PHMSA 19-152443
EXXONMOBIL PIPELINE COMPANY LLC — Integrity Assurance Notification
REPAIRExxonMobil Pipeline Company (EMPCo) is making notification to PHMSA of one (1), sixty day repair condition that will not be remediated within the 195.452(h)(4)(ii) schedule. The condition is located on the 6-inch PCU to Stratton Ridge testable segment, at approximate station number 1249+46, located in Harris County under South Texas Avenue. The 6 inch PCU to Stratton Ridge Testable Segment is 62.8 miles in length.Per 49 CFR 195.452(h)(3), an operator must notify PHMSA if it cannot meet the repair schedule and "justify the reasons why it cannot meet the schedule and that the changed schedule will not jeopardize public safety or environmental protection".On July 12, 2018 EMPCo ran a combination DEF/MFL ILI Tool. EMPCo met discovery on January 4, 2019 and this 60 day repair is the first feature on the current repair plan. This feature was called as a 4.17%OD (0.276” deep) top dent at odometer 117,128.86 ft.Due to delays related to permitting and given that the feature is under a public road, this feature will not be repaired prior to the 60 day deadline.#