KS NG Program Evaluation, 2009, page 1Official PDF1200 New Jersey Avenue SE Washington DC 20590 U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration 2009 Natural Gas State Program Evaluation for KANSAS CORPORATION COMMISSION Document Legend PART: O -- Representative Date and Title Information A -- General Program Qualifications B -- Inspections and Compliance - Procedures/Records/Performance C -- Interstate Agent States D -- Incident Investigations E -- Damage Prevention Initiatives F -- Field Inspection G -- PHMSA Initiatives - Strategic Plan H -- Miscellaneous I -- Program Initiatives DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 1#
KS NG Program Evaluation, 2009, page 22009 Natural Gas State Program Evaluation -- CY 2009 Natural Gas State Agency: Kansas Rating: Agency Status: Date of Visit: 04/05/2010 - 04/09/2010 Agency Representative: Leo Haynos PHMSA Representative: Leonard Steiner Commission Chairman to whom follow up letter is to be sent: Name/Title: Thomas E. Wright, Chairman Agency: Kansas Commerce Commission Address: 1500 Southwest Arrowhead Road City/State/Zip: Topeka, Kansas 66604-4027 60105(a): Yes 60106(a): No Interstate Agent: No INSTRUCTIONS: Complete this evaluation in accordance with the Procedures for Evaluating State Pipeline Safety Program. The evaluation should generally reflect state program performance during CY 2009 (not the status of performance at the time of the evaluation). All items for which criteria have not been established should be answered based on the PHMSA representative's judgment. A deficiency in any one part of a multiple part question should be scored as needs improvement. Determine the answer to the question then select the appropriate point value. If a state receives less then the maximum points, include a brief explanation in the space provided for general comments/regional observations. If a question is not applicable to a state, select NA. Please ensure all responses are COMPLETE and ACCURATE, and OBJECTIVELY reflect state program performance. Increasing emphasis is being placed on performance. This evaluation together with selected factors reported in the state's annual certification/agreement attachments provide the basis for determining the state's pipeline safety grant allocation. Field Inspection (PART F): The field inspection form used will allow different areas of emphasis to be considered for each question. Question 13 is provided for scoring field observation areas. In completing PART F, the PHMSA representative should include a written summary which thoroughly documents the inspection. Scoring Summary PARTS Possible Points Points Scored A General Program Qualifications 26 26 B Inspections and Compliance - Procedures/Records/Performance 23.5 23 C Interstate Agent States 0 0 D Incident Investigations 7 7 E Damage Prevention Initiatives 9 9 F Field Inspection 11 11 G PHMSA Initiatives - Strategic Plan 9.5 9.5 H Miscellaneous 3 3 I Program Initiatives 9 9 TOTALS 98 97.5 State Rating................................................................................................................................................... 99.5 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 2#
KS NG Program Evaluation, 2009, page 3PART A - General Program Qualifications Points(MAX) Score 1 Did the state submit complete and accurate information on the attachments to its most current 60105(a) Certification/60106 (a) Agreement? (NOTE: PHMSA Representative to verify certification/agreement attachments by reviewing appropriate state documentation. Score a deficiency in any one area as "needs improvement". Attachment numbers appear in parenthesis) Previous Question A.1, Items a-h worth 1 point each Yes = 8 No = 0 Needs Minor Improvement = 3-7 Needs Major Improvement = 2 a. State Jurisdiction and agent status over gas facilities (1) b. Total state inspection activity (2) c. Gas facilities subject to state safety jurisdiction (3) d. Gas pipeline incidents (4) e. State compliance actions (5) f. State record maintenance and reporting (6) g. State employees directly involved in the gas pipeline safety program (7) h. State compliance with Federal requirements (8) 8 8 SLR Notes: 2 Did the state have an adequate mechanism to receive operator reporting of incidents to ensure state compliance with 60105(a) Certification/60106(a) Agreement requirements (fatality, injury requiring hospitalization, property damage exceeding $50,000 - Mechanism should include receiving "after hours" reports)? (Chapter 6) Previous Question A.2 Yes = 1 No = 0 1 1 SLR Notes: 3 Has the state held a pipeline safety TQ seminar(s) in the last 3 years? (NOTE: Indicate date of last seminar or if state requested seminar, but T&Q could not provide, indicate date of state request for seminar. Seminars must be held at least once every 3 calendar years.) (Chapter 8.5) Previous Question A.4 Yes = 2 No = 0 2 2 SLR Notes: 4 Were pipeline safety program files well-organized and accessible?