IN NG Program Evaluation, 2016, page 1Official PDF1200 New Jersey Avenue SE Washington DC 20590 U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration 2016 Gas State Program Evaluation for INDIANA UTILITY REGULATORY COMMISSION Document Legend PART: O -- Representative Date and Title Information A -- Progress Report and Program Documentation Review B -- Program Inspection Procedures C -- Program Performance D -- Compliance Activities E -- Incident Investigations F -- Damage Prevention G -- Field Inspections H -- Interstate Agent State (If Applicable) I -- 60106 Agreement State (If Applicable) DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 1#
IN NG Program Evaluation, 2016, page 22016 Gas State Program Evaluation -- CY 2016 Gas State Agency: Indiana Rating: Agency Status: Date of Visit: 08/17/2017 - 08/25/2017 Agency Representative: Steve Allen, Director, & Bill Boyd, Division Manager PHMSA Representative: Patrick Gaume Commission Chairman to whom follow up letter is to be sent: Name/Title: James D. Atterholt, Chairman Agency: Indiana Utility Regulatory Commission Address: 101 West Washington Street, Suite 1500 East City/State/Zip: Indianapolis, Indiana 46204-3407 60105(a): Yes 60106(a): No Interstate Agent: No INSTRUCTIONS: Complete this evaluation in accordance with the Procedures for Evaluating State Pipeline Safety Program. The evaluation should generally reflect state program performance during CY 2016 (not the status of performance at the time of the evaluation). All items for which criteria have not been established should be answered based on the PHMSA representative's judgment. A deficiency in any one part of a multiple part question should be scored as needs improvement. Determine the answer to the question then select the appropriate point value. If a state receives less then the maximum points, include a brief explanation in the space provided for general comments/regional observations. If a question is not applicable to a state, select NA. Please ensure all responses are COMPLETE and ACCURATE, and OBJECTIVELY reflect state program performance. Increasing emphasis is being placed on performance. This evaluation together with selected factors reported in the state's annual progress report attachments provide the basis for determining the state's pipeline safety grant allocation. Field Inspection (PART G): The field inspection form used will allow different areas of emphasis to be considered for each question. Question 13 is provided for scoring field observation areas. In completing PART G, the PHMSA representative should include a written summary which thoroughly documents the inspection. Scoring Summary PARTS Possible Points Points Scored A Progress Report and Program Documentation Review 10 10 B Program Inspection Procedures 13 13 C Program Performance 49 49 D Compliance Activities 15 15 E Incident Investigations 11 11 F Damage Prevention 8 8 G Field Inspections 12 12 H Interstate Agent State (If Applicable) 0 0 I 60106 Agreement State (If Applicable) 0 0 TOTALS 118 118 State Rating................................................................................................................................................... 100.0 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 2#
IN NG Program Evaluation, 2016, page 3PART A - Progress Report and Program Documentation Review Points(MAX) Score 1 Accuracy of Jurisdictional Authority and Operator/Inspection Units Data - Progress Report Attachment 1 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: A1. Yes. Attachment 1 is consistent with internal records & with Attachments 3 and 8. 1 1 2 Review of Inspection Days for accuracy - Progress Report Attachment 2 1 1 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: A2. Yes. Attachment 2 is consistent with internal records (two databases that were exported to a spreadsheet & checked for discrepancies). 3 Accuracy verification of Operators and Operators Inspection Units in State - Progress Report Attachment 3 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: A3. Yes. Attachment 3 is consistent with internal records. 1 1 4 Were all federally reportable incident reports listed and information correct? - Progress Report Attachment 4 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: A4. Yes. Attachment 4 is correct and agrees with DataMart. 1 1 5 Accuracy verification of Compliance Activities - Progress Report Attachment 5 1 1 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: A5. Yes. Attachment 5 is consistent with internal records. 6 Were pipeline program files well-organized and accessible? - Progress Report 2 2 Attachment 6 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: A6. Yes. All records in Attachment 6 are now electronic, but several of these records also have paper files. The paper files are becoming archives. Recommendation: re-label the Records listed in Attachment 6 to better align with the way the Division is now keeping the files electronically. 7 Was employee listing and completed training accurate and complete? - Progress Report Attachment 7 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: A7. Yes. Attachment 7 appears to be consistent with internal records. 1 1 8 Verification of Part 192,193,198,199 Rules and Amendments - Progress Report Attachment 8 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: A8. Yes. Attachment 8 is consistent with IN Law. 1 1 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 3#
