HAR 6-77-120 New service lines not in use
upon completion of installation must comply with one of the following until the customer is supplied with gas:#
(1)the valve that is closed to prevent the flow of gas to the customer must be provided with a locking device or other means designed to prevent the opening of the valve by persons other than those authorized by the operator;#
(2)A mechanical device or fitting that will prevent the flow of gas must be installed in the service line or in the meter assembly; or#
(3)The customer's piping must be physically disconnected from the gas supply and the open pipe ends sealed. [Eff ] (Auth: HRS '269-6) (Imp: 49#
C.F.R. '192.379, October 1, 1990) Subchapter 11 Minimum Safety Standards - Requirements for Corrosion Control#