(NOTE: This also includes electronic files) (Chapter 5) Previous Question A.5 Yes = 1 No = 0 1 1 SLR Notes: 5 Did state records and discussions with the state pipeline safety program manager indicate adequate knowledge of PHMSA program and regulations? (Chapter 4.1, Chapter 8.1) Previous Question A.6 Yes = 2 No = 0 Needs Improvement = 1 2 2 SLR Notes: 6 Did the state respond in writing within 60 days to the requested items in the Chairman's letter following the Region's last program evaluation? (No response is necessary if no items are requested in letter and mark "Yes") (Chapter 8.1) Previous Question A.8 Yes = 1 No = 0 SLR Notes: No reply was required. 1 1 7 What actions, if necessary, did the State initiate as a result of issues raised in the Chairperson's letter from the previous year? Did actions correct or address deficiencies from previous year's evaluation? (No response is necessary if no items are requested in letter and mark "Yes") (Chapter 8.1) Previous Question A.8/A.9 Yes = 1 No = 0 DUNS: 102979593 2009 Natural Gas State Program Evaluation 1 1 Kansas KANSAS CORPORATION COMMISSION, Page: 3#
KS NG Program Evaluation, 2009, page 4SLR Notes: No items required a comment. Personnel and Qualifications 8 Has each inspector fulfilled the 3 year TQ training requirement? If No, has the state been granted a waiver regarding TQ courses by the Associate Administrator for Pipeline Safety? (NOTE: If the State has new inspectors who have not attended all TQ courses, but are in a program which will achieve the completion of all applicable courses within 3 years of taking first course (5 years to sucessfully complete), or if a waiver has been granted by the applicable Region Director for the state, please answer yes.) (Chapter 4.4) Previous Question A.10 Yes = 3 No = 0 3 3 SLR Notes: 9 Brief Description of Non-TQ training Activities: Info Only = No Points For State Personnel: 3-PHMSA Team training, 1 NACE conference, 1 McElroy new product demonstration, 1-Emergency preparedness For Operators: 2-Barton Community County College adjunct instructors, 4-Pipeline Alliance Emergency response meeting, Kansas Municipal Annual roundtable For Non-Operator Entities/Parties, Information Dissemination, Public Meetings: Info Only Info Only SLR Notes: 10 Did the lead inspectors complete all required T&Q OQ courses and Computer Based Training (CBT) before conducting OQ Inspections? (Chapter 4.4.1) Previous Question A.12 Yes = 1 No = 0 1 1 SLR Notes: 11 SLR Notes: Did the lead inspectors complete all required TQ Integrity Management (IMP) Courses/Seminars and CBT before conducting IMP Inspections? (Chapter 4.4.1) Previous Question A.13 Yes = 1 No = 0 1 1 Kent Pribil is lead inspector for all IMP inspections 12 Was the ratio acceptable of Total inspection Person-days to Total Person-days charged to the program by state inspectors? (Region Director may modify points for just cause) (Chapter 4.3) Previous Question B.12 Yes = 5 No = 0 A. Total Inspection Person Days (Attachment 2): 850.00 B. Total Inspection Person Days Charged to the Program (220 X Inspection Person Years) (Attachment 7): 220 X 6.00 = 1320.00 Ratio: A / B 850.00 / 1320.00 = 0.64 If Ratio >= 0.38 Then Points = 5, If Ratio < 0.38 Then Points = 0 Points = 5 5 5 SLR Notes: 13 SLR Notes: DUNS: 102979593 2009 Natural Gas State Program Evaluation Have there been modifications or proposed changes to inspector-staffing levels? (If yes, describe) Previous Question B.13 Info Only = No Points Info Only Info Only Kansas KANSAS CORPORATION COMMISSION, Page: 4#
KS NG Program Evaluation, 2009, page 5No modifications to staffing levels 14 Part-A General Comments/Regional Observations Info Only = No Points Info Only Info Only SLR Notes: Kansas has Jurisdiction of Petroleum gas systems. Total points scored for this section: 26 Total possible points for this section: 26 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 5#
KS NG Program Evaluation, 2009, page 6PART B - Inspections and Compliance - Procedures/Records/ Performance Points(MAX) Score Inspection Procedures 1 Does the State have a written inspection plan to complete the following? (all types of operators including LNG) (Chapter 5.1) Previous Question B.1 + Chapter 5 Changes + Incorporate LNG Yes = 6.5 No = 0 Needs Improvement = 50% Deduction a Standard Inspections (Including LNG) (Max points = 2) b IMP Inspections (Including DIMP) (Max points = .5) c OQ Inspections (Max points = .5) d Damage Prevention (Max points = .5) e On-Site Operator Training (Max points = .5) f Construction Inspections (Max points = .5) g Incident/Accident Investigations (Max points = 1) h Compliance Follow-up (Max points = 1) SLR Notes: 6.5 6 Yes No Needs Improvement Yes No Needs Improvement Yes No Needs Improvement Yes No Needs Improvement Yes No Needs Improvement Yes No Needs Improvement Yes No Needs Improvement Yes No Needs Improvement You need to develop procedures for Integrity Management inspections and Operator Qualification inspections. 