PHMSA nc2014ngprogramevaluation
PHMSA nc2014ngprogramevaluation
NC NG Program Evaluation, 2014, page 1Official PDF1200 New Jersey Avenue SE Washington DC 20590 U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration 2014 Gas State Program Evaluation for NORTH CAROLINA UTILITIES COMMISSION Document Legend PART: O -- Representative Date and Title Information A -- Progress Report and Program Documentation Review B -- Program Inspection Procedures C -- Program Performance D -- Compliance Activities E -- Incident Investigations F -- Damage Prevention G -- Field Inspections H -- Interstate Agent State (If Applicable) I -- 60106 Agreement State (If Applicable) DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 1#
NC NG Program Evaluation, 2014, page 22014 Gas State Program Evaluation -- CY 2014 Gas State Agency: North Carolina Rating: Agency Status: Date of Visit: 06/15/2015 - 06/19/2015 Agency Representative: John Hall PHMSA Representative: Leonard Steiner Commission Chairman to whom follow up letter is to be sent: Name/Title: Edward S. Finley, Chairman Agency: North Carolina Utilities Commission Address: 430 North Salisbury Street. Dobbs Building City/State/Zip: Raleigh, North Carolina 27603-5918 60105(a): Yes 60106(a): No Interstate Agent: No INSTRUCTIONS: Complete this evaluation in accordance with the Procedures for Evaluating State Pipeline Safety Program. The evaluation should generally reflect state program performance during CY 2014 (not the status of performance at the time of the evaluation). All items for which criteria have not been established should be answered based on the PHMSA representative's judgment. A deficiency in any one part of a multiple part question should be scored as needs improvement. Determine the answer to the question then select the appropriate point value. If a state receives less then the maximum points, include a brief explanation in the space provided for general comments/regional observations. If a question is not applicable to a state, select NA. Please ensure all responses are COMPLETE and ACCURATE, and OBJECTIVELY reflect state program performance. Increasing emphasis is being placed on performance. This evaluation together with selected factors reported in the state's annual progress report attachments provide the basis for determining the state's pipeline safety grant allocation. Field Inspection (PART G): The field inspection form used will allow different areas of emphasis to be considered for each question. Question 13 is provided for scoring field observation areas. In completing PART G, the PHMSA representative should include a written summary which thoroughly documents the inspection. Scoring Summary PARTS Possible Points Points Scored A Progress Report and Program Documentation Review 10 10 B Program Inspection Procedures 13 13 C Program Performance 44 44 D Compliance Activities 15 15 E Incident Investigations 11 11 F Damage Prevention 8 8 G Field Inspections 12 12 H Interstate Agent State (If Applicable) 0 0 I 60106 Agreement State (If Applicable) 0 0 TOTALS 113 113 State Rating................................................................................................................................................... 100.0 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 2#
NC NG Program Evaluation, 2014, page 3PART A - Progress Report and Program Documentation Review Points(MAX) Score 1 Accuracy of Jurisdictional Authority and Operator/Inspection Units Data - Progress Report Attachment 1 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Correct on progress report. 1 1 2 Review of Inspection Days for accuracy - Progress Report Attachment 2 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Correct on progress report. 1 1 3 Accuracy verification of Operators and Operators Inspection Units in State - Progress Report Attachment 3 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Correct on progress report. 1 1 4 Were all federally reportable incident reports listed and information correct? - Progress Report Attachment 4 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Two incidents were reported. One incident will be on the Commission's docket. 1 1 5 Accuracy verification of Compliance Activities - Progress Report Attachment 5 1 1 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Correct on progress report. 6 Were pipeline program files well-organized and accessible? - Progress Report Attachment 6 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes 2 2 7 Was employee listing and completed training accurate and complete? - Progress Report Attachment 7 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Correct on progress report. 1 1 8 Verification of Part 192,193,198,199 Rules and Amendments - Progress Report Attachment 8 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Correct on progress report. 1 1 9 List of Planned Performance - Did state describe accomplishments on Progress Report in detail - Progress Report Attachment 10 Yes = 1 No = 0 Needs Improvement = .5 1 1 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 3#
NC NG Program Evaluation, 2014, page 4Evaluator Notes: 10 General Comments: Info Only = No Points Evaluator Notes: Info Only Info Only Total points scored for this section: 10 Total possible points for this section: 10 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 4#