IN NG Program Evaluation, 2016, page 49 List of Planned Performance - Did state describe accomplishments on Progress Report in detail - Progress Report Attachment 10 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 1 A9. Yes. Attachment 10 is a well-developed report. 10 General Comments: Info Only Info Only Info Only = No Points Evaluator Notes: A10. Yes. The IURC has done well in regards to documenting and tracking its inspection activities for annual reporting purposes. The 2016 Annual Progress Report was complete and accurate. The agency's new CRM platform appears to have enhanced the IURC's abilities to efficiently report on and track pipeline safety data and information. Also, in Attachment 10 of the Annual Progress Report (Performance and Damage Prevention Questions), it is clear the IURC has a strong Damage Prevention Program. Total points scored for this section: 10 Total possible points for this section: 10 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 4#
IN NG Program Evaluation, 2016, page 5PART B - Program Inspection Procedures Points(MAX) Score 1 Standard Inspection procedures should give guidance to state inspectors that insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: 2 2 B1. Yes. Inspection procedures including risk model, selection, assignment, pre-inspection, inspection, post inspection, write up, violation handling & closing for all types of inspections are described in Sections V & VI of the program manual. 2 IMP and DIMP Inspection procedures should give guidance to state inspectors that insure 1 1 consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: B2. Yes. Inspection procedures including risk model, selection, assignment, pre-inspection, inspection, post inspection, write up, violation handling & closing for all types of inspections are described in Sections V & VI of the program manual. 3 OQ Inspection procedures should give guidance to state inspectors that insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 1 B3. Yes. Inspection procedures including risk model, selection, assignment, pre-inspection, inspection, post inspection, write up, violation handling & closing for all types of inspections are described in Sections V & VI of the program manual. 4 Damage Prevention Inspection procedures should give guidance to state inspectors that 1 1 insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post- inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: B4. Yes. Inspection procedures including risk model, selection, assignment, pre-inspection, inspection, post inspection, write up, violation handling & closing for all types of inspections are described in Sections V & VI of the program manual. In addition, IURC has developed a Damage Prevention Inspection Form which is used as an addendum to the standard inspection form and expands the Damage Prevention review. 5 Any operator training conducted should be outlined and appropriately documented as needed. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: B5. Yes. Operator Training is addressed in Section V of the program manual under its own sub-heading. 1 1 6 Construction Inspection procedures should give guidance to state inspectors that insure 1 1 consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: B6. Yes. Inspection procedures including risk model, selection, assignment, pre-inspection, inspection, post inspection, write up, violation handling & closing for all types of inspections are described in Sections V & VI of the program manual. Construction Inspection is addressed in Section V of the program manual under its own sub-heading. DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 5#
IN NG Program Evaluation, 2016, page 67 Does inspection plan address inspection priorities of each operator, and if necessary each 6 6 unit, based on the following elements? Yes = 6 No = 0 Needs Improvement = 1-5 a. Length of time since last inspection (Within five year interval) Yes No Needs Improvement b. Operating history of operator/unit and/or location (includes leakage, incident and compliance activities) Yes No Needs Improvement c. Type of activity being undertaken by operators (i.e. construction) Yes No Needs Improvement d. Locations of operators inspection units being inspected - (HCA's, Geographic areas, Population Density, etc) Yes No Needs Improvement e. Process to identify high-risk inspection units that includes all threats - (Excavation Damage, Corrosion, Natural Forces, Outside Forces, Material and Welds, Equipment, Yes No Needs Improvement Operators and any Other Factors) f. Are inspection units broken down appropriately? Yes No Needs Improvement Evaluator Notes: B7. Yes. See Section IV of the program manual, specifically the sub-heading, "Data-Driven Risk Model and subsequent Inspection Plan". 8 General Comments: Info Only Info Only Info Only = No Points Evaluator Notes: B8. Yes. The IURC's operating procedures manual provides acceptable guidance and documentation for their program. Implementation of the agency's new Information Technology platform led to updates to the procedures which adequately demonstrate the divisions current processes. The program's data-driven risk model, which drives the annual Inspection Plan, is well established and is effective in determining the relative risk associated with operators and their corresponding inspection units. Total points scored for this section: 13 Total possible points for this section: 13 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 6#
