Regulationcurrent
ARSD 20:10:37:06
20:10:37:06 Inspector's reporting requirements
Current as of 2009-10-19 Government source
South Dakota Public Utilities CommissionOfficial agency material
View source Regardless of the inspection type, the inspector shall complete a post inspection report within 90 days upon completion of the inspection itself. The report shall include a summary of probable noncompliance issues if any exist. As applicable, the inspection report may include a remediation plan wherein specific corrective action and a time frame for completion shall be stated when probable noncompliance issues exist.#
Source: 36 SDR 57, effective October 19, 2009.#
AuthorityLaw Implemented: SDCL 49-34B-3, 49-34B-4, 49-34B-5, 49-34B-19, 49-34B-27.#