TEXAS EASTERN TRANSMISSION, LP — Integrity Assurance Notification
RMV INSTALLATION DELAY REPLACEDAs allowed under 49 CFR §192.179(f), Texas Eastern Transmission, LP (TETLP) is requesting a one-year extension of the compliance deadline for installation of RMVs on the Bernville to Bechtelsville segment due to the compliance deadline being economically, technically, or operationally infeasible. Lines 12 and 19 of the Bernville to Bechtelsville segment of TETLP, located in Berks County, PA, transport natural gas to the northeast. A Class Location change from Class 2 to Class 3 occurred on August 14th, 2024, requiring pipe replacement to confirm the MAOP. The compliance deadline to confirm the MAOP is August 13th, 2026#