IN NG Program Evaluation, 2016, page 7PART C - Program Performance Points(MAX) Score 1 Was ratio of Total Inspection person-days to total person days acceptable? (Director of State Programs may modify with just cause) Chapter 4.3 Yes = 5 No = 0 A. Total Inspection Person Days (Attachment 2): 832.00 B. Total Inspection Person Days Charged to the Program (220 X Inspection Person Years) (Attachment 7): 220 X 8.62 = 1895.30 Ratio: A / B 832.00 / 1895.30 = 0.44 If Ratio >= 0.38 Then Points = 5, If Ratio < 0.38 Then Points = 0 Points = 5 Evaluator Notes: C1. Yes. 832 AFOD, 8.62 inspector-years, 832/(8.62*220)=.439, >.38, okay. 5 5 2 Has each inspector and program manager fulfilled the T Q Training Requirements? (See 5 5 Guidelines Appendix C for requirements) Chapter 4.4 Yes = 5 No = 0 Needs Improvement = 1-4 a. Completion of Required OQ Training before conducting inspection as lead? Yes No Needs Improvement b. Completion of Required DIMP*/IMP Training before conducting inspection as lead? *Effective Evaluation CY2013 Yes No Needs Improvement c. Root Cause Training by at least one inspector/program manager Yes No Needs Improvement d. Note any outside training completed Yes No Needs Improvement e. Verify inspector has obtained minimum qualifications to lead any applicable standard inspection as the lead inspector. Yes No Needs Improvement Evaluator Notes: C2. Yes. All inspectors with 3+ years have completed their training, including Standard, OQ, & DIMP. Some inspectors are qualified to lead TIMP. New inspectors are in the training cycle. Five inspectors have Root Cause Training. All Inspectors attend one of the Purdue NACE corrosion courses annually. Only qualified inspectors serve as the Lead. 3 Did state records and discussions with state pipeline safety program manager indicate adequate knowledge of PHMSA program and regulations? Chapter 4.1,8.1 Yes = 2 No = 0 Needs Improvement = 1 2 2 Evaluator Notes: C3. Yes. Steve & Bill make a great tag team! They are running a fine program. They show great knowledge. 4 Did state respond to Chairman's letter on previous evaluation within 60 days and correct 2 2 or address any noted deficiencies? (If necessary) Chapter 8.1 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: C4. Yes. The Chairman letter was 10/25/2016, the Chairman response was 12/8/2016. The response addressed the three items of concern. 5 Did State conduct or participate in pipeline safety training session or seminar in Past 3 Years? Chapter 8.5 Yes = 1 No = 0 Evaluator Notes: C5. Yes, in June of 2015. Practice was for every other year. One is scheduled for 2018. 1 1 6 Did state inspect all types of operators and inspection units in accordance with time intervals established in written procedures? Chapter 5.1 Yes = 5 No = 0 Needs Improvement = 1-4 5 5 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 7#
IN NG Program Evaluation, 2016, page 8Evaluator Notes: C6. Yes. Reviewed for Standard, LIMP, GIMP, DIMP, PAPEI, CRM, & OQ; All okay. 7 Did inspection form(s) cover all applicable code requirements addressed on Federal 2 2 Inspection form(s)? Did State complete all applicable portions of inspection forms? Chapter 5.1 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: C7. Yes. Reviewed 8 inspections, most of which had NOPV, and found them to be in order. I strongly recommend that PHMSA Form 11 be used in future significant incident/accident investigations as it is more complete than what IURC is currently using. Inspections reviewed were: #10071, 9901, 10055, 10076, 9601, 10058, 10067, & 9454. 8 Did the state review operator procedures for determining if exposed cast iron pipe was examined for evidence of graphitization and if necessary remedial action was taken? (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: 1 1 C8. Yes. it is on the Std Insp Form #2, Part 192.489 (b), & in the IA Corrosion module, question 27 in Procedures. 9 Did the state review operator procedures for surveillance of cast iron pipelines, including 1 1 appropriate action resulting from tracking circumferential cracking failures, study of leakage history, or other unusual operating maintenance condition? (Note: See GPTC Appendix G-18 for guidance) (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: C9. Yes. it is on the Std Insp Form- #2; pg 4 Part 192.613(a), & in the IA Distr O&M module, question 1 in Continuing Surveillance. 10 Did the state review operator emergency response procedures for leaks caused by 1 1 excavation damage near buildings and determine whether the procedures adequately address the possibility of multiple leaks and underground migration of gas into nearby buildings Refer to 4/12/01 letter from PHMSA in response to NTSB recommendation P-00-20 and P-00-21? (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: C10. Yes. it is on the Std Insp Form- #2; pg 4 Part 192.615 (a) (7), & in the IA Distr O&M module, question 8, pg 8, in Emergency Response. 