PHMSA 22-252987
DAYLIGHT PETROLEUM LLC — Integrity Assurance Notification
START/END POINT DELAY ONSHOREThis letter is to serve as Daylight Petroleum, LLC’s notice of request for an alternative compliance deadline, as is outlined in Title 49 CFR Part 192.18, and is requesting an extension from November 16, 2022 to February 28, 2023 to complete and report Type C Gathering Designations for submission of our Annual Report by March 15, 2023. Daylight Petroleum has made significant progress effectively mapping all of our pipeline assets for the purpose of complying with the new Type C and Type R Gathering Requirements. Currently, we have completed mapping and validating approximately 80 percent of the pipeline mileage in Texas and 100 percent of Oklahoma pipelines. We are just beginning assessing our Louisiana Asset. Daylight Petroleum’s HS&E Manager, who was the designated lead project manager and coordinator for this project, resigned on July 22, 2022. We are now beginning the hiring process to reassign this project. As a result, we are experiencing schedule slippage.#