2 Did the written Procedures for selecting operators adequately address key concerns? (Chapter 5.1) Previous 2 2 Question B.2, items a-d are worth .5 point each Yes = 2 No = 0 Needs Improvement = 50% Deduction a Length of time since last inspection Yes No Needs Improvement b History of Operator/unit and/or location (including leakage , incident and compliance history) Yes No Needs Improvement c Type of activity being undertaken by operator (construction etc) Yes No Needs Improvement d For large operators, rotation of locations inspected Yes No Needs Improvement SLR Notes: Inspection Performance 3 Did the state inspect all types of operators and inspection units in accordance with time intervals established in its written procedures? (Chapter 5.1) Previous Question B.3 Yes = 2 No = 0 SLR Notes: 2 2 4 Did the state inspection form cover all applicable code requirements addressed on the Federal Inspection forms? (Chapter 5.1 (3)) Previous Question B.4 Yes = 1 No = 0 1 1 SLR Notes: 5 Did state complete all applicable portions of inspection forms? (Chapter 5.1 (3)) Previous Question B.5 Yes = 1 No = 0 1 1 SLR Notes: 6 Did the state initiate appropriate follow-up actions to Safety Related Condition Reports? (Chapter 6.3) Previous Question B.6 Yes = .5 No = 0 SLR Notes: No Safety Related Condition Reports were submitted by operators. DUNS: 102979593 2009 Natural Gas State Program Evaluation .5 NA Kansas KANSAS CORPORATION COMMISSION, Page: 6#
KS NG Program Evaluation, 2009, page 77 Did the state review operator procedures for determining if exposed cast iron pipe was examined for evidence of graphitization and if necessary remedial action was taken? (NTSB) Previous Question B.7 Yes = .5 No = 0 .5 .5 SLR Notes: 8 Did the state review operator procedures for surveillance of cast iron pipelines, including appropriate action resulting from tracking circumferential cracking failures, study of leakage history, or other unusual operating maintenance condition? (Note: See GPTC Appendix G-18 for guidance) (NTSB) Previous Question B.8 Yes = .5 No = 0 SLR Notes: .5 .5 9 Did the state review operator emergency response procedures for leaks caused by excavation damage near buildings and determine whether the procedures adequately address the possibility of multiple leaks and underground migration of gas into nearby buildings Refer to 4/12/01 letter from PHMSA in response to NTSB recommendation P-00-20 and P-00-21? (NTSB) Previous Question B.9 Yes = .5 No = 0 .5 .5 SLR Notes: 10 Did the state review operator records of previous accidents and failures including reported third party damage and leak response to ensure appropriate operator response as required by 192.617? (NTSB) Previous Question B.10 Yes = 1 No = 0 1 1 SLR Notes: 11 SLR Notes: Compliance - 60105(a) States Did the state adequately document sufficient information on probable violations? (Chapter 5.2) Previous Question B.14 Yes = 1 No = 0 Needs Improvement = .5 1 1 12 SLR Notes: Does the state have written procedures to identify the steps to be taken from the discovery to the resolution of a probable violation as specified in the "Guidelines for State Participating in the Pipeline Safety Program"? (Chapter 5.1) Previous Question D(1).1 Yes = 1 No = 0 Needs Improvement = .5 1 1 13 SLR Notes: Does the state have written procedures to notify an operator when a noncompliance is identified as specified in the "Guidelines for States Participating in the Pipeline Safety Program"? (Chapter 5.1(4)) Previous Question D (1).2 Yes = 1 No = 0 Needs Improvement = .5 1 1 14 Does the state have a written procedure for routinely reviewing the progress of compliance actions to prevent delays or breakdowns of the enforcement process, as required by the "Guidelines for States Participating in the Pipeline Safety Program"? (Chapter 5.1(5)) Previous Question D(1).3 Yes = 1 No = 0 Needs Improvement = .5 1 1 SLR Notes: complete. Procedures for extended time to correct probably violations, should be clarified. This should include when the correction may require one or more years to DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 7#
