under the Alternative Maximum Operating Pressure rule? References: 192.620(d)(5)#
TD.AMAOPprocedurePage 156TD.AMAOP.AMAOPINTFRCURRENT.PDoes the process include (prior to operating an existing pipeline segment at an alternate maximum allowable operating pressure, or within six months after placing a new pipeline segment in service at an alternate maximum allowable operating pressure) required instructions for addressing any interference currents on the pipeline segment? References: 192.605(b)(2), 192.620(d)(6)#
TD.AMAOPrecordPage 157TD.AMAOP.AMAOPINTFRCURRENT.RDo records document that actions taken (prior to operating an existing pipeline segment at an alternate maximum allowable operating pressure, or within six months after placing a new pipeline segment in service at an alternate maximum allowable operating pressure) have been adequate in addressing any interference currents on the pipeline segment? References: 192.709(c), 192.620(d)(6)#
TD.AMAOPprocedurePage 157TD.AMAOP.AMAOPINDIRECT.PDoes the process require that within six months after placing the cathodic protection of a new pipeline segment in operation, or within six months after an existing pipeline segment under Part 192 has been certified under the Alternative Maximum Operating Pressure rule, that adequacy be assessed of the indirect method such as close-interval survey, and the integrity of the coating using direct current voltage gradient (DCVG) or alternating current voltage gradient (ACVG)? References: 192.605(b)(2), 192.620(d)(7)#
TD.AMAOPrecordPage 157TD.AMAOP.AMAOPINDIRECT.RDo records document that within six months after placing the cathodic protection of a new pipeline segment in operation, or within six months after an existing pipeline segment under Part 192 has been certified under the Alternative Maximum Operating Pressure rule, that adequacy was assessed of the indirect method such as close-interval survey, and the integrity of the coating using direct current voltage gradient (DCVG) or alternating current voltage gradient (ACVG)? References: 192.709(c), 192.620(d)(7)#
TD.AMAOPprocedurePage 157TD.AMAOP.AMAOPTESTREAD.PDoes the process for a pipeline segment operating at an Alternate Maximum Allowable Operating Pressure require: (a) Completion of remedial action within six months of a failed reading at a test station during annual monitoring, or notification of each responsible pipeline safety party demonstrating that the integrity of the pipeline is not compromised; and (b) After completion of the remedial action to address a failed reading, confirmed restoration of adequate corrosion control by a close interval survey on either side of the affected test station to the next test station? References: 192.605(b)(2), 192.620(d)(8)#
TD.AMAOPrecordPage 157TD.AMAOP.AMAOPTESTREAD.RDo records document that for a pipeline segment operating at an alternate maximum allowable operating pressure the following: (a) Completion of remedial action within six months of a failed reading at a test station during annual monitoring, or notification of each responsible pipeline safety party demonstrating that the integrity of the pipeline is not compromised, and (b) After completion of the remedial action to address a failed reading, confirmed restoration of adequate corrosion control by a close interval survey on either side of the affected test station to the next test station? References: 192.709(c), 192.620(d)(8)#
TD.ATMprocedurePage 157TD.ATM.ATMCORRODE.PDoes the process give adequate guidance identifying atmospheric corrosion and for protecting above ground pipe from atmospheric corrosion? References: 192.605(b)(2), 192.479(a), 192.479(b), 192.479(c)#
TD.ATMrecordPage 157TD.ATM.ATMCORRODE.RDo records document the protection of above ground pipe from atmospheric corrosion? References: 192.491(c), 192.479(a), 192.479(b), 192.479(c)#
TD.ATMprocedurePage 158TD.ATM.ATMCORRODEINSP.PDoes the process give adequate instruction for the inspection of aboveground pipeline segments for atmospheric corrosion? References: 192.605(b)(2), 192.481(a), 192.481(b), 192.481(c), 192.481(d)#
TD.ATMrecordPage 158TD.ATM.ATMCORRODEINSP.RDo records document inspection of aboveground pipe for atmospheric corrosion? References: 192.491(c), 192.481(a), 192.481(b), 192.481(c), 192.481(d)#
TD.ATMobservationPage 158TD.ATM.ATMCORRODEINSP.OIs pipe that is exposed to atmospheric corrosion protected? References: 192.481(b), 192.481(c), 192.479(a), 192.479(b), 192.479(c), 192.481(d)#
TD.CPMONITORprocedurePage 158TD.CPMONITOR.MONITORCRITERIA.PDoes the process require CP monitoring criteria to be used that is acceptable? References: 192.605(b)(2), 192.463(a), 192.463(c)#
TD.CPMONITORrecordPage 158TD.CPMONITOR.MONITORCRITERIA.RDo records document that the CP monitoring criteria used was acceptable? References: 192.491(c), 192.463(a)#
TD.CPMONITORobservationPage 158TD.CPMONITOR.MONITORCRITERIA.OAre methods used for taking CP monitoring readings that allow for the application of appropriate CP monitoring criteria? References: 192.465(a), 192.463(a), 192.463(b), 192.463(c)#
TD.CPMONITORprocedurePage 158TD.CPMONITOR.TEST.PDoes the process adequately describe how to monitor CP that has been applied to pipelines? References: 192.605(b)(2), 192.465(a)#
TD.CPMONITORrecordPage 158TD.CPMONITOR.TEST.RDo records adequately document cathodic protection monitoring tests have occurred as required? References: 192.491(c), 192.465(a)#
TD.CPMONITORprocedurePage 158TD.CPMONITOR.CURRENTTEST.PDoes the process give sufficient details for making electrical checks of rectifiers or impressed current sources? References: 192.605(b)(2), 192.465(b)#
TD.CPMONITORrecordPage 159TD.CPMONITOR.CURRENTTEST.RDo records document details of electrical checks of sources of rectifiers or other impressed current sources? References: 192.491(c), 192.465(b)#
TD.CPMONITORobservationPage 159TD.CPMONITOR.CURRENTTEST.OAre impressed current sources properly maintained and are they functioning properly? References: 192.465(b)#
TD.CPMONITORprocedurePage 159TD.CPMONITOR.REVCURRENTTEST.PDoes the process give sufficient details for making electrical checks of interference bonds, diodes, and reverse current switches? References: 192.605(b)(2), 192.465(c)#
TD.CPMONITORrecordPage 159TD.CPMONITOR.REVCURRENTTEST.RDo records document details of electrical checks interference bonds, diodes, and reverse current switches? References: 192.491(c), 192.465(c)#
TD.CPMONITORobservationPage 159TD.CPMONITOR.REVCURRENTTEST.OAre interference bonds, diodes, and reverse current switches properly maintained and are they functioning properly? References: 192.465(c)#
TD.CPMONITORprocedurePage 159TD.CPMONITOR.DEFICIENCY.PDoes the process require that the operator promptly correct any identified deficiencies in corrosion control? References: 192.605(b)(2), 192.465(d)#
TD.CPMONITORrecordPage 159TD.CPMONITOR.DEFICIENCY.RDo records adequately document actions taken to correct any identified deficiencies in corrosion control? References: 192.491(c), 192.465(d)#
TD.CPMONITORprocedurePage 159TD.CPMONITOR.TESTSTATION.PDoes the process contain provisions to assure that each pipeline has sufficient test stations or other contact points to determine the adequacy of cathodic protection? References: 192.469#
TD.CPMONITORrecordPage 159TD.CPMONITOR.TESTSTATION.RDo records identify the location of test stations and show a sufficient number of test stations? References: 192.469#
TD.CPMONITORobservationPage 159TD.CPMONITOR.TESTSTATION.ODo cathodically protected pipelines have a sufficient number of test stations? References: 192.469#
TD.CPMONITORprocedurePage 160TD.CPMONITOR.TESTLEAD.PDoes the process provide adequate instructions for the installation of test leads? References: 192.605(b)(2), 192.471(a), 192.471(b), 192.471(c)#
TD.CPMONITORrecordPage 160TD.CPMONITOR.TESTLEAD.RDo records document that pipelines with cathodic protection have electrical test leads installed in accordance with requirements of Subpart I? References: 192.491(c), 192.471(a), 192.471(b), 192.471(c)#
TD.CPMONITORobservationPage 160TD.CPMONITOR.TESTLEAD.ODo pipelines with cathodic protection have electrical test leads installed in accordance with requirements of Subpart I? References: 192.471(a), 192.471(b), 192.471(c)#
TD.CPMONITORprocedurePage 160TD.CPMONITOR.INTFRCURRENT.PDoes the operator have a program in place to minimize detrimental effects of interference currents on its pipeline system and does the process for designing and installing cathodic protection systems provide for the minimization of detrimental effects of interference currents on existing adjacent metallic structures? References: 192.605(b)(2), 192.473(a)#
TD.CPMONITORrecordPage 160TD.CPMONITOR.INTFRCURRENT.RDo records document an effective program is in place to minimize detrimental effects of interference currents and that detrimental effects of interference currents from CP systems on other underground metallic structures are minimized? References: 192.491(c), 192.473(a)#
TD.CPMONITORobservationPage 160TD.CPMONITOR.INTFRCURRENT.OAre areas of potential stray current identified, and if found, the detrimental effects of stray currents minimized? References: 192.473(a)#
TD.CPprocedurePage 160TD.CP.RECORDS.PDoes the process include records requirements for the corrosion control activities listed in §192.491? References: 192.605(b)(2), 192.491(a), 192.491(b), 192.491(c)#
TD.CPrecordPage 160TD.CP.RECORDS.RDo records indicate the location of all corrosion control items listed in §192.491(a)? References: 192.491(a), 192.491(b), 192.491(c)#
TD.CPprocedurePage 161TD.CP.POST1971.PDoes the process require that each buried or submerged pipeline installed after July 31, 1971, be protected against external corrosion with a cathodic protection system within 1 year after completion of construction, conversion to service, or becoming jurisdictional onshore gathering? References: 192.605(b)(2), 192.455(a), 192.452(a), 192.452(b), 192.455(f), 192.455(g)#
TD.CPrecordPage 161TD.CP.POST1971.RDo records document that each buried or submerged pipeline installed after July 31, 1971, has been protected against external corrosion with a cathodic protection system within 1 year after completion of construction, conversion to service, or becoming jurisdictional onshore gathering? References: 192.491(c), 192.455(a), 192.457(a), 192.452(a), 192.452(b), 192.455(f), 192.455(g)#
TD.CPprocedurePage 161TD.CP.PRE1971.PDoes the process require that pipelines installed before August 1, 1971 (except for cast and ductile iron lines) which are 1) bare or ineffectively coated transmission lines or 2) bare or coated pipes in compressor, regulator or meter stations must be cathodically protected in areas where active corrosion is found? References: 192.605(b)(2), 192.457(b)#
TD.CPrecordPage 161TD.CP.PRE1971.RDo records document that pipelines installed before August 1, 1971 (except for cast and ductile iron lines) which are 1) bare or ineffectively coated transmission lines, or 2) bare or coated pipes in compressor, regulator or meter stations have been cathodically protected in areas where active corrosion was found? References: 192.491(c), 192.457(b)#
TD.CPobservationPage 161TD.CP.PRE1971.OAre bare or coated pipes in compressor, regulator or meter stations installed before August 1, 1971 (except for cast and ductile iron lines) cathodically protected in areas where active corrosion was found in accordance with Subpart I of Part 192? References: 192.457(b)#
TD.CPprocedurePage 161TD.CP.ALUMINUM.PDoes the process give adequate guidance for the installation of aluminum in a submerged or buried pipeline? References: 192.605(b)(2), 192.455(e)#
TD.CPrecordPage 161TD.CP.ALUMINUM.RDo records support the installation of aluminum when it was installed in a submerged or buried pipeline? References: 192.491(c), 192.455(e)#
TD.CPprocedurePage 161TD.CP.AMPHOTERIC.PDoes the process describe criteria to be used for cathodic protection of amphoteric metals (aluminum) that are included in a steel pipeline? References: 192.605(b)(2), 192.463(b), 192.463(c)#
TD.CPrecordPage 162TD.CP.AMPHOTERIC.RDo records document adequate cathodic protection of amphoteric metals (aluminum) that are included in a steel pipeline? References: 192.491(c), 192.463(b)#
TD.CPprocedurePage 162TD.CP.UNPROTECT.PDoes the process give sufficient direction for the monitoring of external corrosion on buried pipelines that are not protected by cathodic protection? References: 192.605(b)(2), 192.465(e)#
TD.CPrecordPage 162TD.CP.UNPROTECT.RDo records adequately document the re- evaluation of non-cathodically protected buried pipelines for areas of active corrosion? References: 192.491(c), 192.465(e)#
TD.CPprocedurePage 162TD.CP.ELECISOLATE.PDoes the process give adequate guidance for electrically isolating each buried or submerged pipeline from other metallic structures unless they electrically interconnect and cathodically protect the pipeline and the other structures as a single unit? References: 192.605(b)(2), 192.467(a), 192.467(b), 192.467(c), 192.467(d), 192.467(e)#
TD.CPrecordPage 162TD.CP.ELECISOLATE.RDo records adequately document electrical isolation of each buried or submerged pipeline from other metallic structures unless they electrically interconnect and cathodically protect the pipeline and the other structures as a single unit? References: 192.491(c), 192.467(a), 192.467(b), 192.467(c), 192.467(d), 192.467(e)#
TD.CPobservationPage 162TD.CP.ELECISOLATE.OAre measures performed to ensure electrical isolation of each buried or submerged pipeline from other metallic structures unless they electrically interconnect and cathodically protect the pipeline and the other structures as a single unit? References: 192.467(a), 192.467(b), 192.467(c), 192.467(d), 192.467(e)#
TD.CPprocedurePage 162TD.CP.ELECISOLATETEST.PDoes the process provide adequate guidance to inspect and electrically test to ensure that electrical isolation is adequate? References: 192.605(b)(2), 192.467(d)#
TD.CPrecordPage 162TD.CP.ELECISOLATETEST.RDo records adequately document the inspection and electrical testing performed to ensure that electrical isolation is adequate? References: 192.491(c), 192.467(d)#
TD.CPobservationPage 162TD.CP.ELECISOLATETEST.ODo field observations verify that inspection and electrical testing ensured that electrical isolation is adequate? References: 192.467(d)#
TD.CPprocedurePage 163TD.CP.FAULTCURRENT.PDoes the process provide sufficient guidance for determining when protection against damage from fault currents or lightning is needed and how that protection must be installed? References: 192.605(b)(2), 192.467(f)#
TD.CPrecordPage 163TD.CP.FAULTCURRENT.RDo records adequately document the installation and inspection of fault current and lightning protection? References: 192.491(c), 192.467(f)#
TD.CPobservationPage 163TD.CP.FAULTCURRENT.OAre fault current and lightning protection for the pipeline installed and inspected? References: 192.467(f)#
TD.CPprocedurePage 163TD.CP.GRAPHITIZE.PDoes the process give adequate guidance for remediation of graphitization of cast iron or ductile iron pipe? References: 192.605(b)(2), 192.489(a), 192.489(b)#
TD.CPrecordPage 163TD.CP.GRAPHITIZE.RDo records document remediation of graphitization of cast iron or ductile iron pipe? References: 192.491(c), 192.489(a), 192.489(b)#
TD.CPprocedurePage 163TD.CP.RECORDS.PDoes the process include records requirements for the corrosion control activities listed in §192.491? References: 192.605(b)(2), 192.491(a), 192.491(b), 192.491(c)#
TD.CPrecordPage 163TD.CP.RECORDS.RDo records indicate the location of all corrosion control items listed in §192.491(a)? References: 192.491(a), 192.491(b), 192.491(c)#
TD.COATprocedurePage 163TD.COAT.NEWPIPE.PDoes the process require that each buried or submerged pipeline installed after July 31, 1971 be externally coated with a material that is adequate for underground service on a cathodically protected pipeline? References: 192.605(b)(2), 192.455(a)(1), 192.461(a), 192.461(b), 192.483(a)#
TD.COATrecordPage 164TD.COAT.NEWPIPE.RDo records document that each buried or submerged pipeline installed after July 31, 1971 has been externally coated with a suitable coating material? References: 192.491(c), 192.455(a)(1), 192.461(a), 192.461(b), 192.483(a)#
TD.COATrecordPage 164TD.COAT.NEWPIPENOCOAT.RIf a buried or submerged pipeline installed after July 31, 1971 was not installed with an external protective coating do records provide adequate documentation why such a coating was not necessary to protect the pipe from external corrosion? References: 192.491(c), 192.455(b)#
TD.COATprocedurePage 164TD.COAT.NEWPIPEINSTALL.PDoes the process give adequate guidance for the application and inspection of protective coatings on pipe? References: 192.605(b)(2), 192.461(c), 192.461(d), 192.461(e), 192.483(a)#
TD.COATrecordPage 164TD.COAT.NEWPIPEINSTALL.RDo records document that acceptable external protective coating materials have been used and the application and inspection was done in accordance with the written procedures? References: 192.491(c), 192.461(c), 192.461(d), 192.461(e), 192.483(a)#
TD.COATobservationPage 164TD.COAT.NEWPIPEINSTALL.ODo field observations confirm pipe protective coating is adequately and properly applied? References: 192.461(a), 192.461(c), 192.461(d), 192.461(e), 192.319(b), 192.483(a)#
TD.COATprocedurePage 164TD.COAT.CONVERTPIPE.PDoes the process require that each buried or submerged pipeline that has been converted to gas service and was installed after July 31, 1971, be protected against external corrosion with an adequate coating unless exempted by §192.455(b)? References: 192.605(b)(2), 192.452(a), 192.455(a), 192.455(b), 192.455(c), 192.455(d), 192.461(a)#
TD.CPEXPOSEDprocedurePage 164TD.CPEXPOSED.EXPOSEINSPECT.PDoes the process require that exposed portions of buried pipeline be examined for external corrosion and coating deterioration, and if external corrosion is found, further examination is required to determine the extent of the corrosion? References: 192.605(b)(2), 192.459#
TD.CPEXPOSEDrecordPage 164TD.CPEXPOSED.EXPOSEINSPECT.RDo records adequately document that exposed buried piping was examined for corrosion and deteriorated coating? References: 192.491(c), 192.459#
TD.CPEXPOSEDobservationPage 165TD.CPEXPOSED.EXPOSEINSPECT.OIs exposed buried piping examined for corrosion and deteriorated coating? References: 192.459#
TD.CPEXPOSEDprocedurePage 165TD.CPEXPOSED.EXTCORRODEEVAL.PDoes the process provide sufficient direction for personnel to evaluate the remaining strength of externally corroded pipe? References: 192.605(b)(2), 192.485(a), 192.485(b), 192.485(c)#
TD.CPEXPOSEDrecordPage 165TD.CPEXPOSED.EXTCORRODEEVAL.RDo records adequately document the evaluation of externally corroded pipe? References: 192.491(c), 192.485(a), 192.485(b), 192.485(c)#
TD.CPEXPOSEDobservationPage 165TD.CPEXPOSED.EXTCORRODEEVAL.ODo field observations confirm externally corroded pipe was properly evaluated? References: 192.485(a), 192.485(b), 192.485(c)#
TD.CPEXPOSEDprocedurePage 165TD.CPEXPOSED.EXTCORRODREPAIR.PDoes the process give sufficient guidance for personnel to repair or replace pipe that is externally corroded to an extent that there is not sufficient remaining strength in the pipe wall? References: 192.605(b)(2), 192.485(a), 192.485(b), 192.485(c)#
TD.CPEXPOSEDrecordPage 165TD.CPEXPOSED.EXTCORRODREPAIR.RDo records document the repair or replacement of pipe that has been externally corroded to an extent that there is not sufficient remaining pipe wall strength? References: 192.491(c), 192.485(a), 192.485(b), 192.485(c)#
TD.CPEXPOSEDobservationPage 165TD.CPEXPOSED.EXTCORRODREPAIR.ODo field observations confirm the repair or replacement of pipe that has been externally corroded to an extent that there is not sufficient remaining pipe wall strength? References: 192.485(a), 192.485(b), 192.485(c)#
TD.CPprocedurePage 165TD.CP.RECORDS.PDoes the process include records requirements for the corrosion control activities listed in §192.491? References: 192.605(b)(2), 192.491(a), 192.491(b), 192.491(c)#
TD.CPrecordPage 165TD.CP.RECORDS.RDo records indicate the location of all corrosion control items listed in §192.491(a)? References: 192.491(a), 192.491(b), 192.491(c)#
TD.ICCGprocedurePage 166TD.ICCG.CORRGAS.PDoes the process require that the corrosive effect of the gas in the pipeline be investigated and if determined to be corrosive, steps be taken to minimize internal corrosion? References: 192.605(b)(2), 192.475(a)#