NC NG Program Evaluation, 2014, page 5PART B - Program Inspection Procedures Points(MAX) Score 1 Standard Inspection procedures should give guidance to state inspectors that insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: 2 2 2 IMP and DIMP Inspection procedures should give guidance to state inspectors that insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 1 3 OQ Inspection procedures should give guidance to state inspectors that insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 1 4 Damage Prevention Inspection procedures should give guidance to state inspectors that insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post- inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 1 5 Any operator training conducted should be outlined and appropriately documented as needed. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 1 6 Construction Inspection procedures should give guidance to state inspectors that insure consistency in all inspections conducted by the state? The following elements should be addressed at a minimum - pre-inspection activities, inspection activities, post-inspection activities. Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 1 DUNS: 780414723 2014 Gas State Program Evaluation 7 Does inspection plan address inspection priorities of each operator, and if necessary each 6 6 unit, based on the following elements? Yes = 6 No = 0 Needs Improvement = 1-5 a. Length of time since last inspection (Within five year interval) Yes No Needs Improvement b. Operating history of operator/unit and/or location (includes leakage, incident and compliance activities) Yes No Needs Improvement North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 5#
NC NG Program Evaluation, 2014, page 6c. Type of activity being undertaken by operators (i.e. construction) Yes No Needs Improvement d. Locations of operators inspection units being inspected - (HCA's, Geographic areas, Population Density, etc) Yes No Needs Improvement e. Process to identify high-risk inspection units that includes all threats - (Excavation Damage, Corrosion, Natural Forces, Outside Forces, Material and Welds, Equipment, Yes No Needs Improvement Operators and any Other Factors) f. Are inspection units broken down appropriately? Yes No Needs Improvement Evaluator Notes: 8 General Comments: Info Only = No Points Evaluator Notes: Info Only Info Only Total points scored for this section: 13 Total possible points for this section: 13 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 6#
NC NG Program Evaluation, 2014, page 7PART C - Program Performance Points(MAX) Score 1 Was ratio of Total Inspection person-days to total person days acceptable? (Director of State Programs may modify with just cause) Chapter 4.3 Yes = 5 No = 0 A. Total Inspection Person Days (Attachment 2): 533.00 B. Total Inspection Person Days Charged to the Program (220 X Inspection Person Years) (Attachment 7): 220 X 3.95 = 869.00 Ratio: A / B 533.00 / 869.00 = 0.61 If Ratio >= 0.38 Then Points = 5, If Ratio < 0.38 Then Points = 0 Points = 5 Evaluator Notes: Ration is .61 5 5 2 Has each inspector and program manager fulfilled the T Q Training Requirements? (See 5 5 Guidelines Appendix C for requirements) Chapter 4.4 Yes = 5 No = 0 Needs Improvement = 1-4 a. Completion of Required OQ Training before conducting inspection as lead? Yes No Needs Improvement b. Completion of Required DIMP*/IMP Training before conducting inspection as lead? *Effective Evaluation CY2013 Yes No Needs Improvement c. Root Cause Training by at least one inspector/program manager Yes No Needs Improvement d. Note any outside training completed Yes No Needs Improvement e. Verify inspector has obtained minimum qualifications to lead any applicable standard inspection as the lead inspector. Yes No Needs Improvement Evaluator Notes: No outside training received. 3 Did state records and discussions with state pipeline safety program manager indicate adequate knowledge of PHMSA program and regulations? Chapter 4.1,8.1 Yes = 2 No = 0 Needs Improvement = 1 2 2 Evaluator Notes: 4 Did state respond to Chairman's letter on previous evaluation within 60 days and correct or address any noted deficiencies? (If necessary) Chapter 8.1 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes, Commission addressed all issues. 2 2 5 Did State hold PHMSA TQ Seminar in Past 3 Years? Chapter 8.5 Yes = 2 No = 0 Evaluator Notes: In CY 2013. 2 2 6 Did state inspect all types of operators and inspection units in accordance with time intervals established in written procedures? Chapter 5.1 Yes = 5 No = 0 Needs Improvement = 1-4 Evaluator Notes: Yes DUNS: 780414723 2014 Gas State Program Evaluation 5 5 North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 7#
NC NG Program Evaluation, 2014, page 87 Did inspection form(s) cover all applicable code requirements addressed on Federal Inspection form(s)? Did State complete all applicable portions of inspection forms? Chapter 5.1 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: North Carolina uses a modified PHMSA inspection form. 2 2 8 Did the state review operator procedures for determining if exposed cast iron pipe was examined for evidence of graphitization and if necessary remedial action was taken? (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: No known cast iron in North Carolina. 1 NA 9 Did the state review operator procedures for surveillance of cast iron pipelines, including appropriate action resulting from tracking circumferential cracking failures, study of leakage history, or other unusual operating maintenance condition? (Note: See GPTC Appendix G-18 for guidance) (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: No known cast iron in North Carolina. 