IN NG Program Evaluation, 2018, page 1Official PDF1200 New Jersey Avenue SE Washington DC 20590 U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration 2018 Gas State Program Evaluation for INDIANA UTILITY REGULATORY COMMISSION Document Legend PART: O -- Representative Date and Title Information A -- Progress Report and Program Documentation Review B -- Program Inspection Procedures C -- Program Performance D -- Compliance Activities E -- Incident Investigations F -- Damage Prevention G -- Field Inspections H -- Interstate Agent State (If Applicable) I -- 60106 Agreement State (If Applicable) DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 1#
IN NG Program Evaluation, 2018, page 22018 Gas State Program Evaluation -- CY 2018 Gas State Agency: Indiana Rating: Agency Status: Date of Visit: 05/13/2019 - 05/17/2017 Agency Representative: William Boyd Director, Pipeline Safety PHMSA Representative: Clint Stephens State Liaison Commission Chairman to whom follow up letter is to be sent: Name/Title: Mr. Jim Huston, Chairman Agency: Indiana Utility Regulatory Commission Address: 101 West Washington Street, Suite 1500 City/State/Zip: Indianapolis, IN 46204-3407 60105(a): Yes 60106(a): No Interstate Agent: No INSTRUCTIONS: Complete this evaluation in accordance with the Procedures for Evaluating State Pipeline Safety Program. The evaluation should generally reflect state program performance during CY 2018 (not the status of performance at the time of the evaluation). All items for which criteria have not been established should be answered based on the PHMSA representative's judgment. A deficiency in any one part of a multiple part question should be scored as needs improvement. Determine the answer to the question then select the appropriate point value. If a state receives less then the maximum points, include a brief explanation in the space provided for general comments/regional observations. If a question is not applicable to a state, select NA. Please ensure all responses are COMPLETE and ACCURATE, and OBJECTIVELY reflect state program performance. Increasing emphasis is being placed on performance. This evaluation together with selected factors reported in the state's annual progress report attachments provide the basis for determining the state's pipeline safety grant allocation. Scoring Summary PARTS Possible Points Points Scored A Progress Report and Program Documentation Review 10 10 B Program Inspection Procedures 13 13 C Program Performance 49 49 D Compliance Activities 15 15 E Incident Investigations 11 11 F Damage Prevention 8 8 G Field Inspections 12 12 H Interstate Agent State (If Applicable) 0 0 I 60106 Agreement State (If Applicable) 0 0 TOTALS 118 118 State Rating................................................................................................................................................... 100.0 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 2#
IN NG Program Evaluation, 2018, page 3PART A - Progress Report and Program Documentation Review Points(MAX) Score 1 Accuracy of Jurisdictional Authority and Operator/Inspection Units Data - Progress 1 1 Report Attachment 1 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: There seems to be no problem with accuracy of jurisdictional authority and operator/inspection units data from Attachment 1 of Progress Report. 2 Review of Inspection Days for accuracy - Progress Report Attachment 2 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: No problem with accuracy of inspection days from Attachment 2 of Progress Report. 1 1 3 Accuracy verification of Operators and Operators Inspection Units in State - Progress 1 1 Report Attachment 3 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: There seems to be no problem with accuracy of operators and operators inspection units in State from Attachment 3 of Progress Report. 4 Were all federally reportable incident reports listed and information correct? - Progress Report Attachment 4 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Checked data with PDM and information is correct as listed in Attachment 4 of Progress Report. 1 1 5 Accuracy verification of Compliance Activities - Progress Report Attachment 5 1 1 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Accuracy of compliance activities seems correct for Attachment 5 of Progress Report. 6 Were pipeline program files well-organized and accessible? - Progress Report Attachment 6 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: The program files were well organized and accessible through their Share Point and CRM database. 2 2 7 Was employee listing and completed training accurate and complete? - Progress Report 1 1 Attachment 7 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: There were two new employees hired in 2018. The employee listing and completed training was verified through TQ blackboard. 8 Verification of Part 192,193,198,199 Rules and Amendments - Progress Report Attachment 8 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Indiana has tried to adopt all rules and amendments. Civil penalties do match PHMSA. 1 1 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 3#