TD.ICCGrecordPage 166TD.ICCG.CORRGAS.RDo the records demonstrate that the corrosive effect of the gas in the pipeline has been investigated and if determined to be corrosive, steps be taken to minimize internal corrosion? References: 192.491(c), 192.475(a)#
TD.ICCGprocedurePage 166TD.ICCG.CORRGASACTION.PDoes the process give adequate direction for actions to be taken if corrosive gas is being transported by pipeline? References: 192.605(b)(2), 192.477#
TD.ICCGrecordPage 166TD.ICCG.CORRGASACTION.RDo records document the actions taken when corrosive gas is being transported by pipeline? References: 192.491(c), 192.477#
TD.ICCGobservationPage 166TD.ICCG.CORRGASACTION.OAre adequate actions taken when corrosive gas is being transported by pipeline? References: 192.477#
TD.ICPprocedurePage 166TD.ICP.EXAMINE.PDoes the process direct personnel to examine removed pipe for evidence of internal corrosion? References: 192.605(b)(2), 192.475(a), 192.475(b)#
TD.ICPrecordPage 166TD.ICP.EXAMINE.RDo records document examination of removed pipe for evidence of internal corrosion? References: 192.491(c), 192.475(a), 192.475(b)#
TD.ICPobservationPage 167TD.ICP.EXAMINE.OIs removed pipe examined for evidence of internal corrosion? References: 192.475(a), 192.475(b)#
TD.ICPobservationPage 167TD.ICP.CORRGASPRVNT.OIf the transportation of corrosive gas is not allowed, is the transportation of corrosive gas prevented? References: 192.475(a)#
TD.ICPprocedurePage 167TD.ICP.EVALUATE.PDoes the process give sufficient guidance for personnel to evaluate the remaining strength of pipe that has been internally corroded? References: 192.605(b)(2), 192.485(c)#
TD.ICPrecordPage 167TD.ICP.EVALUATE.RDo records document adequate evaluation of internally corroded pipe? References: 192.491(c), 192.485(c)#
TD.ICPprocedurePage 167TD.ICP.REPAIRINT.PDoes the process give sufficient guidance for personnel to repair or replace pipe that has internally corroded to an extent that there is no longer sufficient remaining strength in the pipe wall? References: 192.491(c), 192.485(a), 192.485(b)#
TD.ICPrecordPage 167TD.ICP.REPAIRINT.RDo records document the repair or replacement of pipe that has been internally corroded to an extent that there is not sufficient remaining strength in the pipe wall? References: 192.485(a), 192.485(b)#
TD.ICPobservationPage 167TD.ICP.REPAIRINT.ODo field observations confirm repair or replacement of pipe that has been internally corroded to an extent that there is not sufficient remaining strength in the pipe wall? References: 192.485(a), 192.485(b)#
TD.ICPprocedurePage 167TD.ICP.PIPEBOTTLE.PDoes the process preclude storing gas containing more than 0.25 grain of hydrogen sulfide per 100 standard cubic feet (5.8 milligrams/m3) at standard conditions (4 parts per million) in pipe-type or bottle-type holders? References: 192.605(b)(2), 192.475(c)#
TD.ICPrecordPage 167TD.ICP.PIPEBOTTLE.RDo records indicate gas containing more than 0.25 grain of hydrogen sulfide per 100 standard cubic feet (5.8 milligrams/m3) at standard conditions (4 parts per million) is being stored in pipe-type or bottle- type holders? References: 192.475(c)#
TD.ICPobservationPage 168TD.ICP.PIPEBOTTLE.ODo field observations indicate gas containing more than 0.25 grain of hydrogen sulfide per 100 standard cubic feet (5.8 milligrams/m3) at standard conditions (4 parts per million) is being stored in pipe-type or bottle-type holders? References: 192.475(c)#
TD.SPprocedurePage 168TD.SP.CONDITIONS.PHas a process been developed as necessary for complying with the special permit conditions? References: 190.341(d)(2)#
TD.SPrecordPage 168TD.SP.CONDITIONS.RDo records demonstrate compliance with all special permit or waiver requirements? References: 190.341(d)(2)#
TD.SPobservationPage 168TD.SP.CONDITIONS.OAre special permit requirements being complied with? References: 190.341(d)(2)#
TD.SCCprocedurePage 168TD.SCC.SCCIM.PDoes the integrity management program have a process to identify and evaluate stress corrosion cracking threats to each covered pipeline segment? References: 192.911(c), 192.917(a)(1), 192.917(e)#
TD.SCCrecordPage 168TD.SCC.SCCIM.RDo integrity management program records document results of studies to identify and evaluate stress corrosion cracking threats to each covered pipeline segment? References: 192.947(d), 192.917(a)(1), 192.917(e)#
TD.SCCrecordPage 168TD.SCC.SCCREPAIR.RDo records document that the operator has properly remediated any occurrences of SCC? References: 192.709(a), 192.703(b)#
TQ.PROT9observationPage 169TQ.PROT9.CORRECTION.OHave potential issues identified by the OQ plan inspection process been corrected at the operational level? References: 192.801(a), 192.809(a)#
TQ.PROT9observationPage 169TQ.PROT9.TASKPERFORMANCE.OCovered Task Performance Verify the qualified individuals performed the observed covered tasks in accordance with the operator's processes or operator approved contractor processes. References: 192.801(a), 192.809(a)#
TQ.PROT9observationPage 169TQ.PROT9.QUALIFICATIONSTATUS.OQualification Status Verify the individuals performing the observed covered tasks are currently qualified to perform the covered tasks. References: 192.801(a), 192.809(a)#
TQ.PROT9observationPage 169TQ.PROT9.AOCRECOG.OAbnormal Operating Condition Recognition and Reaction Verify the individuals performing covered tasks are cognizant of the AOCs that are applicable to the tasks observed. References: 192.801(a), 192.809(a)#
TQ.PROT9observationPage 169TQ.PROT9.VERIFYQUAL.OVerification of Qualification Observe in the field (job site, local office, etc.) that the foreman/supervisor/manager has verified the qualification of the individual performing the task, that the qualification records are current, and ensure the personal identification of all individuals performing covered tasks are checked, prior to task performance. References: 192.801(a), 192.809(a)#
TQ.OQprocedurePage 169TQ.OQ.OQPLAN.PIs there an OQ plan that includes covered tasks, and the basis used for identifying covered tasks? References: 192.805(a), 192.801(b)#
TQ.OQprocedurePage 169TQ.OQ.REEVALINTERVAL.PDoes the OQ plan establish and justify requirements for reevaluation intervals for each covered task? References: 192.805(g)#
TQ.OQprocedurePage 169TQ.OQ.NONQUALIFIED.PDoes the OQ plan contain provisions for non-qualified individuals to perform covered tasks while being directed and observed by a qualified individual, and are appropriate restrictions and limitations placed on such activities? References: 192.805(c)#
TQ.OQprocedurePage 170TQ.OQ.EVALMETHOD.PAre evaluation methods established and documented appropriate to each covered task? References: 192.805(b), 192.803, 192.809(d), 192.809(e)#
TQ.OQrecordPage 170TQ.OQ.OQCONTRACTOR.RAre adequate records containing the required elements maintained for contractor personnel? References: 192.807(a), 192.807(b)#
TQ.OQrecordPage 170TQ.OQ.RECORDS.RDo records document the evaluation and qualifications of individuals performing covered tasks, and can the qualification of individuals performing covered tasks be verified? References: 192.807#
TQ.OQprocedurePage 170TQ.OQ.TRAINING.PDoes the OQ program provide for initial qualification, retraining and reevaluation of individuals performing covered tasks? References: 192.805(h)#
TQ.OQrecordPage 170TQ.OQ.TRAINING.RDoes the operator have records for initial qualification, re-training and re-evaluation of individuals performing covered tasks? References: 192.807(a), 192.807(b)#
TQ.OQprocedurePage 170TQ.OQ.OQPLANCONTRACTOR.PDoes the OQ plan have a process to communicate the OQ plan requirements to contractors and ensure that contractors are following it? References: 192.805(b), 192.805(f), 192.805(c)#
TQ.OQprocedurePage 170TQ.OQ.OQCONTRACTOR.PDoes the OQ plan require other entities that perform covered tasks on behalf of the operator to be qualified? References: 192.805(b), 192.805(c), 192.805(d), 192.805(e), 192.805(f)#
TQ.OQprocedurePage 170TQ.OQ.OQCONTRACTOREQUIV.PDoes the OQ plan document that the operator has assured that the processes on which an OQ vendor has evaluated qualified personnel are the same or consistent with those used by the operator for employees and contractors in the field? References: 192.805(h)#
TQ.OQrecordPage 170TQ.OQ.OTHERENTITY.RIf the operator employs other entities to perform covered tasks, such as mutual assistance, are adequate records containing the required elements maintained? References: 192.805(b), 192.805(c), 192.803#
TQ.OQprocedurePage 171TQ.OQ.ABNORMAL.PDoes the OQ Plan contain requirements to assure that individuals performing covered tasks are able to recognize and react to abnormal operating conditions (AOCs)? References: 192.803#
TQ.OQrecordPage 171TQ.OQ.ABNORMAL.RDo records document evaluation of qualified individuals for recognition and reaction to AOCs? References: 192.807(a), 192.807(b), 192.803#
TQ.OQobservationPage 171TQ.OQ.ABNORMAL.ODo individuals performing covered tasks have adequate knowledge to recognize and react to abnormal operating conditions? References: 192.803#
TQ.OQprocedurePage 171TQ.OQ.PERFMONITOR.PDoes the program include provisions to evaluate an individual if there is reason to believe that performance of a covered task contributed to an incident or accident as defined in Parts 192 and 195 or there is reason to believe an individual is no longer qualified to perform a covered task? References: 192.805(d), 192.805(e)#
TQ.OQrecordPage 171TQ.OQ.PERFMONITOR.RIf the operator had an incident/accident where there is reason to believe that an individual contributed to the cause, do records indicate evaluation of the individual following the occurrence? References: 192.805(d), 192.805(e)#
TQ.OQobservationPage 171TQ.OQ.OQPLAN.ODo individuals performing covered tasks demonstrate adequate skills, knowledge, and ability? References: 192.805(h)#
TQ.OQprocedurePage 171TQ.OQ.MOC.PDoes the OQ program identify how changes to processes, tools standards and other elements used by individuals in performing covered tasks are communicated to the individuals, including contractor individuals, and how these changes are implemented in the evaluation method(s)? References: 192.805(f)#
TQ.OQprocedurePage 171TQ.OQ.CHANGENOTIFY.PDoes the process require significant OQ program changes to be identified and the Administrator or State agency notified? References: 192.805(i), 192.18#
TQ.OQrecordPage 171TQ.OQ.CHANGERECORD.RAre records maintained for changes that affect covered tasks and significant OQ plan changes? References: 192.805(i), 192.805(f), 192.18#
TQ.QUprocedurePage 172TQ.QU.CORROSION.PDoes the process require corrosion control processes to be carried out by, or under the direction of, qualified personnel? References: 192.453, 192.805(b)#
TQ.QUrecordPage 172TQ.QU.CORROSION.RDo records indicate qualification of personnel implementing pipeline corrosion control methods? References: 192.453, 192.807(a), 192.807(b)#
TQ.QUprocedurePage 172TQ.QU.HOTTAPQUAL.PDoes the process require taps on a pipeline under pressure (hot taps) to be performed by qualified personnel? References: 192.627, 192.805(b)#
TQ.QUrecordPage 172TQ.QU.HOTTAPQUAL.RDo records indicate the qualification of personnel performing hot taps? References: 192.627, 192.807(a), 192.807(b)#
TQ.QUobservationPage 172TQ.QU.HOTTAPQUAL.ODo personnel performing hot taps demonstrate adequate skills and knowledge? References: 192.627, 192.805(h)#
TQ.QUprocedurePage 172TQ.QU.EXCAVATE.PDoes the process require individuals who oversee and perform marking, trenching, and backfilling operations be qualified? References: 192.805(b), 192.801, 192.328#
TQ.QUrecordPage 172TQ.QU.EXCAVATE.RDo records indicate qualification of individuals who oversee marking, trenching, and backfilling operations? References: 192.807(a), 192.807(b), 192.801, 192.328#
TQ.QUobservationPage 172TQ.QU.EXCAVATE.ODo individuals who oversee marking, trenching, and backfilling operations demonstrate adequate skills and knowledge? References: 192.805(b), 192.805(h), 192.801(a), 192.328(a), 192.328(c)#
TQ.QUIMprocedurePage 173TQ.QUIM.IMREVIEWQUAL.PDoes the process require that operator/vendor personnel (including supervisors and persons responsible for preventive and mitigative measures), who review and evaluate results meet acceptable qualification standards? References: 192.915(a), 192.915(b), 192.915(c), 192.935(b), 192.493#
TQ.QUIMrecordPage 173TQ.QUIM.IMREVIEWQUAL.RDo records indicate adequate qualification of integrity management personnel? References: 192.947(e), 192.915(a), 192.915(b), 192.915(c), 192.935(b)(1)(i), 192.947(d), 192.493#
TQ.QUIMprocedurePage 173TQ.QUIM.IMQC.PDoes the process require personnel who execute IM program activities to be competent and qualified in accordance with the quality control plan in accordance with ASME B31.8S- 2004, Section 12.2(b)(4)? References: 192.805(b), 192.935(b)(1)(i), 192.907(b), 192.911(l)#
TQ.QUOMCONSTprocedurePage 173TQ.QUOMCONST.INSPECTOR.PDoes the process require welding inspection personnel to be adequately trained and qualified? References: 192.241(a), 192.241(c), 192.805(b), 192.328(a), 192.328(b)#
TQ.QUOMCONSTrecordPage 173TQ.QUOMCONST.INSPECTOR.RDo records indicate adequate qualification documentation for personnel who conduct welding inspections? References: 192.241(a), 192.241(c), 192.807(a), 192.807(b)#
TQ.QUOMCONSTobservationPage 173TQ.QUOMCONST.INSPECTOR.ODoes the welding inspector demonstrate adequate skills and knowledge? References: 192.241(a), 192.241(c)#
TQ.QUOMCONSTrecordPage 173TQ.QUOMCONST.NDT.RDo records indicate the qualification of nondestructive testing personnel? References: 192.243(b)(2), 192.807(a), 192.807(b), 192.328(a), 192.328(b)#
TQ.QUOMCONSTrecordPage 174TQ.QUOMCONST.WELDER.RDo records indicate that welders are adequately qualified? References: 192.227(a), 192.227(b), 192.229(a), 192.229(b), 192.229(c), 192.229(d), 192.328(a), 192.328(b), 192.807(a), 192.807(b)#
TQ.QUOMCONSTprocedurePage 174TQ.QUOMCONST.WELDER.PDoes the process require welders to be qualified in accordance with API 1104 or the ASME Boiler & Pressure Vessel Code? References: 192.227(a), 192.225(a), 192.225(b), 192.328(a), 192.328(b), 192.805(b)#
TQ.QUOMCONSTprocedurePage 174TQ.QUOMCONST.WELDERLOWSTRESS.PDoes the process require welders who perform welding on low stress pipe on lines that operate at < 20% SMYS to be qualified under Section I of Appendix C to Part 192, and are welders who perform welding on service line connection to a main required to be qualified under Section II of Appendix C to Part 192? References: 192.227(b), 192.225(a), 192.225(b), 192.805(b)#
TQ.QUOMCONSTobservationPage 174TQ.QUOMCONST.WELDER.ODo welders demonstrate adequate skills and knowledge? References: 192.227(a), 192.227(b), 192.229(a), 192.229(b), 192.229(c), 192.229(d), 192.803, 192.328(a), 192.328(b)#
TQ.QUOMCONSTprocedurePage 174TQ.QUOMCONST.NDT.PDoes the process require nondestructive testing of welds to be performed by personnel who are trained and qualified in the established procedures and with the testing equipment employed? References: 192.243(b)(2), 192.803, 192.805(b), 192.805(h), 192.328(a), 192.328(b)#
TQ.QUOMCONSTobservationPage 174TQ.QUOMCONST.NDT.ODo nondestructive testing personnel demonstrate adequate skills and knowledge? References: 192.243(b)(2), 192.803, 192.328(a), 192.328(b)#
TQ.QUOMCONSTprocedurePage 174TQ.QUOMCONST.PLASTIC.PDoes the process require personnel making joints in plastic pipelines be qualified? References: 192.285(a), 192.285(d), 192.805(b), 192.285(c)#
TQ.QUOMCONSTprocedurePage 174TQ.QUOMCONST.PLASTICINSPECT.PDoes the process require that persons who inspect joints in plastic pipes be qualified? References: 192.287, 192.805(b)#
TQ.QUOMCONSTrecordPage 174TQ.QUOMCONST.PLASTIC.RDo records indicate adequate qualification of personnel making/inspecting joints in plastic pipelines? References: 192.285(a), 192.285(d), 192.287, 192.807(a), 192.807(b), 192.285(c)#
TQ.QUOMCONSTobservationPage 175TQ.QUOMCONST.PLASTIC.ODo personnel making/inspecting joints in plastic pipelines demonstrate adequate skills and knowledge? References: 192.285(a), 192.287, 192.803#
TQ.TRprocedurePage 175TQ.TR.TRAINING.PDoes the process require a continuing training program to be in place to effectively instruct emergency response personnel? References: 192.615(b)(2), 192.805(b)#
TQ.TRrecordPage 175TQ.TR.TRAINING.RIs training for emergency response personnel documented? References: 192.615(b)(2), 192.807(a), 192.807(b)#
TQ.TRobservationPage 175TQ.TR.TRAINING.ODo emergency response personnel demonstrate adequate skills and knowledge? References: 192.615(b)(2), 192.805(b)#
TQ.TRprocedurePage 175TQ.TR.TRAININGREVIEW.PDoes the process require review of emergency response personnel performance? References: 192.615(b)(3)#
UNGS.RULEprocedurePage 175UNGS.RULE.RISKPRIORITIES.PAre risk assessments for each storage facility and related wells prioritized based on the results of the safety risk analyses? References: 192.12(d)(2), 192.12(b)(2), 192.12(b)(1), 192.12(a)(3), 192.12(a)(2), 192.12(a)(1)#
UNGS.RULEprocedurePage 175UNGS.RULE.RISKRANKING.PDoes the process require that safety concerns are identified and addressed based on the ranking of the safety risk analyses? References: 192.12(d)(2), 192.12(b)(2), 192.12(b)(1), 192.12(a)(3), 192.12(a)(2), 192.12(a)(1)#
UNGS.RULEprocedurePage 175UNGS.RULE.FAQ27DRUGTEST.PDoes the operator have a DOT D&A program intended to comply with 49CFR Part 199? References: 199.1#
UNGS.RULErecordPage 176UNGS.RULE.FAQ27DRUGTEST.RDo records indicate the operator has a DOT D&A program? References: 199.1#
UNGS.RPTprocedurePage 176UNGS.RPT.INCIDENTDEFN.PHow does the operator define an incident? References: 191.15(c), 191.3#
UNGS.RPTprocedurePage 176UNGS.RPT.IMMEDREPORT.PIs there a process to immediately report incidents to the National Response Center? References: 191.5(a), 191.5(b), 191.3#
UNGS.RPTrecordPage 176UNGS.RPT.IMMEDREPORT.RDo records indicate immediate notifications of incidents were made in accordance with 191.5? References: 191.5(a), 191.5(b), 191.3#
UNGS.RPTprocedurePage 176UNGS.RPT.INCIDENTREPORT.PWhat are the procedures in place for reporting a storage facility incident soon as practicable but no later than 30 days after discovery of a reportable incident? References: 191.15(c), 191.3#
UNGS.RPTrecordPage 176UNGS.RPT.INCIDENTREPORT.RDo records indicate reportable incidents were identified and reports were submitted to DOT on Form 7100.2 within the required time frame? References: 191.15(c), 191.3#
UNGS.RPTprocedurePage 176UNGS.RPT.INCIDENTREPORTSUPP.PWhat are the procedures in place for preparing and filing supplemental incident reports? References: 191.15(d), 191.15(c)#
UNGS.RPTrecordPage 176UNGS.RPT.INCIDENTREPORTSUPP.RDo records indicate accurate supplemental incident reports were filed and within the required time frame? References: 191.15(d), 191.15(c)#
UNGS.RPTprocedurePage 176UNGS.RPT.SRCR.PAre procedures in place to report a safety-related condition as required by 191.23? References: 191.23(a), 191.23(b), 191.25(a), 191.25(b), 191.25(c)#
UNGS.RPTrecordPage 177UNGS.RPT.SRCR.RHave any Safety-Related Condition Reports been submitted to PHMSA/OPS? References: 191.23(a), 191.23(b), 191.25(a), 191.25(b), 191.25(c)#
UNGS.RPTrecordPage 177UNGS.RPT.SRCRBRIDGEPLUG.RHave any wells been isolated using a bridge plug? References: 191.23(a), 191.23(b), 191.25(a)#
UNGS.RPTobservationPage 177UNGS.RPT.SRCRBRIDGEPLUG.ODo field observations confirm Safety- Related Conditions Reporting (SRCR) requirements were met with regards to the use of bridge plugs? References: 191.23(a), 191.25(a), 191.25(c)#
UNGS.RPTrecordPage 177UNGS.RPT.UNIQUEWELLS.RIf applicable, are storage facility wells that are somehow "unique" (i.e., withdrawal only, shallow capture wells or recirculation wells) included in the Annual Report and also included in the Risk Management and Integrity Management programs? References: 191.17(c), 192.12(b), 192.12(a)#
UNGS.RPTobservationPage 177UNGS.RPT.UNIQUEWELLS.OIf applicable, do field observations confirm that “unique” wells were properly included in the Annual Report and are also included in the Risk Management and Integrity Management programs? References: 191.17(c), 192.12(b), 192.12(a)#
UNGS.RPTprocedurePage 177UNGS.RPT.OPID.PDoes the process require the obtaining, and appropriate control, of Operator Identification Numbers (OPIDs) for the storage field? References: 191.22(a), 191.22(b)#
UNGS.RPTprocedurePage 177UNGS.RPT.REGISTRYCHGSNOTIF.PWhat is the process in place to notify PHMSA of any changes that fall under 191.22(c) (i.e., construction, conversions, change in entity, or acquisition or divestiture)? References: 191.22(c)#