KS NG Program Evaluation, 2009, page 815 Has the State issued compliance actions for all probable violations discovered? (Note : PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation) Previous Question D(1).4 Yes = 1 No = 0 SLR Notes: 1 1 16 SLR Notes: Did the state follow its written procedures for reviewing compliance actions and follow-up to determine that prompt corrective actions were taken by operators, within the time frames established by the procedures and compliance correspondence, as required by the "Guidelines for States Participating in the Pipeline Safety Program"? Previous Question D(1).5 Yes = 1 No = 0 Needs Improvement = .5 1 1 17 If compliance could not be established by other means, did state pipeline safety program staff request formal action, such as a "Show Cause Hearing" to correct pipeline safety violations? (check each states enforcement procedures) Previous Question D(1).6 No = 0 Yes = 1 SLR Notes: No "Show Cause" hearings were required. 1 NA 18 SLR Notes: Did the state adequately document the resolution of probable violations? (Chapter 5.1 (6)) Previous Question D(1).7 Yes = 1 No = 0 Needs Improvement = .5 1 1 19 SLR Notes: Were compliance actions sent to a company officer? (manager or board member if municipal/government system) (Chapter 5.1(4)) Previous Question D(1).8 Yes = .5 No = 0 .5 .5 20 SLR Notes: Did the compliance proceedings give reasonable due process to all parties? (check each states enforcement procedures) Previous Question D(1).9 Yes = 1 No = 0 Needs Improvement = .5 1 1 Compliance - 60106(a) States 21 Did the state use the current federal inspection form(s)? Previous Question D(2).1 Yes = 1 No = 0 Needs Improvement = .5 SLR Notes: 1 NA 22 SLR Notes: Are results adequately documented demonstrating inspection units were reviewed in accordance with state inspection plan? Previous Question D(2).2 Yes = 1 No = 0 Needs Improvement = .5 1 NA 23 SLR Notes: DUNS: 102979593 2009 Natural Gas State Program Evaluation Were any probable violations identified by state referred to PHMSA for compliance? (NOTE: PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation.) Previous Question D(2).3 Yes = 1 No = 0 Needs Improvement = .5 1 NA Kansas KANSAS CORPORATION COMMISSION, Page: 8#
KS NG Program Evaluation, 2009, page 924 Did the state immediately report to PHMSA conditions which may pose an imminent safety hazard to the public or to the environment? Previous Question D(2).4 Yes = 1 No = 0 Needs Improvement = .5 1 NA SLR Notes: 25 Did the state give written notice to PHMSA within 60 days of all probable violations found? Previous Question D(2).5 Yes = 1 No = 0 Needs Improvement = .5 1 NA SLR Notes: 26 Did the state initially submit adequate documentation to support compliance action by PHMSA on probable violations? Previous Question D(2).6 Yes = 1 No = 0 Needs Improvement = .5 1 NA SLR Notes: 27 Part B: General Comments/Regional Observations Info Only = No Points Info Only Info Only SLR Notes: Total points scored for this section: 23 Total possible points for this section: 23.5 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 9#
KS NG Program Evaluation, 2009, page 10PART C - Interstate Agent States Points(MAX) Score 1 Did the state use the current federal inspection form(s)? Previous Question D(3).1 Yes = 1 No = 0 Needs Improvement = .5 1 NA SLR Notes: 2 Are results documented demonstrating inspection units were reviewed in accordance with "PHMSA directed inspection plan"? Previous Question D(3).2 Yes = 1 No = 0 Needs Improvement = .5 1 NA SLR Notes: 3 Did the state submit documentation of the inspections within 60 days as stated in its latest Interstate Agent Agreement form? Previous Question D(3).3 Yes = 1 No = 0 1 NA SLR Notes: 4 Were any probable violations identified by state referred to PHMSA for compliance? (NOTE: PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation.) Previous Question D(3).4 Yes = 1 No = 0 1 NA SLR Notes: 5 Did the state immediately report to PHMSA conditions which may pose an imminent safety hazard to the public or to the environment? Previous Question D(3).5 Yes = 1 No = 0 Needs Improvement = .5 1 NA SLR Notes: 6 Did the state give written notice to PHMSA within 60 days of all probable violations found? Previous Question D(3).6 Yes = 1 No = 0 SLR Notes: 1 NA 7 Did the state initially submit documentation to support compliance action by PHMSA on probable violations? Previous Question D(3).7 Yes = 1 No = 0 Needs Improvement = .5 1 NA SLR Notes: 8 Part C: General Comments/Regional Observations Info Only = No Points SLR Notes: Info Only Info Only Total points scored for this section: 0 Total possible points for this section: 0 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 10#
