Regulationcurrent
ARSD 20:10:37:14
20:10:37:14 Pipeline operator's obligations upon completion of inspector's incident report
Current as of 2009-10-19 Government source
South Dakota Public Utilities CommissionOfficial agency material
View source Upon filing of the inspector's incident report with the commission, the pipeline operator shall respond, in writing, within 30 business days from the pipeline operator's receipt of the incident report and state whether the pipeline operator agrees with the report and recommendations or disputes any portion of the report and recommendations.#
Source: 36 SDR 57, effective October 19, 2009.#
AuthorityLaw Implemented: SDCL 49-34B-3, 49-34B-4, 49-34B-5, 49-34B-7, 49-34B-12, 49-34B-19, 49-34B-27.#