Regulationhistorical
HAR 6-77-9
HAR 6-77-9 Transmission and gathering systems: incident report
Snapshot 2026-08-12 Government source
Hawaii Public Utilities CommissionOfficial agency material
View source in subsection (c), each operator of a transmission or a gathering pipeline system shall submit Department of Transportation Form RSPA F 7100.2 as soon as practicable but not more than thirty days after detection of an incident required to be reported under section 6-77-4 and 49 C.F.R. '191.5. (b) Where additional related information is obtained after a report is submitted under subsection (a), the operator shall make a supplemental report as soon as practicable with a clear reference by date and subject to the original report. (c) The incident report required by subsection (a) need not be submitted with respect to LNG facilities. [Eff ] (Auth: HRS '269-6) (Imp: 49 C.F.R. '191.15, October 1, 1990)