IN NG Program Evaluation, 2018, page 49 List of Planned Performance - Did state describe accomplishments on Progress Report in 1 1 detail - Progress Report Attachment 10 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Based on the incident in Massachusetts, the Indiana State Program has put emphasis on inspecting operators with low pressure regulator stations. All low pressure operators were inspected the first quarter of 2019. 10 General Comments: Info Only = No Points Evaluator Notes: There were no issues in Part A. Info Only Info Only Total points scored for this section: 10 Total possible points for this section: 10 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 4#
IN NG Program Evaluation, 2018, page 5PART B - Program Inspection Procedures Points(MAX) Score 1 Standard Inspection procedures should give guidance to state inspectors that insure 2 2 consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Standard inspections which include the pre-inspection and inspection activities are detailed on pages 30 thru 33 of the Indiana Regulatory Commission Pipeline Safety Division Program Manual. Post Inspection Activities are detailed on pages 50 thru 52. 2 IMP and DIMP Inspection procedures should give guidance to state inspectors that insure 1 1 consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The pre-inspection and inspection activities are detailed on pages 30 thru 33 of the Indiana Regulatory Commission Pipeline Safety Division Program Manual. The IMP and DIMP inspection procedures are included on page 48 and 50. 3 OQ Inspection procedures should give guidance to state inspectors that insure 1 1 consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The pre-inspection and inspection activities are detailed on pages 30 thru 33 of the Indiana Regulatory Commission Pipeline Safety Division Program Manual. The OQ procedures are included on page 44. 4 Damage Prevention Inspection procedures should give guidance to state inspectors that 1 1 insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post- inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The pre-inspection and inspection activities are detailed on pages 30 thru 33 of the Indiana Regulatory Commission Pipeline Safety Division Program Manual. The Damage Prevention inspection procedures on page 47 only outlines which form to use; whereas, more detail procedures are listed One-Call Law. 5 Any operator training conducted should be outlined and appropriately documented as 1 1 needed. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Manual. On site operator training is included on page 46 of the Indiana Regulatory Commission Pipeline Safety Division Program 6 Construction Inspection procedures should give guidance to state inspectors that insure 1 1 consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The pre-inspection and inspection activities are detailed on pages 30 thru 33 of the Indiana Regulatory Commission Pipeline Safety Division Program Manual. The construction inspection procedures are included on pages 41 thru 43. DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 5#
IN NG Program Evaluation, 2018, page 67 Does inspection plan address inspection priorities of each operator, and if necessary each 6 6 unit, based on the following elements? Yes = 6 No = 0 Needs Improvement = 1-5 a. Length of time since last inspection (Within five year interval) Yes No Needs Improvement b. Operating history of operator/unit and/or location (includes leakage, incident and compliance activities) Yes No Needs Improvement c. Type of activity being undertaken by operators (i.e. construction) Yes No Needs Improvement d. Locations of operators inspection units being inspected - (HCA's, Geographic areas, Population Density, etc) Yes No Needs Improvement e. Process to identify high-risk inspection units that includes all threats - (Excavation Damage, Corrosion, Natural Forces, Outside Forces, Material and Welds, Equipment, Yes No Needs Improvement Operators and any Other Factors) f. Are inspection units broken down appropriately? Yes No Needs Improvement Evaluator Notes: The inspection priorities of each operator is outlined on pages 16 thru 27 of the Indiana Regulatory Commission Pipeline Safety Division Program Manual. 8 General Comments: Info Only = No Points Evaluator Notes: There were no issues in Part B. Info Only Info Only Total points scored for this section: 13 Total possible points for this section: 13 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 6#