UNGS.RPTrecordPage 177UNGS.RPT.REGISTRYCHGSNOTIF.RNational Registry - Notification of Changes Were notifications for changes to the storage facility submitted per §191.22(c) and with accurate information? References: 191.22(c)#
UNGS.RPTprocedurePage 177UNGS.RPT.ANNUALREPORT.PDoes the process require submittal of an annual report (Form 7100.4-1) by March 15 for the preceding calendar year? References: 191.17(c)#
UNGS.RPTrecordPage 178UNGS.RPT.ANNUALREPORT.RAnnual Report Were annual reports submitted according to procedure and with accurate information? References: 191.17(c)#
UNGS.RESDESprocedurePage 178UNGS.RESDES.GEOLOGICEVAL.PIs there a process for preliminary evaluation, characterization, and mapping of the geologic properties of the reservoir that is intended for storing gas? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 178UNGS.RESDES.GEOLOGICEVAL.RDo records demonstrate that the intended reservoir was evaluated, characterized and mapped for properties intended for gas storage? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 178UNGS.RESDES.GEOLOGICBUFFER.PDoes the process use the geologic characterization to establish the initial vertical and areal buffer zone to protect the integrity of the natural gas storage operation? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 178UNGS.RESDES.GEOLOGICBUFFER.RDo records demonstrate that the initial vertical and areal buffer zones were established based on the geological characterization? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 178UNGS.RESDES.ENGRCHCTR1.PDoes the process require, at a minimum, evaluation of the casing materials, casing configuration, casing set depths, cement materials, and placement depths for mechanical integrity of all existing and abandoned wells that penetrate the formations being characterized for storage purposes? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 178UNGS.RESDES.ENGRCHCTR1.RDo records demonstrate that all existing and abandoned wells, that penetrate the characterized formation for storage, have been evaluated for casing materials, casing configuration, casing set depths, cement materials, and placement depths for functional integrity? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 179UNGS.RESDES.ENGRCHCTR2.PDoes the process account for the corrosive potential of the pore fluids if the storage reservoir was used for gas-liquid or oil production? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 179UNGS.RESDES.ENGRCHCTR2.RDo records demonstrate that pore fluids have been evaluated for corrosive potential? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 179UNGS.RESDES.ENGRCHCTR3.PDoes the process incorporate the corrosive potential of pore fluids, if present, into the design and operation strategies of the storage reservoir ? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 179UNGS.RESDES.ENGRCHCTR3.RIf there is a corrosive potential from pore fluids, do records demonstrate that the design and operation accounts for the corrosive potential? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 179UNGS.RESDES.ENGRCHCTR4.PDoes the process require identification and mitigation of potential mineralogical and fluid compatibility issues? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 179UNGS.RESDES.ENGRCHCTR4.RDo records demonstrate that mineralogical and fluid compatibility issues are identified and mitigated? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 179UNGS.RESDES.ENGRCHCTR5.PDoes the characterization process require the identification of initial and current reservoir pressures based on known data ? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 179UNGS.RESDES.ENGRCHCTR5.RDo records demonstrate that the initial and current pressures, for the target reservoir, are identified based on known data? References: 192.12(b)(1)#
UNGS.RESDESobservationPage 179UNGS.RESDES.ENGRCHCTRALL.OAre field observations consistent with the engineering characterization of the reservoir? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 180UNGS.RESDES.CONTASSURANCE.PDoes the process require that data be acquired to manage uncertainties that were identified during the geologic and engineering characterization process? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 180UNGS.RESDES.CONTASSURANCE.RDo records indicate that data was acquired to manage uncertainties identified during the characterization process? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 180UNGS.RESDES.CONTCAPABILITY.PDoes the process assess the containment capability of the reservoir and the wells for the designed storage operation volumes, pressures, and rates? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 180UNGS.RESDES.CONTCAPABILITY.RDo records demonstrate that the containment capability of the reservoir and wells was assessed for the designed storage operation volumes, pressures, and rates? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 180UNGS.RESDES.GASMIGRATION.PDoes the process address gas migration control and containment when porous zones are connected with the target reservoir? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 180UNGS.RESDES.GASMIGRATION.RDo records demonstrate that gas migration control and containment were addressed in the design, if the target reservoir is connected to another porous zone? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 180UNGS.RESDES.MAXRESPRESS.PDoes the process provide a design basis for the maximum pressure of the storage reservoir? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 180UNGS.RESDES.MAXRESPRESS.RDo records demonstrate that the design basis for the maximum reservoir pressure was documented? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 180UNGS.RESDES.MAXPRESSOTHER.PDoes the process provide a design basis for the maximum pressure of the wells, wellheads, piping, or associated storage facilities? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 181UNGS.RESDES.MAXPRESSOTHER.RDo records demonstrate that the pressure limits of the wells, wellheads, piping, and associated storage facilities are not exceeded? References: 192.12(b)(1)#
UNGS.RESDESobservationPage 181UNGS.RESDES.MAXPRESSALL.ODo pressure reading observations reflect that actual pressures are within the established set limits? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 181UNGS.RESDES.WELLCONTASSURANCE.PDoes the process require evaluation of all wells that penetrate the storage zone for containment assurance? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 181UNGS.RESDES.WELLCONTASSURANCE.RDo records demonstrate that all wells that penetrate the storage zone have been evaluated for containment assurance? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 181UNGS.RESDES.AQUIFEREVAL01.PSupplemental Evaluation of Reservoirs Developed within Aquifers For storage reservoirs developed within aquifers, does the process require supplemental reservoir geological and engineering evaluation for the delineation of the storage reservoir? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 181UNGS.RESDES.AQUIFEREVAL01.RDo records demonstrate that supplemental aquifer reservoir geological and engineering evaluations were performed? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 181UNGS.RESDES.AQUIFEREVAL02.PSupplemental Evaluation of Reservoirs Developed within Aquifers For storage reservoirs developed within aquifers, does the process require data gathering and characterization of the reservoir, caprock, basal rock, and lateral seals through drilling, logging and coring? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 181UNGS.RESDES.AQUIFEREVAL02.RDo records demonstrate that aquifer containment assurance data was acquired through drilling, logging, and coring of the aquifer? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 181UNGS.RESDES.AQUIFEREVAL03.PSupplemental Evaluation of Reservoirs Developed within Aquifers For storage reservoirs developed within aquifers, does the process require that site specific geophysical delineation be performed? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 182UNGS.RESDES.AQUIFEREVAL03.RDo records demonstrate that site specific geophysical delineation was conducted for the aquifer storage? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 182UNGS.RESDES.AQUIFEREVAL04.PSupplemental Evaluation of Reservoirs Developed within Aquifers For storage reservoirs developed within aquifers, is there a process requiring that water pump testing and water level observation be performed to characterize the storage reservoir dimensions, gas capacity, flow performance, and caprock integrity? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 182UNGS.RESDES.AQUIFEREVAL04.RDo records demonstrate that a water pump test and water level observation were performed to characterize the storage reservoir within an aquifer? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 182UNGS.RESDES.DESRECORDS.PDoes the process require design records to be maintained for the following activities: geologic records; engineering records; land and mineral ownership, rights, and control; facility integrity plan; well drilling, completion, workover and plugging records; regulatory records and permits? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 182UNGS.RESDES.DESRECORDS.RDo records demonstrate that the required design records have been maintained? References: 192.12(b)(1)#
UNGS.RESDESprocedurePage 182UNGS.RESDES.DESRECORDSLOF.PDoes the process require that accurate and comprehensive records of natural gas storage design activities be maintained for the life of the facility? References: 192.12(b)(1)#
UNGS.RESDESrecordPage 182UNGS.RESDES.DESRECORDSLOF.RAre design records accurate and comprehensive and maintained for the lifetime of the facility? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 183UNGS.RESWELLDES.WELLHEADEQUIP.PDoes the process ensure that new and replaced wellheads allow for full diameter entry to the wellbore? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 183UNGS.RESWELLDES.WELLHEADEQUIP.RDo records demonstrate that new and replaced wellheads allow for full diameter entry to the wellbore? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 183UNGS.RESWELLDES.WELLHEADENTRY.PDoes the process require review of well records to determine if limited wellhead entry is sufficient for planned activities? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 183UNGS.RESWELLDES.WELLHEADENTRY.RDo records indicate operator reviewed the well records to determine if limited (less-than-full-diameter) wellhead entry is sufficient to allow for the planned activities? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 183UNGS.RESWELLDES.WELLHEADISOLVLV.PDoes the process require that wells be equipped with valves that provide isolation of the well from the pipeline system and for entry into the wellbore? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 183UNGS.RESWELLDES.WELLHEADISOLVLV.RDo records demonstrate that wells are equipped with valves that provide isolation from the pipeline and entry into the wellbore? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 183UNGS.RESWELLDES.WELLHEADRATING.PDoes the process ensure that wellhead equipment is pressure rated to exceed the maximum anticipated operating pressure? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 183UNGS.RESWELLDES.WELLHEADRATING.RDo records demonstrate that wellhead equipment is pressure rated to exceed the maximum anticipated operating pressure? References: 192.12(b)(1)#
UNGS.RESWELLDESobservationPage 184UNGS.RESWELLDES.WELLHEADRATING.ODo pressure ratings of wellhead equipment reflect the documented ratings? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 184UNGS.RESWELLDES.WELLHEADESD.PDoes the process require evaluation of the need of an emergency shut down (ESD) valve by reviewing the requirements of API RP 1171 section 6.2.5? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 184UNGS.RESWELLDES.WELLHEADESD.RDo records demonstrate that the need for emergency shutdown valves were reviewed based on the requirements of API RP 1171 Section 6.2.5? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 184UNGS.RESWELLDES.WELLCOMPLETION.PDoes the process require that well designs are completed with two or more strings of casing to protect ground water, control wellbore conditions, isolate the storage gas, and inject storage gas from the pipeline into and withdraw out of the storage reservoir? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 184UNGS.RESWELLDES.WELLCOMPLETION.RDo well records indicate that storage wells are completed with two or more strings of casing to protect ground water, control wellbore conditions, isolate the storage gas, and inject storage gas from the pipeline into and withdraw out of the storage reservoir? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 184UNGS.RESWELLDES.WELLCASINGDES.PDoes the process require the use API 5C3 for casing designs? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 184UNGS.RESWELLDES.WELLCASINGDES.RDo well records indicate that API 5C3 was used for the design of the casings? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 184UNGS.RESWELLDES.SURFCASINGDES.PDoes the design process require that the surface casing be of sufficient size, grade, and depth to support drilling operations and to protect groundwater? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 184UNGS.RESWELLDES.SURFCASINGDES.RDo records indicate that the surface casing is of sufficient size, grade, and depth to support drilling operations and to protect groundwater? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 185UNGS.RESWELLDES.PRODCASINGDES1.PDoes the design process require that the production casing be of adequate size and strength to maintain the well integrity? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 185UNGS.RESWELLDES.PRODCASINGDES1.RDo records indicate that the production casing is of sufficient size, strength, and depth to maintain the well integrity and be compatible with fluid chemical composition? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 185UNGS.RESWELLDES.PRODCASINGDES2.PDoes the design process require that the production casing be compatible with fluid chemical composition? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 185UNGS.RESWELLDES.PRODCASINGDES2.RDo records indicate that the production casing is compatible with fluid chemical composition? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 185UNGS.RESWELLDES.PRODCASINGDES3.PDoes the process require that the production casing be free of open perforations or holes other than the planned completion interval(s)? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 185UNGS.RESWELLDES.PRODCASINGDES3.RDo records indicate that the production casing is free of open perforations or holes other than the planned completion interval(s)? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 185UNGS.RESWELLDES.PRODCASINGDES4.PDoes the process require that perforations created in production casing for investigative or remedial work be sealed to establish hydraulic isolation? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 185UNGS.RESWELLDES.PRODCASINGDES4.RDo records indicate that perforations created in production casing for investigative or remedial work were sealed to establish hydraulic isolation? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 185UNGS.RESWELLDES.CASINGHANDLING.PDoes the process ensure that the casing is stored, transported, lifted, and installed according to manufacturer specifications and API 5C1? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 186UNGS.RESWELLDES.CASINGHANDLING.RDo records demonstrate that the casing was stored, transported, lifted and installed as specified by the manufacturer and API 5C1? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 186UNGS.RESWELLDES.CASINGCONN1.PDoes the process require that casing connections be designed to accommodate loads associated with placement? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 186UNGS.RESWELLDES.CASINGCONN1.RDo records demonstrate that the casing connections can withstand loads associated with placement of the casing? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 186UNGS.RESWELLDES.CASINGCONN2.PDoes the process ensure that the casing connections can maintain a gas seal under anticipated wellbore flow conditions and subsequent work? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 186UNGS.RESWELLDES.CASINGCONN2.RDo records indicate that casing connections have the ability to maintain a gas seal under well flow conditions and subsequent work? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 186UNGS.RESWELLDES.CASINGCONN3.PDoes the process ensure that casing connections are made up according to manufacturer specifications or in accordance with API 5CT? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 186UNGS.RESWELLDES.CASINGCONN3.RDo records demonstrate that the casing connections are made up according to manufacturer specifications or in accordance with API 5CT? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 186UNGS.RESWELLDES.CASINGCONN4.PDoes the process ensure that casing thread compound or lubricant is compatible with the expected wellbore environment? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 186UNGS.RESWELLDES.CASINGCONN4.RDo records demonstrate that the casing thread compound or lubricant is compatible with the expected wellbore environment? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 187UNGS.RESWELLDES.CASINGCONN5.PDoes the process ensure that casing thread compound or lubricant is consistent with the manufacturer’s recommended lubricant or API 5A3? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 187UNGS.RESWELLDES.CASINGCONN5.RDo records demonstrate that the casing thread compound or lubricant is consistent with the manufacturer’s recommended lubricant or API 5A3? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 187UNGS.RESWELLDES.CASINGCEMENT.PDoes the process ensure that the cement slurry or slurry combination is designed for hydrostatic weight control and strength requirements for the storage reservoir? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 187UNGS.RESWELLDES.CASINGCEMENT.RDo records demonstrate that the cement slurry or slurry combination used for the storage reservoir are/were designed for hydrostatic weight control and strength requirements? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 187UNGS.RESWELLDES.CEMENTSLURRY.PDoes the process ensure that the fracture gradient of the storage zone is not exceeded during cement pumping operations? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 187UNGS.RESWELLDES.CEMENTSLURRY.RDo records demonstrate that the storage zone fracture gradient was not exceeded during cement pumping operations? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 187UNGS.RESWELLDES.CEMENTPUMPING.PDoes the process require that competent uncontaminated cement be placed around the casing shoe and around the circumference of the casing? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 187UNGS.RESWELLDES.CEMENTPUMPING.RDo records indicate that competent, uncontaminated cement is placed at casing shoes and around the circumference of the casing? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 187UNGS.RESWELLDES.CEMENTBOND.PIs there a process for evaluating the cement placement and bond quality through cement bond log or other means that can demonstrate the sealing potential of the cement? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 188UNGS.RESWELLDES.CEMENTBOND.RDo records demonstrate that the bond or seal quality and cement placement were evaluated by cement bond log or other means and demonstrated the bond or seal quality and placement of the cement? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 188UNGS.RESWELLDES.COMPLETION.PDoes the process require that well completion and stimulation operations are done to verify that pressure, flow rates, and other mechanical conditions have no adverse impact on the storage reservoir, caprock, or the mechanical integrity of the well? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 188UNGS.RESWELLDES.COMPLETION.RDo records demonstrate that the pressure, flow rates, and other mechanical conditions have been verified to indicate that there is no adverse impact on the storage reservoir, caprock, or the mechanical integrity of the well? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 188UNGS.RESWELLDES.STIMULATION.PDoes the process for fracture treatment, if used, ensure that the fracture height or length does not compromise the integrity of the storage reservoir? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 188UNGS.RESWELLDES.STIMULATION.RDo records demonstrate that the integrity of the storage reservoir has not been compromised by fracture treatment? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 188UNGS.RESWELLDES.REMEDIATION.PWell Remediation For wells identified as having compromised mechanical integrity, does the process require evaluation and responsive action within a timeframe corresponding to the severity of the integrity risk? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 188UNGS.RESWELLDES.REMEDIATION.RWell Remediation For wells identified as having compromised mechanical integrity, do records demonstrate that they were evaluated and remediated within a time frame corresponding to the severity of the integrity risk? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 188UNGS.RESWELLDES.CLOSURE.PDoes the process for abandonment of a well require a design for long-term isolation of the storage zone and any other penetrated zones from the surface? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 188UNGS.RESWELLDES.CLOSURE.RDo the records demonstrate that well abandonment for long term isolation of the storage zone and any other penetrated zone from the surface was achieved? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 189UNGS.RESWELLDES.CLOSUREREC.PDoes the process define a retention period for abandonment records? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 189UNGS.RESWELLDES.CLOSUREREC.RDo records demonstrate that the retention period for abandonment records was followed? References: 192.12(b)(1)#