11 Did the state review operator records of previous accidents and failures including 1 1 reported third party damage and leak response to ensure appropriate operator response as required by 192.617? Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: C11. Yes. It is on the Std Insp Form- #2; pg 6 of 26 Part 192.617, & in the IA Distr O&M module, question 2, pg 9, in Failure Investigation. 12 Has the state reviewed Operator Annual reports, along with Incident/Accident reports, for accuracy and analyzed data for trends and operator issues? Yes = 2 No = 0 Needs Improvement = 1 2 2 Evaluator Notes: C12. Yes. The annual reports are scored against a checklist, and data from the annual reports is used in the Risk Model. 13 DUNS: 086329518 2016 Gas State Program Evaluation Did state input all applicable OQ, DIMP/IMP inspection results into federal database in a timely manner? This includes replies to Operator notifications into IMDB database. Chapter 5.1 Yes = 2 No = 0 Needs Improvement = 1 2 2 Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 8#
IN NG Program Evaluation, 2016, page 9Evaluator Notes: C13. Yes, the OQ, GIMP, DIMP, & LIMP databases were reviewed and are properly populated. 14 Has state confirmed intrastate transmission operators have submitted information into NPMS database along with changes made after original submission? Yes = 1 No = 0 Needs Improvement = .5 1 1 Evaluator Notes: C14. Yes. Annual report mileage is compared to NPMS mileage for all transmission operators as an annual exercise. 15 Is the state verifying operators are conducting drug and alcohol tests as required by regulations? This should include verifying positive tests are responded to in accordance with program. 49 CFR 199 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: 2 2 C15. Yes. All operators receive the long form and/or short form D&A inspection within the inspection interval. 16 Is state verifying operators OQ programs are up to date? This should include verification of any plan updates and that persons performing covered tasks (including contractors) are properly qualified and requalified at intervals determined in the operators plan. 49 CFR 192 Part N Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: C16. Yes. Full OQ re-inspections are current; OQ Field inspections are part of most Standard Inspections. 2 2 17 Is state verifying operator's gas transmission integrity management programs (IMP) are 2 2 up to date? This should include a previous review of IMP plan, along with monitoring progress on operator tests and remedial actions. In addition, the review should take in to account program review and updates of operators plan(s). (Are the State's largest operators programs being contacted or reviewed annually?). 49 CFR 192 Subpart 0 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: C17. Yes. The GIMP, LIMP, & DIMP re-inspections are current, HCA and new constructions are investigated relative to IMP during most standard inspections. 18 Is state verifying operator's gas distribution integrity management Programs (DIMP)? 2 2 This should include a review of DIMP plans, along with monitoring progress. In addition, the review should take in to account program review and updates of operators plan(s). (Are the State's largest operators programs being contacted or reviewed annually?). 49 CFR 192 Subpart P DIMP ? First round of program inspections should have been complete by December 2014 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: C18. Yes. The DIMP inspections are current, and new constructions are investigated relative to DIMP during most standard inspections 19 Is state verifying operators Public Awareness programs are up to date and being 2 2 followed. State should also verify operators have evaluated Public Awareness programs for effectiveness as described in RP1162. PAPEI Effectiveness Inspections should have been completed by December 2013. PAPEI Effectiveness Inspections should be conducted every four years by operators. 49 CFR 192.616 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: C19. Yes. The PAPEI inspections were finished in 2013, and Public Awareness is touched on during all Standard Inspections. DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 9#
IN NG Program Evaluation, 2016, page 1020 Does the state have a mechanism for communicating with stakeholders - other than state 1 1 pipeline safety seminar? (This should include making enforcement cases available to public). Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: C20. Yes, bi-annual TQ Safety Seminars, email announcements as appropriate, ad hoc & inspection training, MM training seminars, Participation in Indiana Damage Prevention Councils, Participation in the Indiana 811 Association, Participation in the Indiana Pipeline Awareness Association, and has a website for information for all stakeholders. 21 Did state execute appropriate follow-up actions to Safety Related Condition (SRC) Reports? Chapter 6.3 Yes = 1 No = 0 Needs Improvement = .5 1 1 Evaluator Notes: C21. Yes. There were two SRC reported in 2016; reports 20160076 & 20160146. Both were repaired and reported closed in a timely manner. IURC contacts were Dan Novak & Howard Friend for #20160076, and was Bill Boyd for #20160146. 