IN NG Program Evaluation, 2018, page 7PART C - Program Performance Points(MAX) Score 1 Was ratio of Total Inspection person-days to total person days acceptable? (Director of State Programs may modify with just cause) Chapter 4.3 Yes = 5 No = 0 A. Total Inspection Person Days (Attachment 2): 963.00 B. Total Inspection Person Days Charged to the Program (220 X Inspection Person Years) (Attachment 7): 220 X 10.54 = 2318.23 Ratio: A / B 963.00 / 2318.23 = 0.42 If Ratio >= 0.38 Then Points = 5, If Ratio < 0.38 Then Points = 0 Points = 5 Evaluator Notes: 963/220(10.54) = .42 > .38 5 5 2 Has each inspector and program manager fulfilled the T Q Training Requirements? (See 5 5 Guidelines Appendix C for requirements) Chapter 4.4 Yes = 5 No = 0 Needs Improvement = 1-4 a. Completion of Required OQ Training before conducting inspection as lead? Yes No Needs Improvement b. Completion of Required DIMP*/IMP Training before conducting inspection as lead? *Effective Evaluation CY2013 Yes No Needs Improvement c. Root Cause Training by at least one inspector/program manager Yes No Needs Improvement d. Note any outside training completed Yes No Needs Improvement e. Verify inspector has obtained minimum qualifications to lead any applicable standard inspection as the lead inspector. Yes No Needs Improvement Evaluator Notes: All lead inspectors and program manager have fulfilled TQ Training requirements. New inspectors are in process of fulfilling training requirements. 3 Did state records and discussions with state pipeline safety program manager indicate adequate knowledge of PHMSA program and regulations? Chapter 4.1,8.1 Yes = 2 No = 0 Needs Improvement = 1 2 2 Evaluator Notes: Yes. The pipeline safety program manager indicated adequate knowledge of PHMSA program and regulations. 4 Did state respond to Chairman's letter on previous evaluation within 60 days and correct or address any noted deficiencies? (If necessary) Chapter 8.1 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. State did respond to Chairman's letter within 60 days, and correct or address any noted deficiencies. 2 2 5 Did State conduct or participate in pipeline safety training session or seminar in Past 3 Years? Chapter 8.5 Yes = 1 No = 0 Evaluator Notes: Indiana had its last pipeline safety seminar on July 10 thru 12, 2018. 1 1 6 Did state inspect all types of operators and inspection units in accordance with time intervals established in written procedures? Chapter 5.1 Yes = 5 No = 0 Needs Improvement = 1-4 5 5 Evaluator Notes: DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 7#
IN NG Program Evaluation, 2018, page 8Yes. Indiana inspected all types of operators and inspection units in accordance with time intervals established in written procedures. 7 Did inspection form(s) cover all applicable code requirements addressed on Federal 2 2 Inspection form(s)? Did State complete all applicable portions of inspection forms? Chapter 5.1 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Reviewed inspection report numbers 10528, 10518, 10688, 10543, 10692, and 10740. Inspection forms covered all applicable code requirements addressed on Federal Inspection forms. 8 Did the state review operator procedures for determining if exposed cast iron pipe was 1 1 examined for evidence of graphitization and if necessary remedial action was taken? (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: Yes. The procedure question is included in the IA Distribution/Transmission Corrosion Inspection form, question #27. 9 Did the state review operator procedures for surveillance of cast iron pipelines, including appropriate action resulting from tracking circumferential cracking failures, study of leakage history, or other unusual operating maintenance condition? (Note: See GPTC Appendix G-18 for guidance) (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: Yes. The procedure question is included in the IA Distribution O&M Inspection form, question #2. 1 1 10 Did the state review operator emergency response procedures for leaks caused by excavation damage near buildings and determine whether the procedures adequately address the possibility of multiple leaks and underground migration of gas into nearby buildings Refer to 4/12/01 letter from PHMSA in response to NTSB recommendation P-00-20 and P-00-21? (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: Yes. The procedure question is included in the IA Distribution O&M Inspection form, question #8. 1 1 11 Did the state review operator records of previous accidents and failures including reported third party damage and leak response to ensure appropriate operator response as required by 192.617? Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: 1 1 Yes. The procedure question is included in the IA Distribution O&M Inspection form, questions 1 and 2, pages 8 and 9. 12 Has the state reviewed Operator Annual reports, along with Incident/Accident reports, for accuracy and analyzed data for trends and operator issues? Yes = 2 No = 0 Needs Improvement = 1 2 2 Evaluator Notes: Yes. Indiana has a checklist for reviewing the operator annual reports for any discrepancies, along with analyzing the data from Incident/Accident reports for trends and operator issues which is then promulgated in their risk model. 13 Has state confirmed intrastate transmission operators have submitted information into NPMS database along with changes made after original submission? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Yes. Indiana does an annual review by checking data from annual reports and PDM. 1 1 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 8#