1 NA 10 Did the state review operator emergency response procedures for leaks caused by excavation damage near buildings and determine whether the procedures adequately address the possibility of multiple leaks and underground migration of gas into nearby buildings Refer to 4/12/01 letter from PHMSA in response to NTSB recommendation P-00-20 and P-00-21? (NTSB) Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: Has a question on their inspection form. 1 1 11 Did the state review operator records of previous accidents and failures including reported third party damage and leak response to ensure appropriate operator response as required by 192.617? Chapter 5.1 Yes = 1 No = 0 Evaluator Notes: they have a question on their inspection form. 1 1 12 Has the state reviewed Operator Annual reports, along with Incident/Accident reports, for accuracy and analyzed data for trends and operator issues? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: All Annual Reports are inspected and data collected and analyzed by Mr. Hall. 2 2 13 Did state input all applicable OQ, IMP inspection results into federal database in a timely manner? This includes replies to Operator notifications into IMDB database. Chapter 5.1 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes verified they were entered. 2 2 14 DUNS: 780414723 2014 Gas State Program Evaluation Has state confirmed intrastate transmission operators have submitted information into NPMS database along with changes made after original submission? 1 1 North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 8#
NC NG Program Evaluation, 2014, page 9Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Yes, and compares the mileage vs NPMS mileage. 15 Is the state verifying operators are conducting drug and alcohol tests as required by regulations? This should include verifying positive tests are responded to in accordance with program. 49 CFR 199 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: 2 2 North Carolina did not conduct any D&A inspections in CY2014, verified that random testing was conducted. 16 Is state verifying operators OQ programs are up to date? This should include verification of any plan updates and that persons performing covered tasks (including contractors) are properly qualified and requalified at intervals determined in the operators plan. 49 CFR 192 Part N Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: they focus on conducting Protocol 9 inspections. 2 2 17 Is state verifying operator's gas transmission integrity management programs (IMP) are up to date? This should include a previous review of IMP plan, along with monitoring progress on operator tests and remedial actions. In addition, the review should take in to account program review and updates of operators plan(s). 49 CFR 192 Subpart 0 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: The inspectors monitor the progress of assessments. 2 2 18 Is state verifying operator's gas distribution integrity management Programs (DIMP)? This should include a review of DIMP plans, along with monitoring progress. In addition, the review should take in to account program review and updates of operators plan(s). 49 CFR 192 Subpart P DIMP ? First round of program inspections should be complete by December 2014 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: North Carolina has completed all initial DIMP inspections. 2 2 19 Is state verifying operators Public Awareness programs are up to date and being followed. State should also verify operators have evaluated Public Awareness programs for effectiveness as described in RP1162. 49 CFR 192.616 (I13-16) PAPEI Effectiveness Inspections should have been completed by December 2013 Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Have completed all initial PAPEE inspections, and have scheduled the next inspections. 2 2 20 Does the state have a mechanism for communicating with stakeholders - other than state pipeline safety seminar? (This should include making enforcement cases available to public). Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: North Carolina has a commission website and they post violations discovered during inspections. 1 1 21 DUNS: 780414723 2014 Gas State Program Evaluation Did state execute appropriate follow-up actions to Safety Related Condition (SRC) Reports? Chapter 6.3 Yes = 1 No = 0 Needs Improvement = .5 1 1 North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 9#
NC NG Program Evaluation, 2014, page 10Evaluator Notes: The SRCs have been corrected but have not been closed by PHMSA. 22 Did the State ask Operators to identify any plastic pipe and components that has shown a 1 1 record of defects/leaks and what those operators are doing to mitigate the safety concerns? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: They have a question on their inspection form to determine if operators are look for pipe and components that are prone to failure. 23 Did the state participate in/respond to surveys or information requests from NAPSR or PHMSA? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 1 24 If the State has issued any waivers/special permits for any operator, has the state verified conditions of those waivers/special permits are being met? This should include having the operator amend procedures where appropriate.