UNGS.RESWELLDESobservationPage 189UNGS.RESWELLDES.CLOSUREALL.ODo field observations indicate that the operator followed the outlined abandonment process? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 189UNGS.RESWELLDES.PLUGS.PDoes the abandonment process require use of cement plugs and/or mechanical plugs to isolate the storage zone from fluid migration? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 189UNGS.RESWELLDES.PLUGS.RDo records demonstrate which type of abandonment plug was used as defined by API 1171, Section 6.7.2? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 189UNGS.RESWELLDES.ISOLATION.PDoes the process ensure that the location of groundwater and hydrocarbon bearing zones were determined to prevent communication between any of those zones during and after plugging of the wells? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 189UNGS.RESWELLDES.ISOLATION.RDo records indicate the depths of the groundwater and hydrocarbon zones penetrated by the well to be abandoned? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 189UNGS.RESWELLDES.CEMENTEVAL.PDoes the process require that the casing and cement across the water and hydrocarbon zones be properly evaluated before abandoning of the well? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 189UNGS.RESWELLDES.CEMENTEVAL.RDo records demonstrate that casing and cement evaluations were conducted through zones of importance prior to abandoning? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 190UNGS.RESWELLDES.CEMENTPLUGDEPTH.PDoes the process require verification that the abandonment plug is set at the proper depth and has reached sufficient compressive strength? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 190UNGS.RESWELLDES.CEMENTPLUGDEPTH.RDo the records indicate that abandonment plug depths were achieved and verified? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 190UNGS.RESWELLDES.CEMENTPLUGPROP.RDo the records indicate that abandonment plug properties and pressure records of plug testing are maintained? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 190UNGS.RESWELLDES.DEVIATIONS.PDoes the process require that any deviations that threatened the isolation objectives of the abandonment plug are to be corrected? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 190UNGS.RESWELLDES.DEVIATIONS.RDo the records indicate that deviations that threatened the isolation objectives of the abandonment plug were corrected? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 190UNGS.RESWELLDES.PLUGREPAIR.PDoes the process include the repair of failed plugs in an abandoned well? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 190UNGS.RESWELLDES.PLUGREPAIR.RDo records demonstrate that failed abandonment plugs were repaired according to procedure? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 190UNGS.RESWELLDES.WELLREPAIR.PDoes the abandonment process include the repair of a well having any leak indication that may suggest a lack of isolation of the storage reservoir? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 190UNGS.RESWELLDES.WELLREPAIR.RDo records demonstrate that abandoned wells having an indication of leaks were repaired according to procedure? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 191UNGS.RESWELLDES.SURFACEPLUG.PDoes the abandonment process require the installation of a surface plug and cap? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 191UNGS.RESWELLDES.SURFACEPLUG.RDo records indicate that surface plugs and caps were installed in abandoned wells? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 191UNGS.RESWELLDES.CAPIDENTIF.PDoes the process require the abandoned well surface cap to include the API number or another form of identification? References: 192.12(b)(1)#
UNGS.RESWELLDESobservationPage 191UNGS.RESWELLDES.CAPIDENTIF.ODo field observations indicate evidence of an abandoned well surface cap, along with its identification, installed on each abandoned well? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 191UNGS.RESWELLDES.EHSPEOPLEENV.PDoes the design and construction process incorporate safeguards to protect the environment and the safety and health of workers and the public into well design and during well work activities? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 191UNGS.RESWELLDES.EHSPEOPLEENV.RDo records indicate that safeguards to the environment, safety, and health of workers and the public were used in well design and construction, and during well work activities? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 191UNGS.RESWELLDES.EHSWATER.PDoes the design and construction process include protections for surface water and ground water from drilling and well work operations? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 191UNGS.RESWELLDES.EHSWATER.RDo records demonstrate that the surface water and ground water safeguards were used in well design and during drilling and well work operations? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 192UNGS.RESWELLDES.EHSWORKSITE.PDoes the construction process ensure that the worksite is monitored during well drilling, construction, and well work activities to protect the environment and the safety and health of workers and the public? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 192UNGS.RESWELLDES.EHSWORKSITE.RDo records demonstrate that the well site was monitored during drilling, construction and well work activities to protect the environment and the safety and health of workers and the public? References: 192.12(b)(1)#
UNGS.RESWELLDESobservationPage 192UNGS.RESWELLDES.EHSWORKSITE.ODo field observations indicate that safeguards and monitoring methods specific to the safety and health of workers, the public, and the environment are in place as per procedure? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 192UNGS.RESWELLDES.WELLTESTING.PDoes the process require that production casing be tested to demonstrate mechanical integrity and suitability for the designed operating conditions prior to commissioning per API RP 1171, Section 6.9.1? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 192UNGS.RESWELLDES.WELLTESTING.RDo records demonstrate that the production casing was tested to demonstrate mechanical integrity and suitability for designed operating conditions prior to commissioning per API RP 1171 Section 6.9.1? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 192UNGS.RESWELLDES.WELLTESTDES.PDoes the process require test design such that the maximum pressure on the packer seat and the pressure at any point in the wellbore during the test does not compromise the mechanical integrity of the well? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 192UNGS.RESWELLDES.WELLTESTDES.RDo records demonstrate that the test was designed so the maximum pressure does not compromise the mechanical integrity of the wells? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 192UNGS.RESWELLDES.CONSTRMONITOR.PDoes the process require documentation and retention of records of deviations where such deviations from the original design or in the procedures are required to resolve encountered issues or problems during well activities? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 193UNGS.RESWELLDES.CONSTRMONITOR.RDo records demonstrate that deviations from the original well design were documented? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 193UNGS.RESWELLDES.MAINTINTEGRITY.PDoes the process require that well issues or problems are resolved in a manner that maintains the functional integrity of the well and reservoir prior to commissioning? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 193UNGS.RESWELLDES.MAINTINTEGRITY.RDo records demonstrate that functional integrity was maintained during the resolution of issues or problems prior to commissioning? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 193UNGS.RESWELLDES.WELLRECORDS.RAre applicable records available to demonstrate that the items listed in API RP 1171, Section 6.11.1, are being maintained? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 193UNGS.RESWELLDES.WELLRECORDSRET.RAre records for well completion, well construction, and well work activities available to demonstrate that they are being maintained for the life of the facility? References: 192.12(b)(1)#
UNGS.RESWELLDESrecordPage 193UNGS.RESWELLDES.GENRECORDS.RDo records include, as applicable and available, the items listed in API RP 1171, Section 6.11.2? References: 192.12(b)(1)#
UNGS.RESWELLDESprocedurePage 193UNGS.RESWELLDES.GENRECORDSRET.PDoes the process define a retention period for records relating to permitting, procedures, personnel, and equipment? References: 192.12(b)(1)#
UNGS.RESINITIALprocedurePage 193UNGS.RESINITIAL.MATBALANCE1.PDoes the process require monitoring of the material balance behavior relative to the original design and expected reservoir behavior? References: 192.12(b)(1)#
UNGS.RESINITIALrecordPage 194UNGS.RESINITIAL.MATBALANCE1.RDo records demonstrate that the monitored material balance behavior of the storage reservoir is consistent with the expected reservoir behavior? References: 192.12(b)(1)#
UNGS.RESINITIALprocedurePage 194UNGS.RESINITIAL.MATBALANCE2.PDoes the process require evaluation and correcting of any unexpected condition detected during material balance monitoring? References: 192.12(b)(1)#
UNGS.RESINITIALrecordPage 194UNGS.RESINITIAL.MATBALANCE2.RDo records demonstrate that unexpected conditions in the material balance were evaluated and corrected? References: 192.12(b)(1)#
UNGS.RESINITIALprocedurePage 194UNGS.RESINITIAL.PRESSVSINVENT.PDoes the process require that the average reservoir pressure versus inventory graph be monitored to capture any unexpected conditions? References: 192.12(b)(1)#
UNGS.RESINITIALrecordPage 194UNGS.RESINITIAL.PRESSVSINVENT.RDo records demonstrate that the average reservoir pressure versus inventory graph was monitored to capture unexpected conditions? References: 192.12(b)(1)#
UNGS.RESINITIALprocedurePage 194UNGS.RESINITIAL.MECHINTEGMONIT.PDoes the process require that wells and related facilities be monitored for mechanical integrity to discover and correct for abnormal operating conditions? References: 192.12(b)(1)#
UNGS.RESINITIALrecordPage 194UNGS.RESINITIAL.MECHINTEGMONIT.RDo records demonstrate that the mechanical integrity of wells and related facilities are monitored to discover and correct for abnormal operating conditions? References: 192.12(b)(1)#
UNGS.RESINITIALrecordPage 194UNGS.RESINITIAL.RECORDS.RDo records include the required items, as applicable and available, listed in API RP 1171, Section 7.5? References: 192.12(b)(1)#
UNGS.RESINITIALprocedurePage 194UNGS.RESINITIAL.RECORDSRET.PDoes the process require that records for natural gas storage testing and monitoring activities be maintained for the life of the facility? References: 192.12(b)(1)#
UNGS.RESRISKprocedurePage 195UNGS.RESRISK.IMPROGRAM.PAre written procedures in place for an Integrity Management Program that meets all of the requirements listed in 192.12(d)(1) and API RP 1171, Section 8? References: 192.12(d)(1), 192.12(d)(4), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 195UNGS.RESRISK.IMPROGRAM.RDo records indicate the Integrity Management Program has been fully implemented and documented for all of the requirements listed in 192.12(d)(1) and (d)(4) and API RP 1171, Section 8? References: 192.12(d)(1), 192.12(d)(4), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 195UNGS.RESRISK.DEFINITION.PHow is "risk" defined in the Integrity/Risk Management Program? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 195UNGS.RESRISK.DATASOURCES.PDoes the process require that information be collected and used to determine susceptibility to threats and hazard-related events? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 195UNGS.RESRISK.DATASOURCES.RDo records demonstrate that appropriate data was collected and used to determine susceptibility to threats and hazard-related events? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 195UNGS.RESRISK.THREATEVAL.PDoes the process require evaluation for potential threats and hazards impacting storage wells and reservoirs? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 195UNGS.RESRISK.THREATEVAL.RDo records demonstrate that potential threats and hazards impacting storage wells and reservoir were adequately evaluated? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 195UNGS.RESRISK.THREATINTERACT.PDoes the process require that information be collected and used to assess threat and hazard interaction? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 196UNGS.RESRISK.THREATINTERACT.RDo records demonstrate that appropriate data is used to assess threat and hazard interaction? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 196UNGS.RESRISK.THREATEXCLUDE.PDoes the process include provisions for the exclusion of specific hazards or threats events and related threats interactions? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 196UNGS.RESRISK.THREATEXCLUDE.RDo records demonstrate that the process was followed for the exclusion of specific hazards or threat events and related threats interactions? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 196UNGS.RESRISK.RISKBASELINE.PDoes the process require the Integrity Management baseline risk assessments for all reservoirs and wells for each UNGSF to be completed in accordance with the timeframes and prioritization required by 192.12(d)(2)? References: 192.12(d)(2), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 196UNGS.RESRISK.RISKBASELINE.RDo records demonstrate the Integrity Management baseline risk assessments for all reservoirs and wells for each UNGSF are being conducted in accordance with the timeframes and prioritization required in 192.12(d)(2)? References: 192.12(d)(2), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 196UNGS.RESRISK.RISKASSESSMETHOD.PDoes the process assess risk in a consistent manner and with a consistent methodology? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 196UNGS.RESRISK.RISKASSESSMETHOD.RDo the records demonstrate that the risk assessment was done in a consistent manner and with a consistent methodology? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 196UNGS.RESRISK.RISKASSESSRESULT.PDoes the process require review of the risk assessment results to determine whether the risk assessment, resulting prioritization, or ranking accurately represents its facilities and the characterization of the risks? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 196UNGS.RESRISK.RISKASSESSRESULT.RDo the records demonstrate that the results of the risk assessment were reviewed to determine whether the risk assessment, resulting prioritization, or ranking accurately represents its facilities and the characterization of the risks? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 197UNGS.RESRISK.PREVMITIGMETHOD.PDoes the process require identification and implementation of preventive and mitigative measures to manage risks? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 197UNGS.RESRISK.PREVMITIGMETHOD.RDo records demonstrate how the preventative and mitigative measures were identified and implemented to reduce risk? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 197UNGS.RESRISK.RISKMGMTEFFECTIVE.PDoes the process require assessment of the effectiveness of risk monitoring and risk management programs? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 197UNGS.RESRISK.RISKMGMTEFFECTIVE.RDo records demonstrate how the effectiveness of the risk monitoring and risk management is assessed? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 197UNGS.RESRISK.RISKREASSESSINTRVL.PDoes the process require operator to determine the appropriate interval(s) for Integrity Management risk re-assessments for continuous improvement for all reservoirs and wells for each UNGSF in accordance with the requirements in 192.12(d)(3) and RP1171, subsections 8.7.1 and 8.7.2? References: 192.12(d)(3), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 197UNGS.RESRISK.RISKREASSESSINTRVL.RDo records demonstrate operator determined the appropriate interval(s) for Integrity Management risk re-assessments for continuous improvement for all reservoirs and wells for each UNGSF in accordance with the requirements in 192.12(d)(3) and RP1171, subsections 8.7.1 and 8.7.2? References: 192.12(d)(3), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 197UNGS.RESRISK.NEWTHREATS.PIf new threats or hazards are identified, or the impact of threats or hazards changes markedly, does the process assess the risk associated with the new conditions and evaluate and prioritize risk management options in accordance with the risk assessment? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 197UNGS.RESRISK.NEWTHREATS.RDo the records detail the identification of new threats or hazards and how they were evaluated and prioritized in the risk assessment as a result? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKprocedurePage 198UNGS.RESRISK.IMPROGRECORDS.PDoes the written Integrity Management Program require records that are used to demonstrate compliance with §192.12(d) be maintained for the life of the facility? References: 192.12(d)(4), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESRISKrecordPage 198UNGS.RESRISK.IMPROGRECORDS.RAre all Integrity Management Program records that are used to demonstrate compliance with §192.12(d) being documented and maintained for the life of the facility? References: 192.12(d)(4), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 198UNGS.RESINTEG.INTEGSITESPEC.PDo the integrity processes and procedures account for site specific characteristics of the reservoir and wells (API RP1171, Section 9.2.1)? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 198UNGS.RESINTEG.INTEGSITESPEC.RDo records demonstrate that integrity-related site-specific characteristics of the reservoir and wells have been accounted for? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 198UNGS.RESINTEG.RISKBASEDEVAL.PDoes the process use a risk-based approach for developing the integrity demonstration, verification, and monitoring tasks? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 198UNGS.RESINTEG.RISKBASEDEVAL.RDo records demonstrate that a risk-based approach was used as the basis for developing the integrity demonstration, verification, and monitoring tasks? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 198UNGS.RESINTEG.RISKBASEDFREQ.PDoes the process use risk assessments to determine the frequency requirements for integrity demonstration, verification, and monitoring tasks or activities? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 198UNGS.RESINTEG.RISKBASEDFREQ.RDo records demonstrate that risk assessments were used to determine the frequency requirements for integrity demonstration, verification and monitoring tasks? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 199UNGS.RESINTEG.WELLINTEGEVAL.PWhat is the process for determining which method(s), including inspection technologies, are to be (or were) used for the initial and subsequent mechanical integrity evaluations of each well? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 199UNGS.RESINTEG.WELLINTEGEVAL.RDo records demonstrate how the ongoing mechanical integrity of each well was initially and subsequently mechanically integrity tested in accordance with the risk/integrity management process? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 199UNGS.RESINTEG.THIRDPARTYWELLS.PDoes the process detail how, and how frequently, to request well integrity evaluation data from third-party well owner/operators? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 199UNGS.RESINTEG.THIRDPARTYWELLS.RDo the records demonstrate that well integrity evaluation data from third party well owner/operators were requested, and evaluated, according to the established frequency? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 199UNGS.RESINTEG.WELLINTEGRATION.PHow are the risk assessment process and the information derived from the initial (and prior) mechanical integrity evaluations of each well used to determine the type and timing of the next mechanical integrity test for each well? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 199UNGS.RESINTEG.WELLINTEGRATION.RDo records demonstrate that well mechanical integrity evaluations included initial and subsequent evaluations as determined using the risk assessment and the information derived from the initial evaluation? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 199UNGS.RESINTEG.WELLANNULAR.PDo the procedures require monitoring for the presence of annular gas by measuring and recording annular pressure and/or annular gas flow on a regular basis? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 199UNGS.RESINTEG.WELLANNULAR.RDo records demonstrate that the presence of annular gas is monitored according to procedure? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 200UNGS.RESINTEG.WELLANNULARLIMIT.PDo the procedures define a threshold or limit for the annular pressure and/or annular gas flow? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 200UNGS.RESINTEG.WELLANNULARLIMIT.RDo records demonstrate that the set threshold or limit for pressure monitoring was not exceeded? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 200UNGS.RESINTEG.WELLANNULAREXCEEDED.PDoes the process require that each annular gas occurrence that exceeds operator-defined or regulatory-defined threshold levels be evaluated? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 200UNGS.RESINTEG.WELLANNULAREXCEEDED.RDo the records demonstrate that each annular gas occurrence that exceeded operator-defined or regulatory-defined threshold levels was evaluated according to the procedure? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 200UNGS.RESINTEG.WELLVISUALINSPECT.PDoes the process require the visual inspection of each wellhead assembly for leaks at least annually? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 200UNGS.RESINTEG.WELLVISUALINSPECT.RDo the records demonstrate that visual inspections of each wellhead assembly for leaks were conducted in accordance with the procedures? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGobservationPage 200UNGS.RESINTEG.WELLVISUALINSPECT.ODo field observations confirm that wellhead assembly was visually inspected for leaks? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 200UNGS.RESINTEG.WELLHEADVALVETEST.PDoes the procedure describe how to annually test the operation of the master valve and wellhead pipeline isolation valve for proper function and ability to isolate the well? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 200UNGS.RESINTEG.WELLHEADVALVETEST.RDo records demonstrate that the operation of the master valve and wellhead pipeline isolation valve for proper function and ability to isolate the well is being tested according to procedure? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 201UNGS.RESINTEG.WELLHEADVALVEMAINT.PDo the processes and procedures describe the valve maintenance program for maintaining, repairing, and replacing isolation valves? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 201UNGS.RESINTEG.WELLHEADVALVEMAINT.RDo records demonstrate that valves are maintained, repaired, or replaced in accordance with the valve maintenance program for isolation valves? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 201UNGS.RESINTEG.WELLSSSVTEST.PDo procedures explain how surface and subsurface safety valve systems, where installed, are annually function-tested in accordance with manufacturer’s specifications and the operator's procedures? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 201UNGS.RESINTEG.WELLSSSVTEST.RDo records demonstrate that surface and subsurface safety valve systems, where installed, are function-tested at least annually and according to procedure? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 201UNGS.RESINTEG.CLOSEDSAFETYVALVE.PWhere a storage well surface or subsurface automatically-closeable safety valve system is installed, do the safety valve procedures require that it must be manually reopened at the site after closure and not done so remotely? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 201UNGS.RESINTEG.CLOSEDSAFETYVALVE.RWhere a storage well surface or subsurface automatically-closeable safety valve system is installed, do the safety valve records demonstrate that it was manually reopened at the site after closure and not done so remotely? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGobservationPage 201UNGS.RESINTEG.WELLINTEGRITY.OWell Integrity - All Observations Were observed well integrity activities performed adequately and in accordance with established processes? (Reference API RP1171, Section 9) References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 201UNGS.RESINTEG.RECORDS.PDo the procedures require that all integrity-related inspections, tests, patrols and analyses be documented? References: 192.12(d)(4), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 202UNGS.RESINTEG.RECORDS.RDo records demonstrate that all integrity-related inspections, tests, patrols, and analyses are documented according to procedure? References: 192.12(d)(4), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 202UNGS.RESINTEG.RECORDRETAIN.PDo the process and procedures require that the retention period for storage inventory assessments be the “life of the facility”? References: 192.12(d)(4), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 202UNGS.RESINTEG.RECORDRETAIN.RDo records demonstrate that storage inventory assessments are being retained for the life of the facility? References: 192.12(d)(4), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGprocedurePage 202UNGS.RESINTEG.INTEGRESERVOIRS.PDo the processes and procedures ensure the ongoing functional integrity of reservoirs in accordance with API RP1171, Sections 9.2 and 11.2.1? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGrecordPage 202UNGS.RESINTEG.INTEGRESERVOIRS.RDo the records demonstrate that integrity demonstration, integrity verification and monitoring practices are used to maintain ongoing functional integrity of the reservoir(s)? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESINTEGobservationPage 202UNGS.RESINTEG.INTEGOVERALL.OAre there any integrity maintenance activities (i.e., O&M work, well workovers, well-logging, or any integrity verification or monitoring activities) that can be observed during the inspection? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEprocedurePage 202UNGS.RESSITE.SECURITY.PIs there a process or procedure that describes what security and safety measures are required for each well site? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEprocedurePage 203UNGS.RESSITE.FENCES.PDo processes describe how fences or enclosures at well sites comply with applicable fire codes and regulations, where applicable? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITErecordPage 203UNGS.RESSITE.FENCES.RDo records demonstrate compliance with applicable fire codes and regulations for control of site ingress and egress, where applicable? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEobservationPage 203UNGS.RESSITE.FENCES.OAre well location areas secure (which may include fences or enclosures, barriers, chains on valves, locks on fence gate, security cameras, etc.), and do fences or enclosures comply with applicable fire codes and regulations? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEprocedurePage 203UNGS.RESSITE.SIGNAGE.PDoes the process require that there is permanent weatherproof signage installed at each well site? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITErecordPage 203UNGS.RESSITE.SIGNAGE.RDo records demonstrate that there is a sign at each well site? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEobservationPage 203UNGS.RESSITE.SIGNAGE.OIs a permanent weatherproof signage installed at each well site? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEprocedurePage 203UNGS.RESSITE.EMERGPLAN.PIs there a written emergency preparedness / emergency response plan in place that addresses accidental releases, equipment failure, natural disasters, and third-party emergencies? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEprocedurePage 203UNGS.RESSITE.EMERGPLANRVW.PIs the emergency preparedness / emergency response plan (ER Plan manual) required to be reviewed for effectiveness and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITErecordPage 203UNGS.RESSITE.EMERGPLANRVW.RDo records demonstrate the emergency preparedness / emergency response plan (ER Plan manual) was reviewed and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITErecordPage 204UNGS.RESSITE.EMERGPLANDRILLS.RDo records demonstrate that the emergency preparedness/response plan exercises (drills and tabletop exercises) were conducted and documented? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEobservationPage 204UNGS.RESSITE.EMERGPLANDRILLS.OIs an observed emergency preparedness drill or tabletop exercise conducted adequately and in accordance with the established plan? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEprocedurePage 204UNGS.RESSITE.ERTRAINING.PDoes the process require training for storage operations and applicable staff in the use of the emergency preparedness/response plan? References: 192.12(b)(2), 192.12(b)(1), 192.12(c)#
UNGS.RESSITErecordPage 204UNGS.RESSITE.ERTRAINING.RDo records demonstrate that storage facility staff were trained in the use of the emergency preparedness/response plan? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEobservationPage 204UNGS.RESSITE.ERTRAINING.ODo field observations confirm emergency preparedness/response plan training was conducted adequately and in accordance with the established process? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEprocedurePage 204UNGS.RESSITE.BLOWOUTPLAN.PIs there a current written Blowout Contingency Plan in place? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITErecordPage 204UNGS.RESSITE.BLOWOUTPLAN.RDo records demonstrate that the Blowout Contingency Plan was followed according to procedure when activated or when conducted as a drill or tabletop exercise? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEobservationPage 205UNGS.RESSITE.BLOWOUTPLAN.OIs an observed BCP drill and/or tabletop exercise conducted adequately and in accordance with the Plan? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITEprocedurePage 205UNGS.RESSITE.BLOWOUTPLANRVW.PIs the Blowout Contingency Plan required to be reviewed for effectiveness and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESSITErecordPage 205UNGS.RESSITE.BLOWOUTPLANRVW.RDo records demonstrate the Blowout Contingency Plan was reviewed for effectiveness and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 205UNGS.RESPROCED.OMPROCED.PAre there written procedures in place for conducting operations and maintenance (O&M) activities (including drilling and other well entry work) of UNGS facilities, including activities required to establish and maintain functional integrity? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 205UNGS.RESPROCED.OMPROCED.RDo records indicate that the activities required by the Operations and Maintenance Procedures to establish and maintain functional integrity were properly documented/recorded and retained, as required by §192.12(c)? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 205UNGS.RESPROCED.OMPROCEDSCOPE.RDo records demonstrate O&M procedures covering storage wells and reservoirs includes all work activities performed by contractors/vendors and the operator's personnel? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 205UNGS.RESPROCED.OMPROCEDIMPL.RDo records demonstrate that the Operation and Maintenance procedures were in place prior to commencing operations of a new storage facility or beginning an activity not yet implemented? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 206UNGS.RESPROCED.OMPROCEDAVAIL.PAre the most current O&M procedural manuals required to be made available and readily accessible to operations, maintenance, and storage personnel where the work is performed? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDobservationPage 206UNGS.RESPROCED.OMPROCEDAVAIL.ODo field observations confirm current O&M procedures are available and readily accessible to operations, maintenance, and storage personnel? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 206UNGS.RESPROCED.OMPROCEDRVW.PAre the Operations and Maintenance procedures (manuals) required to be reviewed and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 206UNGS.RESPROCED.OMPROCEDRVW.RDo records demonstrate the Operations and Maintenance procedures (manuals) have been reviewed and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 206UNGS.RESPROCED.CONTROLROOM.PDoes the process or procedure describe the interaction and communication between operations & maintenance personnel and the control room for maintaining reservoir and well functional integrity during normal, abnormal, and emergency conditions? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 206UNGS.RESPROCED.CONTROLROOM.RDo records demonstrate that there are communications between operations & maintenance personnel and the control room for maintaining reservoir and well functional integrity during normal, abnormal, and emergency conditions? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 206UNGS.RESPROCED.SFTYENVPROGENV.PDo the process and procedures incorporate safeguards for the Environment, Safety, and Health into storage design, construction, and operations? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 206UNGS.RESPROCED.SFTYENVPROGENV.RDo records demonstrate that safeguards for the Environment, Safety, and Health are incorporated into storage design, construction, and operations? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 207UNGS.RESPROCED.SFTYENVPROGSECUR.PDo the process and procedures incorporate safeguards for Site Security into storage design, construction, and operations? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 207UNGS.RESPROCED.SFTYENVPROGSECUR.RDo records demonstrate that safeguards for Site Security are incorporated into storage design, construction, and operations? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 207UNGS.RESPROCED.MOC.PDo the process or procedures require that changes are accomplished in a controlled manner (use of a Management of Change process)? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 207UNGS.RESPROCED.MOC.RDo records demonstrate that changes are made in a controlled manner (and in accordance with the MOC or equivalent process)? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 207UNGS.RESPROCED.MOCREVISE.PDoes the process require that program documentation, framework, and procedures are revised before the change is implemented? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 207UNGS.RESPROCED.MOCREVISE.RDo records demonstrate that the program documentation, framework and procedures were revised before the change was implemented? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 207UNGS.RESPROCED.TRAINOM.PDoes the process require that operating personnel be notified of changes whenever changes are made to the operating procedures specified in API RP1171, Section 11.3? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 207UNGS.RESPROCED.TRAINOM.RDo records detail how the MOC process for the notification of changes to the operating procedures was followed? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 207UNGS.RESPROCED.TRAINOMCHGS.PDoes the process require that the operating personnel be trained, and the training documented, whenever changes are made to the operating procedures specified in API RP1171, Section 11.3? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 208UNGS.RESPROCED.TRAINOMCHGS.RDo records demonstrate that operating personnel were trained when an applicable change was made to the operating procedures? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 208UNGS.RESPROCED.TRAINRECORDS.PWhat is the established retention interval for training records? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 208UNGS.RESPROCED.TRAINRECORDS.RDo records demonstrate that training records retention meets the operator established interval? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 208UNGS.RESPROCED.RECORDSDOC.PDoes the process include a list of the necessary documents that need to be recorded for compliance with procedures as required in API RP1171, Section 11? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDprocedurePage 208UNGS.RESPROCED.RETENTION.PDoes the process establish a retention interval for all records that satisfy API RP1171, Section 11 requirements and operator requirements? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.RESPROCEDrecordPage 208UNGS.RESPROCED.RETENTION.RDo records demonstrate that the records retention intervals are followed for the API RP1171 Section 11 requirements and operator requirements?? References: 192.12(b)(2), 192.12(b)(1)#
