CHEVRON PIPE LINE CO — Integrity Assurance Notification
Current as of 2003-03-25 Government source
Pipeline and Hazardous Materials Safety AdministrationOfficial agency material
View source REPAIRRepairs delayed one year due to permitting and severe storms 36 anomalies meeting repair criteria in 195.452(h) found by ILI on three parallel pipelines (12-inch and 2 6-inch). MOP reduced 17 percent. Repairs delayed, initially by permitting and then by Tropical Storms and Hurricane Lili. Storm delay resulted in need to re-permit. 20 percent reduction in operating pressure taken when 365-day limit expired on first pressure reduction.#