(New Question for CY2013, no points until CY2015 evaluation conducted in CY2016) Info Only = No Points Evaluator Notes: No waivers were issued in CY2014. 0 0 25 Did the state attend the National NAPSR Board of Directors Meeting in CY being evaluated? (New Question for CY2014, no points first year) Info Only = No Points Evaluator Notes: Yes the Program Manager attended the National meeting. 0 0 26 Discussion on State Program Performance Metrics found on Stakeholder Communication site. (question will be rolled up and included as part of Question C12 on future evaluations) http://primis.phmsa.dot.gov/comm/states.htm Info Only = No Points Evaluator Notes: Yes discussed the website and he is familiar with the data provided. 0 0 27 General Comments: Info Only = No Points Evaluator Notes: Info Only Info Only Total points scored for this section: 44 Total possible points for this section: 44 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 10#
NC NG Program Evaluation, 2014, page 11PART D - Compliance Activities Points(MAX) Score 1 Does the state have written procedures to identify steps to be taken from the discovery to 4 4 resolution of a probable violation? Chapter 5.1 Yes = 4 No = 0 Needs Improvement = 1-3 a. Procedures to notify an operator (company officer) when a noncompliance is identified Yes No Needs Improvement b. Procedures to routinely review progress of compliance actions to prevent delays or breakdowns Yes No Needs Improvement Evaluator Notes: Yes. the NCUC has procedures for implementation in the pipeline safety division. Probably violations that require to be placed on the docket are conducted in accordance with Commission rules. 2 Did the state follow compliance procedures (from discovery to resolution) and adequately 4 4 document all probable violations, including what resolution or further course of action is needed to gain compliance? Chapter 5.1 Yes = 4 No = 0 Needs Improvement = 1-3 a. Were compliance actions sent to company officer or manager/board member if municipal/government system? Yes No Needs Improvement b. Were probable violations documented? Yes No Needs Improvement c. Were probable violations resolved? Yes No Needs Improvement d. Was the progress of probable violations routinely reviewed? Yes No Needs Improvement Evaluator Notes: The notification of probable violations are promptly sent to operators. The response is evaluated and if further action is required, the request for more information is sent. All probable violations were promptly corrected. 3 Did the state issue compliance actions for all probable violations discovered? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: All probable violations discovered had a notice of the probable violations to the operator. 2 2 4 Did compliance actions give reasonable due process to all parties? Including "show cause" hearing if necessary. Yes = 2 No = 0 Evaluator Notes: No actions beyond a notice of probable violation was required. 2 2 5 Is the program manager familiar with state process for imposing civil penalties? Were civil penalties considered for repeat violations (with severity consideration) or violations resulting in incidents/accidents? (describe any actions taken) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. 2 2 6 Can the State demonstrate it is using their enforcement fining authority for pipeline safety violations? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: The NCUC deemed not probable violations met the criteria for a monetary fine. 1 1 7 General Comments: Info Only = No Points Evaluator Notes: DUNS: 780414723 2014 Gas State Program Evaluation Info Only Info Only North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 11#
NC NG Program Evaluation, 2014, page 12Total points scored for this section: 15 Total possible points for this section: 15 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 12#
NC NG Program Evaluation, 2014, page 13PART E - Incident Investigations Points(MAX) Score 1 Does the state have written procedures to address state actions in the event of an incident/ accident? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes, Procedures are adequate. 2 2 2 Does state have adequate mechanism to receive and respond to operator reports of 2 2 incidents, including after-hours reports? And did state keep adequate records of Incident/ Accident notifications received? Chapter 6 Yes = 2 No = 0 Needs Improvement = 1 a. Acknowledgement of MOU between NTSB and PHMSA (Appendix D) Yes No Needs Improvement b. Acknowledgement of Federal/State Cooperation in case of incident/accident (Appendix E) Yes No Needs Improvement Evaluator Notes: The program manager understand the MOUs and aggreements. 3 If onsite investigation was not made, did state obtain sufficient information from the operator and/or by other means to determine the facts to support the decision to not go on-site? Chapter 6 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: There were two incidents and an on-site investigation was conducted. 1 1 4 Were all incidents investigated, thoroughly documented, and with conclusions and recommendations? Yes = 3 No = 0 Needs Improvement = 1-2 a. Observations and document review 3 3 Yes No Needs Improvement b. Contributing Factors Yes No Needs Improvement c. Recommendations to prevent recurrences when appropriate Yes No Needs Improvement Evaluator Notes: The NCUC investigated the incidents and documenting the facts on the PHMSA incident investigation form. Conclusions were documented of the incidents. 