KS NG Program Evaluation, 2009, page 11PART D - Incident Investigations Points(MAX) Score 1 Are state personnel following the procedures for Federal/State cooperation in case of an incident? (See Appendix in "Guidelines for States Participating in the Pipeline Safety Program") (Chapter 6.1) Previous Question E.1 Yes = 1 No = 0 Needs Improvement = .5 SLR Notes: 1 1 2 Are state personnel familiar with the jurisdictional authority and Memorandum of Understanding between NTSB and PHMSA? (See Appendix in "Guidelines for States Participating in the Pipeline Safety Program") (Chapter 6 ? Appendix D) Previous Question E.2 Yes = .5 No = 0 SLR Notes: .5 .5 3 Did the state keep adequate records of incident notifications received? Previous Question E.3 Yes = 1 No = 0 Needs Improvement = .5 1 1 SLR Notes: 4 If an onsite investigation of an incident was not made, did the state obtain sufficient information by other means to determine the facts and support the decision not to go on-site? Previous Question E.4 Yes = 1 No = 0 Needs Improvement = .5 1 1 SLR Notes: 5 Were investigations thorough and conclusions and recommendations documented in an acceptable manner? Previous Question E.5, comprehensive question worth 2 points total Yes = 2 No = 0 Needs Improvement = 1 a. Observations and Document Review b. Contributing Factors c. Recommendations to prevent recurrences where appropriate 2 2 Yes No Needs Improvement Yes No Needs Improvement Yes No Needs Improvement SLR Notes: 6 Did the state initiate enforcement action for violations found during any incident investigation(s)? Previous Question E.6 Variation Yes = 1 No = 0 Needs Improvement = .5 SLR Notes: Three probable violations were identified. 1 1 7 Did the state assist region office by taking appropriate follow-up actions related to the operator incident reports to ensure accuracy and final report has been received by PHMSA? (validate annual report data from operators concerning incidents/accidents and investigate discrepancies) (Chapter 6) Previous Question E.7/E.8 Yes = .5 No = 0 SLR Notes: .5 0.5 8 Part D: General Comments/Regional Observations Info Only = No Points SLR Notes: Info Only Info Only DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 11#
KS NG Program Evaluation, 2009, page 12Total points scored for this section: 7 Total possible points for this section: 7 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 12#
KS NG Program Evaluation, 2009, page 13PART E - Damage Prevention Initiatives Points(MAX) Score 1 Has the state reviewed directional drilling/boring procedures of each pipeline operator or its contractor to determine if they include actions to protect their facilities from the dangers posed by drilling and other trench less technologies? Previous Question B.11 Yes = 2 No = 0 Needs Improvement = 1 2 2 SLR Notes: The state of Kansas has requirements for excavators the conduct trenchless methods. 2 Did the state inspector check to assure the pipeline operator is following its written procedures pertaining to notification of excavation, marking, positive response and the availability and use of the one call system? New 2008 Yes = 2 No = 0 2 2 SLR Notes: 3 Did the state encourage and promote the adoption of the Common Ground Alliance Best Practices document to its regulated companies as a means of reducing damages to all underground facilities? Previous Question A.7 Yes = 2 No = 0 Needs Improvement = 1 2 2 SLR Notes: The Pipeline Safety Division regularly attend regional CGA meetings. 4 Has the agency or another organization within the state collected data and evaluated trends on the number of pipeline damages per 1,000 locate requests? New 2008 Yes = 1 No = 0 1 1 SLR Notes: Operators of pipelines must report damage to pipelines caused by excavation to the One-Call Center. 5 Did the state review operators' records of accidents and failures due to excavation damage to ensure causes of failure are addressed to minimize the possibility of recurrence as required by 192.617? Yes = 2 No = 0 2 2 SLR Notes: Inspections include the review of operator's investigations of accidents and familures. This has been elevated to a high priority. 6 Part E: General Comments/Regional Observations Info Only = No Points Info Only Info Only SLR Notes: Total points scored for this section: 9 Total possible points for this section: 9 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 13#
KS NG Program Evaluation, 2009, page 14PART F - Field Inspection Points(MAX) Score 1 Operator, Inspector, Location, Date and PHMSA Representative Info Only = No Points Name of Operator Inspected: Kansas Gas Service Name of State Inspector(s) Observed: Barry Flohrschutz, Jim Gorman Location of Inspection: Atchison, Kansas Date of Inspection: April 7, 2010 Name of PHMSA Representative: Leonard Steiner Info Only Info Only SLR Notes: 2 Was the operator or operator's representative notified and/or given the opportunity to be present during inspection? New 2008 Yes = 1 No = 0 SLR Notes: All required representatives of the operator were present. 1 1 3 Did the inspector use an acceptable inspection form/checklist and was the form/checklist used as a guide for the inspection? (New regulations shall be incorporated) Previous Question F.2 Yes = 2 No = 0 2 2 SLR Notes: 4 Did the inspector thoroughly document results of the inspection? Previous Question F.3 Yes = 2 No = 0 2 2 SLR Notes: 5 Did the inspector check to see if the operator had necessary equipment during inspection to conduct tasks viewed? (Maps, pyrometer, soap spray, CGI, etc.) New 2008 Yes = 1 No = 0 SLR Notes: This was a records inspection. 