22 Did the State ask Operators to identify any plastic pipe and components that has shown a 1 1 record of defects/leaks and what those operators are doing to mitigate the safety concerns? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: C22. Yes. Aldyl is a Question on the form, conducted during DIMP inspections. That question drives a conversation about other PE pipe. 23 Did the state participate in/respond to surveys or information requests from NAPSR or PHMSA? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: C23. Yes. IURC responds to all NAPSR requests. 1 1 24 If the State has issued any waivers/special permits for any operator, has the state verified conditions of those waivers/special permits are being met? This should include having the operator amend procedures where appropriate. No = 0 Needs Improvement = .5 Yes = 1 Evaluator Notes: 1 1 C24. Yes, a time limit waiver that was issued in 2013 for an extension to 12/31/2013, and is no longer applicable. 25 Did the state attend the National NAPSR Board of Directors Meeting in CY being evaluated? No = 0 Needs Improvement = .5 Yes = 1 Evaluator Notes: C25. Yes. Steve & Bill attended Nat'l NAPSR, and Steve became Past Chairman of the NAPSR Board. 1 1 26 Discussion on State Program Performance Metrics found on Stakeholder Communication 2 2 site - http://primis.phmsa.dot.gov/comm/states.htm No = 0 Needs Improvement = 1 Yes = 2 a. Discussion of Potential Accelerated Actions (AA's) based on any negative trends Yes No Needs Improvement b. NTSB P-11-20 Meaningful Metrics Yes No Needs Improvement Evaluator Notes: C26. Yes. The metrics are reviewed. This information is also available from Annual Reports. The graphs are helpful. There are no negative trends that can't be readily explained. Actually, improvements are being seen. Several of the metrics are fed into the inspection risk model and influence who is visited more frequently and which inspection will be done. NTSB P-11-20 Meaningful Metrics has been read and understood, and IURC supports using these metrics as a monitoring and risking resource. DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 10#
IN NG Program Evaluation, 2016, page 1127 Discussion with State on accuracy of inspection day information submitted into State Info Only Info Only Inspection Day Calculation Tool. (No points) Info Only = No Points Evaluator Notes: C27. The SCIT exercise was worthwhile. The SCIT predicted what IURC does pretty well, even better than expected. The iterative process will only require minor tweaks. 28 Did the State verify Operators took appropriate action regarding Pipeline Flow Reversals, Info Only Info Only Product Changes and Conversions to Service? See ADP-2014-04 (No Points) Info Only = No Points Evaluator Notes: C28. NA. No operators in Indiana had flow reversals in 2016, nor are any expected soon. IURC has notified operators to consider and model effects of flow reversals when such activities are planned. 29 General Comments: Info Only Info Only Info Only = No Points Evaluator Notes: C29. Yes. The IURC has developed a detailed risk model as well as a system for tracking and scheduling inspections. The overall number of inspection days completed by the IURC was acceptable based on the number of dedicated pipeline safety inspection staff and the number of operators, miles of main and number of services within the state. The agency's new IT platform has provided the division with a good method for tracking inspection activities as well as inspection related data and documentation Total points scored for this section: 49 Total possible points for this section: 49 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 11#
IN NG Program Evaluation, 2016, page 12PART D - Compliance Activities Points(MAX) Score 1 Does the state have written procedures to identify steps to be taken from the discovery to 4 4 resolution of a probable violation? Chapter 5.1 Yes = 4 No = 0 Needs Improvement = 1-3 a. Procedures to notify an operator (company officer) when a noncompliance is identified Yes No Needs Improvement b. Procedures to routinely review progress of compliance actions to prevent delays or breakdowns Yes No Needs Improvement c. Procedures regarding closing outstanding probable violations Yes No Needs Improvement Evaluator Notes: D1. Yes. See Section VI in the Program Manual. 2 Did the state follow compliance procedures (from discovery to resolution) and adequately 4 4 document all probable violations, including what resolution or further course of action is needed to gain compliance? Chapter 5.1 Yes = 4 No = 0 Needs Improvement = 1-3 a. Were compliance actions sent to company officer or manager/board member if municipal/government system? Yes No Needs Improvement b. Document probable violations Yes No Needs Improvement c. Resolve probable violations Yes No Needs Improvement d. Routinely review progress of probable violations Yes No Needs Improvement e. Were applicable civil penalties outlined in correspondence with operator(s) Yes No Needs Improvement Evaluator Notes: D2. Yes. The process as described in Section VI is used every time. 3 Did the state issue compliance actions for all probable violations discovered? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: D3. Yes. The violations found were identified in the violation letters. 