IN NG Program Evaluation, 2018, page 914 Is the state verifying operators are conducting drug and alcohol tests as required by regulations? This should include verifying positive tests are responded to in accordance with program. 49 CFR 199 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. Indiana is using the PHMSA long form for drug and alcohol tests as required by regulations. A comprehensive D&A inspection was performed on their three largest operators in 2018. 2 2 15 Is state verifying operators OQ programs are up to date? This should include verification 2 2 of any plan updates and that persons performing covered tasks (including contractors) are properly qualified and requalified at intervals determined in the operators plan. 49 CFR 192 Part N Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Indiana performed 19 OQ Program inspections in 2018. There was 60 inspection person days spent on OQ inspections based on the 2018 Progress Report. 16 Is state verifying operator's gas transmission integrity management programs (IMP) are 2 2 up to date? This should include a previous review of IMP plan, along with monitoring progress on operator tests and remedial actions. In addition, the review should take in to account program review and updates of operators plan(s). (Are the State's largest operators programs being contacted or reviewed annually? Are replies to Operator IM notifications addressed? (formerly part of Question C-13)). 49 CFR 192 Subpart 0 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: A comprehensive IMP inspection was performed on the big three operators in 2018. Indiana meets with the operators on an annual basis to discuss any significant changes with IMP Plan. 17 Is state verifying operator's gas distribution integrity management Programs (DIMP)? 2 2 This should include a review of DIMP plans, along with monitoring progress. In addition, the review should take in to account program review and updates of operators plan(s). (Are the State's largest operators programs being contacted or reviewed annually?). 49 CFR 192 Subpart P Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. Indiana performed 27 gas distribution integrity management program inspections in 2018. They had USDI (small operator contractor) meet with the Indiana State office inspectors to discuss their DIMP Plan which is being used by many of the small operators in the State of Indiana. 18 Is state verifying operators Public Awareness programs are up to date and being followed. State should also verify operators have evaluated Public Awareness programs for effectiveness as described in RP1162. PAPEI Effectiveness Inspections should be conducted every four years by operators. 49 CFR 192.616 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: 2 2 Indiana performed three Public Awareness program inspections in 2018. Will be scheduling more inspections in 2019. 19 Does the state have a mechanism for communicating with stakeholders - other than state 1 1 pipeline safety seminar? (This should include making enforcement cases available to public). Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Yes. Indiana communicates with stakeholders, such as, enforcement cases on State website, sending out emails to operators pertaining to State and Federal regulatory updates, and regular meetings with three big operators. DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 9#
IN NG Program Evaluation, 2018, page 1020 Did state execute appropriate follow-up actions to Safety Related Condition (SRC) Reports? Chapter 6.3 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Indiana has no open SRC Reports. 1 1 21 Did the State ask Operators to identify any plastic pipe and components that has shown a 1 1 record of defects/leaks and what those operators are doing to mitigate the safety concerns? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Yes. Indiana is asking the operator during DIMP inspections if they have any plastic pipe susceptible to failure, such as Aldyl A plastic pipe. 22 Did the state participate in/respond to surveys or information requests from NAPSR or PHMSA? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Yes. The state participated in response to surveys or information requests from NAPSR or PHMSA. 