1 NA 6 What type of inspection(s) did the state inspector conduct during the field portion of the state evaluation? (i.e. Standard, Construction, IMP, etc) New 2008 Info Only = No Points SLR Notes: Standard inspection Info Only Info Only 7 Did the inspector adequately review the following during the field portion of the state evaluation? (check all that apply on list) New 2008, comprehensive question worth 2 points total Yes = 2 No = 0 Needs Improvement = 1 a. Procedures b. Records c. Field Activities/Facilities d. Other (Please Comment) 2 2 SLR Notes: DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 14#
KS NG Program Evaluation, 2009, page 158 Did the inspector have adequate knowledge of the pipeline safety program and regulations? (Liaison will document reasons if unacceptable) Previous Question F.8 Yes = 2 No = 0 2 2 SLR Notes: 9 Did the inspector conduct an exit interview? (If inspection is not totally complete the interview should be based on areas covered during time of field evaluation) Previous Question F.10 Yes = 1 No = 0 1 1 SLR Notes: 10 During the exit interview, did the inspector identify probable violations found during the inspections? Previous Question F.11 Yes = 1 No = 0 1 1 SLR Notes: No probable violations were discovered. 11 What did the inspector observe in the field? (Narrative description of field observations and how inspector Info Only Info Only performed) Info Only = No Points SLR Notes: On April 7, 2010, I observed Barry Florschultz and Jim Gorman conducting a standard inspection of Kansas Gas Service, an operator of distribution pipelines in Kansas. This inspection was conducted at Atchison, Kansas in the operators area office. The inspection was of the field records for operation and maintenance of the Atchison unit. I observed the inspectors arriving at the designated time and place. The operator was adequately notified of the purpose of the inspection and the appropiate operator's employees were available to assist in the inspection. The records were divided between the two inspectors and were adequately inspected, and the results were documented. Each inspector asked questions if the records were unclear. Both inspector conducted their respective inspection portion in a professional and courteous manner. At the conclusion, an exiting briefing was conducted and no probable violations were discovered. 12 Best Practices to Share with Other States - (Field - could be from operator visited or state inspector practices) Info Only = No Points SLR Notes: No best practices identified to share. Info Only Info Only 13 Field Observation Areas Observed (check all that apply) Info Only = No Points a. Abandonment b. Abnormal Operations c. Break-Out Tanks d. Compressor or Pump Stations e. Change in Class Location f. Casings g. Cathodic Protection h. Cast-iron Replacement i. Damage Prevention j. Deactivation k. Emergency Procedures l. Inspection of Right-of-Way m. Line Markers n. Liaison with Public Officials o. Leak Surveys p. MOP Info Only Info Only DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 15#
KS NG Program Evaluation, 2009, page 16q. MAOP r. Moving Pipe s. New Construction t. Navigable Waterway Crossings u. Odorization v. Overpressure Safety Devices w. Plastic Pipe Installation x. Public Education y. Purging z. Prevention of Accidental Ignition A. Repairs B. Signs C. Tapping D. Valve Maintenance E. Vault Maintenance F. Welding G. OQ - Operator Qualification H. Compliance Follow-up I. Atmospheric Corrosion J. Other SLR Notes: 14 Part F: General Comments/Regional Observations Info Only = No Points SLR Notes: DUNS: 102979593 2009 Natural Gas State Program Evaluation Info Only Info Only Total points scored for this section: 11 Total possible points for this section: 11 Kansas KANSAS CORPORATION COMMISSION, Page: 16#
KS NG Program Evaluation, 2009, page 17PART G - PHMSA Initiatives - Strategic Plan Points(MAX) Score Risk base Inspections - Targeting High Risk Areas 1 Does state have process to identify high risk inspection units? Yes = 1.5 No = 0 Risk Factors (criteria) to consider may include: Miles of HCA's, Geographic area, Population Density Length of time since last inspection History of Individual Operator units (leakage, incident and compliance history, etc.) Threats - (Excavation Damage, Corrosion, Natural Forces, Other Outside Forces, Material or Welds, Equipment, Operations, Other) 1.5 1.5 SLR Notes: 2 Are inspection units broken down appropriately? (see definitions in Guidelines) Yes = .5 No = 0 .5 0.5 SLR Notes: 3 Consideration of operators DIMP Plan? (if