UNGS.CAVERNGEOLprocedurePage 208UNGS.CAVERNGEOL.SPECIMENTEST1.PDoes the process for core testing require that ASTM D4543 be used? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLrecordPage 208UNGS.CAVERNGEOL.SPECIMENTEST1.RDo records for core testing demonstrate that ASTM D4543 was used? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLprocedurePage 209UNGS.CAVERNGEOL.SPECIMENTEST2.PDoes the process for triaxial core testing require that the specimen have a length to diameter ratio of 2.0 to 2.5 and a diameter not less than 1-7/8 inches? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLrecordPage 209UNGS.CAVERNGEOL.SPECIMENTEST2.RDo records demonstrate that triaxial core testing maintained a specimen length to diameter ratio of 2.0 to 2.5 and a diameter not less than 1-7/8 inches? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLprocedurePage 209UNGS.CAVERNGEOL.TENSIONTEST.PDoes the process require Brazilian indirect tension testing of core samples to meet or exceed the method specified by ASTM D3967? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLrecordPage 209UNGS.CAVERNGEOL.TENSIONTEST.RDo records indicate that the specific method outlined by ASTM D3967 was met or exceeded? followed? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLprocedurePage 209UNGS.CAVERNGEOL.TRIAXIALTEST.PDoes the process for triaxial compression testing of cores require that the procedures of ASTM D7012 be followed or exceeded? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLrecordPage 209UNGS.CAVERNGEOL.TRIAXIALTEST.RDo record demonstrate that ASTM D7012 was used for triaxial compression testing of cores? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLprocedurePage 209UNGS.CAVERNGEOL.TRIAXIALCREEP.PDoes the process for triaxial creep tests require that the procedure meet or exceed the Triaxial Compression Method specified by ASTM D7070? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLrecordPage 209UNGS.CAVERNGEOL.TRIAXIALCREEP.RDo records demonstrate that the process for triaxial creep tests exceed or meet ASTM D7070? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLprocedurePage 209UNGS.CAVERNGEOL.STRESSTEST.PDoes the process require procedures that meet or exceed ASTM D4645 if a stress test is performed? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLrecordPage 210UNGS.CAVERNGEOL.STRESSTEST.RDo records demonstrate that the stress test procedures meet or exceed ASTM D4645? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLprocedurePage 210UNGS.CAVERNGEOL.MAXPRESS.PDoes the process require that maximum pressure be limited to ensure gas containment? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNGEOLrecordPage 210UNGS.CAVERNGEOL.MAXPRESS.RDo records demonstrate that a maximum pressure was established to ensure gas containment? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 210UNGS.CAVERNWELLDES.WELLDESGEN.PDoes the process ensure that the design of the well system will contain the stored gas? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 210UNGS.CAVERNWELLDES.WELLDESGEN.RDo records demonstrate that the well system was designed to ensure that gas containment is sufficient? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 210UNGS.CAVERNWELLDES.CONDUCTORCASING.PDoes the design process include that a conductor casing be installed in the first section of the well system? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 210UNGS.CAVERNWELLDES.CONDUCTORCASING.RDo records demonstrate that a conductor casing was installed as the first line of casing for the system? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 210UNGS.CAVERNWELLDES.INTERMEDCASING.PDoes the design process for domal salts require that two casing strings be set into the salt? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 211UNGS.CAVERNWELLDES.INTERMEDCASING.RDo records indicate that there are two casing strings set in the domal salt? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 211UNGS.CAVERNWELLDES.CONDUCTOR1.PConductor Casing Design - Driven Conductors For driven conductor casings, does the design process require that the conductor casing to withstand lithostatic (overburden) pressure at the anticipated setting depth? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 211UNGS.CAVERNWELLDES.CONDUCTOR1.RDo records demonstrate that the design of the conductor casing was calculated to withstand lithostatic (overburden) pressures at the anticipated setting depth when it was driven into the ground? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 211UNGS.CAVERNWELLDES.CONDUCTOR2.PConductor Casing Design - Augered Conductors For augered conductor casings, does the design process require the collapse design of the conductor casing be calculated to withstand the differential pressures during cementing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 211UNGS.CAVERNWELLDES.CONDUCTOR2.RDo records demonstrate that the design of the conductor casing was calculated to withstand differential pressures during cementing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 211UNGS.CAVERNWELLDES.SURFCASING1.PDoes the process require that the surface casing be designed to withstand pressures encountered during cementing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 211UNGS.CAVERNWELLDES.SURFCASING1.RDo records demonstrate that the surface casing was designed to withstand pressures encountered during cementing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 211UNGS.CAVERNWELLDES.SURFCASING2.PDoes the design process require that gas bearing formations be accounted for in the burst design? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 211UNGS.CAVERNWELLDES.SURFCASING2.RDo records demonstrate that the burst design of the surface casing account for known gas bearing formations? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 212UNGS.CAVERNWELLDES.SURFCASING3.PSurface Casing Design - Bedded Salt Well For bedded salt well design, does the design process require that the top of the surface casing be based on maximum operating pressure? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 212UNGS.CAVERNWELLDES.SURFCASING3.RSurface Casing Design - Bedded Salt Well For bedded salt well design, do records demonstrate that the design of the top of the surface casing were based on maximum operating pressures? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 212UNGS.CAVERNWELLDES.SURFCASING4.PSurface Casing Design - Bedded Salt Well For bedded salt well design, does the design process require that the bottom of the surface casing be based on the cementing differential pressures? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 212UNGS.CAVERNWELLDES.SURFCASING4.RSurface Casing Design - Bedded Salt Well For bedded salt well design, do records demonstrate that the design of the bottom of the surface casing handle cementing differential pressures? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 212UNGS.CAVERNWELLDES.INTERMEDCASING1.PDoes the design process require that the collapse pressure of the intermediate casing be designed to the casing cementing pressures? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 212UNGS.CAVERNWELLDES.INTERMEDCASING1.RDo records demonstrate that the collapse pressure of the intermediate casing was designed to withstand casing cementing pressures? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 212UNGS.CAVERNWELLDES.INTERMEDCASING2.PDoes the design process require that the burst pressure of the intermediate casing be based on maximum operating pressure for the top portion and on cementing differential pressures for the bottom portion of the casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 212UNGS.CAVERNWELLDES.INTERMEDCASING2.RDo records indicate that the burst pressure design account for maximum operating pressure and cementing differential pressures? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 213UNGS.CAVERNWELLDES.INTERMEDCASING3.PDoes the design process have welding and inspection procedures developed if the intermediate casing has welded connections? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 213UNGS.CAVERNWELLDES.INTERMEDCASING3.RDo records demonstrate that welding and inspections procedures were developed for welded connections of the intermediate casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 213UNGS.CAVERNWELLDES.INTERMEDCASING4.PDoes the design process require welded connections be inspected by X-ray or NDT methods if there are welded connections for the intermediate casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 213UNGS.CAVERNWELLDES.INTERMEDCASING4.RDo records demonstrate that welded connections were inspected by X-ray or NDT methods for welded intermediate casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 213UNGS.CAVERNWELLDES.PRODCASING1.PDoes the design process for the tensile, collapse and burst strengths follow the requirements of API 1170, Section 6.3.6 for production casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 213UNGS.CAVERNWELLDES.PRODCASING1.RDo records demonstrate that the design of the production casing met the requirements of API 1170 Section 6.3.6? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 213UNGS.CAVERNWELLDES.PRODCASING2.PDoes the design process require that welded connections be used for the production casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 213UNGS.CAVERNWELLDES.PRODCASING2.RDo records demonstrate that welded connections were used for the production casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 213UNGS.CAVERNWELLDES.PRODCASING3.PDoes the design process require welded connections to be inspected by X-ray or NDT methods if there are welded connections for the production casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 214UNGS.CAVERNWELLDES.PRODCASING3.RDo records demonstrate that welded connections were inspected by X-ray or NDT methods for the welded production casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 214UNGS.CAVERNWELLDES.WELLHEAD.PDoes the design process for the wellhead meet requirements of API RP1170, Section 6.4.2? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 214UNGS.CAVERNWELLDES.WELLHEAD.RDo records demonstrate that the design of the wellhead meets the requirements of API RP1170, Section 6.4.2? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 214UNGS.CAVERNWELLDES.BRADENHEAD.PDoes the design process require Bradenhead welded connections be inspected by X-ray or NDT methods? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 214UNGS.CAVERNWELLDES.BRADENHEAD.RDo records demonstrate that Bradenhead welded connections were inspected by X-ray or NDT methods? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 214UNGS.CAVERNWELLDES.CASINGHANGER1.PDoes the design process require the casing hanger to fit in the bowl of the Bradenhead and fully close around the O.D. of the production casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 214UNGS.CAVERNWELLDES.CASINGHANGER1.RDo records demonstrate that the casing hanger fits in the bowl of the Bradenhead to allow full closure around the O.D. of the production casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 214UNGS.CAVERNWELLDES.CASINGHANGER2.PDoes the design process for the casing account for the entire weight of the casing string? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 214UNGS.CAVERNWELLDES.CASINGHANGER2.RDo records demonstrate that the casing hanger was designed to handle the entire weight of the casing string? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 215UNGS.CAVERNWELLDES.ADAPTERFLANGE.PDoes the design process for the wellhead require that a double studded adapter pack- off flange be used if the Bradenhead Flange has lower pressure rating than the wellhead components above it? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 215UNGS.CAVERNWELLDES.ADAPTERFLANGE.RDo records indicate that a double studded adapter pack off flange was installed if the Bradenhead flange has a lower pressure rating than the wellhead components above it? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 215UNGS.CAVERNWELLDES.MANUALVALVES.PDoes the wellhead design process include suitable pressure rated manual solution mining valves installed for injection and removal of blanket materials? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESrecordPage 215UNGS.CAVERNWELLDES.MANUALVALVES.RDo records indicate that manual valves were installed on the wellhead? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNWELLDESprocedurePage 215UNGS.CAVERNWELLDES.CONVERSIONVALVES.PDoes the wellhead design process include a manual gas storage valve be placed on the storage wellhead during conversion workover? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 215UNGS.CAVERNDRILL.RIGSELECTION.PDoes the process include the requirements of API 1170, Section 7.1 for rig selection? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 215UNGS.CAVERNDRILL.RIGSELECTION.RDo records demonstrate that the rig selection was based on API 1170, Section 7.1 criteria? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 215UNGS.CAVERNDRILL.BOP.PDoes the process require the use and test of a BOP system to ensure well control during drilling of the pilot hole of each hole section? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 216UNGS.CAVERNDRILL.BOP.RDo records demonstrate that a BOP system was used and tested to maintain well control during drilling operations? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 216UNGS.CAVERNDRILL.DRILLINGFLUID1.PDoes the process require that a salt saturated drilling fluid to be used when drilling through halite formations? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 216UNGS.CAVERNDRILL.DRILLINGFLUID1.RDo records indicate that a salt saturated drilling fluid was used when drilling through halite formations? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 216UNGS.CAVERNDRILL.DRILLINGFLUID2.PDoes the process require that highly soluble salts be accounted for when selecting a drilling fluid? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 216UNGS.CAVERNDRILL.DRILLINGFLUID2.RDo records indicate that highly soluble salts were accounted for when selecting a drilling fluid? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 216UNGS.CAVERNDRILL.CASINGLOG.PDoes the process allow sufficient time after cementing given before a cement bond log can be run? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 216UNGS.CAVERNDRILL.CASINGLOG.RDo records indicate that sufficient time was given before the bond long was completed? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 216UNGS.CAVERNDRILL.CEMENTZONE.PDoes the process for cement design provide isolation of the storage zone from all sources of porosity and permeability and secure the casing in the borehole? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 216UNGS.CAVERNDRILL.CEMENTZONE.RDo records demonstrate that the cement design isolates the storage zone from all sources of porosity and permeability and secures the casing in the borehole? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 216UNGS.CAVERNDRILL.CEMENT2SURF.PDoes the process require all cemented strings to be cemented to surface? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 217UNGS.CAVERNDRILL.CEMENT2SURF.RDo records indicate that all cemented strings are cemented to surface? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 217UNGS.CAVERNDRILL.CEMENTTEST.PDoes the process require cement quality and testing to meet or exceed API 10A and API 10F? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 217UNGS.CAVERNDRILL.CEMENTTEST.RDo records indicate that cement quality and testing meet or exceed API 10A and API 10F? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 217UNGS.CAVERNDRILL.CEMENTVOL.PDoes the process require that an excess cement volume be calculated based on the open-hole caliper log? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 217UNGS.CAVERNDRILL.CEMENTVOL.RDo records demonstrate that an excess amount of cement volume was calculated based on open-hole caliper log? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 217UNGS.CAVERNDRILL.CENTRALIZERS.PDoes the design process require that casing centralizers be used to center the casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 217UNGS.CAVERNDRILL.CENTRALIZERS.RDo records demonstrate that casing centralizers were used to achieve the proper placement of cement around the casing? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 217UNGS.CAVERNDRILL.CEMENTBOND.PDoes the process ensure that a proper bond be created between the production casing, cement, and the surrounding salt to ensure a seal for containment of pressurized gas? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 217UNGS.CAVERNDRILL.CEMENTBOND.RDo records demonstrate that a proper bond was created between the production casing, cement and surrounding salt? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLprocedurePage 218UNGS.CAVERNDRILL.COMPLETION.PDoes the process require that all drilling fluid in the wellbore be displaced by clean, fully saturated brine water? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNDRILLrecordPage 218UNGS.CAVERNDRILL.COMPLETION.RDo records demonstrate that the wellbore was displaced with clean, fully saturated brine water? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 218UNGS.CAVERNMINE.ROOFDEVEL.PDoes the design process require that the roof of the cavern be developed based on detailed planning, modeling and execution? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 218UNGS.CAVERNMINE.ROOFDEVEL.RDo records demonstrate that the roof of the cavern was designed based on detailed planning, modeling and execution? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 218UNGS.CAVERNMINE.CEMENTCURE.PDoes the process allow sufficient time for the production casing cement to reach full compressive strength before pressuring the annular space to the MAOP? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 218UNGS.CAVERNMINE.CEMENTCURE.RDo records indicate that there was sufficient time for the production casing cement to reach full compressive strength before pressuring the annular space to the MAOP? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 218UNGS.CAVERNMINE.BLANKETINTERFACE.PDoes the process require that a blanket material be placed in the roof of the cavern and the blanket-water interface to be carefully monitored and periodically verified with a wireline log along with other methods? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 218UNGS.CAVERNMINE.BLANKETINTERFACE.RDo records demonstrate that a blanket material was placed in the roof of the cavern and that the blanket-water interface was carefully monitored and periodically verified with a wireline log along with other methods? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 219UNGS.CAVERNMINE.ROOFCONTROLS.PDoes the process require the use of roof controls during reverse circulation so that the salt neck below the casing seat is left intact? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 219UNGS.CAVERNMINE.ROOFCONTROLS.RDo records demonstrate that roof controls were utilized during reverse circulation so that the salt neck below the casing seat remained intact? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 219UNGS.CAVERNMINE.MININGMODEL.PDoes the design process require that a solution mining model be used to develop the salt cavern? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 219UNGS.CAVERNMINE.MININGMODEL.RDo records demonstrate that a solution mining model was used to develop the salt cavern? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 219UNGS.CAVERNMINE.ROOFGROWTH.PDoes the design process require that upward roof growth be controlled by planned use of raw water injection points, flow rates, and blanket material positioning? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 219UNGS.CAVERNMINE.ROOFGROWTH.RDo records demonstrate that upward roof growth was controlled through planned use of raw water injection points, flow rates, and blanket material positioning? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 219UNGS.CAVERNMINE.ROOFSHAPE.RDoes the design process require that frequent interface logs and sonar surveys be performed to confirm desired roof shape and volume? (UNGS.CAVERNMINE.ROOFSHAPE .P) 192.12(a)(1) (192.12(a)(2);API RP1170, Section 8.3.4) 14. Upper Cavern Development - Confirm Roof Shape Do records indicate that frequent interface logs and sonar surveys were used to confirm desired roof shape and volume? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 219UNGS.CAVERNMINE.ESDEQUIP.PDoes the process used during solution mining require the use of ESD valves? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 220UNGS.CAVERNMINE.ESDEQUIP.RDo records indicate that ESD valves were used during solution mining? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 220UNGS.CAVERNMINE.HANGINGSTRING.PDoes the design process require that the hanging string be sized based on the criteria of API 1170, Section 8.4.2.2? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 220UNGS.CAVERNMINE.HANGINGSTRING.RDo records demonstrate that the hanging string size is based on the criteria in API 1170, Section 8.4.2.2? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 220UNGS.CAVERNMINE.CONNECTIONS.PDoes the design process require that hanging string connections be made-up to manufacturer’s specifications? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 220UNGS.CAVERNMINE.CONNECTIONS.RDo records demonstrate that the hanging string connections were made up to manufacturer’s specifications? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 220UNGS.CAVERNMINE.FLUIDINJECTION.PDoes the process during mining require fluid injection rates to be metered and recorded? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 220UNGS.CAVERNMINE.FLUIDINJECTION.RDo records indicate that fluid injection rates were metered and recorded during solution mining? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 220UNGS.CAVERNMINE.SHUTDOWN.PDoes the process require that the system components have instrumentation control and shutdown during the solution mining process? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 220UNGS.CAVERNMINE.SHUTDOWN.RDo records indicate that the cavern system components have instrumentation control and shutdown during the mining process? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 221UNGS.CAVERNMINE.PRESSPROTECT.PDoes the process require that OPP be installed if the cavern system is connected to a plant pump with the capacity to increase pressure of the cavern over MAOP? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 221UNGS.CAVERNMINE.PRESSPROTECT.RDo records demonstrate that OPP was used for the cavern system if the cavern system was connected to a plant pump with the capacity to increase pressure of the cavern over MAOP? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 221UNGS.CAVERNMINE.MONITORING.PDoes the process require that the cavern be monitored throughout the solution mining and debrining processes? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 221UNGS.CAVERNMINE.MONITORING.RDo records demonstrate that the cavern was monitored during the mining and debrining processes? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 221UNGS.CAVERNMINE.SALINITY.PDoes the process require that the salinity of the brine in/out of the cavern be measured during the mining process? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 221UNGS.CAVERNMINE.SALINITY.RDo records indicate that the salinity of the water in/out of the cavern was/is measured during the mining process? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 221UNGS.CAVERNMINE.WORKOVER.PDoes the conversion to gas storage process require that a workover (including a casing inspection of the production casing, installation of the gas storage wellhead, and a mechanical integrity test) is performed? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 221UNGS.CAVERNMINE.WORKOVER.RDo records indicate that a workover (including a casing inspection, installation of a gas storage wellhead, and a mechanical integrity test) was performed before conversion to gas storage? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 221UNGS.CAVERNMINE.STRINGINSP1.PDoes the process require that hanging strings be inspected by a full body electromagnetic and ultrasonic inspection and a thread and coupling inspection if the hanging string were to be reused? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 222UNGS.CAVERNMINE.STRINGINSP2.PDoes the process require that hanging strings joints or connections that fail the inspection be removed and discarded? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 222UNGS.CAVERNMINE.STRINGINSP.RDo records indicate that an inspection was done on all reused hanging strings and that joints or connections that failed the inspection were removed and discarded? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 222UNGS.CAVERNMINE.SONARSURVEY.PDoes the process require a sonar survey be conducted to verify the final cavern geometry? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 222UNGS.CAVERNMINE.SONARSURVEY.RDo records indicate that a final sonar survey was conducted to verify the cavern geometry? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 222UNGS.CAVERNMINE.REUSEDCOMP.PDoes the process require that any reused components from the wellhead be removed, inspected, and tested prior to re-use for gas storage? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 222UNGS.CAVERNMINE.REUSEDCOMP.RDo records demonstrate that any reused components from the wellhead be removed, inspected, and tested prior to re-use in gas service? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 222UNGS.CAVERNMINE.DEBRININGSTRING1.PDoes the process require that debrining strings of unknown quality (salvaged) be discarded? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 222UNGS.CAVERNMINE.DEBRININGSTRING1.RDo records demonstrate that debrining strings of unknown quality (salvaged) be discarded? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 222UNGS.CAVERNMINE.DEBRININGSTRING2.PDoes the process require that each connection of the debrining string be pressure tested? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 223UNGS.CAVERNMINE.DEBRININGSTRING2.RDo records demonstrate that each connection of the debrining string were successfully pressure tested? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 223UNGS.CAVERNMINE.CAVERNMIT.PDoes the process require that a nitrogen/brine interface MIT be performed to ensure cavern integrity before it is placed into gas service? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 223UNGS.CAVERNMINE.CAVERNMIT.RDo records demonstrate that a nitrogen/brine interface MIT was performed, prior to placing cavern into gas service, to ensure cavern integrity? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 223UNGS.CAVERNMINE.MONITORDEBRINE.PDoes the process require that the debrining piping be monitored during the debrining process? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 223UNGS.CAVERNMINE.MONITORDEBRINE.RDo records demonstrate that the debrining piping was monitored during the debrining process? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 223UNGS.CAVERNMINE.CONVERTEDCAVERN.PDoes the process ensure that a converted cavern (cavern not initially intended for gas storage) meet the same criteria as a developed natural gas storage cavern and undergo a thorough review as stated in API 1170, Section 8.10? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 223UNGS.CAVERNMINE.CONVERTEDCAVERN.RDo records indicate that a converted cavern undergo a thorough review as outlined in API RP1170, Section 8.10? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINEprocedurePage 223UNGS.CAVERNMINE.ENLARGEMENT.PDoes the enlarging process for caverns include the criteria outlined in API 1170, Section 8.12? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNMINErecordPage 223UNGS.CAVERNMINE.ENLARGEMENT.RDo records indicate that the cavern was enlarged based on the criteria outlined in API 1170, Section 8.12? References: 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 224UNGS.CAVERNRISK.IMPROGRAM.PAre there written procedures in place for an Integrity Management Program that meets all of the requirements listed in 192.12(d)(1) and API RP 1171, Section 8? References: 192.12(d)(1), 192.12(d)(4), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 224UNGS.CAVERNRISK.IMPROGRAM.RDo records indicate the Integrity Management Program has been fully implemented and documented for all of the requirements listed in 192.12(d)(1) and (d)(4) and API RP 1171, Section 8? References: 192.12(d)(1), 192.12(d)(4), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 224UNGS.CAVERNRISK.DEFINITION.PHow is "risk" defined in the Integrity/Risk Management Program? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 224UNGS.CAVERNRISK.DATASOURCES.PDoes the process require that information be collected and used to determine susceptibility to threats and hazard-related events? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 224UNGS.CAVERNRISK.DATASOURCES.RDo records demonstrate that appropriate data was collected and used to determine susceptibility to threats and hazard-related events? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 224UNGS.CAVERNRISK.THREATEVAL.PDoes the process require evaluation for potential threats and hazards impacting storage wells and caverns? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 224UNGS.CAVERNRISK.THREATEVAL.RDo records demonstrate that potential threats and hazards impacting storage wells and cavern were adequately evaluated? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 224UNGS.CAVERNRISK.THREATINTERACT.PDoes the process require that information be collected and used to assess threat and hazard interaction? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 225UNGS.CAVERNRISK.THREATINTERACT.RDo records demonstrate that appropriate data is used to assess threat and hazard interaction? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 225UNGS.CAVERNRISK.THREATEXCLUDE.PDoes the process include provisions for the exclusion of specific hazards or threats events and related threats interactions? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 225UNGS.CAVERNRISK.THREATEXCLUDE.RDo records demonstrate that the process was followed for the exclusion of specific hazards or threat events and related threats interactions? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 225UNGS.CAVERNRISK.RISKBASELINE.PDoes the process require the Integrity Management baseline risk assessments for all caverns and wells for each UNGSF to be completed in accordance with the timeframes and prioritization required by 192.12(d)(2)? References: 192.12(d)(2), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 225UNGS.CAVERNRISK.RISKBASELINE.RDo records demonstrate the Integrity Management baseline risk assessments for all caverns and wells for each UNGSF are being conducted in accordance with the timeframes and prioritization required in 192.12(d)(2)? References: 192.12(d)(2), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 225UNGS.CAVERNRISK.RISKASSESSMETHOD.PDoes the process assess risk in a consistent manner and with a consistent methodology? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 225UNGS.CAVERNRISK.RISKASSESSMETHOD.RDo the records demonstrate that the risk assessment was done in a consistent manner and with a consistent methodology? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 225UNGS.CAVERNRISK.RISKASSESSRESULT.PDoes the process require review of the risk assessment results to determine whether the risk assessment, resulting prioritization, or ranking accurately represents its facilities and the characterization of the risks? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 226UNGS.CAVERNRISK.RISKASSESSRESULT.RDo the records demonstrate that the results of the risk assessment were reviewed to determine whether the risk assessment, resulting prioritization, or ranking accurately represents its facilities and the characterization of the risks? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 226UNGS.CAVERNRISK.PREVMITIGMETHOD.PDoes the process require identification and implementation of preventive and mitigative measures to manage risks? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 226UNGS.CAVERNRISK.PREVMITIGMETHOD.RDo records demonstrate how the preventative and mitigative measures were identified and implemented to reduce risk? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 226UNGS.CAVERNRISK.RISKMGMTEFFECTIVE.PDoes the process require assessment of the effectiveness of risk monitoring and risk management programs? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 226UNGS.CAVERNRISK.RISKMGMTEFFECTIVE.RDo records demonstrate how the effectiveness of the risk monitoring and risk management is assessed? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 226UNGS.CAVERNRISK.RISKREASSESSINTRVL.PDoes the process require operator to determine the appropriate interval(s) for Integrity Management risk re-assessments for continuous improvement for all caverns and wells for each UNGSF in accordance with the requirements in 192.12(d)(3) and RP1171, subsections 8.7.1 and 8.7.2? References: 192.12(d)(3), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 226UNGS.CAVERNRISK.RISKREASSESSINTRVL.RDo records demonstrate operator determined the appropriate interval(s) for Integrity Management risk re-assessments for continuous improvement for all caverns and wells for each UNGSF in accordance with the requirements in 192.12(d)(3) and RP1171, subsections 8.7.1 and 8.7.2? References: 192.12(d)(3), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 226UNGS.CAVERNRISK.NEWTHREATS.PIf new threats or hazards are identified, or the impact of threats or hazards changes markedly, does the process assess the risk associated with the new conditions and evaluate and prioritize risk management options in accordance with the risk assessment? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 227UNGS.CAVERNRISK.NEWTHREATS.RDo the records detail the identification of new threats or hazards and how they were evaluated and prioritized in the risk assessment as a result? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKprocedurePage 227UNGS.CAVERNRISK.IMPROGRECORDS.PDoes the written Integrity Management Program require records that are used to demonstrate compliance with 192.12(d) be maintained for the life of the facility? References: 192.12(d)(4), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNRISKrecordPage 227UNGS.CAVERNRISK.IMPROGRECORDS.RAre all Integrity Management Program records that are used to demonstrate compliance with 192.12(d) being documented and maintained for the life of the facility? References: 192.12(d)(4), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 227UNGS.CAVERNOPS.MAOPLIMIT.PDoes the process establish a maximum and minimum storage operating pressure? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 227UNGS.CAVERNOPS.MAOPLIMIT.RDo records demonstrate that a maximum and minimum operating pressure have been established? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 227UNGS.CAVERNOPS.MAOPWELLHEAD.PIf the wellhead is the monitoring point of record for pressure, does the process convert the maximum and minimum pressure at the casing seat to a maximum and minimum wellhead pressure? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 227UNGS.CAVERNOPS.MAOPWELLHEAD.RDo records demonstrate that the casing seat pressure was converted to a maximum and minimum wellhead pressure (if the wellhead is the monitoring point of record for pressure)? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 228UNGS.CAVERNOPS.WELLHEADREPL.PDoes the process require the replacement of solution mined wellheads before commencing natural gas storage service? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 228UNGS.CAVERNOPS.WELLHEADREPL.RDo records demonstrate that the solution mined wellhead has been changed prior to commencing gas operations? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 228UNGS.CAVERNOPS.ESDVALVE.PDoes the process require that an Emergency Shutdown (ESD) Valve is installed at or near the manual valves (wing valves) to isolate the cavern in the event of an emergency? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 228UNGS.CAVERNOPS.ESDVALVE.RDo records demonstrate that ESD valves are installed at or near the manual valves (wing valves) for isolation purposes? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 228UNGS.CAVERNOPS.ESDFLANGE.PIf an instrument flange is located between the wing valve and ESD valve, and it is used to gather real-time pressure data, does the process ensure that the flange is rated for the same pressure as the valves? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 228UNGS.CAVERNOPS.ESDFLANGE.RDo records demonstrate that instrument flanges are rated for the same pressure as the valves surrounding the instrument flange? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 228UNGS.CAVERNOPS.UPSETCOND.PDoes the process require monitoring equipment to detect upset conditions during the debrining process? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 228UNGS.CAVERNOPS.UPSETCOND.RDo records demonstrate that upset conditions are monitored during the debrining process? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 229UNGS.CAVERNOPS.ESDUPSETCOND.PDoes the process ensure that monitoring equipment that is used as a warning device be connected to the ESD system to automatically close-in the cavern? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 229UNGS.CAVERNOPS.ESDUPSETCOND.RDo records demonstrate that the monitoring devices that are connected to an ESD system are tested on a periodic basis? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 229UNGS.CAVERNOPS.ESDSYSTEM.PDoes the process require an Emergency Shutdown (ESD) system to isolate the cavern and wellhead from any attached piping in an emergency? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 229UNGS.CAVERNOPS.ESDSYSTEM.RDo records demonstrate that an ESD system is installed to isolate the cavern(s) in an emergency? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSobservationPage 229UNGS.CAVERNOPS.ESDSYSTEM.ODo field observations on the presence of monitoring equipment and the ESD system on the cavern and testing/calibration of the monitoring equipment and/or ESD system match with the process and records? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 229UNGS.CAVERNOPS.ANNULUSPRESS.PIf the production casing annular space is monitored for pressure, does the process ensure that the pressure tap is not inside the wing valve? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 229UNGS.CAVERNOPS.ANNULUSPRESS.RDo records demonstrate that there is no pressure tap within the wing valve? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSobservationPage 229UNGS.CAVERNOPS.ANNULUSPRESS.ODo field observations related to wellhead configuration, pressure taps, and annulus pressure monitoring match with the process and records? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 229UNGS.CAVERNOPS.TESTDEVICES.PDo procedures require the testing and calibrating of wellhead gauges, transmitters, and safety devices to be conducted annually? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 230UNGS.CAVERNOPS.TESTDEVICES.RDo records demonstrate that wellhead gauges, transmitters, and safety devices are tested and calibrated on an annual basis? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 230UNGS.CAVERNOPS.REPLDEVICES.PDoes the process require that any malfunctioning equipment/devices be repaired or replaced if it fails testing/calibration? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 230UNGS.CAVERNOPS.REPLDEVICES.RDo records demonstrate that any malfunctioning equipment has repaired or replaced? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSobservationPage 230UNGS.CAVERNOPS.TESTDEVICES.ODo field observations of testing, calibration, and/or the repair / replacement of gauges, transmitters, and safety devices match with the procedures and records? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 230UNGS.CAVERNOPS.WORKOVER.PAre there procedures in place for conducting a well workover with the cavern under pressure? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 230UNGS.CAVERNOPS.WORKOVER.RDo records demonstrate that procedures were designed to provide for maximum anticipated cavern pressure prior to conducting pressurized workovers? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 230UNGS.CAVERNOPS.WORKOVEREQUIP.PDoes the process ensure that the rig(s) and equipment to be used for the workover is designed for the maximum anticipated pressure? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 230UNGS.CAVERNOPS.WORKOVEREQUIP.RDo records demonstrate that the rig(s) and equipment used for the workover were rated for the maximum anticipated cavern pressure? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 230UNGS.CAVERNOPS.LOTO.PIs there a process for Lockout and Tagout (LOTO) at the storage facility to protect workers from hazardous energy sources? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 231UNGS.CAVERNOPS.LOTO.RDo records demonstrate that the Lockout and Tagout (LOTO) procedures were followed? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSobservationPage 231UNGS.CAVERNOPS.LOTO.ODo field observations of the Lockout and Tagout procedures in use demonstrate that it being properly performed? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSprocedurePage 231UNGS.CAVERNOPS.OMPROCED.PAre there written procedures in place for conducting Operation and Maintenance (O&M) activities of UNGS facilities, including activities such as workovers and activities required to establish and maintain functional integrity? References: 192.12(c), 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNOPSrecordPage 231UNGS.CAVERNOPS.OMPROCED.RDo records indicate that the activities required by the Operations and Maintenance procedures to establish and maintain functional integrity were properly documented/recorded and retained, as required by 192.12(c)? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSrecordPage 231UNGS.CAVERNOPS.OMPROCEDIMPL.RDo records demonstrate O&M procedures covering storage wells and reservoirs were developed and implemented prior to commencing operations or beginning an activity not yet implemented? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSprocedurePage 231UNGS.CAVERNOPS.OMPROCEDOTHER.PDo the O&M Procedures include any other components related to the safe operation and necessary maintenance of the cavern or facility? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSrecordPage 231UNGS.CAVERNOPS.OMPROCEDOTHER.RDo the records demonstrate that the other components of the O&M or Other Procedures related to the safe operation and necessary maintenance of the cavern or facility were conducted in accordance with the established procedures? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSprocedurePage 231UNGS.CAVERNOPS.OMPROCEDRVW.PAre the Operation and Maintenance (O&M) procedures (manuals) required to be reviewed and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSrecordPage 232UNGS.CAVERNOPS.OMPROCEDRVW.RDo records demonstrate that the Operation and Maintenance (O&M) procedures (manuals) have been reviewed and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSobservationPage 232UNGS.CAVERNOPS.OMPROCEDAVAIL.ODo field observations confirm current O&M procedures are available and readily accessible to operations, maintenance, and storage personnel? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSprocedurePage 232UNGS.CAVERNOPS.OMRECORDS.PDo the O&M Procedures include requirements for records documentation and retention? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSrecordPage 232UNGS.CAVERNOPS.OMRECORDS.RDo records demonstrate that the required O&M inspections, testing, calibration, and monitoring activities are documented and retained in accordance with the O&M Procedure requirements? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSprocedurePage 232UNGS.CAVERNOPS.EMERGPLAN.PIs there an Emergency Response Plan in place to provide for the safe control or shutdown of the storage facility, including the storage cavern(s), in the event of a failure or other emergency condition? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSrecordPage 232UNGS.CAVERNOPS.EMERGPLAN.RDo records demonstrate that the Emergency Response Plan provides for the safe control or shutdown of the storage facility, including the storage cavern(s), in the event of a failure or other emergency condition? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSprocedurePage 232UNGS.CAVERNOPS.EMERGPLANRVW.PIs the Emergency Response Plan / Emergency Preparedness Plan (or manual) required to be reviewed and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSrecordPage 232UNGS.CAVERNOPS.EMERGPLANRVW.RDo records demonstrate the Emergency Response Plan / Emergency Preparedness Plan (or manual) was reviewed and updated at intervals not exceeding 15 months, but at least once each calendar year? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSprocedurePage 232UNGS.CAVERNOPS.BLOWOUTPLAN.PIs there a Blowout Contingency Plan in place to address an uncontrolled release of gas (loss of well control) from the cavern? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSrecordPage 233UNGS.CAVERNOPS.BLOWOUTPLAN.RDo records demonstrate that procedures in the Blowout Contingency Plan were designed to address an uncontrolled release of gas (loss of well control) from the cavern? References: 192.12(c), 192.12(a)#