2 2 4 Did compliance actions give reasonable due process to all parties? Including "show cause" hearing if necessary. Yes = 2 No = 0 Evaluator Notes: D4. Yes. Due process is given to all. 2 2 5 Is the program manager familiar with state process for imposing civil penalties? Were civil penalties considered for repeat violations (with severity consideration) or violations resulting in incidents/accidents? (describe any actions taken) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: D5. Yes. IURC has developed a matrix for fine assessment. 2 2 6 Can the State demonstrate it is using their enforcement fining authority for pipeline safety violations? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: D6. Yes. Assessed $180,000 fine in CY2013, and assessed a $900,000 fine in early CY2017. 1 1 7 General Comments: Info Only = No Points DUNS: 086329518 2016 Gas State Program Evaluation Info Only Info Only Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 12#
IN NG Program Evaluation, 2016, page 13Evaluator Notes: D7. Yes. The IURC has demonstrated the use of several types enforcement methods to ensure operator compliance with pipeline safety regulations. The IURC works in collaboration with operators to achieve compliance in addition to the use of Warning Letters, Notices of Probable Violations, the issuance of civil fines, etc. Total points scored for this section: 15 Total possible points for this section: 15 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 13#
IN NG Program Evaluation, 2016, page 14PART E - Incident Investigations Points(MAX) Score 1 Does the state have written procedures to address state actions in the event of an incident/ accident? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: E1. Yes. See Section IX of the Program Manual. 2 2 2 Does state have adequate mechanism to receive and respond to operator reports of 2 2 incidents, including after-hours reports? And did state keep adequate records of Incident/ Accident notifications received? Chapter 6 Yes = 2 No = 0 Needs Improvement = 1 a. Acknowledgement of MOU between NTSB and PHMSA (Appendix D) Yes No Needs Improvement b. Acknowledgement of Federal/State Cooperation in case of incident/accident (Appendix E) Yes No Needs Improvement Evaluator Notes: E2. Yes. The 24 hr no. is 317-232-2707. IURC is very aware of appendix D & E. The website has the phone number for the reporting of incidents/accidents. 3 If onsite investigation was not made, did state obtain sufficient information from the 1 1 operator and/or by other means to determine the facts to support the decision to not go on-site? Chapter 6 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: E3. Yes. Most significant incidents/accidents are investigated on-site. The others are reviewed telephonically, with emails, with 30 day reports, and with other timely written reports. 4 Were all incidents investigated, thoroughly documented, and with conclusions and 3 3 recommendations? Yes = 3 No = 0 Needs Improvement = 1-2 a. Observations and document review Yes No Needs Improvement b. Contributing Factors Yes No Needs Improvement c. Recommendations to prevent recurrences when appropriate Yes No Needs Improvement Evaluator Notes: E4. Yes, Attachment 4 of the Base Grant Progress Report is adequate, and the Incident/Accident files are complete. 5 Did the state initiate compliance action for violations found during any incident/accident 1 1 investigation? Yes = 1 No = 0 Evaluator Notes: E5. Yes. There was one NOPV found and processed for one of the incidents. No probable violations were discovered concerning the other two reportable incidents in CY 2016. 6 Did the state assist region office by taking appropriate follow-up actions related to the operator incident reports to ensure accuracy and final report has been received by PHMSA? (validate report data from operators concerning incidents/accidents and investigate discrepancies) Chapter 6 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: E6. Yes, Appendix E in the Guidelines is understood and IURC will assist whenever requested. 1 1 7 Does state share lessons learned from incidents/accidents? (sharing information, such as: at NAPSR Region meetings, state seminars, etc) Yes = 1 No = 0 1 1 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 14#
IN NG Program Evaluation, 2016, page 15Evaluator Notes: E7. Yes, during the Central Region NAPSR meetings. 8 General Comments: Info Only Info Only Info Only = No Points Evaluator Notes: E8. There were three reportable incidents in CY 2016. Each incident was investigated thoroughly for compliance with regulations as well as for lessons learned. All investigations are complete with one investigation resulting in a compliance action in the form of a Notice of Probable Violation letter to an operator. Total points scored for this section: 11 Total possible points for this section: 11 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 15#