available and pending rulemaking) Info Only = No Points SLR Notes: No DIMP plans have been developed. Info Only Info Only 4 Does state inspection process target high risk areas? Yes = .5 No = 0 .5 0.5 SLR Notes: Use of Data to Help Drive Program Priority and Inspections 5 Does state use data to analyze effectiveness of damage prevention efforts in the state? (DIRT or other data, etc) Yes = .5 No = 0 SLR Notes: All operators are required to report damages and the operators report into DIRT. .5 0.5 6 Has state reviewed data on Operator Annual reports for accuracy? Yes = .5 No = 0 SLR Notes: The Annual Reports are reviewed for accuracy. It is suggested that each report be notated when and who reviewed the report. .5 0.5 7 Has state analyzed annual report data for trends and operator issues? Yes = .5 No = 0 SLR Notes: The lost and unaccounted gas is analyzed. They should review what additional areas to analyze. .5 0.5 8 Has state reviewed data on Incident/Accident reports for accuracy? Yes = .5 No = 0 SLR Notes: Incident reports are reviewed for accuracy. .5 0.5 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 17#
KS NG Program Evaluation, 2009, page 189 Does state do evaluation of effectiveness of program based on data? (i.e. performance measures, trends, etc.) .5 0.5 Yes = .5 No = 0 SLR Notes: others. Kansas evaluated their program from several tracked data points, loss and unaccounted for gas, damages versus tickets, number of possible incidents, and 10 SLR Notes: Did the State input all operator qualification inspection results into web based database provided by PHMSA in a timely manner upon completion of OQ inspections? Previous Question B.15 Yes = .5 No = 0 .5 0.5 11 Did the State submit their replies into the Integrity Management Database (IMDB) in response to the Operators notifications for their integrity management program? Previous Question B.16 Yes = .5 No = 0 SLR Notes: No IMP inspections conducted. .5 NA 12 SLR Notes: Have the IMP Federal Protocol forms been uploaded to the IMDB? Previous Question B.17 Yes = .5 No = 0 .5 0.5 13 SLR Notes: Did the State ask Operators to identify any plastic pipe and components that has shown a record of defects/leaks and what those operators are doing to mitigate the safety concerns? Previous Question B.18 Yes = .5 No = 0 .5 0.5 14 SLR Notes: Has state confirmed transmission operators have submitted information into National Pipeline Mapping System (NPMS) database along with any changes made after original submission? Yes = .5 No = 0 .5 0.5 Accident/Incident Investigation Learning and Sharing Lessons Learned 15 Has state shared lessons learned from incidents/accidents? (i.e. NAPSR meetings and communications) Yes = .5 No = 0 SLR Notes: Kansas uses the PHMSA forum. .5 0.5 16 Does the State support data gathering efforts concerning accidents? (Frequency/Consequence/etc) .5 0.5 Yes = .5 No = 0 SLR Notes: Kansas supports DIRT reporting, and all operators must report damages to Kansas One-Call. 17 SLR Notes: Not yet. Does state have incident/accident criteria for conducting root cause analysis? Info Only = No Points Info Only Info Only 18 Does state conduct root cause analysis on incidents/accidents in state? Info Only = No Points DUNS: 102979593 2009 Natural Gas State Program Evaluation Info Only Info Only Kansas KANSAS CORPORATION COMMISSION, Page: 18#
KS NG Program Evaluation, 2009, page 19SLR Notes: NO 19 Has state participated on root cause analysis training? (can also be on wait list) Yes = .5 No = 0 .5 0.5 SLR Notes: Transparency - Communication with Stakeholders 20 Other than pipeline safety seminar does State communicate with stakeholders? (Communicate program data, pub awareness, etc.) Yes = .5 No = 0 .5 0.5 SLR Notes: Kansas uses the One-Call system to diseminate information to operators. 21 Does state share enforcement data with public? (Website, newsletters, docket access, etc.) Yes = .5 No = 0 .5 0.5 SLR Notes: All enforcement actions are "docketed" and available on the Commission website. 22 Part G: General Comments/Regional Observations Info Only = No Points Info Only Info Only SLR Notes: Total points scored for this section: 9.5 Total possible points for this section: 9.5 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 19#