5 Did the state initiate compliance action for violations found during any incident/accident investigation? Yes = 1 No = 0 Evaluator Notes: Yes, A serious violation was discovered and a compliance action is in process. 1 1 6 Did the state assist region office by taking appropriate follow-up actions related to the operator incident reports to ensure accuracy and final report has been received by PHMSA? (validate report data from operators concerning incidents/accidents and investigate discrepancies) Chapter 6 Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: Yes, Close coordination is with the Eastern Region. 1 1 7 Does state share lessons learned from incidents/accidents? (sharing information, such as: at NAPSR Region meetings, state seminars, etc) Yes = 1 No = 0 Evaluator Notes: DUNS: 780414723 2014 Gas State Program Evaluation 1 1 North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 13#
NC NG Program Evaluation, 2014, page 14yes, Presented at the Region NAPSR/PHMSA meeting. 8 General Comments: Info Only = No Points Evaluator Notes: Info Only Info Only Total points scored for this section: 11 Total possible points for this section: 11 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 14#
NC NG Program Evaluation, 2014, page 15PART F - Damage Prevention Points(MAX) Score 1 Has the state reviewed directional drilling/boring procedures of each pipeline operator or its contractor to determine if they include actions to protect their facilities from the dangers posed by drilling and other trench less technologies? NTSB Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: The NCUC has questions on their Standard Inspection form. 2 2 2 Did the state inspector check to assure the pipeline operator is following its written procedures pertaining to notification of excavation, marking, positive response and the availability and use of the one call system? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Locating records are inspected during the Standard Inspection of records. 2 2 3 Did the state encourage and promote practices for reducing damages to all underground 2 2 facilities to its regulated companies? (i.e. such as promoting/adopting the CGA Best Practices encouraging adoption of the 9 Elements, etc.) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: The NCUC encourages operators to use the CGA Best Practices in developing their procedures. The pipeline safety works closely with the North Carolina One-Call System. 4 Has the agency or another organization within the state collected data and evaluated trends on the number of pipeline damages per 1,000 locate requests? (This can include DIRT and other data shared and reviewed by the pipeline safety program) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Pipeline Safety collects data from annual reports and analyzes for trends. 2 2 5 General Comments: Info Only = No Points Evaluator Notes: Info Only Info Only Total points scored for this section: 8 Total possible points for this section: 8 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 15#
NC NG Program Evaluation, 2014, page 16PART G - Field Inspections Points(MAX) Score 1 Operator, Inspector, Location, Date and PHMSA Representative Info Only = No Points Name of Operator Inspected: Public Service Company of North Carolina OPID15938 Name of State Inspector(s) Observed: Harry Bryant Location of Inspection: Raleigh-Durham area Date of Inspection: June 17, 2015 Name of PHMSA Representative: Leonard Steiner Evaluator Notes: Info Only Info Only 2 Was the operator or operator's representative notified and/or given the opportunity to be present during inspection? Yes = 1 No = 0 Evaluator Notes: Adequate notice was provided and the operator was prepared. 1 1 3 Did the inspector use an appropriate inspection form/checklist and was the form/checklist used as a guide for the inspection? (New regulations shall be incorporated) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes A modified standard inspection form was used. 2 2 4 Did the inspector thoroughly document results of the inspection? Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Yes. All observations were documented. 2 2 5 Did the inspector check to see if the operator had necessary equipment during inspection to conduct tasks viewed? (Maps,pyrometer,soap spray,CGI,etc.) Yes = 1 No = 0 Evaluator Notes: Yes, a technician was available for any equipment needed. 1 1 2 2 6 Did the inspector adequately review the following during the field portion of the state evaluation? (check all that apply on list) Yes = 2 No = 0 Needs Improvement = 1 a. Procedures b. Records c. Field Activities d. Other (please comment) Evaluator Notes: This inspection was addition to the standard inspection. The purpose was to verify the records of maintenance and operation on the pipeline. While inspecting the records, Mr. Bryant inspected the actions documented in the records. DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 16#