IN NG Program Evaluation, 2016, page 16PART F - Damage Prevention Points(MAX) Score 1 Has the state reviewed directional drilling/boring procedures of each pipeline operator or its contractor to determine if they include actions to protect their facilities from the dangers posed by drilling and other trench less technologies? NTSB Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: F1. Yes, It is a question on the Std Insp Form 2 2 2 Did the state inspector check to assure the pipeline operator is following its written 2 2 procedures pertaining to notification of excavation, marking, positive response and the availability and use of the one call system? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: F2. Yes, the questions are on the IN State -Damage Prevention Form which is used as an addendum to every Standard Inspection. 3 Did the state encourage and promote practices for reducing damages to all underground 2 2 facilities to its regulated companies? (i.e. such as promoting/adopting the CGA Best Practices encouraging adoption of the 9 Elements, etc.) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: F3. Yes, the IURC is actively engaged with the various Damage Prevention Councils that exist throughout the state. They are also actively engaged with the state's Underground Plant Protection Advisory Committee and are aggressively enforcing the state's One-Call Law. 4 Has the agency or another organization within the state collected data and evaluated trends on the number of pipeline damages per 1,000 locate requests? (This can include DIRT and other data shared and reviewed by the pipeline safety program) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: F4. Yes, 'hits per thousand' is rolled into the risk management model. 2 2 5 General Comments: Info Only Info Only Info Only = No Points Evaluator Notes: F5. In Indiana, fines collected for One-Call violations are dedicated to damage prevention efforts through the Underground Plant Protection Account. This is accomplished by developing programs related to Public Awareness, Training, and Incentives designed to reduce excavation damages. IURC has also developed a specific Damage Prevention Inspection Form and holds all operators accountable for damage prevention through inspections and enforcement of the state's One-Call law. Damage prevention is a high priority for the IURC and they have assessed numerous small fines to encourage compliance with Damage Prevention; as such it has issued more than 2.7M$ in fines and collected more than 2M$ from 1712 individual penalties since inception in 2012; for an average of $1577 collected per penalty. Total points scored for this section: 8 Total possible points for this section: 8 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 16#
IN NG Program Evaluation, 2016, page 17PART G - Field Inspections Points(MAX) Score 1 Operator, Inspector, Location, Date and PHMSA Representative Info Only = No Points Name of Operator Inspected: Indiana Gas Company, opid 8070 Name of State Inspector(s) Observed: Dan Novak, Inspector Location of Inspection: at Maloney Rd & 800 East, Brownsburg, IN Date of Inspection: 8/16/2017 Name of PHMSA Representative: Patrick Gaume Evaluator Notes: G1. Indiana Gas Company, opid 8070 Dan Novak, Inspector Construction Inspection, a 20" tie-in at Maloney Rd & 800 East, Brownsburg, IN, Near Brownsburg, IN 46112 8/16/2017 Patrick Gaume Info Only Info Only 2 Was the operator or operator's representative notified and/or given the opportunity to be 1 1 present during inspection? Yes = 1 No = 0 Evaluator Notes: G2. Yes. They had been contacted and they dedicated personnel for the inspection. The Operator's personnel & contractors actively participated. 3 Did the inspector use an appropriate inspection form/checklist and was the form/checklist used as a guide for the inspection? (New regulations shall be incorporated) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: G3. Yes. IURC used their State Construction form and the Federal Form 5. 2 2 4 Did the inspector thoroughly document results of the inspection? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: G4. Yes. He filled out the form. 2 2 5 Did the inspector check to see if the operator had necessary equipment during inspection 1 1 to conduct tasks viewed? (Maps,pyrometer,soap spray,CGI,etc.) Yes = 1 No = 0 Evaluator Notes: G5. Yes. Backhoes, welder rigs, sand blast equipment, Holiday checks (jeeping), slings, cleaning supplies, PPE, shoring and ditch safety, hand tools, Damage Prevention as the representative from the offset pipeline, Marathon, was present, & radiographic NDT. 6 Did the inspector adequately review the following during the field portion of the state evaluation? (check all that apply on list) Yes = 2 No = 0 Needs Improvement = 1 a. Procedures 2 2 b. Records c. Field Activities d. Other (please comment) Evaluator Notes: DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 17#