1 1 23 If the State has issued any waivers/special permits for any operator, has the state verified conditions of those waivers/special permits are being met? This should include having the operator amend procedures where appropriate. No = 0 Needs Improvement = .5 Yes = 1 Evaluator Notes: Indiana has no waivers or special permits for any operators. 1 1 24 Did the state attend the NAPSR National Meeting in CY being evaluated? No = 0 Needs Improvement = .5 Yes = 1 Evaluator Notes: Yes. Program manager attended NAPSR National Meeting in 2018 in Santa Fe, New Mexico. 1 1 25 Discussion on State Program Performance Metrics found on Stakeholder Communication 2 2 site - http://primis.phmsa.dot.gov/comm/states.htm No = 0 Needs Improvement = 1 Yes = 2 a. Discussion of Potential Accelerated Actions (AA's) based on any negative trends Yes No Needs Improvement b. NTSB P-11-20 Meaningful Metrics Yes No Needs Improvement Evaluator Notes: Yes. Discussed Inspector qualifications (core training, % additional training, and % 5-year retention) for gas program decreased from 2016 to 2017. They have lost staff to retirement and PHMSA. Indiana has hired new staff recently, but they have not completed core training. 26 Discussion with State on accuracy of inspection day information submitted into State 1 1 Inspection Day Calculation Tool (SICT) Has the State updated SICT data? No = 0 Yes = 1 Evaluator Notes: Indiana had no problem meeting inspection days calculated from the SICT tool (736), and had 963 inspection days based on Attachment 2 of 2018 Progress Report. 27 Did the State verify Operators took appropriate action regarding Pipeline Flow Reversals, Product Changes and Conversions to Service? See ADP-2014-04 Needs Improvement = .5 No = 0 Yes = 1 Evaluator Notes: An email was sent out to all operators in May 2018 notifying them of ADP. DUNS: 086329518 2018 Gas State Program Evaluation 1 1 Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 10#
IN NG Program Evaluation, 2018, page 1128 General Comments: Info Only = No Points Evaluator Notes: There were no issues in Part C. DUNS: 086329518 2018 Gas State Program Evaluation Info Only Info Only Total points scored for this section: 49 Total possible points for this section: 49 Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 11#
IN NG Program Evaluation, 2018, page 12PART D - Compliance Activities Points(MAX) Score 1 Does the state have written procedures to identify steps to be taken from the discovery to 4 4 resolution of a probable violation? Chapter 5.1 Yes = 4 No = 0 Needs Improvement = 1-3 a. Procedures to notify an operator (company officer) when a noncompliance is identified Yes No Needs Improvement b. Procedures to routinely review progress of compliance actions to prevent delays or breakdowns Yes No Needs Improvement c. Procedures regarding closing outstanding probable violations Yes No Needs Improvement Evaluator Notes: Yes. The procedures are detailed on pages 50 thru 52 of the IURC Pipeline Safety Division Program Manual. More detail was added to Manual to explain in detail the process for monitoring progress of compliance action until closing probable violations or outstanding probable violations. 2 Did the state follow compliance procedures (from discovery to resolution) and adequately 4 4 document all probable violations, including what resolution or further course of action is needed to gain compliance? (Incident Investigations do not need to meet 30/90 day requirement) Chapter 5.1 Yes = 4 No = 0 Needs Improvement = 1-3 a. Were compliance actions sent to company officer or manager/board member if municipal/government system? Yes No Needs Improvement b. Document probable violations Yes No Needs Improvement c. Resolve probable violations Yes No Needs Improvement d. Routinely review progress of probable violations Yes No Needs Improvement e. Within 30 days, conduct a post-inspection briefing with the owner or operator of the gas or hazardous liquid pipeline facility inspected outlining any concerns; and Yes No Needs Improvement f. Within 90 days, to the extent practicable, provide the owner or operator with written preliminary findings of the inspection. Yes No Needs Improvement Evaluator Notes: Reviewed inspection report numbers 10518, 10528, 10738, 10712 (report needs to be closed out), 10692, 10688 (report has not been resolved), and 10740 (report has not been resolved). 3 Did the state issue compliance actions for all probable violations discovered? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. Indiana issued compliance actions for all probable violations discovered in 2018. 2 2 4 Did compliance actions give reasonable due process to all parties? Including "show 2 2 cause" hearing if necessary. Yes = 2 No = 0 Evaluator Notes: Yes. Based on the Vectren incident, the operator was given due process to negotiate civil penalty with the possibility of show cause hearing if requested. 5 Is the program manager familiar with state process for imposing civil penalties? Were 2 2 civil penalties considered for repeat violations (with severity consideration) or violations resulting in incidents/accidents? (describe any actions taken) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. The program manager is familiar with the state process for imposing civil penalties. There was a $736,000 civil penalty levied against Vectren for an incident that occurred in 2018. 6 Can the State demonstrate it is using their enforcement fining authority for pipeline safety violations? DUNS: 086329518 2018 Gas State Program Evaluation 1 1 Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 12#