UNGS.CAVERNOPSprocedurePage 233UNGS.CAVERNOPS.OMTRAINING.PIs there a personnel Training Program in place to address normal (routine) operations, abnormal operations, and emergency conditions? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2), 192.12(c)#
UNGS.CAVERNOPSrecordPage 233UNGS.CAVERNOPS.OMTRAINING.RDo records demonstrate that the Training Program was designed to address normal (routine) operations, abnormal operations, and emergency conditions? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 233UNGS.CAVERNINTEG.IMMONITOR.PIs there a formally written Integrity Monitoring Program in place? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 233UNGS.CAVERNINTEG.IMMONITOR.RDo records demonstrate that the Integrity Monitoring Program has been formally written and implemented? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 233UNGS.CAVERNINTEG.IMAPPROACH.PIs a holistic and comprehensive approach in place for monitoring cavern integrity for design, monitoring, and engineering evaluation? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 233UNGS.CAVERNINTEG.IMAPPROACH.RDo records demonstrate that a holistic and comprehensive approach to cavern system integrity has been undertaken? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 234UNGS.CAVERNINTEG.IMMETHODS.PDoes the process require monitoring of the cavern system to ensure ongoing functional integrity using the monitoring methods listed in RP1170 Section 10.1 Table 1 in the Integrity Monitoring Program? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 234UNGS.CAVERNINTEG.IMMETHODS.RDo records demonstrate that the cavern system is being monitored to ensure ongoing functional integrity? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGobservationPage 234UNGS.CAVERNINTEG.IMMETHODS.ODo field observations verify that the cavern system is being monitored according to procedures and to ensure the continuance of functional integrity? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 234UNGS.CAVERNINTEG.IMPROGCOMP.PDoes the Integrity Monitoring Program include identification of cavern systems components to be monitored? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 234UNGS.CAVERNINTEG.IMPROGCOMP.RDo records demonstrate what cavern systems components need to be monitored per the Integrity Monitoring Program? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 234UNGS.CAVERNINTEG.IMPROGVOL.PDoes the Integrity Monitoring Program require cavern volume and inventory verification? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 234UNGS.CAVERNINTEG.IMPROGVOL.RDo records reflect that cavern volume and inventory verification have been conducted in accordance with the Integrity Monitoring Program? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 234UNGS.CAVERNINTEG.IMMETHODS2.RDo records demonstrate that all of the employed integrity monitoring methods are being conducted/applied according to the Integrity Monitoring Program procedure(s)? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 235UNGS.CAVERNINTEG.IMPROGFREQ.PDoes the Integrity Monitoring Program require a specific monitoring frequency for each integrity monitoring method employed? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 235UNGS.CAVERNINTEG.IMPROGFREQ.RDo records demonstrate that the frequency of cavern integrity monitoring has been followed in accordance with the Integrity Monitoring Program? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 235UNGS.CAVERNINTEG.IMPROGDATA.PDoes the Integrity Monitoring Program require incorporation of data analysis from inspections and reporting? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 235UNGS.CAVERNINTEG.IMPROGDATA.RDo records demonstrate that the data from inspections and reporting has been analyzed and incorporated into the Integrity Monitoring Program? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 235UNGS.CAVERNINTEG.IMPROGRESULTS.PIs there a process in place to archive results of the Integrity Monitoring Program? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 235UNGS.CAVERNINTEG.IMPROGRESULTS.RDo records demonstrate that the results of the Integrity Monitoring Program have been properly archived? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGprocedurePage 235UNGS.CAVERNINTEG.IMPROGEFF.PIs there a process to periodically review the effectiveness of the Integrity Monitoring Program and the monitoring methods employed? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNINTEGrecordPage 235UNGS.CAVERNINTEG.IMPROGEFF.RDo records demonstrate that the Integrity Monitoring Program and the monitoring methods have been reviewed for effectiveness? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNABANDprocedurePage 236UNGS.CAVERNABAND.GASREMOVE.PDoes the cavern abandonment process include the evacuation of natural gas, to the extent practicable, with saturated brine or with raw water? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNABANDrecordPage 236UNGS.CAVERNABAND.GASREMOVE.RDo records demonstrate that the cavern has been evacuated to the maximum practicable extent? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNABANDprocedurePage 236UNGS.CAVERNABAND.MONITOR.PDoes the cavern abandonment process require a long- term monitoring program for cavern wells that are not plugged? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNABANDrecordPage 236UNGS.CAVERNABAND.MONITOR.RDo records demonstrate that a long-term monitoring program was developed and implemented for cavern wells that are not plugged? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNABANDprocedurePage 236UNGS.CAVERNABAND.MONITORPROG.PDoes the long-term monitoring program for abandoned cavern wells follow the criteria of API RP1170, Section 10.3 for integrity monitoring programs? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
UNGS.CAVERNABANDrecordPage 236UNGS.CAVERNABAND.MONITORPROG.RDo records demonstrate that the long-term monitoring program for abandoned cavern wells follows API RP1170, Section 10.3? References: 192.12(a)(3), 192.12(a)(1), 192.12(a)(2)#
SRN.114supplementalPage 236SRN.114.INSPECTCVRG.SWhat are your assets comprised of?#
SRN.114supplementalPage 237SRN.114.GASTRANSPORT.SDo you transport natural gas as a specific commodity (i.e., not a byproduct or constituent of another substance)?#
SRN.114supplementalPage 237SRN.114.DRIVERENGINE.SDo you use natural gas-fueled drivers or engines to compress natural gas?#
SRN.114supplementalPage 237SRN.114.NGUSE.SDo you use natural gas for fuel or power appurtenances or instrument gas on regulated facilities?#
114.114procedurePage 237114.114.COMPRESSOR.PDo the maintenance and operations procedures for compressors include provisions to minimize fugitive natural gas losses?#
114.114procedurePage 237114.114.DRIVERENGINE.PDo maintenance procedures include measures for monitoring and correcting incomplete combustion of natural gas in driver or engine exhausts and taking corrective action if identified?#
114.114procedurePage 237114.114.LKRLSID.PDo procedures provide a methodology for identifying sources of fugitive natural gas emissions in the system?#
114.114procedurePage 237114.114.LKRLSVENT.PDo procedures identify measures for minimizing natural gas release volumes associated with non-emergency venting and blowdowns from operations and maintenance?#
114.114procedurePage 238114.114.LKRLSUNEXPCTVENT.PDo procedures provide for investigation of any unanticipated vented releases of natural gas, and if so, what are the associated actions?#
114.114procedurePage 238114.114.LKRLSLKDATA.PDo procedures include a methodology to collect, retain and analyze detailed information from detected natural gas leaks, including those eliminated by lubrication, adjustment, tightening or otherwise below thresholds for regulatory reporting?#
114.114procedurePage 238114.114.LKRLSDETECTLK.PDo procedures include instructions for personnel to detect leaks to help further reduce emission in stations and along the right of way?#
114.114procedurePage 238114.114.LKMITGRPRREPAIR.PDo procedures provide alternatives to cutouts (to reduce emissions)?#
114.114procedurePage 238114.114.TESTESD.PDo procedures contain measures for ensuring ESD testing minimizes natural gas releases?#
114.114procedurePage 238114.114.TESTRELIEFVLV.PDo relief valve testing procedures include measures to minimize natural gas releases?#
114.114procedurePage 238114.114.FLARE.PDo procedures for flaring from pipeline facilities for transporting natural gas include measures for minimization of natural gas emissions?#
114.114procedurePage 239114.114.GNLDSGNCNFG.PDo operation and maintenance procedures contain mechanisms for identifying potential design/configuration changes for reducing natural gas releases?#
114.114procedurePage 239114.114.GNLCMPSTATION.PDo procedures contain mechanisms for minimizing natural gas emissions from operations and maintenance activities within a compressor station (i.e., beyond compressor/driver-specific procedures)?#
114.LEAKPRONEprocedurePage 239114.LEAKPRONE.LKRLS.PWhat procedures are in place to monitor for and identify pipe segments that are leak-prone, and what criteria (e.g., frequency of leak or failure events) are specified for determining a pipeline segment is leak- prone?#
114.LEAKPRONEprocedurePage 239114.LEAKPRONE.LKRLSLKDATA.PDo procedures include a methodology to collect, retain and analyze detailed information from detected leaks, including those eliminated by lubrication, adjustment, tightening or otherwise below thresholds for regulatory reporting?#
114.LEAKPRONEprocedurePage 239114.LEAKPRONE.LKMITGRPREXAMPLE.PDo procedures identify cast iron, unprotected steel, wrought iron, and vintage plastic pipe with known leak issues?#
114.LEAKPRONEprocedurePage 239114.LEAKPRONE.LKMITGRPROTHER.PDo procedures clearly define a process to address replacement or remediation of pipe segments with known leak issues beyond those specifically identified in Section 114?#
SRN.114supplementalPage 240SRN.114.INSPECTCVRG.SWhat are your assets comprised of?#
SRN.114supplementalPage 240SRN.114.GASTRANSPORT.SDo you transport natural gas as a specific commodity (i.e., not a byproduct or constituent of another substance)?#
SRN.114supplementalPage 240SRN.114.DRIVERENGINE.SDo you use natural gas-fueled drivers or engines to compress natural gas?#
SRN.114supplementalPage 240SRN.114.NGUSE.SDo you use natural gas for fuel or power appurtenances or instrument gas on regulated facilities?#
114.114procedurePage 240114.114.COMPRESSOR.PDo the maintenance and operations procedures for compressors include provisions to minimize fugitive natural gas losses?#
114.114procedurePage 240114.114.DRIVERENGINE.PDo maintenance procedures include measures for monitoring and correcting incomplete combustion of natural gas in driver or engine exhausts and taking corrective action if identified?#
114.114procedurePage 240114.114.LKRLSVENT.PDo procedures identify measures for minimizing natural gas release volumes associated with non-emergency venting and blowdowns from operations and maintenance?#
114.114procedurePage 241114.114.LKRLSUNEXPCTVENT.PDo procedures provide for investigation of any unanticipated vented releases of natural gas, and if so, what are the associated actions?#
114.114procedurePage 241114.114.LKRLSLKDATA.PDo procedures include a methodology to collect, retain and analyze detailed information from detected natural gas leaks, including those eliminated by lubrication, adjustment, tightening or otherwise below thresholds for regulatory reporting?#
114.114procedurePage 241114.114.LKRLSWELLHD.PDo procedures provide for periodic leakage surveys around the wellhead?#
114.114procedurePage 241114.114.LKRLSANN.PDo procedures provide for periodic checking of wellhead annuluses for indications of leaks (e.g., unexplained pressure variations)?#
114.114procedurePage 241114.114.LKRLSFIELD.PDo procedures provide for leak surveys for well casing containment or geologic issues?#
114.114procedurePage 241114.114.TESTRELIEFVLV.PDo relief valve testing procedures include measures to minimize natural gas releases?#
114.114procedurePage 241114.114.GNLDSGNCNFG.PDo operation and maintenance procedures contain mechanisms for identifying potential design/configuration changes for reducing natural gas releases?#
114.LEAKPRONEprocedurePage 242114.LEAKPRONE.LKRLS.PWhat procedures are in place to monitor for and identify pipe segments that are leak-prone, and what criteria (e.g., frequency of leak or failure events) are specified for determining a pipeline segment is leak- prone?#
114.LEAKPRONEprocedurePage 242114.LEAKPRONE.LKRLSLKDATA.PDo procedures include a methodology to collect, retain and analyze detailed information from detected leaks, including those eliminated by lubrication, adjustment, tightening or otherwise below thresholds for regulatory reporting?#
114.LEAKPRONEprocedurePage 242114.LEAKPRONE.LKMITGRPREXAMPLE.PDo procedures identify cast iron, unprotected steel, wrought iron, and vintage plastic pipe with known leak issues?#
114.LEAKPRONEprocedurePage 242114.LEAKPRONE.LKMITGRPROTHER.PDo procedures clearly define a process to address replacement or remediation of pipe segments with known leak issues beyond those specifically identified in Section 114?#
SRN.114supplementalPage 242SRN.114.INSPECTCVRG.SWhat are your assets comprised of?#
SRN.114supplementalPage 242SRN.114.GASTRANSPORT.SDo you transport natural gas as a specific commodity (i.e., not a byproduct or constituent of another substance)?#
SRN.114supplementalPage 243SRN.114.DRIVERENGINE.SDo you use natural gas-fueled drivers or engines to compress natural gas?#
SRN.114supplementalPage 243SRN.114.NGUSE.SDo you use natural gas for fuel or power appurtenances or instrument gas on regulated facilities?#
114.114procedurePage 243114.114.COMPRESSOR.PDo the maintenance and operations procedures for compressors include provisions to minimize fugitive natural gas losses?#
114.114procedurePage 243114.114.DRIVERENGINE.PDo maintenance procedures include measures for monitoring and correcting incomplete combustion of natural gas in driver or engine exhausts and taking corrective action if identified?#
114.114procedurePage 243114.114.LKRLSID.PDo procedures provide a methodology for identifying sources of fugitive natural gas emissions in the system?#
114.114procedurePage 243114.114.LKRLSVENT.PDo procedures identify measures for minimizing natural gas release volumes associated with non-emergency venting and blowdowns from operations and maintenance?#
114.114procedurePage 243114.114.LKRLSUNEXPCTVENT.PDo procedures provide for investigation of any unanticipated vented releases of natural gas, and if so, what are the associated actions?#
114.114procedurePage 244114.114.LKRLSLKDATA.PDo procedures include a methodology to collect, retain and analyze detailed information from detected natural gas leaks, including those eliminated by lubrication, adjustment, tightening or otherwise below thresholds for regulatory reporting?#
114.114procedurePage 244114.114.TESTESD.PDo procedures contain measures for ensuring ESD testing minimizes natural gas releases?#
114.114procedurePage 244114.114.TESTRELIEFVLV.PDo relief valve testing procedures include measures to minimize natural gas releases?#
114.114procedurePage 244114.114.FLARE.PDo procedures for flaring from pipeline facilities for transporting natural gas include measures for minimization of natural gas emissions?#
114.114procedurePage 244114.114.GNLDSGNCNFG.PDo operation and maintenance procedures contain mechanisms for identifying potential design/configuration changes for reducing natural gas releases?#
114.114procedurePage 244114.114.GNLCMPSTATION.PDo procedures contain mechanisms for minimizing natural gas emissions from operations and maintenance activities within a compressor station (i.e., beyond compressor/driver-specific procedures)?#
114.LEAKPRONEprocedurePage 244114.LEAKPRONE.LKRLS.PWhat procedures are in place to monitor for and identify pipe segments that are leak-prone, and what criteria (e.g., frequency of leak or failure events) are specified for determining a pipeline segment is leak- prone?#
114.LEAKPRONEprocedurePage 245114.LEAKPRONE.LKRLSLKDATA.PDo procedures include a methodology to collect, retain and analyze detailed information from detected leaks, including those eliminated by lubrication, adjustment, tightening or otherwise below thresholds for regulatory reporting?#
114.LEAKPRONEprocedurePage 245114.LEAKPRONE.LKMITGRPREXAMPLE.PDo procedures identify cast iron, unprotected steel, wrought iron, and vintage plastic pipe with known leak issues?#
114.LEAKPRONEprocedurePage 245114.LEAKPRONE.LKMITGRPROTHER.PDo procedures clearly define a process to address replacement or remediation of pipe segments with known leak issues beyond those specifically identified in Section 114?#
GENERIC.GENERICSPprocedurePage 245GENERIC.GENERICSP.GENPROCEDURE.PGeneric Question - Special Permit Generic question - please provide context in result notes.#
GENERIC.GENERICSPrecordPage 245GENERIC.GENERICSP.GENRECORD.RGeneric Question Generic question - please provide context in result notes.#
GENERIC.GENERICSPobservationPage 245GENERIC.GENERICSP.GENOBSERVE.OGeneric Question Generic question - please provide context in result notes.#
GENERIC.GENERICprocedurePage 245GENERIC.GENERIC.GENPROCEDURE.PGeneric Question Generic question - please provide context in result notes.#
GENERIC.GENERICrecordPage 246GENERIC.GENERIC.GENRECORD.RGeneric Question Generic question - please provide context in result notes.#
GENERIC.GENERICobservationPage 246GENERIC.GENERIC.GENOBSERVE.OGeneric Question Generic question - please provide context in result notes.#
This material provides agency context. It does not replace binding regulatory text, and its legal effect depends on the underlying authority and facts.