IN NG Program Evaluation, 2016, page 18G6. Yes. Construction Field inspection; A tie-in of a 20" line, including procedures and records applicable to the day's work. 7 Did the inspector have adequate knowledge of the pipeline safety program and regulations? (Evaluator will document reasons if unacceptable) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: G7. Yes. Dan was very knowledgeable about the regulations and about the job he was inspecting. 2 2 8 Did the inspector conduct an exit interview? (If inspection is not totally complete the 1 1 interview should be based on areas covered during time of field evaluation) Yes = 1 No = 0 Evaluator Notes: G8. Yes. No violations found. The day's work was well planned, according to the procedure, and the equipment and personnel performed their jobs well and safely. 9 During the exit interview, did the inspector identify probable violations found during the 1 1 inspections? (if applicable) Yes = 1 No = 0 Evaluator Notes: G9. Yes. No violations found. The day's work was well planned, according to the procedure, and the equipment and personnel performed their jobs well and safely. 10 General Comments: 1) What did the inspector observe in the field? (Narrative description of field observations and how inspector performed) 2) Best Practices to Share with Other States - (Field - could be from operator visited or state inspector practices) 3) Other. Info Only = No Points a. Abandonment b. Abnormal Operations c. Break-Out Tanks d. Compressor or Pump Stations e. Change in Class Location f. Casings g. Cathodic Protection h. Cast-iron Replacement i. Damage Prevention j. Deactivation k. Emergency Procedures l. Inspection of Right-of-Way m. Line Markers n. Liaison with Public Officials o. Leak Surveys p. MOP q. MAOP r. Moving Pipe s. New Construction t. Navigable Waterway Crossings u. Odorization v. Overpressure Safety Devices w. Plastic Pipe Installation x. Public Education y. Purging z. Prevention of Accidental Ignition Info Only Info Only DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 18#
IN NG Program Evaluation, 2016, page 19A. Repairs B. Signs C. Tapping D. Valve Maintenance E. Vault Maintenance F. Welding G. OQ - Operator Qualification H. Compliance Follow-up I. Atmospheric Corrosion J. Other Evaluator Notes: G10. Yes. b, g, i, l, r, s, F, &G. construction of a 20" tie-in. Observed ditching and shoring, pipe movement, welding, jeeping, sand blasting, & coating. Also reviewed the procedures and records relative to the day's work. Total points scored for this section: 12 Total possible points for this section: 12 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 19#
IN NG Program Evaluation, 2016, page 20PART H - Interstate Agent State (If Applicable) Points(MAX) Score 1 Did the state use the current federal inspection form(s)? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: H1-8. NA. Not an Interstate Agent Program. 1 NA 2 Are results documented demonstrating inspection units were reviewed in accordance with "PHMSA directed inspection plan"? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: H1-8. NA. Not an Interstate Agent Program. 1 NA 3 Did the state submit documentation of the inspections within 60 days as stated in its latest Interstate Agent Agreement form? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: H1-8. NA. Not an Interstate Agent Program. 1 NA 4 Were probable violations identified by state referred to PHMSA for compliance? (NOTE: PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation.) Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: H1-8. NA. Not an Interstate Agent Program. 1 NA 5 Did the state immediately report to PHMSA conditions which may pose an imminent safety hazard to the public or to the environment? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: H1-8. NA. Not an Interstate Agent Program. 1 NA 6 Did the state give written notice to PHMSA within 60 days of all probable violations found? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: H1-8. NA. Not an Interstate Agent Program. 1 NA 7 Did the state initially submit documentation to support compliance action by PHMSA on probable violations? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: H1-8. NA. Not an Interstate Agent Program. 1 NA 8 General Comments: Info Only = No Points Evaluator Notes: H1-8. NA. Not an Interstate Agent Program. Info Only Info Only Total points scored for this section: 0 Total possible points for this section: 0 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 20#
IN NG Program Evaluation, 2016, page 21PART I - 60106 Agreement State (If Applicable) Points(MAX) Score 1 Did the state use the current federal inspection form(s)? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: I1-7. NA. Not a 60106 Program. 1 NA 2 Are results documented demonstrating inspection units were reviewed in accordance with state inspection plan? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: I1-7. NA. Not a 60106 Program. 1 NA 3 Were any probable violations identified by state referred to PHMSA for compliance? (NOTE: PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation.) Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: I1-7. NA. Not a 60106 Program. 1 NA 4 Did the state immediately report to PHMSA conditions which may pose an imminent safety hazard to the public or to the environment? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: I1-7. NA. Not a 60106 Program. 1 NA 5 Did the state give written notice to PHMSA within 60 days of all probable violations found? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: I1-7. NA. Not a 60106 Program. 1 NA 6 Did the state initially submit adequate documentation to support compliance action by PHMSA on probable violations? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: I1-7. NA. Not a 60106 Program. 1 NA 7 General Comments: Info Only = No Points Evaluator Notes: I1-7. NA. Not a 60106 Program. Info Only Info Only Total points scored for this section: 0 Total possible points for this section: 0 DUNS: 086329518 2016 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 21#