IN NG Program Evaluation, 2018, page 13Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Yes. There was a $736,000 civil penalty levied against Vectren for an incident that occurred in 2018. 7 General Comments: Info Only = No Points Evaluator Notes: There were no issues in Part D. Info Only Info Only Total points scored for this section: 15 Total possible points for this section: 15 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 13#
IN NG Program Evaluation, 2018, page 14PART E - Incident Investigations Points(MAX) Score 1 Does the state have written procedures to address state actions in the event of an incident/ 2 2 accident? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. The procedure is detailed in the IURC Pipeline Safety Division Incident Investigation Procedures, page 75 thru 83. 2 Does state have adequate mechanism to receive and respond to operator reports of 2 2 incidents, including after-hours reports? And did state keep adequate records of Incident/ Accident notifications received? Chapter 6 Yes = 2 No = 0 Needs Improvement = 1 a. Acknowledgement of MOU between NTSB and PHMSA (Appendix D) Yes No Needs Improvement b. Acknowledgement of Federal/State Cooperation in case of incident/accident (Appendix E) Yes No Needs Improvement Evaluator Notes: Yes. The procedure is detailed in the IURC Pipeline Safety Division Incident Investigation Procedures, page 75 thru 83. Indiana has a 24 hour call in number to report a possible incident. That information is recorded on a Telephonic Report form to document whether call-in is a reportable incident and should be investigated. 3 If onsite investigation was not made, did state obtain sufficient information from the 1 1 operator and/or by other means to determine the facts to support the decision to not go on-site? Chapter 6 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: After reviewing a few of the Telephonic Reports in 2018, some were not completely filled out to determine the facts to determine if pipeline safety had decided to go onsite to investigate. Staff indicated that during staff meetings that discussions were made to properly fill out forms. 4 Were all incidents investigated, thoroughly documented, and with conclusions and 3 3 recommendations? Yes = 3 No = 0 Needs Improvement = 1-2 a. Observations and document review Yes No Needs Improvement b. Contributing Factors Yes No Needs Improvement c. Recommendations to prevent recurrences when appropriate Yes No Needs Improvement Evaluator Notes: Yes. There was one incident that was investigated thoroughly, documented with conclusions and recommendations. 5 Did the state initiate compliance action for violations found during any incident/accident investigation? Yes = 1 No = 0 Evaluator Notes: There was no compliance actions or violations found during any incident/accident investigation in 2018. 1 1 6 Did the state assist Region Office or Accident Investigation Division (AID) by taking appropriate follow-up actions related to the operator incident reports to ensure accuracy and final report has been received by PHMSA? (validate report data from operators concerning incidents/accidents and investigate discrepancies) Chapter 6 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Indiana was not requested by AID to assist during any incident investigation in 2018. 1 1 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 14#
IN NG Program Evaluation, 2018, page 157 Does state share lessons learned from incidents/accidents? (sharing information, such as: at NAPSR Region meetings, state seminars, etc) Yes = 1 No = 0 Evaluator Notes: 1 1 Yes. This information is presented during the State of State address during NAPSR Region meeting and State seminars. 8 General Comments: Info Only = No Points Evaluator Notes: There were no issues in Part E. Info Only Info Only Total points scored for this section: 11 Total possible points for this section: 11 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 15#
