RCSA § 16-280b-A38
Pipe in a Conduit
(a)Conduit shall be prepared to the extent necessary to remove any sharp edges, projections, dust, welding slag, or abrasive material which could damage the Pipe during or after insertion.#
(b)A device shall be used to prevent the Pipe from being damaged on the end of the Conduit.#
(c)Prior to inserting Pipe, any valves through which the Pipe would be inserted shall be removed. All Abandoned Mains to be used as Conduit shall be inspected with a camera to locate all valves, unless the Abandoned Main is short enough such that the entire length can be visually inspected to locate all valves.#
(d)Pipe shall be sealed on the leading edge prior to insertion. 15#
(e)Welding, brazing or cad welding shall not be performed on a Conduit through which plastic Pipe has been inserted.#