16 NYCRR 255.329
255.329 Installation of plastic pipelines by trenchless excavation.
Current as of source date Government source
New York State Public Service CommissionOfficial agency material
View source Plastic pipelines installed by trenchless excavation must comply with the following:#
(a)Each operator must take practicable steps to provide sufficient clearance for installation and maintenance activities from other underground utilities and/or structures at the time of installations.#
(b)For each pipeline section, plastic pipe and components that are pulled through the ground must use a weak link, as defined by section 255.3 of this Part, to ensure the pipeline will not be damaged by any excessive forces during the pulling process.#