IN NG Program Evaluation, 2018, page 16PART F - Damage Prevention Points(MAX) Score 1 Has the state reviewed directional drilling/boring procedures of each pipeline operator or its contractor to determine if they include actions to protect their facilities from the dangers posed by drilling and other trench less technologies? NTSB Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. Question is listed on the O&M Inspection Form, question 9, page 7. 2 2 2 Did the state inspector verify pipeline operators are following their written procedures pertaining to notification of excavation, marking, positive response and the availability and use of the one call system? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. Question is listed on the Damage Prevention Inspection Form. 2 2 3 Did the state encourage and promote practices for reducing damages to all underground 2 2 facilities to its regulated companies? (i.e. such as promoting/adopting the CGA Best Practices encouraging adoption of the 9 Elements, etc.) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. Indiana's Damage Prevention Program was deemed adequate by PHMSA. Through there website, information is available for all stakeholders to obtain training and resources for CGA Best Practices. 4 Has the agency or another organization within the state collected data and evaluated trends on the number of pipeline damages per 1,000 locate requests? (This can include DIRT and other data shared and reviewed by the pipeline safety program) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: 2 2 Indiana is analyzing data from annual reports to evaluate trends on the number of pipeline damages per 1,000 locate tickets. 5 General Comments: Info Only = No Points Evaluator Notes: There were no issues in Part F. Info Only Info Only Total points scored for this section: 8 Total possible points for this section: 8 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 16#
IN NG Program Evaluation, 2018, page 17PART G - Field Inspections Points(MAX) Score 1 Operator, Inspector, Location, Date and PHMSA Representative Info Only Info Only Info Only = No Points Name of Operator Inspected: NIPSCO, a subsidiary of NiSource Name of State Inspector(s) Observed: Dan Novak and Mike Martin Location of Inspection: 1000 East Blvd. Street, Kokomo, IN Date of Inspection: April 16, 2019 Name of PHMSA Representative: Clint Stephens Evaluator Notes: The IURC performed a construction inspection on NIPSCO. NIPSCO was installing a new 2" and 8" plastic main, and retiring 2600' of 2" steel main. 2 Was the operator or operator's representative notified and/or given the opportunity to be present during inspection? Yes = 1 No = 0 1 1 Evaluator Notes: Yes. The operator's representative was notified and given the opportunity to be present during the inspection. 3 Did the inspector use an appropriate inspection form/checklist and was the form/checklist used as a guide for the inspection? (New regulations shall be incorporated) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. The inspector used the IURC "Inspection Report of Construction" form as a guide for the inspection. 2 2 4 Did the inspector thoroughly document results of the inspection? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. The inspector thoroughly documented the results of the inspection. 2 2 5 Did the inspector check to see if the operator had necessary equipment during inspection to conduct tasks viewed? (Maps,pyrometer,soap spray,CGI,etc.) Yes = 1 No = 0 Evaluator Notes: 1 1 Yes. The inspector checked piping construction maps and diagrams, pipeline locators, pressure gauges, and pipe wrenches. 2 2 6 Did the inspector adequately review the following during the field portion of the state evaluation? (check all that apply on list) Yes = 2 No = 0 Needs Improvement = 1 a. Procedures b. Records c. Field Activities d. Other (please comment) Evaluator Notes: Yes. The inspector reviewed the operator's construction procedures, pipeline maps and diagrams, and observed the operator locate its underground pipeline facilities. DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 17#
IN NG Program Evaluation, 2018, page 187 Did the inspector have adequate knowledge of the pipeline safety program and regulations? (Evaluator will document reasons if unacceptable) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. The inspector had adequate knowledge of the pipeline safety program and regulations. 2 2 8 Did the inspector conduct an exit interview? (If inspection is not totally complete the 1 1 interview should be based on areas covered during time of field evaluation) Yes = 1 No = 0 Evaluator Notes: The construction project was not complete at the time of the evaluation, so no exit interview was performed during the inspection. 9 During the exit interview, did the inspector identify probable violations found during the 1 1 inspections? (if applicable) Yes = 1 No = 0 Evaluator Notes: The construction project was not complete at the time of the evaluation, so no exit interview was performed during the inspection. 