HAR 6-77-185
HAR 6-77-185 Test requirements for reinstating service lines
Snapshot 2026-08-12 Government source
Hawaii Public Utilities CommissionOfficial agency material
View source subsection (b), each disconnected service line must be tested in the same manner as a new service line, before being reinstated. (b) Each service line temporarily disconnected from the main must be tested from the point of disconnection to the service line valve in the same manner as a new service line, before reconnecting. However, if provisions are made to maintain continuous service, such as by installation of a bypass, any part of the original service line used to maintain continuous service need not be tested. [Eff ] (Auth: HRS '269-6) (Imp: 49 C.F.R. '192.725, October 1, 1990)