NC NG Program Evaluation, 2014, page 177 Did the inspector have adequate knowledge of the pipeline safety program and regulations? (Evaluator will document reasons if unacceptable) Yes = 2 No = 0 Needs Improvement = 1 Evaluator Notes: Mr. Bryant was very knowledgeable of the regulations. 2 2 8 Did the inspector conduct an exit interview? (If inspection is not totally complete the interview should be based on areas covered during time of field evaluation) Yes = 1 No = 0 Evaluator Notes: Yes, 1 1 9 During the exit interview, did the inspector identify probable violations found during the 1 1 inspections? (if applicable) Yes = 1 No = 0 Evaluator Notes: Yes, one probable violation that could be a hazardous situation was identified, and immediate action was initiated by the operator. 10 General Comments: 1) What did the inspector observe in the field? (Narrative description of field observations and how inspector performed) 2) Best Practices to Share with Other States - (Field - could be from operator visited or state inspector practices) 3) Other. Info Only = No Points a. Abandonment b. Abnormal Operations c. Break-Out Tanks d. Compressor or Pump Stations e. Change in Class Location f. Casings g. Cathodic Protection h. Cast-iron Replacement i. Damage Prevention j. Deactivation k. Emergency Procedures l. Inspection of Right-of-Way m. Line Markers n. Liaison with Public Officials o. Leak Surveys p. MOP q. MAOP r. Moving Pipe s. New Construction t. Navigable Waterway Crossings u. Odorization v. Overpressure Safety Devices w. Plastic Pipe Installation x. Public Education y. Purging z. Prevention of Accidental Ignition A. Repairs B. Signs C. Tapping Info Only Info Only DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 17#
NC NG Program Evaluation, 2014, page 18D. Valve Maintenance E. Vault Maintenance F. Welding G. OQ - Operator Qualification H. Compliance Follow-up I. Atmospheric Corrosion J. Other Evaluator Notes: On June 17, 2015, I, accompanied by John Hall, Program Manager, observed Harry Bryant, a North Carolina pipeline safety inspector conduct one day of a standard inspection. This inspection focused on records that required a follow-up in the maintenance and operations. Mr. Bryant has prepared a list of nine items that he wanted to inspect to ensure the records accurately documented the actions on the facilities. During the inspection, one leak was discovered that was hazardous as defined by the operator's O&M. The operator initiated an immediate action. Mr. Bryant was well prepared and was knowledgeable of the safety regulations and the application of the regulations. Mr. Bryant conducted the inspection in a professional and courteous manner. Total points scored for this section: 12 Total possible points for this section: 12 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 18#
NC NG Program Evaluation, 2014, page 19PART H - Interstate Agent State (If Applicable) Points(MAX) Score 1 Did the state use the current federal inspection form(s)? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 2 Are results documented demonstrating inspection units were reviewed in accordance with "PHMSA directed inspection plan"? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 3 Did the state submit documentation of the inspections within 60 days as stated in its latest Interstate Agent Agreement form? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 4 Were probable violations identified by state referred to PHMSA for compliance? (NOTE: PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation.) Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 5 Did the state immediately report to PHMSA conditions which may pose an imminent safety hazard to the public or to the environment? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 6 Did the state give written notice to PHMSA within 60 days of all probable violations found? Evaluator Notes: Yes = 1 No = 0 Needs Improvement = .5 1 NA 7 Did the state initially submit documentation to support compliance action by PHMSA on probable violations? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 8 General Comments: Info Only = No Points Evaluator Notes: Info Only Info Only Total points scored for this section: 0 Total possible points for this section: 0 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 19#
NC NG Program Evaluation, 2014, page 20PART I - 60106 Agreement State (If Applicable) Points(MAX) Score 1 Did the state use the current federal inspection form(s)? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 2 Are results documented demonstrating inspection units were reviewed in accordance with state inspection plan? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 3 Were any probable violations identified by state referred to PHMSA for compliance? (NOTE: PHMSA representative has discretion to delete question or adjust points, as appropriate, based on number of probable violations; any change requires written explanation.) Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 4 Did the state immediately report to PHMSA conditions which may pose an imminent safety hazard to the public or to the environment? Yes = 1 No = 0 Needs Improvement = .5 1 NA Evaluator Notes: 5 Did the state give written notice to PHMSA within 60 days of all probable violations found? Evaluator Notes: Yes = 1 No = 0 Needs Improvement = .5 1 NA 6 Did the state initially submit adequate documentation to support compliance action by PHMSA on probable violations? Yes = 1 No = 0 Needs Improvement = .5 Evaluator Notes: 1 NA 7 General Comments: Info Only = No Points Evaluator Notes: Info Only Info Only Total points scored for this section: 0 Total possible points for this section: 0 DUNS: 780414723 2014 Gas State Program Evaluation North Carolina NORTH CAROLINA UTILITIES COMMISSION, Page: 20#
This material provides agency context. It does not replace binding regulatory text, and its legal effect depends on the underlying authority and facts.