10 General Comments: 1) What did the inspector observe in the field? (Narrative description of field observations and how inspector performed) 2) Best Practices to Share with Other States - (Field - could be from operator visited or state inspector practices) 3) Other. Info Only = No Points a. Abandonment b. Abnormal Operations c. Break-Out Tanks d. Compressor or Pump Stations e. Change in Class Location f. Casings g. Cathodic Protection h. Cast-iron Replacement i. Damage Prevention j. Deactivation k. Emergency Procedures l. Inspection of Right-of-Way m. Line Markers n. Liaison with Public Officials o. Leak Surveys p. MOP q. MAOP r. Moving Pipe s. New Construction t. Navigable Waterway Crossings u. Odorization v. Overpressure Safety Devices w. Plastic Pipe Installation x. Public Education y. Purging z. Prevention of Accidental Ignition A. Repairs B. Signs C. Tapping Info Only Info Only DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 18#
IN NG Program Evaluation, 2018, page 19D. Valve Maintenance E. Vault Maintenance F. Welding G. OQ - Operator Qualification H. Compliance Follow-up I. Atmospheric Corrosion J. Other Evaluator Notes: The inspector observed the operator locate its underground facilities, reviewed construction maps and procedures, and check operating pressure at a home meter set. Total points scored for this section: 12 Total possible points for this section: 12 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 19#
IN NG Program Evaluation, 2018, page 20PART H - Interstate Agent State (If Applicable) Points(MAX) Score 1 Did the state use the current federal inspection form(s)? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC is not an Interstate Agent. 1 NA 2 Are results documented demonstrating inspection units were reviewed in accordance with "PHMSA directed inspection plan"? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC is not an Interstate Agent. 1 NA 3 Did the state submit documentation of the inspections within 60 days as stated in its latest Interstate Agent Agreement form? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC is not an Interstate Agent. 1 NA 4 Were probable violations identified by state referred to PHMSA for compliance? (NOTE: PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation.) Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC is not an Interstate Agent. 1 NA 5 Did the state immediately report to PHMSA conditions which may pose an imminent safety hazard to the public or to the environment? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC is not an Interstate Agent. 1 NA 6 Did the state give written notice to PHMSA within 60 days of all probable violations found? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC is not an Interstate Agent. 1 NA 7 Did the state initially submit documentation to support compliance action by PHMSA on probable violations? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC is not an Interstate Agent. 1 NA 8 General Comments: Info Only = No Points Evaluator Notes: The IURC is not an Interstate Agent. Info Only Info Only Total points scored for this section: 0 Total possible points for this section: 0 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 20#
IN NG Program Evaluation, 2018, page 21PART I - 60106 Agreement State (If Applicable) Points(MAX) Score 1 Did the state use the current federal inspection form(s)? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC does not have a 60106 Agreement. 1 NA 2 Are results documented demonstrating inspection units were reviewed in accordance with state inspection plan? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC does not have a 60106 Agreement. 1 NA 3 Were any probable violations identified by state referred to PHMSA for compliance? (NOTE: PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation.) Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC does not have a 60106 Agreement. 1 NA 4 Did the state immediately report to PHMSA conditions which may pose an imminent safety hazard to the public or to the environment? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC does not have a 60106 Agreement. 1 NA 5 Did the state give written notice to PHMSA within 60 days of all probable violations found? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC does not have a 60106 Agreement. 1 NA 6 Did the state initially submit adequate documentation to support compliance action by PHMSA on probable violations? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The IURC does not have a 60106 Agreement. 1 NA 7 General Comments: Info Only = No Points Evaluator Notes: The IURC does not have a 60106 Agreement. Info Only Info Only Total points scored for this section: 0 Total possible points for this section: 0 DUNS: 086329518 2018 Gas State Program Evaluation Indiana INDIANA UTILITY REGULATORY COMMISSION, Page: 21#
This material provides agency context. It does not replace binding regulatory text, and its legal effect depends on the underlying authority and facts.