Regulationcurrent
HAR 6-77-188
HAR 6-77-188 Compressor stations: inspection and testing of relief devices
Current as of 1994-09-03 Government source
Hawaii Public Utilities CommissionOfficial agency material
View source rupture discs, each pressure relieving device in a compressor station must be inspected and tested in accordance with sections 6-77-192 and 6-77-194, and must be operated periodically to determine that it opens at the correct set pressure.#
(b)Any defective or inadequate equipment found must be promptly repaired or replaced.#
(c)Each remote control shutdown device must be inspected and tested at intervals not exceeding fifteen months, but at least once each calendar year, to determine that it functions properly. [Eff ] (Auth: HRS '269-6) (Imp: 49#