CPF 420205003W
CPF 420205003W
420205003W_Warning Letter_01132020_text.pdf, page 1Official PDFWARNING LETTER CERTIFIED MAIL - RETURN RECEIPT REQUESTED January 13, 2020 Allen Satterwhite President Chevron Pipeline Company 1400 Smith Street Houston, Texas 77002 CPF 4-2020-5003W Dear Mr. Satterwhite: From September 23, 2019 to September 26, 2019, representatives of the Pipeline and Hazardous Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.) inspected your Control Center in Houston, Texas. As a result of the inspection, it is alleged that you have committed a probable violation of the Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The item inspected and the probable violation is: 1. §195.446 Control room management. (d) Fatigue mitigation. Each operator must implement the following methods to reduce the risk associated with controller fatigue that could inhibit a controller's ability to carry out the roles and responsibilities the operator has defined: (3) Train controllers and supervisors to recognize the effects of fatigue. Chevron failed to fully train their controllers to recognize the effects of fatigue in 2018. Chevron provided PHMSA inspectors with its fatigue training records for 2017-2019. The inspectors noted that four controllers had failed to complete one of their two required training courses in 2018.#
420205003W_Warning Letter_01132020_text.pdf, page 2Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed $218,647 per violation per day the violation persists, up to a maximum of $2,186,465 for a related series of violations. For violation occurring on or after November 27, 2018 and before July 31, 2019, the maximum penalty may not exceed $213,268 per violation per day, with a maximum penalty not to exceed $2,132,679. For violation occurring on or after November 2, 2015 and before November 27, 2018, the maximum penalty may not exceed $209,002 per violation per day, with a maximum penalty not to exceed $2,090,022. For violations occurring prior to November 2, 2015, the maximum penalty may not exceed $200,000 per violation per day, with a maximum penalty not to exceed $2,000,000 for a related series of violations. We have reviewed the circumstances and supporting documents involved in this case, and have decided not to conduct additional enforcement action or penalty assessment proceedings at this time. We advise you to correct the item identified in this letter. Failure to do so will result in Chevron Pipeline Co being subject to additional enforcement action. No reply to this letter is required. If you choose to reply, in your correspondence please refer to CPF 4-2020-5003W. Be advised that all material you submit in response to this enforcement action is subject to being made publicly available. If you believe that any portion of your responsive material qualifies for confidential treatment under 5 U.S.C. 552(b), along with the complete original document you must provide a second copy of the document with the portions you believe qualify for confidential treatment redacted and an explanation of why you believe the redacted information qualifies for confidential treatment under 5 U.S.C. 552(b). Sincerely, Mary L. McDaniel, P.E. Director, Southwest Region Pipeline and Hazardous Materials Safety Administration 2#
This material provides agency context. It does not replace binding regulatory text, and its legal effect depends on the underlying authority and facts.