KS NG Program Evaluation, 2009, page 20PART H - Miscellaneous Points(MAX) Score 1 What were the major accomplishments for the year being evaluated? (Describe the accomplishments, NAPSR Activities and Participation, etc.) Yes = .5 No = 0 .5 0.5 SLR Notes: Completed review of large LDC mobile leak survey methodology, reviewed training sessions for large LDC supervisors, surveyed gas gathering systems to determine if they are regulated, participated in the organization of OQ requalification training for municipals. 2 What legislative or program initiatives are taking place/planned in the state, past, present, and future? (Describe initiatives (i.e. damage prevention, jurisdiction/authority, compliance/administrative, etc.) Yes = .5 No = 0 .5 0.5 SLR Notes: Support for requiring that all operators of underground facilities to participate in the Kansas One-Call System. 3 Any Risk Reduction Accomplishments/Projects? (i.e. Cast iron replacement projects,bare steel,third-party damage reductions, etc.) Yes = .5 No = 0 .5 0.5 SLR Notes: Three operators must remove Cast iron pipe, and remove bare steel pipe. Operators can report third partydamage by e-mail. 4 Did the state participate in/respond to surveys or information requests from NAPSR or PHMSA? Yes = 1 No = 0 1 1 SLR Notes: 5 Sharing Best Practices with Other States - (General Program) Yes = .5 No = 0 .5 0.5 SLR Notes: Excellent participation in region meetings. 6 Part H: General Comments/Regional Observations Info Only = No Points Info Only Info Only SLR Notes: Total points scored for this section: 3 Total possible points for this section: 3 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 20#
KS NG Program Evaluation, 2009, page 21PART I - Program Initiatives Points(MAX) Score Drug and Alcohol Testing (49 CFR Part 199) 1 Has the state verified that operators have drug and alcohol testing programs? Yes = 1 No = 0 SLR Notes: 1 1 2 Is the state verifying that operators are conducting the drug and alcohol tests required by the operators program (random, post-incident, etc.) Yes = .5 No = 0 SLR Notes: .5 0.5 3 Is the state verifying that any positive tests are responded to in accordance with the operator's program? Yes = .5 No = 0 .5 0.5 SLR Notes: Qualification of Pipeline Personnel (49 CFR Part 192 Subpart N) 4 Has the state verified that operators have a written qualification program? Yes = 1 No = 0 1 1 SLR Notes: 5 Has the state reviewed operator qualification programs for compliance with PHMSA rules and protocols? Yes = .5 No = 0 .5 0.5 SLR Notes: 6 Is the state verifying that persons who perform covered tasks for the operator are qualified in accordance with the operator's program? Yes = .5 No = 0 SLR Notes: .5 0.5 7 Is the state verifying that persons who perform covered task for the operator are requalified at the intervals specified in the operator's program? Yes = .5 No = 0 .5 0.5 SLR Notes: Gas Transmission Pipeline Integrity Management (49 CFR Part 192 Subpart O) 8 Has the state verified that all operators with transmission pipelines have either adopted an integrity management program (IMP), or have properly determined that one is not required? Yes = 1 No = 0 1 1 SLR Notes: 9 Has the state verified that in determining whether a plan is required, the operator correctly calculated the potential impact radii and properly applied the definition of a high consequence area? Yes = .5 No = 0 SLR Notes: They have a question about the PIR calculation. DUNS: 102979593 2009 Natural Gas State Program Evaluation .5 0.5 Kansas KANSAS CORPORATION COMMISSION, Page: 21#
KS NG Program Evaluation, 2009, page 2210 Has the state reviewed operator IMPs for compliance with Subpart O? (In accordance with State Inspection plan) Yes = .5 No = 0 SLR Notes: .5 0.5 11 SLR Notes: Is the state monitoring operator progress on the inspections, tests and remedial actions required by the operator's IMP, including that they are being done in the manner and schedule called for in its IMP? Yes = .5 No = 0 .5 0.5 12 Is the state verifying that operators are periodically examining their transmission line routes for the appearance of new HCAs? Yes = .5 No = 0 SLR Notes: Kansas requires operators to examine transmission pipelines once a year. .5 0.5 13 SLR Notes: Public Awareness (49 CFR Section 192.616) Has the state verified that each operator has developed a continuing public awareness program? (due date was 6/20/06 for most operators, 6/20/07 for certain very small operators,6/13/08 for master meters) Yes = .5 No = 0 .5 0.5 14 SLR Notes: Has the state reviewed the content of these programs for compliance with 192.616 (by participating in the Clearinghouse or by other means)? Yes = .5 No = 0 .5 0.5 15 SLR Notes: Is the state verifying that operators are conducting the public awareness activities called for in its program? Yes = .5 No = 0 .5 0.5 16 Is the state verifying that operators have evaluated their Public Awareness programs for effectiveness as described in RP1162? Info Only = No Points SLR Notes: Kansas has several questions about the Public Awareness porgrams on the inspection form. Info Only Info Only 17 Part I: General Comments/Regional Observations Info Only = No Points SLR Notes: Info Only Info Only Total points scored for this section: 9 Total possible points for this section: 9 DUNS: 102979593 2009 Natural Gas State Program Evaluation Kansas KANSAS CORPORATION COMMISSION, Page: 22#